Question 1
[TOTAL: 40 MARKS]
1
CMPM5103JAN07/SI
Question 2
For each of the following questions, select the correct answer, and justify your
choice (10 lines maximum per question).
a) George works for a medium-size IT consulting company and likes his job. He
recently became involved with an upgrade of his company’s IT system, and it
will likely become an ongoing activity for him in addition to his other
responsibilities. Which of the following describes the work that George is
doing for this new assignment?
b) Project human resource management includes numerous “soft” skills that are
not easy to learn, and many project managers require additional training or
development to effectively schedule and coordinate resources. Human
resource planning includes all of the following, except:
2
CMPM5103JAN07/SI
f) There are a number of tools and techniques that project managers can utilize
in order to create synergy on a project. Some of these skills cannot be
developed by reading a book and must be learned on the job. Project
managers need solid communication and negotiation skills primarily because:
3
CMPM5103JAN07/SI
g) All projects should have basic elements in order to be planned and executed
efficiently and successfully. Many project managers do not plan properly and,
ultimately, the projects fail and money and resources are lost. One of the
following documents authorizes and initiates the project while empowering
the project manager to begin working on it. This document is known as a:
i. Project charter
ii. Project plan
iii. Work authorization form
iv. Project approval requisition
[5 marks]
i. John is working on activity sequencing and the plans are needed for
helping to determine dependencies.
ii. John needs to archive all the documents for the project in one project
folder for future use.
iii. You know John is not an engineer and that he was not at the steering
committee meeting.
iv. John does not need the plans, but from a management standpoint,
you want to respect his authority as the project manager.
[ 5 marks]
4
CMPM5103JAN07/SI
j) As a project manager, you know the WBS is important. What are the key
planning processes in which the WBS is an input?
l) A golf club manufacturer is starting a project to develop a new club head out
of a titanium alloy using an unproven high heat and cooling method. The
product will have embedded “flex beads,” and is expected to revolutionize the
5
CMPM5103JAN07/SI
[TOTAL: 60 MARKS]