RESUMEN

ITEM DESCRIPCION UND N° VECES LARGO (m) ALTO(m)

2.01 SOLADOS
2.01.01 SOLADO PARA ZAPATA (Z7) E=4" m2 4 1.25
2.01.02 SOLADO PARA VIGA DE CONEXIÓN E=4" m2 4 3.45
2.02 CIMIENTO CORRIDO C:H 1:10 + 30% PG (max. 6")
2.02.01 EJE 2 2 m3 1 4.4 0.6
2.02.02 EJE A A m3 1 4.45 0.6
2.02.03 EJE B B m3 1 4.45 0.6
2.02.04 ENTRE EJE 1 1 Y 2 2 TRAMO 1 m3 1 2.4 0.6
2.02.05 ENTRE EJE 1 1 Y 2 2 TRAMO 2 m3 1 1.275 0.6
2.02.06 ENTRE EJE A A Y B B m3 1 1.775 0.6
2.03 SOBRECIMIENTO C:H 1:8 + 25% PM (max. 3")
2.03.01 EJE 2 2 m3 1 2.55 0.55
2.03.02 EJE A A m3 1 3.8 0.55
2.03.03 EJE B B m3 1 3.8 0.55
2.03.04 ENTRE EJE 1 1 Y 2 2 m3 1 2.75 0.55
2.03.06 ENTRE EJE A A Y B B m3 1 2.05 0.55
2.04 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS
2.04.01 EJE 2 2 m2 2 2.55 0.65
2.04.02 EJE A A m2 2 3.8 0.65
2.04.03 EJE B B m2 2 3.8 0.65
2.04.04 ENTRE EJE 1 1 Y 2 2 m2 2 2.75 0.65
2.04.05 ENTRE EJE A A Y B B m2 2 2.05 0.65
2.05 FALSO PISO E=4" m2 1
ANCHO(m) PARCIAL TOTAL

9.7
1.25 6.25
0.25 3.45
4.8795
0.45 1.188
0.45 1.2015
0.45 1.2015
0.45 0.648
0.35 0.2678
0.35 0.3728
1.2334
0.15 0.2104
0.15 0.3135
0.15 0.3135
0.15 0.2269
0.15 0.1691
19.435
3.315
4.94
4.94
3.575
2.665
21.1663 21.1663