Está en la página 1de 6

CIGRE Symposium "Working Plants and Systems Harder", London, 7-9 June 1999, paper 200-06

POWER SYSTEM TRANSIENT STABILITY ENHANCEMENT BY CO-ORDINATED FAST VALVING AND


EXCITATION CONTROL OF SYNCHRONOUS GENERATORS

J. Machowski, A. Smolarczyk J. W. Bialek


Warsaw University of Technology University of Durham
Instytyt Elektroenergetyki School of Engineering
ul. Koszykowa 75 Science Site, South Road
00-662 Warszawa, Poland Durham, DH1 3LE, England

Summary: Severe faults like short-circuits occurring For some power stations the stability margin is small
near power stations may result in system instability. In and any severe, but credible, fault will be very likely to
order to prevent asynchronous operation of the system cause the loss of synchronism of all the generators in the
an automatic generator tripping is often used but this station. In such situations the automatic generator
method of transient stability enhancement disturbs the tripping is used which trips off some of the generators
power balance in the system and starts a long-term in the station in order to prevent the synchronism of the
dynamic regulatiuon process. This paper proposes a remaining ones. Automatic generator tripping is usually
new control algorithm which may be used instead of the executed either as a simple circuit based on a pre-
automatic generator tripping. The algorithm identifies determined logic or as a sophisticated computerised
the transition to the asynchronous operation and acts on system [5].
the turbine governing and the excitation systems in
It is difficult to predict how many generators should be
order to stabilise the generator. Simulation results show
tripped in order to save the synchronism of the
that stabilisation can be achieved after one-two
remaining generators in the station. Therefore the
asynchronous rotations.
simple circuits with pre-determined logic have to be
Keywords: Transient stability - Stabilising control conservative, i.e. they usually trip more generators than
it is necessary. This is obviously a serious disadvantage.
1. INTRODUCTION Computerised systems are less conservative but involve
more equipment and higher cost.
Power system is a non-linear object and its stability
depends on the type, location and duration of a Whichever the technical solution adopted, the main
disturbance [1,2]. For a given fault, the longest fault disadvantage of automatic generator tripping is the fact
duration time which does not result in instability is that a generator has to be tripped. When the main
referred to the critical clearing time. When the actual circuit breaker opens following a tripping command,
clearing time, which depends on the speed of operation the generating unit must reject the load and switch to
of circuit-breakers and protection systems, is longer covering only its own auxiliary demand for power.
than the critical clearing time the generator loses After clearing the fault, the generator is re-
synchronism with rest of the system and begins the synchronised with the system which usually takes at
asynchronous (out-of-step) operation. least several minutes (often much longer). During this
time there is a deficit of generation in the system which
The asynchronous operation of the generator is not
starts a long-term process of frequency and load
permissible due to the thermal effect of large currents,
control. If the control system of the turbine and the
large power and voltage swings in the network and the
boiler is not prepared for load rejection without turbine
adverse effect on stability of other generators. To
tripping, the turbine must be tripped as well leading to
prevent this, the generators which lost synchronism are
cooling of the boiler. With a cold boiler, re-
disconnected after a few asynchronous rotations by the
synchronisation of the unit takes much longer.
pole-slip protection [3,4].
This paper suggests that maintaining the synchronism rotor will pass point 6 starting the asynchronous
following severe faults can be done without operation.
disconnecting the generator from the network. Instead
of automatic generator tripping, a co-ordinated control
P
of turbine valves and excitation voltage can be used. 11``

Pe (δ ) 11`
2. ASYNCHRONOUS OPERATION 5 14
Detailed description of what happens when a generator 1 4 6 12
loses synchronism and starts to operate asynchronously 10
Pm
can be found in [1]. In short, when a generator loses 3
2 δ
synchronism the rotor speed is higher than the
7 9 15 13
synchronous speed. This causes the turbine governing
system to close the turbine valves in order to reduce the π 2π
mechanical power. Reduced mechanical power 8``
improves the conditions for stabilising the unit. The
possibility of stabilisation is increased if the amplitude 8`
of synchronising power is large, i.e. the excitation level
Figure 1. Loss of synchronism and stabilisation.
is high. With appropriately low mechanical power and
large amplitude of synchronising power the generator When the rotor passes point 6 its mechanical power is
may be stabilised. greater than the electrical power and the rotor is further
accelerated. As the excess of mechanical power over the
Unfortunately the time necessary to stabilise the unit,
electrical power is large on the way to the equilibrium
using standard unit controllers, is long in the range of
point 10, the rotor gains large kinetic energy
several seconds. During that time the rotor would make
proportional to the area 6-7-8’-9-10. After passing point
many asynchronous revolutions which, as explained
10, the electrical power is greater than the electrical
earlier, would be unacceptable for both the generating
power and the rotor is decelerated. The sum of
unit and the system.
deceleration areas 4-5-6 and 10-11’-12 is less than the
Next section presents a new control algorithm which sum of acceleration areas 1-2-3 and 6-7-8’-9-10 which
stabilises the generating unit after one-two means that it is not possible for the rotor to return to the
asynchronous revolutions even for most severe faults. synchronous speed. The rotor passes point 12 further
accelerating and the asynchronous operation continues.
3. PRINCIPLES OF PROPOSED CONTROL
The above description shows that with the constant
In order to stabilise the generator-turbine unit quickly mechanical power and constant amplitude of power-
and effectively, it is necessary to act on all its angle characteristic (i.e. constant excitation) it is not
regulators, i.e. on the turbine valves and on the possible to stabilise the generator. The stabilisation can
excitation system. The proposed control has been only be made possible by intensive action of regulators.
derived after analysing the phenomena accompanying
3.2. Fast reduction of mechanical power
the loss of synchronism and out-of-step operation. This
is illustrated in Figure 1. Figure 1 shows that the excess of the acceleration areas
over the deceleration areas is caused by keeping high
3.1. The loss of synchronism value of mechanical power. Reduction in mechanical
power Pm will reduce the acceleration areas and enlarge
The loss of synchronism is illustrated on the left hand
the deceleration areas.
side of Figure 1. Curve Pe (δ ) corresponds to the
power-angle characteristic of the generator while the The middle part of Figure 1 corresponds to an
horizontal line Pm corresponds to the mechanical assumption that, when the out-of-step operation has
(turbine) power. Initially it will be assumed that Pm and been detected (i.e. the rotor passed the equilibrium point
the amplitude of Pe (δ ) characteristic are constant. The 6), the mechanical power Pm is quickly reduced to zero.
This causes a reduction of the acceleration area and
system operates at point 1 corresponding to the
enlargement of the deceleration area. However the sum
intersection of both characteristics. A short-circuit
of acceleration areas 1-2-3-4 and 6-8’-9 is still greater
lowers the electrical power to point 2. The acceleration
than the sum of the deceleration areas 4-5-6 and 9-11’-
power proportional to segment 1-2 accelerates the rotor
13 so that the stabilisation is not possible after the first
so that it follows the lower fault characteristic reaching
asynchronous rotation.
point 3 when the fault is cleared. At this moment the
rotor has excess kinetic energy proportional to the area During the subsequent asynchronous rotations the
1-2-3-4. This acceleration area is greater than the acceleration areas are equal to the deceleration areas as
maximum deceleration area 4-5-6 which means that the Pm = 0. However the rotor has earlier acquired kinetic
energy so that the stabilisation is still not possible. It can
be only made possible by an appropriate change of the advantageous to keep the high ceiling value of
amplitude of the power-angle characteristic. excitation voltage and the mechanical power equal to
zero.
3.3. Bang-bang excitation control
The amplitude of the power-angle characteristic P 11``
depends on the equivalent reactance of the system and
the generator transient emf. Thus the stabilisation can be
14
achieved by changing the transient emf which, in turn,
can be changed by changing the field current. Obviously Pm 0
the field current cannot be changed instantaneously as 23
21
the excitation circuit has a large time constant. However 17 Pm = 0 δ
a fast bang-bang control of the excitation voltage, i.e. 7 9 15 13
fast alternation between the maximum (positive) and
minimum (negative) values of the excitation voltage, 16
can enforce fast changes in the field current.
Middle part of Figure 1 illustrates the situation when the 8``
generator enters the motoring region of operation, point 22
7, and the excitation voltage is switched to the negative 8```
limiting value thus quickly reducing the transient emf.
Figure 2 Influence of the proposed control on the
This causes a reduction in the acceleration area 6-7-8’’-
amplitude of rotor backswing.
9 when compared to the area 6-7-8’-9 when the
excitation voltage was not changed. When the generator
Figure 2 shows that reducing the transient emf (solid
now enters the generating region (point 9) the
curve 14-21) and, at the same time, increasing the
excitation voltage is changed to its positive ceiling value
mechanical power during backswing (curve 15-21)
so that the transient emf, and the amplitude of power-
reduces the deceleration area to area 15-14-21. Further
angle characteristic, is quickly increased. This causes an
increasing the mechanical power (curve 21-23) and
increase in the deceleration area 9-11``-13 when
increasing the transient emf (curve 9-8'''-7) reduces the
compared with area 9-11`-13, i.e. when the excitation
amplitude of the backswing (point 22).
voltage was not changed.
Thus the conclusion for the stabilising control during
In the situation shown in Figure 1, the sum of
the backswing is that the mechanical power should be
deceleration areas 4-5-6 and 9-11``-13 is greater than
increased while the excitation voltage reduced in the
the sum of the acceleration areas 1-2-3-4 and 6-7-8’’-9.
generating area of operation.
The rotor swings until it reaches point 14 (when the sum
of acceleration areas balances the sum of the 3.5. Modification of PSS for deep swings
deceleration areas) and swings back towards the
equilibrium point 9. This means that the generator is In the proposed algorithm the described above bang-
prevented from doing the second asynchronous rotation bang excitation control is executed only during
and may be stabilised. asynchronous (out-of-step) operation and terminates
when, during the backswing, the generator moves from
3.4. Backward motion
the generating to the motoring part of power-angle
The turbine and excitation control described in the characteristic (point 9 in Figure 2). From this moment
previous section was correct in preventing the rotor on the standard Automatic Voltage Regulator (AVR)
from making the second asynchronous rotation. equipped with the Power System Stabiliser (PSS) takes
However once this is achieved and the rotor swings over the excitation control.
back from point 14, the control strategy has to be
The generator is re-stabilised with the system when its
different as illustrated in Figure 2.
mechanical power is small. For such a case the
When mechanical power is equal to zero, the backswing of the rotor is deep reaching the motoring
instantaneous equilibrium point is point 9. During the region of operation (negative real power). In this region
backswing from point 14 the generator does the the typical PSS, which uses the speed deviation as its
deceleration work proportional to the area 15-14-11’’-9. feedback signal, does not operate correctly. This is
Due to the rotor inertia, the rotor passes the equilibrium illustrated in Figure 3.
point 9 and reaches point 16 at which the acceleration
When the speed deviation is positive (i.e. rotor angle
area 9-8’’-16-17 balances the area 15-14-11’’-9. The
increases) the PSS causes an increase in the transient
amplitude of rotor backswing is high because area 15-
emf so that the amplitude of the power-angle
14-11’’-9 is large due to high amplitude of the power-
characteristic increases. Figure 3 shows that the rotor
angle characteristic with the mechanical power equal to
motion is then along the upper power-angle
zero. This shows that, during the backswing, it is not
Vref smoothed value of this signal is then multiplied by the
+
output signal from the PSS. Gain KP is added in order to
1 - Ef
KA compensate the amplitude reduction introduced by the
1+ sTR filter. The proposed multiplication of signal of PSS has
+
two positive effects:
ω sTW 1 + sT3 1 + sT1
Π (i) When the real power changes sign, the sign of the
1+ sTW 1 + sT4 1 + sT2
output signal is automatically reversed which is
Bessel filter necessary in the motoring region of operation.
P KP a (ii) The multiplication results in the output signal of the
s2 + bs + a PSS (i.e. its gain) being dependent on the rotor
angle. When the rotor angle is small and the
Figure 4. Block diagram of the modified AVR+PSS stabilising control is ineffective, the modified PSS
gives a small signal so that the AVR has a priority.
characteristic 9-24-25. However, during the backswing, This helps the voltage control in the transient state.
when the speed deviation is negative, the PSS reduces When the rotor angle is large and the stabilising
the transient emf and the amplitude of the power-angle control is effective, the modified PSS gives a strong
characteristic. The trajectory of the rotor motion is then signal.
along the lower power-angle characteristic 25-26-9. The
area between the upper and lower characteristic Therefore the modified PSS acts like an adaptive
corresponds to the positive damping of the oscillations. control system in which the gain and the sign of the
control signal depend on the properties of the controlled
object.
P 24
Computer simulations, described in Section 6, have
26
shown that the damping due to the proposed
25
modification is better when a large disturbance causes
asynchronous or deep synchronous power swings. Also
the voltage recovery is much improved.
9 δ
π
π
2 4. TECHNICAL FEASIBILITY
27
29 Fast control of the mechanical power produced by a
steam turbine can be obtained by acting directly on the
28 turbine valves omitting the speed turbine control. Fast
changes in mechanical power can be obtained by acting
on both main governor and intercept control valves.
Figure 3. Influence of the PSS. Acting only on the main control valves does not bring a
During a deep backswing, the rotor exceeds point 9 and quick change in the mechanical power as the high-
the PSS continues to lower the amplitude of the power- pressure stage produces only about 30% of power. The
angle characteristic. The rotor motion is then along reheater stores a large volume of steam and, even with
curve 9-27-28-29-9. It can be easily shown, using the the main governor valve closed, the turbine still supplies
equal area criterion [1], that this direction of the about 70% of power through its intermediate and low-
trajectory results in negative damping. In order to pressure stages.
achieve positive damping the PSS should enforce the The total time of closing the valves is relatively short
system trajectory to be directed 9-29-28-27-9. This can for modern turbines with electrohydraulic governing
be easily achieved by changing the sign of PSS signal in systems (about 0.1 to 0.4 s). This allows a fast reduction
the motoring region of power-angle characteristic . Such of mechanical power when the generator loses
a change can be done automatically by multiplying the synchronism. A fast increase in the mechanical power
PSS signal by the sign of the generator real power, or during the backswing is not possible because of the
even better by the value of the generator real power in limits on the speed of opening the valves. This speed is
p.u. limited due to the strength of turbine blades and the
A corresponding block diagram has been shown in Fig. speed of operation of servomotors. The strength of
4. The upper part of the diagram corresponds to a well- turbine blades limits the speed of opening the valves to
known [2] system consisting of a static exciter with about 1 to 2 s. In some types of turbines after a fast
closing of the valves their re-opening requires re-
proportional AVR and PSS using speed ω as the
pumping the oil which may take a few seconds. Thus the
feedback signal. The lower part of the diagram shown
time of re-opening the valves, after their closing down,
by the dashed line corresponds to the proposed
may take between 2 and 10 s, depending on the type of
modification. The real power signal is passed through a
the servomotor.
low-pass filter eliminating high frequency changes. The
Technical feasibility of implementation of such fast interrupted and the excitation voltage is controlled by
valving has been consulted with the engineers working AVR+PSS with described modification.
in a modern Polish power plant Elektrownia "Opole"
During the backswing, the control algorithm gives
[6]. Such control is obviously only possible if the
signal to opening up the turbine valves with taking into
control system of the turbine and the boiler is prepared
account the limits on the speed of opening.
for load rejection without turbine tripping.
Bang-bang excitation control consists of alternating the 6. SIMULATION RESULTS
excitation voltage between its upper and lower limits.
For the simulation tests the generator has been modelled
The effectiveness of such two-state control depends on
by the Park's 8th-order differential equations with the
the type of exciter used. When a static thyristor-
static thyristor controlled excitation system. The turbine
controlled exciter is used, the reverse of the sign of the
has been modelled taking into account high-,
excitation voltage can be achieved relatively easily.
intermediate- and low-pressure stages and the reheater.
Such a sign reverse ensures a fast change of the field
Both main and intercept turbine valves have been
current and a corresponding fast change in the transient
modelled.
emf, the magnitude of which determines the amplitude
of power-angle characteristic. A number of simulation tests assuming a variety of
possible operating conditions and disturbances have
5. CONTROL ALGORITHM been executed in order to check the effectiveness of the
proposed control algorithm. Typical simulation results
The first signal about the initiation of the turbine closing
are shown in Figure 5. In this case the generator was
should come when it is certain that the generator is
loaded by an inductive real load and the fault consisted
entering out-of-step operation. Figure 1 shows that a
of a three-phase short-circuit at the end of the
reliable criterion for this is a conjunction of the
transmission line.
following three events: (i) the speed deviation is
positive, ∆ω > 0 ; (ii) electrical power Pe is slightly Figure 5a shows that the fault caused a sudden drop of
larger but close to mechanical power, the generator power with characteristic 50 Hz
(1+ ε ) Pm > Pe (t ) > Pm , where ε > 0 is small; and (iii) oscillations. The speed deviation (Figure 5b) and the
rotor angle (Figure 5c) increase rapidly. After the fault
electrical power is decreasing, dPe / dt < 0 .
is cleared the generator loses synchronism and makes
When the turbine valves are being closed, the bang- one asynchronous rotation (vertical line in Figure 5c).
bang excitation control is initiated. Obviously the pre- Approximately half-way through the asynchronous
requisite for the initiation of the bang-bang excitation rotation, a signal is given to close the turbine valves
control is that the signal has been already given for (Figure 5d) and the mechanical power is reduced.
closing down the turbine valves, i.e. that the generator is Stabilisation occurs after only one asynchronous
losing synchronism. This criterion eliminates the rotation. The turbine main and intercept control valves
possibility of bang-bang excitation control during are completely closed for about 1s and then slowly
synchronous power swings. opened. This causes the mechanical power to be
reduced first to almost zero and then to be slowly
The sign of the excitation voltage during bang-bang restored. During opening of the turbine valves the
control depends on the direction of rotor swing (forward electrical power follows, with small oscillations, the
or backswing) and on whether the generator is (or tends mechanical power. The generator voltage was kept
towards) the generating or motoring region of operation. within the limits (Vg<1.15Vn) due to a proper operation
During the forward swing when the generator tends of the bang-bang excitation control.
towards the motoring region (criterion: ∆ω > 0 and
8. CONCLUSIONS
Pe (t ) > ε Pm and dPe / dt < 0 ) the algorithm chooses
the negative limiting value of the excitation voltage. In this paper a co-ordinated excitation and turbine
When the generator tends to the generating region control has been described which prevents generator
(criterion: ∆ω > 0 and Pe (t ) > −ε Pm and dPe / dt > 0 ) tripping following severe faults. The algorithm is simple
and easy for practical implementation. Simulation tests
the excitation voltage is switched to its positive ceiling have confirmed the effectiveness of the proposed
value. algorithm. The proposed controller can be used when a
In order to prevent the rising of the generator voltage to power station is in danger of losing transient stability
an unacceptably high value, the algorithm removes the and can replace the automatic generator tripping. The
ceiling value of the excitation voltage when the terminal algorithm acts only when the fault would indeed cause
voltage exceeds a prescribed value (e.g. 1.15 p.u.) the loss of synchronism and it does not lead to a
conservative action. In all simulated cases the generator
When the speed deviation changes its sign and the returned to the synchronous operation after one, or a
generator is within its generating range (criterion: maximum of two, asynchronous rotations.
∆ω < 0 and Pe (t ) > ε Pm ) the bang-bang control is
Pe 3. A.Stalewski, J.L.H.Goody, J.A.Downes: “Pole
2.0 slipping protection”, IEE Conf. Publ. 185, 1980, pp.
1.5 38-44.
1.0 4. J.A.Imhof, J.Berdy, W.A.Elmore, L.E.Goff,
W.C.New, G.C.Parr, A.H.Summers, C.L. Wagner:
0.5
t “Out of step relaying for generators - working grup
0 report”, IEEE Trans. on PAS, Vol. PAS.-96, No. 5,
1 2 3 4 5 6 7 8 s
-0.5 September/October 1977.
-1.0
5. K.Matsuzawa, K.Yanagihasi, J.Tsukita, M.Sato,
T.Nakamura, A.Takeuchi: "Stabilizing control
system preventing loss of synchronism from
0.04
extension and its actual operating experience". IEEE
Transaction on Power Systems, Vol. 10, No.3,
August 1995.
0.02
6. A. Smolarczyk, J. Machowski, H. Majchrzak:
t "Automatyka przeciwkolysaniowo-odciazajaca",
0
1 2 3 4 5 6 7 8 s Seminarium '98 - Elektroenergetyczna automatyka
w elektrowniach cieplnych, Opole 17-19 June 1998.
-0.02
11. RESUME
Les coûts et les problèmes liés à la construction de
200 lignes de transmission pousse les spécialistes en la
matière à surcharger des lignes existantes, provoquant
100 ainsi les réseaux de transmission de l'énergie électrique
t à travailler dans des conditions limites de stabilité. Un
0 court-circuit qui apparaissant non loin d'une station
1 2 3 4 5 6 7 8 s énergétique peut perturber le régime synchrone de tout
-100 le système. Un des moyens d'éviter le régime
asynchrone des alternateurs est leur coupure
-200 automatique. Comme la coupure d'un alternateur
possède un inconvéniant grave, une nouvelle stratégie
d'évitation de futiles coupures d'alternateurs est
1.0 proposée dans cet article. Ce système de contrôle
0.8 identifie d'avance la possibilité de passage de
l'alternateur au régime asynchrone et réagit sur les
0.6
signaux émis par les systèmes de réglage de l'alternateur
0.4 et de la turbine. Ceci a pour but de stabiliser
0.2 l'alternateur après un ou deux rotations asynchrones. Ce
t système de contrôle nécessite uniquement des mesures
0 de signaux locaux. Les résultats des tests de simulation
1 2 3 4 5 6 7 8 s
et le principe de fonctionnement de ce nouveau système
Figure 5. Results of a typical simulation test: (a) de réglage est décrit dans cet article.
generator electrical power; (b) speed deviation; (c) rotor
angle; (d) valve position (α) and mechanical power
(Pm).
9. ACKNOWLEDGEMENT
The Polish authors would like to acknowledge the
financial help of Komitet Badan Naukowych (KBN).
10. REFERENCES
1. J.Machowski, J.W.Bialek, J.R.Bumby: Power
System Dynamics and Stability, John Wiley & Sons,
Chichester, New York 1997.
2. P.Kundur: Power System Stability and Control
McGraw-Hill, Inc. 1994.

También podría gustarte