Está en la página 1de 2

METRADO - Badenes Carretera Tramo 0+000 - 29+533

Baden Tipico

EMBOQUILLA CONCRETO ACERO


B e Mat. Gran. L EXCAVACION JUNTA ENCOFRADO Rell. Comp. TRAZO Y
ITEM PROGRESIVA CANTIDAD DO f'c=175Kg/cm2 fy=4200Kg/cm2
(m) (m) (Esp.) (m) (m3) ASFALT. (ml) (m2) (m3) REPLANTEO
(m2) (m3) (kg)

METRADO TOTAL DE LOSAS

1 13+908 8.00 0.40 0.10 7.60 1.00 30.40 15.60 24.32 12.48 0.00 4.092 60.8
2 22+893.62 9.29 0.40 0.10 7.60 1.00 35.30 16.89 28.24 13.51 0.00 4.8918 70.604
3 23+542.27 9.29 0.40 0.10 7.60 1.00 35.30 16.89 28.24 13.51 0.00 4.8918 70.604
4 23+732.00 8.00 0.40 0.10 7.60 1.00 30.40 15.60 24.32 12.48 0.00 4.092 60.8

SUBTOTAL 131.40 63.73 0.00 105.12 51.98 0.00 18.15 262.81

EMBOQUILLADO DE PIEDRA

EMBOQUILLA CONCRETO ACERO


B e L EXCAVACION JUNTA ENCOFRADO Rell. Comp. TRAZO Y
ITEM PROGRESIVA AREA CANTIDAD DO f'c=175Kg/cm2 fy=4200Kg/cm2
(m) (m) (m) (m3) ASFALT. (ml) (m2) (m3) REPLANTEO
(m2) (m3) (kg)

1 13+908 8.00 0.30 1.94 3.74 1.00 8.98 10.77 15.52 4.64
2 22+893.62 9.29 0.30 1.94 3.50 1.00 9.75 11.71 4.89
3 23+542.27 9.29 0.30 1.94 3.50 1.00 9.75 11.71 4.89
4 23+732.00 8.00 0.30 1.94 3.74 1.00 8.98 10.77 4.64
SUBTOTAL 37.46 0.00 44.70 15.52 18.08 0.00 0.00 0.00

TOTAL 168.87 63.73 44.70 120.64 70.07 0.00 18.15 262.81

BADENES Unidad Cantidad


07.04.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 262.81
07.04.02 EXCAVACION NO CLASIFICADA PARA ESTRUCT m3 168.87
07.04.03 ENCOFRADO Y DESENCOFRADO m2 70.07
07.04.04 CONCRETO F'C=175Kg/cm2 m3 120.64
07.04.05 MAMPOSTERIA DE PIEDRA P/BADENES E=0.2M m2 44.70
07.04.06 JUNTA ASFALTICA LONGITUDINAL m 63.73
07.04.07 ELIMINACION DE MATERIAL EXCEDENTE m3 202.64