DISEÑO DE LA CIMENTACION

EJE A

SOBRECIMIENTO

DATOS:

tmuro= 25 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2

DETERMINACION DE "σn"

σn= 0.80 kg/cm2


σn= 8 tn/m2

CARGA TOTAL DE SERVICIO (CTS)

DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 1.973 1.973 1.09 5.036
CV 0.558 0.35 0.175 1.083
6.12

DETERMINACION DE Pn (Pn)

PARA :
t= 25 cms
L= 100 cms
A= 2500 cms2
f'c= 145 kg/cm2

Pn= 362.5 tn

CTS < Pn H= 0.40 mts

AREA DE ACERO

р= рmin= 0.0033333
Asmin= 3.3333333 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 5.036 tn/m


PL= 1.083 tn/m
σt= 0.80 kg/cm2
muro= 25 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2

ESTIMAMOS PESO DE ZAPATA

1 - 10%
0.80 - 10.4%
4 - 4%

PESO ZAPATA:
Pz= 0.52 tn/m

AREA DE CIMIENTO

b= 83.03 cm

b= 85 cm
L= 100 cm

PERALTE

Pu= 9624.74 kg
b= 85 cm
muro= 25 cms
φ= 0.7

Wu= 113.23 kg/cm


d= 66.25 cm
Mu= 248491.72 kg.cm
Mn= 354988.17 kg.cm

fr= 13.3 kg/cm2


h= 40.02 cm
h min= 60 cm

2X= 60 cm

h= 60 cm

SECCION TIPICA

25
2 ф 3/8''
40 NTN+0.00

2 ф 5/8''

POR NORMA
Df>=80cms
60

85

EJE A'

SOBRECIMIENTO

DATOS:

tmuro= 25 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2

DETERMINACION DE "σn"

σn= 0.80 kg/cm2


σn= 8 tn/m2

CARGA TOTAL DE SERVICIO (CTS)


DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 2.111 2.111 1.456 5.678
CV 0.948 0.948 0.319 2.215
7.89

DETERMINACION DE Pn (Pn)

PARA :
t= 25 cms
L= 100 cms
A= 2500 cms2
f'c= 145 kg/cm2

Pn= 362.5 tn

CTS < Pn H= 0.40 mts

AREA DE ACERO

р= рmin= 0.0033333
Asmin= 3.3333333 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 5.678 tn/m


PL= 2.215 tn/m
σt= 0.80 kg/cm2
muro= 25 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2

ESTIMAMOS PESO DE ZAPATA

1 - 10%
0.80 - 10.4%
4 - 4%
PESO ZAPATA:
Pz= 0.59 tn/m

AREA DE CIMIENTO

b= 106.04 cm

b= 110 cm
L= 100 cm

PERALTE

Pu= 12541.42 kg
b= 110 cm
muro= 25 cms
φ= 0.7

Wu= 114.01 kg/cm


d= 48.75 cm
Mu= 135479.37 kg.cm
Mn= 193542 kg.cm

fr= 13.3 kg/cm2

h= 29.55 cm
h min= 60 cm

2X= 85 cm

h= 85 cm

SECCION TIPICA

25
2 ф 3/8''
40 NTN+0.00

2 ф 5/8''

POR NORMA
Df>=80cms
85
110

EJE C

SOBRECIMIENTO

DATOS:

tmuro= 25 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2

DETERMINACION DE "σn"

σn= 0.80 kg/cm2


σn= 8 tn/m2

CARGA TOTAL DE SERVICIO (CTS)

DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 2.106 2.106 1.45 5.662
CV 0.635 0.635 0.318 1.588
7.25

DETERMINACION DE Pn (Pn)

PARA :
t= 25 cms
L= 100 cms
A= 2500 cms2
f'c= 145 kg/cm2

Pn= 362.5 tn

CTS < Pn H= 0.40 mts

AREA DE ACERO
р= рmin= 0.0033333
Asmin= 3.3333333 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 5.662 tn/m


PL= 1.588 tn/m
σt= 0.80 kg/cm2
muro= 25 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2

ESTIMAMOS PESO DE ZAPATA

1 - 10%
0.80 - 10.4%
4 - 4%

PESO ZAPATA:
Pz= 0.59 tn/m

AREA DE CIMIENTO

b= 97.99 cm

b= 100 cm
L= 100 cm

PERALTE

Pu= 11450.79 kg
b= 100 cm
muro= 25 cms
φ= 0.7

Wu= 114.51 kg/cm


d= 43.75 cm
Mu= 109587.61 kg.cm
Mn= 156553.73 kg.cm

fr= 13.3 kg/cm2

h= 26.58 cm
h min= 60 cm

2X= 75 cm

h= 75 cm

SECCION TIPICA

25
2 ф 3/8''
40 NTN+0.00

2 ф 5/8''

POR NORMA
Df>=80cms
75

100

EJE D

SOBRECIMIENTO

DATOS:

tmuro= 25 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2

DETERMINACION DE "σn"

σn= 0.80 kg/cm2


σn= 8 tn/m2
CARGA TOTAL DE SERVICIO (CTS)

DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 2.248 2.248 1.22 5.716
CV 0.928 0.298 0.208 1.434
7.15

DETERMINACION DE Pn (Pn)

PARA :
t= 25 cms
L= 100 cms
A= 2500 cms2
f'c= 145 kg/cm2

Pn= 362.5 tn

CTS < Pn H= 0.40 mts

AREA DE ACERO

р= рmin= 0.0033333
Asmin= 3.3333333 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 5.716 tn/m


PL= 1.434 tn/m
σt= 0.80 kg/cm2
muro= 25 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2

ESTIMAMOS PESO DE ZAPATA

1 - 10%
0.80 - 10.4%
4 - 4%

PESO ZAPATA:
Pz= 0.59 tn/m

AREA DE CIMIENTO

b= 96.81 cm

b= 100 cm
L= 100 cm

PERALTE

Pu= 11272.45 kg
b= 100 cm
muro= 25 cms
φ= 0.7

Wu= 112.72 kg/cm


d= 81.25 cm
Mu= 372078.9 kg.cm
Mn= 531541.29 kg.cm

fr= 13.3 kg/cm2

h= 48.97 cm
h min= 60 cm

2X= 75 cm

h= 75 cm

SECCION TIPICA

25
2 ф 3/8''
40 NTN+0.00

2 ф 5/8''

POR NORMA
Df>=80cms
75

100

EJE 1

SOBRECIMIENTO

DATOS:

tmuro= 25 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2

DETERMINACION DE "σn"

σn= 0.80 kg/cm2


σn= 8 tn/m2

CARGA TOTAL DE SERVICIO (CTS)

DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 1.861 1.861 2.288 6.01
CV 0.79 0.79 0.79 2.37
8.38

DETERMINACION DE Pn (Pn)

PARA :
t= 25 cms
L= 100 cms
A= 2500 cms2
f'c= 145 kg/cm2

Pn= 362.5 tn

CTS < Pn H= 0.40 mts


AREA DE ACERO

р= рmin= 0.0033333
Asmin= 3.3333333 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 6.01 tn/m


PL= 2.37 tn/m
σt= 0.80 kg/cm2
muro= 25 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2

ESTIMAMOS PESO DE ZAPATA

1 - 10%
0.80 - 10.4%
4 - 4%

PESO ZAPATA:
Pz= 0.63 tn/m

AREA DE CIMIENTO

b= 112.56 cm

b= 115 cm
L= 100 cm

PERALTE

Pu= 13318.06 kg
b= 115 cm
muro= 25 cms
φ= 0.7

Wu= 115.81 kg/cm


d= 96.25 cm
Mu= 536431.75 kg.cm
Mn= 766331.08 kg.cm

fr= 13.3 kg/cm2

h= 58.80 cm
h min= 60 cm

2X= 90 cm

h= 90 cm

SECCION TIPICA

25
2 ф 3/8''
40 NTN+0.00

2 ф 5/8''

POR NORMA
Df>=80cms
90

115

EJE 2

SOBRECIMIENTO

DATOS:

tmuro= 25 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2

DETERMINACION DE "σn"
σn= 0.80 kg/cm2
σn= 8 tn/m2

CARGA TOTAL DE SERVICIO (CTS)

DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 1.558 1.558 1.908 5.024
CV 0.95 0.95 0.87 2.77
7.79

DETERMINACION DE Pn (Pn)

PARA :
t= 25 cms
L= 100 cms
A= 2500 cms2
f'c= 145 kg/cm2

Pn= 362.5 tn

CTS < Pn H= 0.40 mts

AREA DE ACERO

р= рmin= 0.0033333
Asmin= 3.3333333 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 5.024 tn/m


PL= 2.77 tn/m
σt= 0.80 kg/cm2
muro= 25 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2

ESTIMAMOS PESO DE ZAPATA


1 - 10%
0.80 - 10.4%
4 - 4%

PESO ZAPATA:
Pz= 0.52 tn/m

AREA DE CIMIENTO

b= 103.96 cm

b= 105 cm
L= 100 cm

PERALTE

Pu= 12474.09 kg
b= 105 cm
muro= 25 cms
φ= 0.7

Wu= 118.80 kg/cm


d= 46.25 cm
Mu= 127061.27 kg.cm
Mn= 181516.11 kg.cm

fr= 13.3 kg/cm2

h= 28.62 cm
h min= 60 cm

2X= 80 cm

h= 80 cm

SECCION TIPICA

25
2 ф 3/8''
40 NTN+0.00

2 ф 5/8''
POR NORMA
Df>=80cms
80

105

EJE 3

SOBRECIMIENTO

DATOS:

tmuro= 15 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2

DETERMINACION DE "σn"

σn= 0.80 kg/cm2


σn= 8 tn/m2

CARGA TOTAL DE SERVICIO (CTS)

DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 1.524 1.524 1.908 4.956
CV 0.52 0.52 0.16 1.2
6.16

DETERMINACION DE Pn (Pn)

PARA :
t= 15 cms
L= 100 cms
A= 1500 cms2
f'c= 145 kg/cm2
Pn= 217.5 tn

CTS < Pn H= 0.40 mts

AREA DE ACERO

р= рmin= 0.0033333
Asmin= 2 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 4.956 tn/m


PL= 1.2 tn/m
σt= 0.80 kg/cm2
muro= 15 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2

ESTIMAMOS PESO DE ZAPATA

1 - 10%
0.80 - 10.4%
4 - 4%

PESO ZAPATA:
Pz= 0.52 tn/m

AREA DE CIMIENTO

b= 83.39 cm

b= 85 cm
L= 100 cm

PERALTE

Pu= 9699.99 kg
b= 85 cm
muro= 15 cms
φ= 0.7

Wu= 114.12 kg/cm


d= 38.75 cm
Mu= 85677.333 kg.cm
Mn= 122396.19 kg.cm

fr= 13.3 kg/cm2

h= 23.50 cm
h min= 60 cm

2X= 70 cm

h= 70 cm

SECCION TIPICA

15
2 ф 3/8''
40 NTN+0.00

2 ф 5/8''

POR NORMA
Df>=80cms
70

85

EJE 4

SOBRECIMIENTO

DATOS:

tmuro= 25 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2
DETERMINACION DE "σn"

σn= 0.80 kg/cm2


σn= 8 tn/m2

CARGA TOTAL DE SERVICIO (CTS)

DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 1.524 1.524 0.76 3.808
CV 0.36 0.36 0.16 0.88
4.69

DETERMINACION DE Pn (Pn)

PARA :
t= 25 cms
L= 100 cms
A= 2500 cms2
f'c= 145 kg/cm2

Pn= 362.5 tn

CTS < Pn H= 0.40 mts

AREA DE ACERO

р= рmin= 0.0033333
Asmin= 3.3333333 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 3.808 tn/m


PL= 0.88 tn/m
σt= 0.80 kg/cm2
muro= 25 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2
ESTIMAMOS PESO DE ZAPATA

1 - 10%
0.80 - 10.4%
4 - 4%

PESO ZAPATA:
Pz= 0.40 tn/m

AREA DE CIMIENTO

b= 63.55 cm

b= 65 cm
L= 100 cm

PERALTE

Pu= 7381.64 kg
b= 65 cm
muro= 25 cms
φ= 0.7

Wu= 113.56 kg/cm


d= 26.25 cm
Mu= 39126.266 kg.cm
Mn= 55894.666 kg.cm

fr= 13.3 kg/cm2

h= 15.88 cm
h min= 60 cm

2X= 40 cm

h= 60 cm

SECCION TIPICA

25
2 ф 3/8''
40 NTN+0.00
2 ф 5/8''

POR NORMA
Df>=80cms
60

65

EJE 5

SOBRECIMIENTO

DATOS:

tmuro= 25 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2

DETERMINACION DE "σn"

σn= 0.80 kg/cm2


σn= 8 tn/m2

CARGA TOTAL DE SERVICIO (CTS)

DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 0.697 0.697 0.65 2.044
CV 0.16 0.16 0.08 0.4
2.44

DETERMINACION DE Pn (Pn)

PARA :
t= 25 cms
L= 100 cms
A= 2500 cms2
f'c= 145 kg/cm2
Pn= 362.5 tn

CTS < Pn H= 0.40 mts

AREA DE ACERO

р= рmin= 0.0033333
Asmin= 3.3333333 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 2.044 tn/m


PL= 0.4 tn/m
σt= 0.80 kg/cm2
muro= 25 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2

ESTIMAMOS PESO DE ZAPATA

1 - 10%
0.80 - 10.4%
4 - 4%

PESO ZAPATA:
Pz= 0.21 tn/m

AREA DE CIMIENTO

b= 33.21 cm

b= 40 cm
L= 100 cm

PERALTE

Pu= 3839.21 kg
b= 40 cm
muro= 25 cms
φ= 0.7

Wu= 95.98 kg/cm


d= 13.75 cm
Mu= 9073.1245 kg.cm
Mn= 12961.606 kg.cm

fr= 13.3 kg/cm2

h= 7.65 cm
h min= 60 cm

2X= 15 cm

h= 60 cm

SECCION TIPICA

25
2 ф 3/8''
40 NTN+0.00

2 ф 5/8''

POR NORMA
Df>=80cms
60

40

EJE 6

SOBRECIMIENTO

DATOS:

tmuro= 15 cms
f'c= 145 kg/cm2 CONCRETO ARMADO
fy= 4200 kg/cm2
DETERMINACION DE "σn"

σn= 0.80 kg/cm2


σn= 8 tn/m2

CARGA TOTAL DE SERVICIO (CTS)

DEL METRADO DE CARGAS, TOMAMOS LA CARGA MAXIMA DE SERVICIO ACTUANTE

P (TN)
1ER PISO 2DO PISO 3ER PISO CT (TN)
CM 1.124 1.124 0.65 2.898
CV 0.16 0.16 0.08 0.4
3.3

DETERMINACION DE Pn (Pn)

PARA :
t= 15 cms
L= 100 cms
A= 1500 cms2
f'c= 145 kg/cm2

Pn= 217.5 tn

CTS < Pn H= 0.40 mts

AREA DE ACERO

р= рmin= 0.0033333
Asmin= 2 cm2
As1= 1.42 cm2 2 ф 3/8''
As2= 3.96 cm2 2 ф 5/8''

CIMIENTO

DATOS:

PD= 2.898 tn/m


PL= 0.4 tn/m
σt= 0.80 kg/cm2
muro= 15 cms
CC: 1:10+30%PG
f`c= 100 kg/cm2

ESTIMAMOS PESO DE ZAPATA

1 - 10%
0.80 - 10.4%
4 - 4%

PESO ZAPATA:
Pz= 0.30 tn/m

AREA DE CIMIENTO

b= 44.99 cm

b= 45 cm
L= 100 cm

PERALTE

Pu= 5159.15 kg
b= 45 cm
muro= 15 cms
φ= 0.7

Wu= 114.65 kg/cm


d= 33.75 cm
Mu= 65295.477 kg.cm
Mn= 93279.253 kg.cm

fr= 13.3 kg/cm2

h= 20.51 cm
h min= 60 cm

2X= 30 cm

h= 60 cm

SECCION TIPICA

15
2 ф 3/8''
40 NTN+0.00

2 ф 5/8''

POR NORMA
Df>=80cms
60

45