MATERIALES PARA SEMANA 4 (DEL 08/11/2021 AL 13/11/2021)

ZAPATA
MODULO DE COCINA COMEDOR

CONCRETO 210 KG/CM2 CANTIDAD L B H


Z1 4 1.2 1.2 0.5
Z2 4 1.25 1.25 0.5
Z3 3 1 1 0.5
TOTAL

MODULO DE SUM

CONCRETO 210 KG/CM2 CANTIDAD L B H


Z1 3 1.1 1 0.45
Z2 4 1.4 1.25 0.45
Z3 6 1.6 1.5 0.45
TOTAL

MODULO DE AULA

CONCRETO 210 KG/CM2 CANTIDAD L B H


Z1 2 1.1 1 0.45
Z2 4 1.4 1.25 0.45
Z3 2 1.6 1.5 0.45
TOTAL

MODULO DE SSHH

CONCRETO 210 KG/CM2 CANTIDAD L B H


Z1 9 1.1 1 0.45
TOTAL

CIMIENTO CORRIDO

MODULO DE COCINA COMEDOR

CONCRETO 1:10 +30%PG CANTIDAD L B H


ELEMENTO 1 6 1.72 0.4 0.4
ELEMENTO 2 1 3.66 0.4 0.4
ELEMENTO 3 4 4.29 0.4 0.4
ELEMENTO 4 2 2.63 0.4 0.4
ELEMENTO 5 1 1.93 0.4 0.8
TOTAL

MODULO DE SUM

CONCRETO 1:10 +30%PG CANTIDAD L B H


ELEMENTO 1 6 3.1 0.5 0.6
ELEMENTO 2 8 3.44 0.5 0.6
TOTAL

MODULO DE AULA

CONCRETO 1:10 +30%PG CANTIDAD L B H


ELEMENTO 1 4 3.1 0.5 0.6
ELEMENTO 2 4 3.49 0.5 0.6
TOTAL

MODULO DE SSHH

CONCRETO 1:10 +30%PG CANTIDAD L B H


ELEMENTO 1 3 1.76 0.5 0.7
ELEMENTO 2 3 3.56 0.5 0.7
ELEMENTO 3 6 2.7 0.5 0.7
ELEMENTO A1 5.15 0.7
TOTAL
08/11/2021 AL 13/11/2021)

h VOLUMEN ZAPATA VOLUMEN SOLADO


0.1 2.88 0.58
0.1 3.13 0.63
0.1 1.50 0.30
7.51 1.50

h VOLUMEN VOLUMEN SOLADO


0.1 1.49 0.33
0.1 3.15 0.70
0.1 6.48 1.44
11.12 2.47

h VOLUMEN VOLUMEN SOLADO


0.1 0.99 0.22
0.1 3.15 0.70
0.1 2.16 0.48
6.30 1.40

h VOLUMEN VOLUMEN SOLADO


0.1 4.46 0.99
4.46 0.99

RRIDO

VOLUMEN
1.65
0.59
2.75
0.84
0.62
6.44

VOLUMEN
5.58
8.26
13.84

VOLUMEN
3.72
4.19
7.91

VOLUMEN
1.85
3.74
5.67
3.61
14.86
MATERIALES PARA SEMANA 4 (DEL 08/11/2021 AL 13/11/2021)

MODULOS (VOLUMEN) M3
TOTAL m3
SSHH AULA I AULA SUM COMEDOR+COCINA
SOLADO DE ZAPATAS 0.99 1.40 2.47 1.50 6.36
ZAPATAS 4.46 6.30 11.12 7.51 29.38
CIMIENTO CORRIDO 14.86 7.91 13.84 6.44 43.05

SOLADO DE ZAPATAS-CONCRETO 100KG/CM2

DOSIFICACION CANTIDAD UNIDAD


CEMENTO 5.7 36.26 BOLSAS
HORMIGON 0.8 0.39 VOLQUETADAS
AGUA

ZAPATAS-CONCRETO 210KG/CM2

DOSIFICACION CANTIDAD UNIDAD


CEMENTO 9.73 285.82 BOLSAS
ARENA GRUESA 0.52 1.18 VOLQUETADAS
PIEDRA CHANCADA 1/2-3/4 0.53 1.20 VOLQUETADAS
AGUA 0.184 5.405

CIMIENTO CORRIDO CONCRETO 1:10 + 30 PG

DOSIFICACION CANTIDAD UNIDAD


CEMENTO 3.14 135.17 BOLSAS
HORMIGON 0.89 2.95 VOLQUETADAS
PIEDRA DE 8" 0.3 0.99 VOLQUETADAS

REQUERIMIENTO MATERIAL SEMANA 4


MATERIAL CANTIDAD UNIDAD EN OBRA
CEMENTO 457.24 BOLSAS
ARENA GRUESA 1.18 VOLQUETADAS
PIEDRA CHANCADA 1/2-3/4 1.20 VOLQUETADAS
HORMIGON 3.34 VOLQUETADAS
PIEDRA DE 8" 0.99 VOLQUETADAS
PROYECTO:“REHABILITACIÓN DEL LOCAL ESCOLAR 86254 MARCOS LEMUS RIVAS CON CÓDIGO LOCAL 019504 DE
LA LOCALIDAD DE SANTA ROSA, DISTRITO DE AQUIA, PROVINCIA DE BOLOGNESI - ÁNCASH.CON CODIGO UNICO DE
LA IRI 2478465"
ELEMENTO TIPO DE CONCRETO CANTERA MODULO
SOLADO DE ZAPATA 100KG/CM2 TACLLAN
MODULO DE
CONCRETO EN ZAPATA 210 KG/CM2 TACLLAN COCINA +
CONCRETO EN CIMIENTO CORRIDO 1:10 +30% PG TACLLAN COMEDOR