Testing: Unit Testing / User Manual Module: Quality Management

ENVIRONMENT

SYSTEM : SAP R/3 ECC 6.0

CLIENT : 200

UNIT TESTING SCENARIO

SCENARIO NUMBER : BPML QM03-02

DESCRIPTION : In Process Inspection in Machine Shop

PREPARED & TESTED BY

NAME : S R Baviskar

SIGNATURE :

DATE :

TEAM :

Approved By : Kabir R (PwC)

Page 1 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

A) By Manual Lot Preparation:

1) First change the material (mm02) for “Inspection Type 89”

Change material
“mm02”

Page 2 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

Click on
Tick
button

Click on
Insp. setup

Page 3 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

1. Click on Inspection type

2. Enter 89

3. Click on Active

4. Click on Tick button

Save the changes in “Material change”

2) Create the Inspection Plan to “Usage 3 –Universal”


Page 4 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

Page 5 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

1. Change Usage 3

2. Enter Task list button


& enter the Insp.
Characteristics for usage 3
and save the plan.

Page 6 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

3) Create Inspection lot manually

Page 7 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

Put inspection lot origin as 89.

Page 8 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

1. Put Inspection lot qty.

2. Save the Inspection Lot

4) Clear the “manual inspection lot” through QA32 transaction as a regular process.

Select the manual


inspection lot and
complete the
transaction as a
regular process.

Page 9 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

This manual lot creation procedure can be adopted for Layout Inspection, Product Audit
or any specific inspection of the component for ex. investigation.

B) Production Order - Inspection Lot:

1)By transaction COOIS see the details of Production Information System

2) Clear the “Inspection lot” through qa32 transaction as a regular process.

Page 10 of 11
 

Testing: Unit Testing / User Manual Module: Quality Management

Select the inspection


lot and complete the
transaction as a
regular process.

3) Give reference of Manual inspection lot number and production order number:

Enter Transaction Code:QPR6.Select the Inspection Lot & Execute.

Page 11 of 11