VALORIZACION DE AVANCE DE OBRA

PROYECTO: "MEJORAMIENTO VIAL DEL JIRON MOQUEGUA Y ADYACENTES TRAMO JR. BOLOGNESI - AV. LA MARINA DISTRITO DEL TAMBO - HUANCAYO - JUNIN"

ENTIDAD: MUNICIPALIDAD DISTRITAL DEL TAMBO CONTRATISTA: PLAZO DE EJECUCION: 90 DIAS


UBICACIÓN: JUNIN - HUANCAYO - EL TAMBO SUPERVISOR: VALOR REFERENCIAL: 336, 920.09

PRESUPUESTADO VALORIZACION ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR VALORIZAR
ITEM DESCRIPCION
UND METRADO PRECIO PARCIAL METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL % METRADO PARCIAL %
PAVIMENTO RIGIDO
01 OBRAS PROVISIONALES
01.01 GUARDIANIA Y ALMACEN DIA 90.00 135.04 12,153.60 51.00 6,887.04 56.67% 30.00 4,051.20 33.33% 81.00 10,938.24 90.00% 9.00 1,215.36 10.00%
01.02 CARTEL DE IDENTIFICACION DE OBRA Y PROMOCION DE OBRA und 1.00 1,200.00 1,200.00 0.00 0.00 0.00% 1.00 1,200.00 100.00% 1.00 1,200.00 100.00% 0.00 0.00 0.00%
01.03 CARTEL DE SEÑALIZACION PARA DESVIACION DE TRANSITO und 1.00 45.61 45.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 45.61 100.00%
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 2,000.00 2,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2,000.00 100.00%
02 TRABAJOS PRELIMINARES
02.01 TRAZO DE NIVELES Y REPLANTEO m2 2,284.08 0.75 1,713.06 2,284.08 1,713.06 100.00% 0.00 0.00 0.00% 2,284.08 1,713.06 100.00% 0.00 0.00 0.00%
02.02 TRAZO DE NIVELES Y REPLANTEO DURANTE LA EJECUCION DE LA O und 2,284.08 0.75 1,713.06 1,121.02 840.77 49.08% 571.02 428.27 25.00% 1,692.04 1,269.03 74.08% 592.04 444.03 25.92%
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE TERRENO CON MAQ. A NIVEL DE SUB RASANTE m3 701.99 5.86 4,113.66 495.40 2,903.03 70.57% 120.00 703.20 17.09% 615.40 3,606.23 87.66% 86.59 507.43 12.34%
03.02 EXCAVACION MANUAL m3 38.65 32.08 1,239.89 7.37 236.56 19.08% 31.28 1,003.33 80.92% 38.65 1,239.89 100.00% 0.00 0.00 0.00%
03.03 ACARREO INTERNO DE MATERIAL DE CORTE m3 48.31 18.05 872.00 9.22 166.38 19.08% 39.09 705.62 80.92% 48.31 872.00 100.00% 0.00 0.00 0.00%
03.04 CARGUIO DE MATERIAL EXCEDENTE m3 925.80 3.97 3,675.43 638.13 2,533.37 68.93% 227.84 904.52 24.61% 865.97 3,437.89 93.54% 59.83 237.53 6.46%
03.05 TRANSPORTE DE MATERIAL EXCEDENTE m3 925.80 3.75 3,471.75 638.13 2,392.98 68.93% 227.84 854.39 24.61% 865.97 3,247.37 93.54% 59.83 224.38 6.46%
04 EXPLANACIONES
04.01 ESCARIF. PERFIL. Y COMPACT. DE SUB RASANTE m2 1,626.00 3.27 5,317.02 1,452.61 4,750.02 89.34% 173.39 566.99 10.66% 1,626.00 5,317.02 100.00% 0.00 0.00 0.00%
05 SUB BASE GRANULAR
05.01 MATERIAL P/SUB BASE PUESTO EN OBRA m3 406.50 35.58 14,463.27 86.06 3,062.10 21.17% 320.44 11,401.17 78.83% 406.50 14,463.27 100.00% 0.00 0.00 0.00%
05.02 EXTENDIDO RIEGO Y COMPACTACION SUB-BASE E=0.20m. m2 1,626.00 5.10 8,292.60 344.25 1,755.68 21.17% 1,281.75 6,536.93 78.83% 1,626.00 8,292.60 100.00% 0.00 0.00 0.00%
06 PAVIMENTO RIGIDO
06.01 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO m2 160.13 31.09 4,978.44 35.04 1,089.39 21.88% 72.90 2,266.46 45.53% 107.94 3,355.85 67.41% 52.19 1,622.59 32.59%
06.02 CONCRETO FC=210 KG/CM2 EN PAVIMENTO m3 286.60 350.80 100,539.28 64.80 22,731.84 22.61% 129.60 45,463.68 45.22% 194.40 68,195.52 67.83% 92.20 32,343.76 32.17%
06.03 ACABADO EN PAVIMENTO RIGIDO m2 1,432.99 10.63 15,232.68 324.00 3,444.12 22.61% 647.95 6,887.71 45.22% 971.95 10,331.83 67.83% 461.04 4,900.86 32.17%
07 DOWELLS (JUNTA TRANSVERSAL)
07.01 JUNTA DE DILATACION kg 2,701.19 6.15 16,612.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,701.19 16,612.32 100.00%
07.02 JUNTA DE CONSTRUCCION kg 198.01 4.61 912.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 198.01 912.83 100.00%
08 CURADO DE PAVIMENTO RIGIDO
08.01 CURADO CON ARROCERAS m2 1,432.99 0.52 745.15 324.00 168.48 22.61% 648.00 336.96 45.22% 972.00 505.44 67.83% 460.99 239.71 32.17%
09 BADENES
09.01 ENCOFRADO Y DESENCOFRADO EN BADEN m2 10.22 31.09 317.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.22 317.74 100.00%
09.02 CONCRETO FC=210 KG/CM2 EN BADEN INCL ACABADO m3 8.24 358.66 2,955.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.24 2,955.36 100.00%
10 SARDINEL
10.01 ENCOFRADO Y DESENCOFRADO EN SARDINEL m2 129.48 47.95 6,208.57 117.20 5,619.74 90.52% 0.00 0.00 0.00% 117.20 5,619.74 90.52% 12.28 588.83 9.48%
10.02 CONCRETO F'c=175 KG/CM2 EN SARDINEL INCL. ACABADO m3 19.42 340.66 6,615.62 16.93 5,766.56 87.17% 0.65 222.25 3.36% 17.58 5,988.80 90.53% 1.84 626.81 9.47%
11 DRENAJE
11.01 ENCOFRADO Y DESENCOFRADO EN CUNETA m2 86.03 31.09 2,674.67 12.50 388.63 14.53% 38.90 1,209.40 45.22% 51.40 1,598.03 59.75% 34.63 1,076.65 40.25%
11.02 CONCRETO FC=210 KG/CM2 EN CUNETAS INCL. ACABADO m3 20.65 358.66 7,406.33 3.00 1,075.98 14.53% 9.33 3,346.30 45.18% 12.33 4,422.28 59.71% 8.32 2,984.05 40.29%
12 SELLADO DE JUNTAS
12.01 SELLADO DE JUNTAS CON ASFALTO m 851.34 3.49 2,971.18 0.00 0.00 0.00% 372.00 1,298.28 43.70% 372.00 1,298.28 43.70% 479.34 1,672.90 56.30%
13 SEÑALIZACION HORIZONTAL
13.01 PINTURA LINEAL EN SARDINEL m 323.69 9.06 2,932.63 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 323.69 2,932.63 100.00%
13.02 PINTURA ZONAL CRUCE PEATONAL m2 153.00 21.06 3,222.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 153.00 3,222.18 100.00%
13.03 PINTURA INTERM. DISCONT. - CENTRO DE VIA m 190.34 5.61 1,067.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 190.34 1,067.81 100.00%
13.04 PINTURA DE SIMBOLOS - FLECHAS m2 9.55 22.42 214.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.55 214.11 100.00%
14 SEÑALIZACION VERTICAL
14.01 SEÑALES INFORMATIVAS TIPO 01 und 4.00 262.35 1,049.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 1,049.40 100.00%
15 VARIOS
15.01 REEMPLAZO DE TUBERIA PARA DESAGUE m 233.13 12.17 2,837.19 233.13 2,837.19 100.00% 0.00 0.00 0.00% 233.13 2,837.19 100.00% 0.00 0.00 0.00%
15.02 REEMPLAZO DE TUBERIA PARA AGUA m 29.00 9.73 282.17 29.00 282.17 100.00% 0.00 0.00 0.00% 29.00 282.17 100.00% 0.00 0.00 0.00%
15.03 RECONEXION DE INSTALACION DE PUNTOS DE DESAGUE pto 26.00 62.32 1,620.32 21.00 1,308.72 80.77% 0.00 0.00 0.00% 21.00 1,308.72 80.77% 5.00 311.60 19.23%
15.04 RECONEXION DE INSTALACION DE PUNTOS DE AGUA m 26.00 34.42 894.92 21.00 722.82 80.77% 0.00 0.00 0.00% 21.00 722.82 80.77% 5.00 172.10 19.23%
15.05 SEGURIDAD Y SALUD EN OBRA glb 1.00 10,450.00 10,450.00 0.61 6,322.25 60.50% 0.40 4,127.75 39.50% 1.00 10,450.00 100.00% 0.00 0.00 0.00%
15.06 MITIGACION DE IMPACTO AMBIENTAL glb 1.00 500.00 500.00 0.61 302.50 60.50% 0.40 197.50 39.50% 1.00 500.00 100.00% 0.00 0.00 0.00%
15.07 LIMPIEZA FINAL DE OBRA m2 2,284.08 0.08 182.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,284.08 182.73 100.00%
16 PLACA RECORDATORIA
16.01 PLACA RECORDATORIA GLB 1.00 430.08 430.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 430.08 100.00%
VEREDAS
01 TRABAJOS PRELIMINARES
01.01 DEMOLICION DE VEREDAS EXISTENTES m3 31.87 77.59 2,472.79 31.87 2,472.79 100.00% 0.00 0.00 0.00% 31.87 2,472.79 100.00% 0.00 0.00 0.00%
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACION MANUAL PARA ACERA PEATONAL m3 49.97 32.08 1,603.04 46.58 1,494.26 93.21% 1.73 55.50 3.46% 48.31 1,549.76 96.68% 1.66 53.28 3.32%
03 ELIMINACION
03.01 ACARREO MANUAL DE MATERIAL DE CORTE m3 62.46 18.05 1,127.40 58.22 1,050.95 93.22% 2.16 38.99 3.46% 60.38 1,089.93 96.68% 2.08 37.47 3.32%
03.02 CARGUIO DE MATERIAL EXCEDENTE m3 107.08 3.97 425.11 102.85 408.30 96.05% 2.15 8.54 2.01% 105.00 416.84 98.05% 2.08 8.27 1.95%
03.03 TRANSPORTE DE MATERIAL EXCEDENTE m3 107.08 3.75 401.55 102.85 385.67 96.05% 2.15 8.06 2.01% 105.00 393.74 98.05% 2.08 7.81 1.95%
04 SUB BASE GRANULAR
04.01 MATERIAL P/SUB BASE PUESTO EN OBRA m3 49.92 35.58 1,776.15 44.38 1,579.19 88.91% 0.25 8.90 0.50% 44.63 1,588.09 89.41% 5.29 188.06 10.59%
04.02 EXTENDIDO RIEGO Y COMPACTACION SUB-BASE E=0.10m. m2 399.37 3.62 1,445.72 355.07 1,285.37 88.91% 2.02 7.31 0.51% 357.09 1,292.68 89.41% 42.28 153.04 10.59%
05 ACERA PEATONAL
05.01 ENCOFRADO Y DESENCOFRADO EN ACERA m2 15.39 27.00 415.53 13.73 370.71 89.21% 0.00 0.00 0.00% 13.73 370.71 89.21% 1.66 44.82 10.79%
05.02 CONCRETO FC=175 KG/CM2 EN ACERA INCL. ACABADO m3 38.52 327.30 12,607.60 33.75 11,047.83 87.63% 2.35 769.16 6.10% 36.10 11,816.99 93.73% 2.42 790.61 6.27%
06 SARDINEL DE JARDINERIA
06.01 ENCOFRADO Y DESENCOFRADO EN SARDINEL DE JARDINERIA m2 76.30 47.95 3,658.59 76.30 3,658.59 100.00% 0.00 0.00 0.00% 76.30 3,658.59 100.00% 0.00 0.00 0.00%
06.02 CONCRETO F'c=175 KG/CM2 EN SARDINEL DE JARDINERIA INCL. AC m3 11.44 340.66 3,897.15 11.44 3,897.15 100.00% 0.00 0.00 0.00% 11.44 3,897.15 100.00% 0.00 0.00 0.00%
07 RAMPAS
07.01 ENCOFRADO Y DESENCOFRADO EN RAMPAS m2 2.88 29.66 85.42 0.00 0.00 0.00% 2.24 66.44 77.78% 2.24 66.44 77.78% 0.64 18.98 22.22%
07.02 CONCRETO F'c=175 KG/CM2 EN RAMPAS INCL. ACABADO m3 0.99 332.27 328.95 0.00 0.00 0.00% 0.77 255.85 77.78% 0.77 255.85 77.78% 0.22 73.10 22.22%
08 TRATAMIENTO DE JARDINERIA
08.01 REFINE Y PERFILADO DE SUSTRATO DE JARDINERIA m2 190.65 0.97 184.93 0.00 0.00 0.00% 90.21 87.50 47.32% 90.21 87.50 47.32% 100.44 97.43 52.68%
08.02 SEMBRADO DE GRASS m2 190.65 4.36 831.23 0.00 0.00 0.00% 90.21 393.32 47.32% 90.21 393.32 47.32% 100.44 437.92 52.68%
08.03 RIEGO Y MANTENIMIENTO DE GRASS m2 190.65 0.18 34.32 0.00 0.00 0.00% 90.21 16.24 47.32% 90.21 16.24 47.32% 100.44 18.08 52.68%
08.04 PLANTADO DE ARBUSTOS und 37.00 13.61 503.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 37.00 503.57 100.00%
09 SELLADO DE JUNTAS
09.01 RELLENO DE JUNTAS CON ASFALTO m 159.42 3.49 556.38 155.35 542.16 97.44% 4.07 14.22 2.56% 159.42 556.38 100.00% 0.00 0.00 0.00%
10 VARIOS
10.01 REPOSICION DE CAJAS DE AGUA POTABLE pto 26.00 48.14 1,251.64 26.00 1,251.64 100.00% 0.00 0.00 0.00% 26.00 1,251.64 100.00% 0.00 0.00 0.00%
10.02 REPOSICION DE CAJAS DE DESAGUE pto 26.00 60.17 1,564.42 26.00 1,564.42 100.00% 0.00 0.00 0.00% 26.00 1,564.42 100.00% 0.00 0.00 0.00%

COSTO DIRECTO 289,296.13 110,310.42 95,441.90 205,752.32 83,543.81


GASTOS GENERALES (12.35%) 35,728.07 13,623.34 11,787.07 25,410.41 10,317.66
SUB TOTAL 325,024.20 123,933.76 107,228.97 231,162.73 93,861.47
SUPERVICION (3.66%) 11,895.89 4,535.98 3,924.58 8,460.56 3,435.33
PRESUPUESTO TOTAL 336,920.09 128,469.74 111,153.55 239,623.29 97,296.80
PORCENTAJE DE AVANCE 38.13% 32.99% 71.12% 28.88%
METRADOS EJECUTADOS DESAGUE PLUVIAL

PROYECTO: "MEJORAMIENTO VIAL DEL JIRON MOQUEGUA Y ADYACENTES TRAMO JR. BOLOGNESI - AV. LA MARINA
DISTRITO DEL TAMBO - HUANCAYO - JUNIN"

ENTIDAD: MUNICIPALIDAD DISTRITAL DEL TAMBO


UBICACIÓN: JUNIN - HUANCAYO - EL TAMBO
CONTRATISTA:
SUPERVISOR:
PLAZO DE EJECUCION: 90 DIAS CALENDARIOS
VALOR REFERENCIAL: 336, 920.09

ITEM DESCRIPCION UND METRADO


PAVIMENTO RIGIDO
01 OBRAS PROVISIONALES
01.01 GUARDIANIA Y ALMACEN Dia 90.00
01.02 CARTEL DE IDENTIFICACION DE OBRA Y PROMOCION DE OBRA und 1.00
01.03 CARTEL DE SEÑALIZACION PARA DESVIACION DE TRANSITO und 1.00
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Glb 1.00
02 TRABAJOS PRELIMINARES
02.01 TRAZO DE NIVELES Y REPLANTEO m2 2,284.08
02.02 TRAZO DE NIVELES Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA und 2,284.08
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE TERRENO CON MAQ. A NIVEL DE SUB RASANTE m3 701.99
03.02 EXCAVACION MANUAL m3 38.65
03.03 ACARREO INTERNO DE MATERIAL DE CORTE m3 48.31
03.04 CARGUIO DE MATERIAL EXCEDENTE m3 925.80
03.05 TRANSPORTE DE MATERIAL EXCEDENTE m3 925.80
04 EXPLANACIONES
04.01 ESCARIF. PERFIL. Y COMPACT. DE SUB RASANTE m2 1,626.00
05 SUB BASE GRANULAR
05.01 MATERIAL P/SUB BASE PUESTO EN OBRA m3 406.50
05.02 EXTENDIDO RIEGO Y COMPACTACION SUB-BASE E=0.20m. m2 1,626.00
06 PAVIMENTO RIGIDO
06.01 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO m2 160.13
06.02 CONCRETO FC=210 KG/CM2 EN PAVIMENTO m3 286.60
06.03 ACABADO EN PAVIMENTO RIGIDO m2 1,432.99
07 DOWELLS (JUNTA TRANSVERSAL)
07.01 JUNTA DE DILATACION kg 2,701.19
07.02 JUNTA DE CONSTRUCCION kg 198.01
08 CURADO DE PAVIMENTO RIGIDO
08.01 CURADO CON ARROCERAS m2 1,432.99
09 BADENES
09.01 ENCOFRADO Y DESENCOFRADO EN BADEN m2 10.22
09.02 CONCRETO FC=210 KG/CM2 EN BADEN INCL ACABADO m3 8.24
METRADOS EJECUTADOS ACERA PEATONAL

PROYECTO: "MEJORAMIENTO VIAL DEL JIRON MOQUEGUA Y ADYACENTES TRAMO JR. BOLOGNESI - AV. LA MARINA
DISTRITO DEL TAMBO - HUANCAYO - JUNIN"

ENTIDAD: MUNICIPALIDAD DISTRITAL DEL TAMBO


UBICACIÓN: JUNIN - HUANCAYO - EL TAMBO
CONTRATISTA:
SUPERVISOR:
PLAZO DE EJECUCION: 90 DIAS CALENDARIOS
VALOR REFERENCIAL: 336, 920.09

ITEM DESCRIPCION UND METRADO


PAVIMENTO RIGIDO
01 OBRAS PROVISIONALES
01.01 GUARDIANIA Y ALMACEN Dia 90.00
01.02 CARTEL DE IDENTIFICACION DE OBRA Y PROMOCION DE OBRA und 1.00
01.03 CARTEL DE SEÑALIZACION PARA DESVIACION DE TRANSITO und 1.00
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Glb 1.00
02 TRABAJOS PRELIMINARES
02.01 TRAZO DE NIVELES Y REPLANTEO m2 2,284.08
02.02 TRAZO DE NIVELES Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA und 2,284.08
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE TERRENO CON MAQ. A NIVEL DE SUB RASANTE m3 701.99
03.02 EXCAVACION MANUAL m3 38.65
03.03 ACARREO INTERNO DE MATERIAL DE CORTE m3 48.31
03.04 CARGUIO DE MATERIAL EXCEDENTE m3 925.80
03.05 TRANSPORTE DE MATERIAL EXCEDENTE m3 925.80
04 EXPLANACIONES
04.01 ESCARIF. PERFIL. Y COMPACT. DE SUB RASANTE m2 1,626.00
05 SUB BASE GRANULAR
05.01 MATERIAL P/SUB BASE PUESTO EN OBRA m3 406.50
05.02 EXTENDIDO RIEGO Y COMPACTACION SUB-BASE E=0.20m. m2 1,626.00
06 PAVIMENTO RIGIDO
06.01 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO m2 160.13
06.02 CONCRETO FC=210 KG/CM2 EN PAVIMENTO m3 286.60
06.03 ACABADO EN PAVIMENTO RIGIDO m2 1,432.99
07 DOWELLS (JUNTA TRANSVERSAL)
07.01 JUNTA DE DILATACION kg 2,701.19
07.02 JUNTA DE CONSTRUCCION kg 198.01
08 CURADO DE PAVIMENTO RIGIDO
08.01 CURADO CON ARROCERAS m2 1,432.99
09 BADENES
09.01 ENCOFRADO Y DESENCOFRADO EN BADEN m2 10.22
09.02 CONCRETO FC=210 KG/CM2 EN BADEN INCL ACABADO m3 8.24
METRADOS EJECUTADOS PAVIMENTO RIGIDO

PROYECTO: "MEJORAMIENTO VIAL DEL JIRON MOQUEGUA Y ADYACENTES TRAMO JR. BOLOGNESI - AV. LA MARINA
DISTRITO DEL TAMBO - HUANCAYO - JUNIN"

ENTIDAD: MUNICIPALIDAD DISTRITAL DEL TAMBO


UBICACIÓN: JUNIN - HUANCAYO - EL TAMBO
CONTRATISTA:
SUPERVISOR:
PLAZO DE EJECUCION: 90 DIAS CALENDARIOS
VALOR REFERENCIAL: 336, 920.09

ITEM DESCRIPCION UND METRADO


PAVIMENTO RIGIDO
01 OBRAS PROVISIONALES
01.01 GUARDIANIA Y ALMACEN Dia 90.00
01.02 CARTEL DE IDENTIFICACION DE OBRA Y PROMOCION DE OBRA und 1.00
01.03 CARTEL DE SEÑALIZACION PARA DESVIACION DE TRANSITO und 1.00
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Glb 1.00
02 TRABAJOS PRELIMINARES
02.01 TRAZO DE NIVELES Y REPLANTEO m2 2,284.08
02.02 TRAZO DE NIVELES Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA und 2,284.08
03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE TERRENO CON MAQ. A NIVEL DE SUB RASANTE m3 701.99
03.02 EXCAVACION MANUAL m3 38.65
03.03 ACARREO INTERNO DE MATERIAL DE CORTE m3 48.31
03.04 CARGUIO DE MATERIAL EXCEDENTE m3 925.80
03.05 TRANSPORTE DE MATERIAL EXCEDENTE m3 925.80
04 EXPLANACIONES
04.01 ESCARIF. PERFIL. Y COMPACT. DE SUB RASANTE m2 1,626.00
05 SUB BASE GRANULAR
05.01 MATERIAL P/SUB BASE PUESTO EN OBRA m3 406.50
05.02 EXTENDIDO RIEGO Y COMPACTACION SUB-BASE E=0.20m. m2 1,626.00
06 PAVIMENTO RIGIDO
06.01 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO m2 160.13
06.02 CONCRETO FC=210 KG/CM2 EN PAVIMENTO m3 286.60
06.03 ACABADO EN PAVIMENTO RIGIDO m2 1,432.99
07 DOWELLS (JUNTA TRANSVERSAL)
07.01 JUNTA DE DILATACION kg 2,701.19
07.02 JUNTA DE CONSTRUCCION kg 198.01
08 CURADO DE PAVIMENTO RIGIDO
08.01 CURADO CON ARROCERAS m2 1,432.99
09 BADENES
09.01 ENCOFRADO Y DESENCOFRADO EN BADEN m2 10.22
09.02 CONCRETO FC=210 KG/CM2 EN BADEN INCL ACABADO m3 8.24