20,380.12
1.3 ENSAYOS
4,120.00
28,800.00
75,600.00
2.2.2 ALIMENTACION
INGENIERO 1 500.00 7.00 3,500.00
MAESTRO DE OBRA 1 500.00 7.00 3,500.00
7,000.00
2.2.3 OTROS
CAMIONETA 7.00 3,000.00 21,000.00
UTILES PARA OBRA 1.00 2,350.66 2,350.66
23,350.66
COSTO DIRECTO
ESTRUCTURAS 3,630,925.94
ARQUITECTURA 2,469,419.03
SANITARIAS 213,472.89
ELECTRICAS Y MECANICAS 359,575.51
COSTO DIRECTO OBRA 6,673,393.37
SUBTOTAL 7,674,402.38
IGV (18%) 18.00% 1,381,392.43
VALOR REFERENCIAL: 9,055,794.81
SUPERVISION Y LIQUIDACION DE SUPERVISION 360,632.32
PLAN DE CONTINGENCIA 172,042.64
MOBILIARIO Y EQUIPAMIENTO 654,324.98
COSTO TOTAL 10,242,794.75
GASTOS FIJOS
1.1. VARIOS
DESCRIPCION UNIDAD CANTIDAD PRECIO PARCIAL
PLANOS DE REPLANTEO EST 1 5,000.00 5,000.00
NOTARIALES 1,743.82
CARTA FIANZA
N= 9,449,525.01 (COSTO TOTAL SIN MOBILIARIO)
DURACION (MESES) = 6
MONTO AFIANZADO = 10% + 10% + 20% = 0.40 N
CARTA FIANZA = (1x2.00x0.40N)/100 = 0.008 N 75,596.20
SENCICO
0.20% 0.002N 18,899.05
202,436.51
SUBTOTAL 197,000.00
2.3. MOBILIARIO
DESCRIPCION UND CANTIDAD PRECIO PARCIAL
PIZARRA ACRILICA DE 1.20 X 3.00 GLB 1.00 250.00 250.00
MOBILIARIO PARA OFICINA GLB 1.00 2,184.96 2,184.96
2,434.96
COSTO DIRECTO
OBRAS PRELIMINARES 98,472.04
ESTRUCTURAS 2,063,284.31
ARQUITECTURA 1,043,247.50
SANITARIAS 309,115.46
ELECTRICAS Y MECANICAS 735,966.33
COSTO DIRECTO OBRA 4,250,085.64
MITIGACION 37,345.07
PLAN DE CONTINGENCIA 7,237.00
MOBILIARIO Y EQUIPAMIENTO 1,138,888.91
CAPACITACION 22,615.20
COSTO DIRECTO DE OBRA INCL. SUB-PRESUPUESTOS 5,456,171.82
SUBTOTAL 6,376,572.85
IGV (18%) 18.00% 1,147,783.11
VALOR REFERENCIAL: 7,524,355.96
SUPERVISION Y LIQUIDACION DE SUPERVISION 320,925.00
EXPEDIENTE TECNICO 170,704.00
COSTO TOTAL 8,015,984.96
GASTOS FIJOS
1.1. VARIOS
DESCRIPCION UNIDAD CANTIDAD PRECIO PARCIAL
PLANOS DE REPLANTEO MOBILIARIO EST 1 1,444.45 1,444.45
ALMACEN DE MATERIAL MES 2 2,500.00 5,000.00
6,444.45
GASTOS VARIABLES
SUBTOTAL 9,000.00
2.3. MOBILIARIO
DESCRIPCION UND CANTIDAD PRECIO PARCIAL
TARIMAS PARA SOPORTE DE MOBILIARIO MES 2.00 750.00 1,500.00
COMPUTADOR PERSONAL MES 2.00 2,000.00 4,000.00
ALQUILER DE ALMACEN PARA MOBILIARIO MES 2.00 3,500.00 7,000.00
02 UNDS CAMIONETA (TRASLADO DE MOBILIARIO) MES 2.00 7,000.00 14,000.00
26,500.00
COSTO DIRECTO
OBRAS PRELIMINARES 90,906.20
ESTRUCTURAS 1,501,032.77
ARQUITECTURA 962,804.19
SANITARIAS 189,160.71
ELECTRICAS Y MECANICAS 151,447.48
COSTO DIRECTO OBRA 2,895,351.35
SUBTOTAL 3,329,654.05
IGV (18%) 18.00% 599,337.73
VALOR REFERENCIAL: 3,928,991.78
SUPERVISION Y LIQUIDACION 289,535.14
MITIGACION 25,452.15
PLAN DE CONTINGENCIA 14,078.00
MOBILIARIO 165,560.20
EXPEDIENTE TECNICO 170,704.00
CAPACITACION 22,615.20
COSTO TOTAL 4,616,936.47
TIEMPO DE EJECUCION: 150 Días calendarios
GASTOS FIJOS
1.1. VARIOS
DESCRIPCION UNIDAD CANTIDAD PRECIO PARCIAL
PLANOS DE REPLANTEO EST 1 3,084.13 3,084.13
MOVILIDADES PARA OBRA GLB 1 15,000.00 15,000.00
18,084.13
GASTOS VARIABLES
SUBTOTAL 185,000.00
2.2. PERSONAL TECNICO
DESCRIPCION UND CANTIDAD PRECIO PARCIAL
TOPOGRAFO MES 5.00 5,000.00 25,000.00
AYUDANTES TOPOGRAFIA MES 5.00 2,500.00 12,500.00
37,500.00
2.3. MOBILIARIO
DESCRIPCION UND CANTIDAD PRECIO PARCIAL
PIZARRA ACRILICA DE 1.20 X 3.00 MES 2.00 272.50 545.00
COMPUTADOR PERSONAL GLB 3.00 2,973.33 8,920.00
ALQUILER DE OFICINA MES 5.00 1,110.00 5,550.00
15,015.00
17,551.21
1.2 ENSAYOS
4,120.00
20,650.00
63,700.00
2.2.3 OTROS
CAMIONETA 7.00 2,400.00 16,800.00
TOPOGRAFIA 1.00 1,203.83 1,203.83
18,003.83