ANALISIS DE REDUCCION
PRESUPUESTO VIGENTE ACUMULADO ANTERIOR PRESENTE VALORIZACION ACUMULADO ACTUAL SALDO POR VALORIZAR
ITEM DESCRIPCION UND. METRADO PRECIO MONTO METRADO MONTO % DE METRADO MONTO % DE METRADO MONTO % DE SALDO DE MONTO % DE
CONTRATO UNITARIO S/. ANTERIOR S/. AVANCE DEL MES S/. AVANCE ACUMULADO S/. AVANCE METRADO S/. AVANCE
1 ESTRUCTURAS
01.05.09 ESCALERAS - - - - -
01.05.09.01 ESCALERAS, CONCRETO F'C=210 kg/cm2 m3 15.89 389.23 6,184.86 15.89 6,184.86 100.00% -1.54 -599.41 -9.69% 14.35 5,585.45 90.31% 1.54 599.41 9.69%
01.05.09.02 ESCALERAS, ENCOFRADO Y DESENCOFRADO m2 98.75 57.06 5,634.68 98.75 5,634.68 100.00% -1.01 -57.63 -1.02% 97.74 5,577.04 98.98% 1.01 57.63 1.02%
01.06 VARIOS - - - - -
01.06.02 JUNTA DE DILATACION C/TEKNOPORT Y SELLANTE ELASTOMERICO m 175.24 30.48 5,341.32 175.24 5,341.32 100.00% -1.60 -48.77 -0.91% 173.64 5,292.55 99.09% 1.60 48.77 0.91%
02 ARQUITECTURA - - - - -
02.01 MUROS Y TABIQUES DE ALBAÑILERIA - - - - -
02.01.01 MURO DE LADRILLO KK CABEZA M:1:1:4 e=1.5 cm m2 1,851.72 106.30 196,837.84 1,851.35 196,798.29 99.98% -4.15 -441.15 -0.22% 1,847.20 196,357.15 99.76% 4.52 480.69 0.24%
02.02 REVOQUES, ENLUCIDOS Y REVESTIMIENTOS - - - - -
02.02.02 TARRAJEO EN EXTERIORES ACABADO CEMENTO-ARENA m2 1,391.19 22.11 30,759.21 1,391.19 30,759.21 100.00% -7.33 -162.07 -0.53% 1,383.86 30,597.14 99.47% 7.33 162.07 0.53%
02.02.05 VESTIDURA DE DERRAMES m 808.83 14.43 11,671.42 808.83 11,671.42 100.00% -12.22 -176.33 -1.51% 796.61 11,495.08 98.49% 12.22 176.33 1.51%
02.04 PISOS Y PAVIMENTOS - - - - -
02.04.02 PISO PORCELANATO 0.60 m. x 0.60 m. ALTO TRANSITO m2 2,363.55 50.97 120,470.14 2,363.55 120,470.14 100.00% -6.35 -323.66 -0.27% 2,357.20 120,146.48 99.73% 6.35 323.66 0.27%
02.06 ZOCALOS Y CONTRAZOCALOS - - - - -
02.06.02 CONTRAZOCALO DE PORCELANATO DE H=10 cm m 1,176.48 24.81 29,188.47 1,176.48 29,188.47 100.00% -8.26 -204.93 -0.70% 1,168.22 28,983.54 99.30% 8.26 204.93 0.70%
02.06.03 CANTONERA DE ALUMINIO m 121.80 24.52 2,986.54 121.80 2,986.54 100.00% -9.00 -220.68 -7.39% 112.80 2,765.86 92.61% 9.00 220.68 7.39%
02.07 REVESTIMIENTO DE GRADAS, ESCALERAS Y RAMPAS - - - - -
02.07.01 REVESTIMIENTO C/CEMENTO PULIDO PASO Y CONTRAPASO m 145.00 34.89 5,059.05 145.00 5,059.05 100.00% -5.07 -176.89 -3.50% 139.93 4,882.16 96.50% 5.07 176.89 3.50%
02.07.02 REVESTIMIENTO C/CEMENTO PULIDO EN DESCANSOS C:A, 1:5 m2 29.56 28.37 838.62 29.56 838.62 100.00% -1.17 -33.19 -3.96% 28.39 805.42 96.04% 1.17 33.19 3.96%
02.10 CARPINTERIA METALICA Y HERRERIA - - - - -
02.10.01 BARANDA METALICA H=1.00m INC/COLOCADO m 248.40 184.46 45,819.86 248.40 45,819.86 100.00% -2.62 -483.29 -1.05% 245.78 45,336.58 98.95% 2.62 483.29 1.05%
02.13 PINTURA - - - - -
02.13.04 PINTURA LATEX SUPERMATE EN EXTERIORES m2 1,391.19 14.19 19,740.99 1,391.19 19,740.99 100.00% -7.33 -104.01 -0.53% 1,383.86 19,636.97 99.47% 7.33 104.01 0.53%