CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

PROYECTO: "CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE
OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

PRIMERA ETAPA DE EJECUCION TRAMOS I: GEUNOEPAMPA – HUARISCA

DEPARTAMENTO: HUANCAVELICA PROVINCIA: TAYACAJA DISTRITO: QUICHUAS

MES 01 MES 02 MES 03


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) INICICIO 12/04/2021 INICICIO 01/05/2021 INICICIO 01/06/2021
TERMINA 30/04/2021 TERMINA 31/05/2021 TERMINA 10/06/2021
COSTO % COSTO % COSTO %
01 TRAMO I GEUNOEPAMPA - HUARISCA 240,492.50 S/. 154,084.44 64.07% S/. 85,408.58 35.51% S/. 1,199.48 0.50%
01.01 OBRAS PROVISIONALES 6,464.46
01.01.01 ALMACEN, OFICINA Y GUARDIANIA mes 3.50 400.00 1,400.00 S/. 466.67 33.33% S/. 466.67 33.33% S/. 466.67 33.33%
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA glb 1.00 400.00 400.00 S/. 400.00 100.00%
01.01.03 LIMPIEZA Y DEFORESTACION MANUAL m2 8,480.84 0.55 4,664.46 S/. 500.00 10.72% S/. 2,082.23 44.64% S/. 2,082.23 44.64%
01.02 OBRAS PRELIMINARES 8,960.83
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 4,885.45 4,885.45 S/. 2,442.73 50.00% S/. 2,442.73 50.00%
01.02.02 TRAZO Y REPLANTEO INICAL km 2.12 1,083.51 2,297.04 S/. 2,297.04 100.00%
01.02.03 TRAZO Y REPLANTEO (EJECUCION DE OBRA) km 2.12 838.84 1,778.34 S/. 592.78 33.33% S/. 592.78 33.33% S/. 592.78 33.33%
01.03 MOVIMIENTO DE TIERRAS 194,736.11
01.03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA m3 8,351.89 2.69 22,466.58 S/. 3,500.00 15.58% S/. 9,483.29 42.21% S/. 9,483.29 42.21%
01.03.02 TRANSPORTE DE MATERIAL EXCEDENTE (ELIMINACION) m3 8,500.00 4.48 38,080.00 S/. 500.00 1.31% S/. 18,790.00 49.34% S/. 18,790.00 49.34%
01.03.03 CORTE ROCA SUELTO (PERF. Y DISP.) m3 2,443.20 16.52 40,361.66 S/. 5,000.00 12.39% S/. 17,680.83 43.81% S/. 17,680.83 43.81%
01.03.04 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA m3 2,443.20 5.54 13,535.33 S/. 2,200.00 16.25% S/. 5,667.67 41.87% S/. 5,667.67 41.87%
01.03.05 CORTE ROCA FIJA (PERF. Y DISP.) m3 965.11 18.98 18,317.79 S/. 120.00 0.66% S/. 9,098.90 49.67% S/. 9,098.90 49.67%
01.03.06 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA m3 965.11 5.90 5,694.15 S/. 700.00 12.29% S/. 2,497.08 43.85% S/. 2,497.08 43.85%
01.03.07 RELLENO CON MATERIAL PROPIO CON MAQUINARIA m3 3,260.20 8.09 26,375.02 S/. 5,000.00 18.96% S/. 10,687.51 40.52% S/. 10,687.51 40.52%
01.03.08 PERFILADO Y COMPACTACION SUB-RASANTES ZONAS CORTE m2 7,420.74 4.03 29,905.58 S/. 29,905.58 100.00%
01.04 OBRAS DE ARTE Y DRENAJE 19,254.37
01.04.01 ALCANTARILLA DE TIPO I (1 UND) 3,720.50
01.04.01.01 LIMPIEZA DEL TERRENO MANUAL m2 10.80 0.50 5.40 S/. 5.40 100.00%
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 10.80 2.26 24.41 S/. 24.41 100.00%
01.04.01.03 EXCAVACION DE MATERIAL COMPACTO PARA ESTRUCTURAS m3 3.55 36.74 130.43 S/. 130.43 100.00%
01.04.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 4.43 31.49 139.50 S/. 139.50 100.00%
01.04.01.05 ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 kg 86.39 5.29 457.00 S/. 457.00 100.00%
01.04.01.06 CONCRETO f'c=210Kg/cm2 EN ALCANTARILLAS m3 1.11 592.44 657.61 S/. 657.61 100.00%
01.04.01.07 CONCRETO CICLOPEO Fc=175kg/cm2 + 35% PM. EN ALCANTARILLAS m3 2.56 394.46 1,009.82 S/. 1,009.82 100.00%
01.04.01.08 ENCOFRADO Y DESENCOFRADO m2 18.61 51.08 950.60 S/. 950.60 100.00%
01.04.01.09 EMBOQUILLADO PARA LOSA DE ENCAUSAMIENTO m3 0.55 390.16 214.59 S/. 214.59 100.00%
01.04.01.10 TARRAJEO EXTERIOR CON MORTERO 1.5 x 1.5 CM. m2 7.43 17.65 131.14 S/. 131.14 100.00%
01.04.03 CUNETAS LATERALES (SIN REVESTIR) 14,481.03
01.04.03.01 CUNETA TRIANGULARES H=0.30, B=0.50 m 2,120.21 6.83 14,481.03 S/. 6,000.00 41.43% S/. 8,481.03 58.57%
01.04.04 SEÑALIZACION 1,052.84
01.04.04.01 POSTES KILOMETRICOS und 4.00 113.39 453.56 S/. 285.74 63.00% S/. 167.82 37.00%
01.04.04.02 SEÑAL IMFORMATIVA und 1.00 599.28 599.28 S/. 599.28 100.00%
01.05 CONTROL DE CALIDAD 490.00
01.05.01 DISEÑO DEL MEZCLA und 1.00 350.00 350.00 S/. 350.00 100.00%
01.05.02 PRUEBA A LA COMPRESION und 4.00 35.00 140.00 S/. 140.00 100.00%
01.06 MANTENIMIENTO DE MAQUINARIA 6,000.00
01.06.01 MANTENIMIENTO DE MAQUINARIAS glb 1.00 6,000.00 6,000.00 S/. 6,000.00 100.00%
01.07 MITIGACION E IMPACTO AMBIENTAL 1,377.20
01.07.01 RESTAURACION DE AREAS AFECTADA POR CAMPAMENTOS, PATIO DE MAQUINAS m2 120.00 3.61 433.20 S/. 433.20 100.00%
01.07.02 REVEGETACION / REFOSTERACION m2 1,600.00 0.59 944.00 S/. 944.00 100.00%
01.08 FLETE 3,209.53
01.08.01 TRANSPORTE DE MATERIALES. glb 1.00 3,209.53 3,209.53 S/. 1,069.84 33.33% S/. 1,069.84 33.33% S/. 1,069.84 33.33%
COSTO DIRECTO (1) 240,492.50 30,789.06 12.80% 118,378.61 49.22% 91,324.84 37.97%
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

PROYECTO: "CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE
OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

PRIMERA ETAPA DE EJECUCION TRAMOS I: GEUNOEPAMPA – HUARISCA

DEPARTAMENTO: HUANCAVELICA PROVINCIA: TAYACAJA DISTRITO: QUICHUAS

MES 01 MES 02 MES 03


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) INICICIO 12/04/2021 INICICIO 01/05/2021 INICICIO 01/06/2021
TERMINA 30/04/2021 TERMINA 31/05/2021 TERMINA 10/06/2021
COSTO % COSTO % COSTO %
GASTOS GENERALES (2) 5.41% 13,000.00 S/. 1,664.33 S/. 6,399.04 S/. 4,936.63

SUB TOTAL (1+2) 253,492.50 S/. 32,453.38 S/. 124,777.65 S/. 96,261.47
TOTAL DE PRESUPUESTO 253,492.50 S/. 32,453.38 S/. 124,777.65 S/. 96,261.47
PORCENTAJE DE AVANCE DE OBRA PROGRAMADO 12.80% 49.22% 37.97%
PORCETNAJE DE AVANCE DE OBRA ACUMULADO 12.80% 62.03% 100.00%
RESUMEN DE METAS EJECUTADOS VALORIZACION N° 01- ABRIL
(12/04/2021 AL 30/04/2021)

Items PARTIDAS ACTUAL


Metrado Valorizado %
01 TRAMO I GEUNOEPAMPA - HUARISCA
01.01 OBRAS PROVISIONALES
01.01.01 ALMACEN, OFICINA Y GUARDIANIA 0.35 S/. 140.00 10.00%
01.01.03 LIMPIEZA Y DEFORESTACION MANUAL 4,000.00 S/. 2,200.00 47.17%
01.02 OBRAS PRELIMINARES
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 0.50 S/. 2,442.73 50.00%
01.02.02 TRAZO Y REPLANTEO INICAL 1.28 S/. 1,381.48 60.14%
01.02.03 TRAZO Y REPLANTEO (EJECUCION DE OBRA) 1.28 S/. 1,069.52 60.14%
01.03 MOVIMIENTO DE TIERRAS
01.03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA 1,493.18 S/. 4,016.66 17.88%
01.03.03 CORTE ROCA SUELTO (PERF. Y DISP.) 511.06 S/. 8,442.65 20.92%
01.03.04 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA 511.06 S/. 2,831.25 20.92%
01.03.05 CORTE ROCA FIJA (PERF. Y DISP.) 19.01 S/. 360.85 1.97%
01.03.06 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA 19.01 S/. 112.17 1.97%
01.03.07 RELLENO CON MATERIAL PROPIO CON MAQUINARIA 1,121.10 S/. 9,069.70 34.39%
01.06.01 MANTENIMIENTO DE MAQUINARIAS 1.00 S/. 6,000.00 100.00%
01.08 FLETE
01.08.01 TRANSPORTE DE MATERIALES. 0.50 S/. 1,604.77 50.00%
CUADRO COMPARATIVO METRADO PROGRAMADO VS EJECUTADO
VALORIZACION N° 02- MAYO (01/05/2021 AL 31/05/2021)

OBRA:
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE
QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE QUICHUAS FECHA DE INICIO DE OBRA Lunes 12 de abril el 2021
MODALIDAD DE EJECUCIÓN ADMINISTRACION DIRECTA FECHA DE CULMINACION DE OBRA Jueves, 10 de Junio del 2021
RESIDENTE ING. ROGER BENDEZU DE LA CRUZ CORRESPONDIENTE AL MES DE MAYO DEL2021
SUPERVISOR ING. JACK M. PUMACAHUA QUISPE FECHA DE PRESENTACION 01 de Junio del 2021

AVANCE
PRESUPUESTO SALDO
Items PARTIDAS ANTERIOR ACTUAL ACUMULADO
Unid Metrado Precio PARCIAL Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01 TRAMO I GEUNOEPAMPA - HUARISCA 240,492.50
01.01 OBRAS PROVISIONALES 6,464.46
01.01.01 ALMACEN, OFICINA Y GUARDIANIA mes 3.50 400.00 1,400.00 0.35 S/. 140.00 10.00% 0.35 S/. 140.00 10.00% 0.70 S/. 280.00 20.00% 2.80 S/. 1,120.00 80.00%
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA glb 1.00 400.00 400.00 S/. 0.00 0.00% 1.00 S/. 400.00 100.00% 1.00 S/. 400.00 100.00% - S/. 0.00 0.00%
01.01.03 LIMPIEZA Y DEFORESTACION MANUAL m2 8,480.84 0.55 4,664.46 3,444.84 S/. 1,894.66 40.62% 3,444.84 S/. 1,894.66 40.62% 6,889.68 S/. 3,789.32 81.24% 1,591.16 S/. 875.14 18.76%
01.02 OBRAS PRELIMINARES 8,960.83
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 4,885.45 4,885.45 0.50 S/. 2,442.73 50.00% - S/. 0.00 0.00% 0.50 S/. 2,442.73 50.00% 0.50 S/. 2,442.73 50.00%
01.02.02 TRAZO Y REPLANTEO INICAL km 2.12 1,083.51 2,297.04 0.86 S/. 933.13 40.62% 0.58 S/. 629.75 27.42% 1.44 S/. 1,562.88 68.04% 0.68 S/. 734.16 31.96%
01.02.03 TRAZO Y REPLANTEO (EJECUCION DE OBRA) km 2.12 838.84 1,778.34 0.86 S/. 722.42 40.62% 0.58 S/. 487.54 27.42% 1.44 S/. 1,209.96 68.04% 0.68 S/. 568.38 31.96%
01.03 MOVIMIENTO DE TIERRAS 194,736.11
01.03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA m3 8,351.89 2.69 22,466.58 1,493.18 S/. 4,016.66 17.88% 5,617.40 S/. 15,110.79 67.26% 7,110.58 S/. 19,127.45 85.14% 1,241.31 S/. 3,339.13 14.86%
01.03.02 TRANSPORTE DE MATERIAL EXCEDENTE (ELIMINACION) m3 8,500.00 4.48 38,080.00 S/. 0.00 0.00% 7,470.94 S/. 33,469.79 87.89% 7,470.94 S/. 33,469.79 87.89% 1,029.06 S/. 4,610.21 12.11%
01.03.03 CORTE ROCA SUELTO (PERF. Y DISP.) m3 2,443.20 16.52 40,361.66 511.06 S/. 8,442.65 20.92% 1,853.54 S/. 30,620.50 75.87% 2,364.60 S/. 39,063.15 96.78% 78.60 S/. 1,298.51 3.22%
01.03.04 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA m3 2,443.20 5.54 13,535.33 511.06 S/. 2,831.25 20.92% 1,853.54 S/. 10,268.62 75.87% 2,364.60 S/. 13,099.87 96.78% 78.60 S/. 435.46 3.22%
01.03.05 CORTE ROCA FIJA (PERF. Y DISP.) m3 965.11 18.98 18,317.79 19.01 S/. 360.85 1.97% 941.68 S/. 17,873.14 97.57% 960.70 S/. 18,233.99 99.54% 4.42 S/. 83.80 0.46%
01.03.06 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA m3 965.11 5.90 5,694.15 19.01 S/. 112.17 1.97% 941.68 S/. 5,555.93 97.57% 960.70 S/. 5,668.10 99.54% 4.42 S/. 26.05 0.46%
01.03.07 RELLENO CON MATERIAL PROPIO CON MAQUINARIA m3 3,260.20 8.09 26,375.02 1,121.10 S/. 9,069.70 34.39% 1,948.10 S/. 15,760.12 59.75% 3,069.20 S/. 24,829.82 94.14% 191.00 S/. 1,545.20 5.86%
01.03.08 PERFILADO Y COMPACTACION SUB-RASANTES ZONAS CORTE m2 7,420.74 4.03 29,905.58 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 7,420.74 S/. 29,905.58 100.00%
01.04 OBRAS DE ARTE Y DRENAJE 19,254.37
01.04.01 ALCANTARILLA DE TIPO I (1 UND) 3,720.50
01.04.01.01 LIMPIEZA DEL TERRENO MANUAL m2 10.80 0.50 5.40 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 10.80 S/. 5.40 100.00%
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 10.80 2.26 24.41 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 10.80 S/. 24.41 100.00%
01.04.01.03 EXCAVACION DE MATERIAL COMPACTO PARA ESTRUCTURAS m3 3.55 36.74 130.43 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 3.55 S/. 130.43 100.00%
01.04.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 4.43 31.49 139.50 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.43 S/. 139.50 100.00%
01.04.01.05 ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 kg 86.39 5.29 457.00 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 86.39 S/. 457.00 100.00%
01.04.01.06 CONCRETO f'c=210Kg/cm2 EN ALCANTARILLAS m3 1.11 592.44 657.61 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.11 S/. 657.61 100.00%
01.04.01.07 CONCRETO CICLOPEO Fc=175kg/cm2 + 35% PM. EN ALCANTARILLAS m3 2.56 394.46 1,009.82 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 2.56 S/. 1,009.82 100.00%
01.04.01.08 ENCOFRADO Y DESENCOFRADO m2 18.61 51.08 950.60 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 18.61 S/. 950.60 100.00%
01.04.01.09 EMBOQUILLADO PARA LOSA DE ENCAUSAMIENTO m3 0.55 390.16 214.59 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 0.55 S/. 214.59 100.00%
01.04.01.10 TARRAJEO EXTERIOR CON MORTERO 1.5 x 1.5 CM. m2 7.43 17.65 131.14 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 7.43 S/. 131.14 100.00%
01.04.03 CUNETAS LATERALES (SIN REVESTIR) 14,481.03
01.04.03.01 CUNETA TRIANGULARES H=0.30, B=0.50 m 2,120.21 6.83 14,481.03 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 2,120.21 S/. 14,481.03 100.00%
01.04.04 SEÑALIZACION 1,052.84
01.04.04.01 POSTES KILOMETRICOS und 4.00 113.39 453.56 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 453.56 100.00%
01.04.04.02 SEÑAL IMFORMATIVA und 1.00 599.28 599.28 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 599.28 100.00%
01.05 CONTROL DE CALIDAD 490.00 S/. 0.00 0.00%
01.05.01 DISEÑO DEL MEZCLA und 1.00 350.00 350.00 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 350.00 100.00%
01.05.02 PRUEBA A LA COMPRESION und 4.00 35.00 140.00 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 140.00 100.00%
01.06 MANTENIMIENTO DE MAQUINARIA 6,000.00
01.06.01 MANTENIMIENTO DE MAQUINARIAS glb 1.00 6,000.00 6,000.00 1.00 S/. 6,000.00 100.00% - S/. 0.00 0.00% 1.00 S/. 6,000.00 100.00% - S/. 0.00 0.00%
01.07 MITIGACION E IMPACTO AMBIENTAL 1,377.20
01.07.01 RESTAURACION DE AREAS AFECTADA POR CAMPAMENTOS, PATIO DE MAQUI m2 120.00 3.61 433.20 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 120.00 S/. 433.20 100.00%
01.07.02 REVEGETACION / REFOSTERACION m2 1,600.00 0.59 944.00 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1,600.00 S/. 944.00 100.00%
01.08 FLETE 3,209.53
01.08.01 TRANSPORTE DE MATERIALES. glb 1.00 3,209.53 3,209.53 0.50 S/. 1,604.77 50.00% 0.40 S/. 1,283.81 40.00% 0.90 S/. 2,888.58 90.00% 0.10 S/. 320.95 10.00%
RESUMEN DE METAS EJECUTADOS VALORIZACION N° 02- MAYO
(01/05/2021 AL 31/05/2021)

AVANCE
Items PARTIDAS ACTUAL
Metrado Valorizado %
01 TRAMO I GEUNOEPAMPA - HUARISCA
01.01 OBRAS PROVISIONALES
01.01.01 ALMACEN, OFICINA Y GUARDIANIA 1.00 S/. 400.00 28.57%
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA 1.00 S/. 400.00 100.00%
01.01.03 LIMPIEZA Y DEFORESTACION MANUAL 3,444.84 S/. 1,894.66 40.62%
01.02 OBRAS PRELIMINARES
01.02.02 TRAZO Y REPLANTEO INICAL 0.58 S/. 629.75 27.42%
01.02.03 TRAZO Y REPLANTEO (EJECUCION DE OBRA) 0.58 S/. 487.54 27.42%
01.03 MOVIMIENTO DE TIERRAS
01.03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA 5,617.40 S/. 15,110.79 67.26%
01.03.02 TRANSPORTE DE MATERIAL EXCEDENTE (ELIMINACION) 7,470.94 S/. 33,469.79 87.89%
01.03.03 CORTE ROCA SUELTO (PERF. Y DISP.) 1,853.54 S/. 30,620.50 75.87%
01.03.04 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA 1,853.54 S/. 10,268.62 75.87%
01.03.05 CORTE ROCA FIJA (PERF. Y DISP.) 941.68 S/. 17,873.14 97.57%
01.03.06 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA 941.68 S/. 5,555.93 97.57%
01.03.07 RELLENO CON MATERIAL PROPIO CON MAQUINARIA 1,948.10 S/. 15,760.12 59.75%
01.08 FLETE
01.08.01 TRANSPORTE DE MATERIALES. 0.40 S/. 1,283.81 40.00%
CUADRO COMPARATIVO METRADO PROGRAMADO VS EJECUTADO
VALORIZACION N° 03- JUNIO (01/06/2021 AL 10/06/2021)

OBRA:
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE
QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE QUICHUAS FECHA DE INICIO DE OBRA Lunes 12 de abril el 2021
MODALIDAD DE EJECUCIÓN ADMINISTRACION DIRECTA FECHA DE CULMINACION DE OBRA Jueves, 10 de Junio del 2021
RESIDENTE ING. ROGER BENDEZU DE LA CRUZ CORRESPONDIENTE AL MES DE JUNIO DEL2021
SUPERVISOR ING. JACK M. PUMACAHUA QUISPE FECHA DE PRESENTACION 30 de junio del 2021

AVANCE
PRESUPUESTO SALDO
Items PARTIDAS ANTERIOR ACTUAL ACUMULADO
Unid Metrado Precio PARCIAL Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01 TRAMO I GEUNOEPAMPA - HUARISCA 240,492.50
01.01 OBRAS PROVISIONALES 6,464.46
01.01.01 ALMACEN, OFICINA Y GUARDIANIA mes 3.50 400.00 1,400.00 1.35 S/. 540.00 38.57% 0.65 S/. 260.00 18.57% 2.00 S/. 800.00 57.14% 1.50 S/. 600.00 42.86%
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA glb 1.00 400.00 400.00 1.00 S/. 400.00 100.00% - S/. 0.00 0.00% 1.00 S/. 400.00 100.00% - S/. 0.00 0.00%
01.01.03 LIMPIEZA Y DEFORESTACION MANUAL m2 8,480.84 0.55 4,664.46 7,444.84 S/. 4,094.66 87.78% - S/. 0.00 0.00% 7,444.84 S/. 4,094.66 87.78% 1,036.00 S/. 569.80 12.22%
01.02 OBRAS PRELIMINARES 8,960.83
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 4,885.45 4,885.45 0.50 S/. 2,442.73 50.00% 0.50 S/. 2,442.73 50.00% 1.00 S/. 4,885.45 100.00% - S/. 0.00 0.00%
01.02.02 TRAZO Y REPLANTEO INICAL km 2.12 1,083.51 2,297.04 1.86 S/. 2,011.22 87.56% 0.26 S/. 285.82 12.44% 2.12 S/. 2,297.04 100.00% - S/. -0.00 0.00%
01.02.03 TRAZO Y REPLANTEO (EJECUCION DE OBRA) km 2.12 838.84 1,778.34 1.86 S/. 1,557.06 87.56% 0.26 S/. 221.28 12.44% 2.12 S/. 1,778.34 100.00% - S/. -0.00 0.00%
01.03 MOVIMIENTO DE TIERRAS 194,736.11
01.03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA m3 8,351.89 2.69 22,466.58 7,110.58 S/. 19,127.45 85.14% 762.53 S/. 2,051.21 9.13% 7,873.11 S/. 21,178.66 94.27% 478.78 S/. 1,287.92 5.73%
01.03.02 TRANSPORTE DE MATERIAL EXCEDENTE (ELIMINACION) m3 8,500.00 4.48 38,080.00 7,470.94 S/. 33,469.79 87.89% 841.13 S/. 3,768.28 9.90% 8,312.07 S/. 37,238.07 97.79% 187.93 S/. 841.93 2.21%
01.03.03 CORTE ROCA SUELTO (PERF. Y DISP.) m3 2,443.20 16.52 40,361.66 2,364.60 S/. 39,063.15 96.78% 78.60 S/. 1,298.51 3.22% 2,443.20 S/. 40,361.66 100.00% - S/. -0.00 0.00%
01.03.04 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA m3 2,443.20 5.54 13,535.33 2,364.60 S/. 13,099.87 96.78% 78.60 S/. 435.46 3.22% 2,443.20 S/. 13,535.33 100.00% - S/. 0.00 0.00%
01.03.05 CORTE ROCA FIJA (PERF. Y DISP.) m3 965.11 18.98 18,317.79 960.70 S/. 18,233.99 99.54% 4.42 S/. 83.80 0.46% 965.11 S/. 18,317.79 100.00% - S/. 0.00 0.00%
01.03.06 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA m3 965.11 5.90 5,694.15 960.70 S/. 5,668.10 99.54% 4.42 S/. 26.05 0.46% 965.11 S/. 5,694.15 100.00% - S/. 0.00 0.00%
01.03.07 RELLENO CON MATERIAL PROPIO CON MAQUINARIA m3 3,260.20 8.09 26,375.02 3,069.20 S/. 24,829.82 94.14% - S/. 0.00 0.00% 3,069.20 S/. 24,829.82 94.14% 191.00 S/. 1,545.20 5.86%
01.03.08 PERFILADO Y COMPACTACION SUB-RASANTES ZONAS CORTE m2 7,420.74 4.03 29,905.58 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 7,420.74 S/. 29,905.58 100.00%
01.04 OBRAS DE ARTE Y DRENAJE 19,254.37
01.04.01 ALCANTARILLA DE TIPO I (1 UND) 3,720.50
01.04.01.01 LIMPIEZA DEL TERRENO MANUAL m2 10.80 0.50 5.40 - S/. 0.00 0.00% 10.80 S/. 5.40 100.00% 10.80 S/. 5.40 100.00% - S/. 0.00 0.00%
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 10.80 2.26 24.41 - S/. 0.00 0.00% 10.80 S/. 24.41 99.99% 10.80 S/. 24.41 99.99% - S/. 0.00 0.00%
01.04.01.03 EXCAVACION DE MATERIAL COMPACTO PARA ESTRUCTURAS m3 3.55 36.74 130.43 - S/. 0.00 0.00% 3.55 S/. 130.43 100.00% 3.55 S/. 130.43 100.00% - S/. 0.00 0.00%
01.04.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 4.43 31.49 139.50 - S/. 0.00 0.00% 4.43 S/. 139.50 100.00% 4.43 S/. 139.50 100.00% - S/. 0.00 0.00%
01.04.01.05 ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 kg 86.39 5.29 457.00 - S/. 0.00 0.00% 86.39 S/. 457.00 100.00% 86.39 S/. 457.00 100.00% - S/. -0.00 0.00%
01.04.01.06 CONCRETO f'c=210Kg/cm2 EN ALCANTARILLAS m3 1.11 592.44 657.61 - S/. 0.00 0.00% 1.11 S/. 657.61 100.00% 1.11 S/. 657.61 100.00% - S/. 0.00 0.00%
01.04.01.07 CONCRETO CICLOPEO Fc=175kg/cm2 + 35% PM. EN ALCANTARILLAS m3 2.56 394.46 1,009.82 - S/. 0.00 0.00% 2.56 S/. 1,009.82 100.00% 2.56 S/. 1,009.82 100.00% - S/. 0.00 0.00%
01.04.01.08 ENCOFRADO Y DESENCOFRADO m2 18.61 51.08 950.60 - S/. 0.00 0.00% 18.61 S/. 950.60 100.00% 18.61 S/. 950.60 100.00% - S/. 0.00 0.00%
01.04.01.09 EMBOQUILLADO PARA LOSA DE ENCAUSAMIENTO m3 0.55 390.16 214.59 - S/. 0.00 0.00% 0.55 S/. 214.59 100.00% 0.55 S/. 214.59 100.00% - S/. 0.00 0.00%
01.04.01.10 TARRAJEO EXTERIOR CON MORTERO 1.5 x 1.5 CM. m2 7.43 17.65 131.14 - S/. 0.00 0.00% 7.43 S/. 131.14 100.00% 7.43 S/. 131.14 100.00% - S/. 0.00 0.00%
01.04.03 CUNETAS LATERALES (SIN REVESTIR) 14,481.03
01.04.03.01 CUNETA TRIANGULARES H=0.30, B=0.50 m 2,120.21 6.83 14,481.03 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 2,120.21 S/. 14,481.03 100.00%
01.04.04 SEÑALIZACION 1,052.84
01.04.04.01 POSTES KILOMETRICOS und 4.00 113.39 453.56 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 453.56 100.00%
01.04.04.02 SEÑAL IMFORMATIVA und 1.00 599.28 599.28 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 599.28 100.00%
01.05 CONTROL DE CALIDAD 490.00 S/. 0.00 0.00%
01.05.01 DISEÑO DEL MEZCLA und 1.00 350.00 350.00 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 350.00 100.00%
01.05.02 PRUEBA A LA COMPRESION und 4.00 35.00 140.00 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 140.00 100.00%
01.06 MANTENIMIENTO DE MAQUINARIA 6,000.00
01.06.01 MANTENIMIENTO DE MAQUINARIAS glb 1.00 6,000.00 6,000.00 1.00 S/. 6,000.00 100.00% - S/. 0.00 0.00% 1.00 S/. 6,000.00 100.00% - S/. 0.00 0.00%
01.07 MITIGACION E IMPACTO AMBIENTAL 1,377.20
01.07.01 RESTAURACION DE AREAS AFECTADA POR CAMPAMENTOS, PATIO DE MAQUI m2 120.00 3.61 433.20 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 120.00 S/. 433.20 100.00%
01.07.02 REVEGETACION / REFOSTERACION m2 1,600.00 0.59 944.00 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1,600.00 S/. 944.00 100.00%
01.08 FLETE 3,209.53
01.08.01 TRANSPORTE DE MATERIALES. glb 1.00 3,209.53 3,209.53 0.90 S/. 2,888.58 90.00% 0.10 S/. 320.95 10.00% 1.00 S/. 3,209.53 100.00% - S/. 0.00 0.00%
RESUMEN DE METRADOS N° 03- JUNIO
(1/06/2021 AL 10/06/2021)
"CREACION DE CAMINOS VECINALES DE LOS
TRAMOS; I: GEUNOEPAMPA – HUARISCA, II:
OBRA: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA
– NEGRO PUQUIO, EN EL ANEXO DE
OCCOBAMBA DEL CENTRO POBLADO DE
UCHUYMARCA DEL DISTRITO DE QUICHUAS -
ENTIDAD EJECUTORA PROVINCIA
FECHA DE DE
DE INICIO TAYACAJA
OBRA - DEPARTAMENTO DE
HUANCAVELICA"
MODALIDAD DE EJECUCIÓN FECHA DE CULMINACION DE OBRA

RESIDENTE CORRESPONDIENTE AL MES DE

SUPERVISOR FECHA DE PRESENTACION

AVANCE
Items PARTIDAS ACTUAL
Metrado Valorizado %
01 TRAMO I GEUNOEPAMPA - HUARISCA
01.01 OBRAS PROVISIONALES
01.01.01 ALMACEN, OFICINA Y GUARDIANIA 0.65 S/. 260.00 18.57%
01.02 OBRAS PRELIMINARES
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 0.50 S/. 2,442.73 50.00%
01.02.02 TRAZO Y REPLANTEO INICAL 0.26 S/. 285.82 12.44%
01.02.03 TRAZO Y REPLANTEO (EJECUCION DE OBRA) 0.26 S/. 221.28 12.44%
01.03 MOVIMIENTO DE TIERRAS
01.03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA 762.53 S/. 2,051.21 9.13%
01.03.02 TRANSPORTE DE MATERIAL EXCEDENTE (ELIMINACION) 841.13 S/. 3,768.28 9.90%
01.03.03 CORTE ROCA SUELTO (PERF. Y DISP.) 78.60 S/. 1,298.51 3.22%
01.03.04 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA 78.60 S/. 435.46 3.22%
01.03.05 CORTE ROCA FIJA (PERF. Y DISP.) 4.42 S/. 83.80 0.46%
01.03.06 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA 4.42 S/. 26.05 0.46%
01.04 OBRAS DE ARTE Y DRENAJE
01.04.01 ALCANTARILLA DE TIPO I (1 UND)
01.04.01.01 LIMPIEZA DEL TERRENO MANUAL 10.80 S/. 5.40 100.00%
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR 10.80 S/. 24.41 99.99%
01.04.01.03 EXCAVACION DE MATERIAL COMPACTO PARA ESTRUCTURAS 3.55 S/. 130.43 100.00%
01.04.01.04 ELIMINACION DE MATERIAL EXCEDENTE 4.43 S/. 139.50 100.00%
01.04.01.05 ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 86.39 S/. 457.00 100.00%
01.04.01.06 CONCRETO f'c=210Kg/cm2 EN ALCANTARILLAS 1.11 S/. 657.61 100.00%
01.04.01.07 CONCRETO CICLOPEO Fc=175kg/cm2 + 35% PM. EN ALCANTARILLAS 2.56 S/. 1,009.82 100.00%
01.04.01.08 ENCOFRADO Y DESENCOFRADO 18.61 S/. 950.60 100.00%
01.04.01.09 EMBOQUILLADO PARA LOSA DE ENCAUSAMIENTO 0.55 S/. 214.59 100.00%
01.04.01.10 TARRAJEO EXTERIOR CON MORTERO 1.5 x 1.5 CM. 7.43 S/. 131.14 100.00%
01.08 FLETE
01.08.01 TRANSPORTE DE MATERIALES. 0.10 S/. 320.95 10.00%
VALORIZACION MENSUAL DE OBRA N° 03- JUNIO
(1/06/2021 AL 10/06/2021)

OBRA:
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE
QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE QUICHUAS FECHA DE INICIO DE OBRA Lunes 12 de abril el 2021
MODALIDAD DE EJECUCIÓN ADMINISTRACION DIRECTA FECHA DE CULMINACION DE OBRA Jueves, 10 de Junio del 2021
RESIDENTE ING. ROGER BENDEZU DE LA CRUZ CORRESPONDIENTE AL MES DE JUNIO DEL2021
SUPERVISOR ING. JACK M. PUMACAHUA QUISPE FECHA DE PRESENTACION 30 de junio del 2021

AVANCE
PRESUPUESTO SALDO
Items PARTIDAS ANTERIOR ACTUAL ACUMULADO
Unid Metrado Precio PARCIAL Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01 TRAMO I GEUNOEPAMPA - HUARISCA 240,492.50
01.01 OBRAS PROVISIONALES 6,464.46
01.01.01 ALMACEN, OFICINA Y GUARDIANIA mes 3.50 400.00 1,400.00 1.35 S/. 540.00 38.57% 0.65 S/. 260.00 18.57% 2.00 S/. 800.00 57.14% 1.50 S/. 600.00 42.86%
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA glb 1.00 400.00 400.00 1.00 S/. 400.00 100.00% - S/. 0.00 0.00% 1.00 S/. 400.00 100.00% - S/. 0.00 0.00%
01.01.03 LIMPIEZA Y DEFORESTACION MANUAL m2 8,480.84 0.55 4,664.46 7,444.84 S/. 4,094.66 87.78% - S/. 0.00 0.00% 7,444.84 S/. 4,094.66 87.78% 1,036.00 S/. 569.80 12.22%
01.02 OBRAS PRELIMINARES 8,960.83
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 4,885.45 4,885.45 0.50 S/. 2,442.73 50.00% 0.50 S/. 2,442.73 50.00% 1.00 S/. 4,885.45 100.00% - S/. 0.00 0.00%
01.02.02 TRAZO Y REPLANTEO INICAL km 2.12 1,083.51 2,297.04 1.86 S/. 2,011.22 87.56% 0.26 S/. 285.82 12.44% 2.12 S/. 2,297.04 100.00% - S/. -0.00 0.00%
01.02.03 TRAZO Y REPLANTEO (EJECUCION DE OBRA) km 2.12 838.84 1,778.34 1.86 S/. 1,557.06 87.56% 0.26 S/. 221.28 12.44% 2.12 S/. 1,778.34 100.00% - S/. -0.00 0.00%
01.03 MOVIMIENTO DE TIERRAS 194,736.11
01.03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA m3 8,351.89 2.69 22,466.58 7,110.58 S/. 19,127.45 85.14% 762.53 S/. 2,051.21 9.13% 7,873.11 S/. 21,178.66 94.27% 478.78 S/. 1,287.92 5.73%
01.03.02 TRANSPORTE DE MATERIAL EXCEDENTE (ELIMINACION) m3 8,500.00 4.48 38,080.00 7,470.94 S/. 33,469.79 87.89% 841.13 S/. 3,768.28 9.90% 8,312.07 S/. 37,238.07 97.79% 187.93 S/. 841.93 2.21%
01.03.03 CORTE ROCA SUELTO (PERF. Y DISP.) m3 2,443.20 16.52 40,361.66 2,364.60 S/. 39,063.15 96.78% 78.60 S/. 1,298.51 3.22% 2,443.20 S/. 40,361.66 100.00% - S/. -0.00 0.00%
01.03.04 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA m3 2,443.20 5.54 13,535.33 2,364.60 S/. 13,099.87 96.78% 78.60 S/. 435.46 3.22% 2,443.20 S/. 13,535.33 100.00% - S/. 0.00 0.00%
01.03.05 CORTE ROCA FIJA (PERF. Y DISP.) m3 965.11 18.98 18,317.79 960.70 S/. 18,233.99 99.54% 4.42 S/. 83.80 0.46% 965.11 S/. 18,317.79 100.00% - S/. 0.00 0.00%
01.03.06 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA m3 965.11 5.90 5,694.15 960.70 S/. 5,668.10 99.54% 4.42 S/. 26.05 0.46% 965.11 S/. 5,694.15 100.00% - S/. 0.00 0.00%
01.03.07 RELLENO CON MATERIAL PROPIO CON MAQUINARIA m3 3,260.20 8.09 26,375.02 3,069.20 S/. 24,829.82 94.14% - S/. 0.00 0.00% 3,069.20 S/. 24,829.82 94.14% 191.00 S/. 1,545.20 5.86%
01.03.08 PERFILADO Y COMPACTACION SUB-RASANTES ZONAS CORTE m2 7,420.74 4.03 29,905.58 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 7,420.74 S/. 29,905.58 100.00%
01.04 OBRAS DE ARTE Y DRENAJE 19,254.37
01.04.01 ALCANTARILLA DE TIPO I (1 UND) 3,720.50
01.04.01.01 LIMPIEZA DEL TERRENO MANUAL m2 10.80 0.50 5.40 - S/. 0.00 0.00% 10.80 S/. 5.40 100.00% 10.80 S/. 5.40 100.00% - S/. 0.00 0.00%
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 10.80 2.26 24.41 - S/. 0.00 0.00% 10.80 S/. 24.41 99.99% 10.80 S/. 24.41 99.99% - S/. 0.00 0.00%
01.04.01.03 EXCAVACION DE MATERIAL COMPACTO PARA ESTRUCTURAS m3 3.55 36.74 130.43 - S/. 0.00 0.00% 3.55 S/. 130.43 100.00% 3.55 S/. 130.43 100.00% - S/. 0.00 0.00%
01.04.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 4.43 31.49 139.50 - S/. 0.00 0.00% 4.43 S/. 139.50 100.00% 4.43 S/. 139.50 100.00% - S/. 0.00 0.00%
01.04.01.05 ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 kg 86.39 5.29 457.00 - S/. 0.00 0.00% 86.39 S/. 457.00 100.00% 86.39 S/. 457.00 100.00% - S/. -0.00 0.00%
01.04.01.06 CONCRETO f'c=210Kg/cm2 EN ALCANTARILLAS m3 1.11 592.44 657.61 - S/. 0.00 0.00% 1.11 S/. 657.61 100.00% 1.11 S/. 657.61 100.00% - S/. 0.00 0.00%
01.04.01.07 CONCRETO CICLOPEO Fc=175kg/cm2 + 35% PM. EN ALCANTARILLAS m3 2.56 394.46 1,009.82 - S/. 0.00 0.00% 2.56 S/. 1,009.82 100.00% 2.56 S/. 1,009.82 100.00% - S/. 0.00 0.00%
01.04.01.08 ENCOFRADO Y DESENCOFRADO m2 18.61 51.08 950.60 - S/. 0.00 0.00% 18.61 S/. 950.60 100.00% 18.61 S/. 950.60 100.00% - S/. 0.00 0.00%
01.04.01.09 EMBOQUILLADO PARA LOSA DE ENCAUSAMIENTO m3 0.55 390.16 214.59 - S/. 0.00 0.00% 0.55 S/. 214.59 100.00% 0.55 S/. 214.59 100.00% - S/. 0.00 0.00%
01.04.01.10 TARRAJEO EXTERIOR CON MORTERO 1.5 x 1.5 CM. m2 7.43 17.65 131.14 - S/. 0.00 0.00% 7.43 S/. 131.14 100.00% 7.43 S/. 131.14 100.00% - S/. 0.00 0.00%
01.04.03 CUNETAS LATERALES (SIN REVESTIR) 14,481.03
01.04.03.01 CUNETA TRIANGULARES H=0.30, B=0.50 m 2,120.21 6.83 14,481.03 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 2,120.21 S/. 14,481.03 100.00%
01.04.04 SEÑALIZACION 1,052.84
01.04.04.01 POSTES KILOMETRICOS und 4.00 113.39 453.56 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 453.56 100.00%
01.04.04.02 SEÑAL IMFORMATIVA und 1.00 599.28 599.28 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 599.28 100.00%
01.05 CONTROL DE CALIDAD 490.00 S/. 0.00 0.00%
01.05.01 DISEÑO DEL MEZCLA und 1.00 350.00 350.00 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 350.00 100.00%
01.05.02 PRUEBA A LA COMPRESION und 4.00 35.00 140.00 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 140.00 100.00%
01.06 MANTENIMIENTO DE MAQUINARIA 6,000.00
01.06.01 MANTENIMIENTO DE MAQUINARIAS glb 1.00 6,000.00 6,000.00 1.00 S/. 6,000.00 100.00% - S/. 0.00 0.00% 1.00 S/. 6,000.00 100.00% - S/. 0.00 0.00%
01.07 MITIGACION E IMPACTO AMBIENTAL 1,377.20
01.07.01 RESTAURACION DE AREAS AFECTADA POR CAMPAMENTOS, PATIO DE MAQUI m2 120.00 3.61 433.20 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 120.00 S/. 433.20 100.00%
01.07.02 REVEGETACION / REFOSTERACION m2 1,600.00 0.59 944.00 - S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1,600.00 S/. 944.00 100.00%
01.08 FLETE 3,209.53
01.08.01 TRANSPORTE DE MATERIALES. glb 1.00 3,209.53 3,209.53 0.90 S/. 2,888.58 90.00% 0.10 S/. 320.95 10.00% 1.00 S/. 3,209.53 100.00% - S/. 0.00 0.00%
COSTO DIRECTO S/240,492.50 S/173,426.42 72.11% S/14,914.57 6.20% S/188,340.99 78.31% S/52,151.50 21.69%
GASTOS GENERALES (10.00 %) 5.41% S/13,000.00 S/9,374.69 72.11% S/806.22 6.20% S/10,180.91 78.31% S/2,819.09 21.69%
VALORIZACION MENSUAL DE OBRA N° 03- JUNIO
(1/06/2021 AL 10/06/2021)

OBRA:
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE
QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE QUICHUAS FECHA DE INICIO DE OBRA Lunes 12 de abril el 2021
MODALIDAD DE EJECUCIÓN ADMINISTRACION DIRECTA FECHA DE CULMINACION DE OBRA Jueves, 10 de Junio del 2021
RESIDENTE ING. ROGER BENDEZU DE LA CRUZ CORRESPONDIENTE AL MES DE JUNIO DEL2021
SUPERVISOR ING. JACK M. PUMACAHUA QUISPE FECHA DE PRESENTACION 30 de junio del 2021

AVANCE
PRESUPUESTO SALDO
Items PARTIDAS ANTERIOR ACTUAL ACUMULADO
Unid Metrado Precio PARCIAL Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
=========
SUB TOTAL S/253,492.50 S/182,801.12 72.11% S/15,720.79 6.20% S/198,521.90 78.31% S/54,970.59 21.69%
=========
PRESUPUESTO REFERENCIAL S/253,492.50
=========
PRESUPUESTO TOTAL S/253,492.50
PORCENTAJE MENSUAL VALORIZADO 72.11% 6.20% 78.31% 21.69%
VALORIZACION MENSUAL DE OBRA N° 02- MAYO
(1/05/2021 AL 31/05/2021)

OBRA:
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE
QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE QUICHUAS FECHA DE INICIO DE OBRA Lunes 12 de abril el 2021
MODALIDAD DE EJECUCIÓN ADMINISTRACION DIRECTA FECHA DE CULMINACION DE OBRA Jueves, 10 de Junio del 2021
RESIDENTE ING. ROGER BENDEZU DE LA CRUZ CORRESPONDIENTE AL MES DE MAYO DEL2021
SUPERVISOR ING. JACK M. PUMACAHUA QUISPE FECHA DE PRESENTACION 01 de mayo del 2021

AVANCE
PRESUPUESTO SALDO
Items PARTIDAS ANTERIOR ACTUAL ACUMULADO
Unid Metrado Precio PARCIAL Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01 TRAMO I GEUNOEPAMPA - HUARISCA 240,492.50
01.01 OBRAS PROVISIONALES 6,464.46
01.01.01 ALMACEN, OFICINA Y GUARDIANIA mes 3.50 400.00 1,400.00 0.35 S/. 140.00 10.00% 1.00 S/. 400.00 28.57% 1.35 S/. 540.00 38.57% 2.15 S/. 860.00 61.43%
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA glb 1.00 400.00 400.00 S/. 0.00 0.00% 1.00 S/. 400.00 100.00% 1.00 S/. 400.00 100.00% - S/. 0.00 0.00%
01.01.03 LIMPIEZA Y DEFORESTACION MANUAL m2 8,480.84 0.55 4,664.46 4,000.00 S/. 2,200.00 47.17% 3,444.84 S/. 1,894.66 40.62% 7,444.84 S/. 4,094.66 87.78% 1,036.00 S/. 569.80 12.22%
01.02 OBRAS PRELIMINARES 8,960.83
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 4,885.45 4,885.45 0.50 S/. 2,442.73 50.00% - S/. 0.00 0.00% 0.50 S/. 2,442.73 50.00% 0.50 S/. 2,442.73 50.00%
01.02.02 TRAZO Y REPLANTEO INICAL km 2.12 1,083.51 2,297.04 1.28 S/. 1,381.48 60.14% 0.58 S/. 629.75 27.42% 1.86 S/. 2,011.22 87.56% 0.26 S/. 285.82 12.44%
01.02.03 TRAZO Y REPLANTEO (EJECUCION DE OBRA) km 2.12 838.84 1,778.34 1.28 S/. 1,069.52 60.14% 0.58 S/. 487.54 27.42% 1.86 S/. 1,557.06 87.56% 0.26 S/. 221.28 12.44%
01.03 MOVIMIENTO DE TIERRAS 194,736.11
01.03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA m3 8,351.89 2.69 22,466.58 1,493.18 S/. 4,016.66 17.88% 5,617.40 S/. 15,110.79 67.26% 7,110.58 S/. 19,127.45 85.14% 1,241.31 S/. 3,339.13 14.86%
01.03.02 TRANSPORTE DE MATERIAL EXCEDENTE (ELIMINACION) m3 8,500.00 4.48 38,080.00 S/. 0.00 0.00% 7,470.94 S/. 33,469.79 87.89% 7,470.94 S/. 33,469.79 87.89% 1,029.06 S/. 4,610.21 12.11%
01.03.03 CORTE ROCA SUELTO (PERF. Y DISP.) m3 2,443.20 16.52 40,361.66 511.06 S/. 8,442.65 20.92% 1,853.54 S/. 30,620.50 75.87% 2,364.60 S/. 39,063.15 96.78% 78.60 S/. 1,298.51 3.22%
01.03.04 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA m3 2,443.20 5.54 13,535.33 511.06 S/. 2,831.25 20.92% 1,853.54 S/. 10,268.62 75.87% 2,364.60 S/. 13,099.87 96.78% 78.60 S/. 435.46 3.22%
01.03.05 CORTE ROCA FIJA (PERF. Y DISP.) m3 965.11 18.98 18,317.79 19.01 S/. 360.85 1.97% 941.68 S/. 17,873.14 97.57% 960.70 S/. 18,233.99 99.54% 4.42 S/. 83.80 0.46%
01.03.06 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA m3 965.11 5.90 5,694.15 19.01 S/. 112.17 1.97% 941.68 S/. 5,555.93 97.57% 960.70 S/. 5,668.10 99.54% 4.42 S/. 26.05 0.46%
01.03.07 RELLENO CON MATERIAL PROPIO CON MAQUINARIA m3 3,260.20 8.09 26,375.02 1,121.10 S/. 9,069.70 34.39% 1,948.10 S/. 15,760.12 59.75% 3,069.20 S/. 24,829.82 94.14% 191.00 S/. 1,545.20 5.86%
01.03.08 PERFILADO Y COMPACTACION SUB-RASANTES ZONAS CORTE m2 7,420.74 4.03 29,905.58 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 7,420.74 S/. 29,905.58 100.00%
01.04 OBRAS DE ARTE Y DRENAJE 19,254.37
01.04.01 ALCANTARILLA DE TIPO I (1 UND) 3,720.50
01.04.01.01 LIMPIEZA DEL TERRENO MANUAL m2 10.80 0.50 5.40 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 10.80 S/. 0.00 0.00%
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 10.80 2.26 24.41 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 10.80 S/. 0.00 0.00%
01.04.01.03 EXCAVACION DE MATERIAL COMPACTO PARA ESTRUCTURAS m3 3.55 36.74 130.43 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 3.55 S/. 0.00 0.00%
01.04.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 4.43 31.49 139.50 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.43 S/. 0.00 0.00%
01.04.01.05 ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 kg 86.39 5.29 457.00 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 86.39 S/. 457.00 100.00%
01.04.01.06 CONCRETO f'c=210Kg/cm2 EN ALCANTARILLAS m3 1.11 592.44 657.61 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.11 S/. 657.61 100.00%
01.04.01.07 CONCRETO CICLOPEO Fc=175kg/cm2 + 35% PM. EN ALCANTARILLAS m3 2.56 394.46 1,009.82 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 2.56 S/. 1,009.82 100.00%
01.04.01.08 ENCOFRADO Y DESENCOFRADO m2 18.61 51.08 950.60 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 18.61 S/. 950.60 100.00%
01.04.01.09 EMBOQUILLADO PARA LOSA DE ENCAUSAMIENTO m3 0.55 390.16 214.59 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 0.55 S/. 214.59 100.00%
01.04.01.10 TARRAJEO EXTERIOR CON MORTERO 1.5 x 1.5 CM. m2 7.43 17.65 131.14 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 7.43 S/. 131.14 100.00%
01.04.03 CUNETAS LATERALES (SIN REVESTIR) 14,481.03
01.04.03.01 CUNETA TRIANGULARES H=0.30, B=0.50 m 2,120.21 6.83 14,481.03 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 2,120.21 S/. 14,481.03 100.00%
01.04.04 SEÑALIZACION 1,052.84
01.04.04.01 POSTES KILOMETRICOS und 4.00 113.39 453.56 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 453.56 100.00%
01.04.04.02 SEÑAL IMFORMATIVA und 1.00 599.28 599.28 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 599.28 100.00%
01.05 CONTROL DE CALIDAD 490.00 S/. 0.00 0.00%
01.05.01 DISEÑO DEL MEZCLA und 1.00 350.00 350.00 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 350.00 100.00%
01.05.02 PRUEBA A LA COMPRESION und 4.00 35.00 140.00 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 140.00 100.00%
01.06 MANTENIMIENTO DE MAQUINARIA 6,000.00
01.06.01 MANTENIMIENTO DE MAQUINARIAS glb 1.00 6,000.00 6,000.00 1.00 S/. 6,000.00 100.00% - S/. 0.00 0.00% 1.00 S/. 6,000.00 100.00% - S/. 0.00 0.00%
01.07 MITIGACION E IMPACTO AMBIENTAL 1,377.20
01.07.01 RESTAURACION DE AREAS AFECTADA POR CAMPAMENTOS, PATIO DE MAQUI m2 120.00 3.61 433.20 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 120.00 S/. 433.20 100.00%
01.07.02 REVEGETACION / REFOSTERACION m2 1,600.00 0.59 944.00 S/. 0.00 0.00% - S/. 0.00 0.00% - S/. 0.00 0.00% 1,600.00 S/. 944.00 100.00%
01.08 FLETE 3,209.53
01.08.01 TRANSPORTE DE MATERIALES. glb 1.00 3,209.53 3,209.53 0.50 S/. 1,604.77 50.00% 0.40 S/. 1,283.81 40.00% 0.90 S/. 2,888.58 90.00% 0.10 S/. 320.95 10.00%
COSTO DIRECTO S/240,492.50 S/39,671.77 16.50% S/133,754.65 55.62% S/173,426.42 72.11% S/66,766.34 27.76%
GASTOS GENERALES (10.00 %) 5.41% S/13,000.00 S/2,144.49 16.50% S/7,230.21 55.62% S/9,374.69 72.11% S/3,609.10 27.76%
VALORIZACION MENSUAL DE OBRA N° 02- MAYO
(1/05/2021 AL 31/05/2021)

OBRA:
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE
QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE QUICHUAS FECHA DE INICIO DE OBRA Lunes 12 de abril el 2021
MODALIDAD DE EJECUCIÓN ADMINISTRACION DIRECTA FECHA DE CULMINACION DE OBRA Jueves, 10 de Junio del 2021
RESIDENTE ING. ROGER BENDEZU DE LA CRUZ CORRESPONDIENTE AL MES DE MAYO DEL2021
SUPERVISOR ING. JACK M. PUMACAHUA QUISPE FECHA DE PRESENTACION 01 de mayo del 2021

AVANCE
PRESUPUESTO SALDO
Items PARTIDAS ANTERIOR ACTUAL ACUMULADO
Unid Metrado Precio PARCIAL Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
=========
SUB TOTAL S/253,492.50 S/41,816.26 16.50% S/140,984.86 55.62% S/182,801.12 72.11% S/70,375.44 27.76%
=========
PRESUPUESTO REFERENCIAL S/253,492.50
=========
PRESUPUESTO TOTAL S/253,492.50
PORCENTAJE MENSUAL VALORIZADO 16.50% 55.62% 72.11% 27.76%
VALORIZACION MENSUAL DE OBRA N° 01- ABRIL
(12/04/2021 AL 30/04/2021)

OBRA:
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO
DE QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE QUICHUAS FECHA DE INICIO DE OBRA Lunes 12 de abril el 2021
MODALIDAD DE EJECUCIÓN ADMINISTRACION DIRECTA FECHA DE CULMINACION DE OBRA Jueves, 10 de Junio del 2021
RESIDENTE ING. ROGER BENDEZU DE LA CRUZ CORRESPONDIENTE AL MES DE ABRIL DEL2021
SUPERVISOR ING. FECHA DE PRESENTACION 01 de mayo del 2021

AVANCE
PRESUPUESTO SALDO
Items PARTIDAS ANTERIOR ACTUAL ACUMULADO
Unid Metrado Precio PARCIAL Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01 TRAMO I GEUNOEPAMPA - HUARISCA 240,492.50
01.01 OBRAS PROVISIONALES 6,464.46
01.01.01 ALMACEN, OFICINA Y GUARDIANIA mes 3.50 400.00 1,400.00 - S/. 0.00 0.00% 0.35 S/. 140.00 10.00% 0.35 S/. 140.00 10.00% 3.15 S/. 1,260.00 90.00%
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA glb 1.00 400.00 400.00 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 400.00 100.00%
01.01.03 LIMPIEZA Y DEFORESTACION MANUAL m2 8,480.84 0.55 4,664.46 - S/. 0.00 0.00% 3,444.84 S/. 1,894.66 40.62% 3,444.84 S/. 1,894.66 40.62% 5,036.00 S/. 2,769.80 59.38%
01.02 OBRAS PRELIMINARES 8,960.83
01.02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 4,885.45 4,885.45 - S/. 0.00 0.00% 0.50 S/. 2,442.73 50.00% 0.50 S/. 2,442.73 50.00% 0.50 S/. 2,442.73 50.00%
01.02.02 TRAZO Y REPLANTEO INICAL km 2.12 1,083.51 2,297.04 - S/. 0.00 0.00% 0.58 S/. 628.44 27.36% 0.58 S/. 628.44 27.36% 1.54 S/. 1,668.60 72.64%
01.02.03 TRAZO Y REPLANTEO (EJECUCION DE OBRA) km 2.12 838.84 1,778.34 - S/. 0.00 0.00% 0.58 S/. 486.53 27.36% 0.58 S/. 486.53 27.36% 1.54 S/. 1,291.81 72.64%
01.03 MOVIMIENTO DE TIERRAS 194,736.11
01.03.01 CORTE DE MATERIAL SUELTO CON MAQUINARIA m3 8,351.89 2.69 22,466.58 - S/. 0.00 0.00% 1,493.18 S/. 4,016.66 17.88% 1,493.18 S/. 4,016.66 17.88% 6,858.71 S/. 18,449.92 82.12%
01.03.02 TRANSPORTE DE MATERIAL EXCEDENTE (ELIMINACION) m3 8,500.00 4.48 38,080.00 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 8,500.00 S/. 38,080.00 100.00%
01.03.03 CORTE ROCA SUELTO (PERF. Y DISP.) m3 2,443.20 16.52 40,361.66 - S/. 0.00 0.00% 511.06 S/. 8,442.65 20.92% 511.06 S/. 8,442.65 20.92% 1,932.14 S/. 31,919.01 79.08%
01.03.04 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA SUELTA m3 2,443.20 5.54 13,535.33 - S/. 0.00 0.00% 511.06 S/. 2,831.25 20.92% 511.06 S/. 2,831.25 20.92% 1,932.14 S/. 10,704.08 79.08%
01.03.05 CORTE ROCA FIJA (PERF. Y DISP.) m3 965.11 18.98 18,317.79 - S/. 0.00 0.00% 19.01 S/. 360.85 1.97% 19.01 S/. 360.85 1.97% 946.10 S/. 17,956.94 98.03%
01.03.06 LIMPIEZA DE PLATAFORMA Y DESQUINCHE DE TALUD EN ROCA FIJA m3 965.11 5.90 5,694.15 - S/. 0.00 0.00% 19.01 S/. 112.17 1.97% 19.01 S/. 112.17 1.97% 946.10 S/. 5,581.98 98.03%
01.03.07 RELLENO CON MATERIAL PROPIO CON MAQUINARIA m3 3,260.20 8.09 26,375.02 - S/. 0.00 0.00% 1,121.10 S/. 9,069.70 34.39% 1,121.10 S/. 9,069.70 34.39% 2,139.10 S/. 17,305.32 65.61%
01.03.08 PERFILADO Y COMPACTACION SUB-RASANTES ZONAS CORTE m2 7,420.74 4.03 29,905.58 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 7,420.74 S/. 29,905.58 100.00%
01.04 OBRAS DE ARTE Y DRENAJE 19,254.37
01.04.01 ALCANTARILLA DE TIPO I (1 UND) 3,720.50
01.04.01.01 LIMPIEZA DEL TERRENO MANUAL m2 10.80 0.50 5.40 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 10.80 S/. 5.40 100.00%
01.04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 10.80 2.26 24.41 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 10.80 S/. 24.41 100.00%
01.04.01.03 EXCAVACION DE MATERIAL COMPACTO PARA ESTRUCTURAS m3 3.55 36.74 130.43 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 3.55 S/. 130.43 100.00%
01.04.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 4.43 31.49 139.50 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 4.43 S/. 139.50 100.00%
01.04.01.05 ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 kg 86.39 5.29 457.00 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 86.39 S/. 457.00 100.00%
01.04.01.06 CONCRETO f'c=210Kg/cm2 EN ALCANTARILLAS m3 1.11 592.44 657.61 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 1.11 S/. 657.61 100.00%
01.04.01.07 CONCRETO CICLOPEO Fc=175kg/cm2 + 35% PM. EN ALCANTARILLAS m3 2.56 394.46 1,009.82 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 2.56 S/. 1,009.82 100.00%
01.04.01.08 ENCOFRADO Y DESENCOFRADO m2 18.61 51.08 950.60 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 18.61 S/. 950.60 100.00%
01.04.01.09 EMBOQUILLADO PARA LOSA DE ENCAUSAMIENTO m3 0.55 390.16 214.59 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 0.55 S/. 214.59 100.00%
01.04.01.10 TARRAJEO EXTERIOR CON MORTERO 1.5 x 1.5 CM. m2 7.43 17.65 131.14 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 7.43 S/. 131.14 100.00%
01.04.03 CUNETAS LATERALES (SIN REVESTIR) 14,481.03
01.04.03.01 CUNETA TRIANGULARES H=0.30, B=0.50 m 2,120.21 6.83 14,481.03 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 2,120.21 S/. 14,481.03 100.00%
01.04.04 SEÑALIZACION 1,052.84
01.04.04.01 POSTES KILOMETRICOS und 4.00 113.39 453.56 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 453.56 100.00%
01.04.04.02 SEÑAL IMFORMATIVA und 1.00 599.28 599.28 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 599.28 100.00%
01.05 CONTROL DE CALIDAD 490.00 S/. 0.00 0.00%
01.05.01 DISEÑO DEL MEZCLA und 1.00 350.00 350.00 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 1.00 S/. 350.00 100.00%
01.05.02 PRUEBA A LA COMPRESION und 4.00 35.00 140.00 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 4.00 S/. 140.00 100.00%
01.06 MANTENIMIENTO DE MAQUINARIA 6,000.00
01.06.01 MANTENIMIENTO DE MAQUINARIAS glb 1.00 6,000.00 6,000.00 - S/. 0.00 0.00% 1.00 S/. 6,000.00 100.00% 1.00 S/. 6,000.00 100.00% - S/. 0.00 0.00%
01.07 MITIGACION E IMPACTO AMBIENTAL 1,377.20
01.07.01 RESTAURACION DE AREAS AFECTADA POR CAMPAMENTOS, PATIO DE MAQUIm2 120.00 3.61 433.20 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 120.00 S/. 433.20 100.00%
01.07.02 REVEGETACION / REFOSTERACION m2 1,600.00 0.59 944.00 - S/. 0.00 0.00% S/. 0.00 0.00% - S/. 0.00 0.00% 1,600.00 S/. 944.00 100.00%
01.08 FLETE 3,209.53
01.08.01 TRANSPORTE DE MATERIALES. glb 1.00 3,209.53 3,209.53 - S/. 0.00 0.00% 0.50 S/. 1,604.77 50.00% 0.50 S/. 1,604.77 50.00% 0.50 S/. 1,604.77 50.00%
COSTO DIRECTO S/240,492.50 S/0.00 0.00% S/38,030.40 15.81% S/38,030.40 15.81% S/202,462.10 84.19%
GASTOS GENERALES (10.00 %) 5.41% S/13,000.00 S/0.00 0.00% S/2,055.76 15.81% S/2,055.76 15.81% S/10,944.24 84.19%
=========
SUB TOTAL S/253,492.50 S/0.00 0.00% S/40,086.16 15.81% S/40,086.16 15.81% S/213,406.34 84.19%
=========
VALORIZACION MENSUAL DE OBRA N° 01- ABRIL
(12/04/2021 AL 30/04/2021)

OBRA:
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO
DE QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE QUICHUAS FECHA DE INICIO DE OBRA Lunes 12 de abril el 2021
MODALIDAD DE EJECUCIÓN ADMINISTRACION DIRECTA FECHA DE CULMINACION DE OBRA Jueves, 10 de Junio del 2021
RESIDENTE ING. ROGER BENDEZU DE LA CRUZ CORRESPONDIENTE AL MES DE ABRIL DEL2021
SUPERVISOR ING. FECHA DE PRESENTACION 01 de mayo del 2021

AVANCE
PRESUPUESTO SALDO
Items PARTIDAS ANTERIOR ACTUAL ACUMULADO
Unid Metrado Precio PARCIAL Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
PRESUPUESTO REFERENCIAL S/253,492.50
=========
PRESUPUESTO TOTAL S/253,492.50
FICHA DE IDENTIFICACION DE OBRA

PROYECTO: "CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III:
GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE QUICHUAS -
PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

DATOS GENERALES
UNIDAD EJECUTORA DE INVERSIONES : MUNICIPALIDAD DISTRITAL DE QUICHUAS
CODIGO UNICO DE INVERSIONES : 2488493
UBICACIÓN
DEPARTAMENTO : HUANCAVELICA
PROVINCIA : TAYACAJA
DISTRITO : QUICHUAS

BENEFICIARIOS : LOCALIDAD DE GENUOEPAMPA - HUARISCA

SUPERVISOR DE OBRA : ING. JACK M. PUMACAHUA QUISPE


RESIDENTE DE OBRA : ING. ROGER BENDEZU DE LA CRUZ
CONTRATO DE RESIDENTE DE OBRA CONTRATO N° 08 - 2020/AGRO/UL/MDA
FECHA DE SUSCRIPCION DEL CONTRATO 3/11/2020
MONTO DEL SERVICIO DE RESIDENTE DE OBRA S/9,000.00
MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA
DOCUMENTO DE APROBACION DEL EXPEDIENTE TECNICO : RESOLUCION DE GERENCIA MUNICIPAL N°176-2020-MDQ/GM
COSTO DIRECTO : S/. 240,492.50 SOLES
GASTOS GENERALES : S/. 13,000.00 SOLES
PRESUPUESTO SUB TOTAL DE LA OBRA : S/. 253,492.50 SOLES
LIQUIDACION : S/. 0.00 SOLES
EXPEDIENTE TECNICO : S/. 27,000.00 SOLES
COSTO TOTAL DE OBRA : S/. 280,492.50 SOLES
SUPERVISION : S/. 11,000.00 SOLES
COSTO TOTAL DEL PROYECTO : S/. 291,492.50 SOLES
PLAZO DE EJECUCION DE OBRA SEGÚN EXPEDIENTE TECNICO : 60 DIAS CALENDARIOS
ADICIONALES DE OBRA
DOCUMENTO DE APROBACION : NO SE SOLICITO
MAYORES METRADOS
DOCUMENTO DE APROBACION : NO SE SOLICITO
DEL PLAZO DE EJECUCION DE OBRA
FECHA DE ENTREGA DE TERRENO : 4/12/2021
FECHA DE INICIO DE OBRA : 4/12/2021
FECHA DE TERMINO PROGRAMADO : 6/10/2021

PRESUPUESTO ANALITICO DE OBRA


DOCUMENTO DE APROBACION : INFORME DE RESIDENTE DE OBRA

DE LA SUPERVISION
SUPERVISOR DE OBRA : ING. JACK M. PUMACAHUA QUISPE
PROFESION : INGENIERO CIVIL
PRESUPUESTO DE SUPERVISION SEGÚN EXPEDIENTE TECNICO : S/. 11,000.00 SOLES

DE LA OBRA
RESIDENTE DE OBRA : ING. ROGER BENDEZU DE LA CRUZ
FECHA DE ENTREGA DE TERRENO : 4/12/2021
FECHA DE INICIO DE OBRA : 4/12/2021
FECHA DE TERMINO PROGRAMADO DE OBRA SEGÚN EXPEDIENTE TECNICO : 6/10/2021
AMPLIACIONES DE PLAZO : NO SE SOLICITA
AVANCE FISICO PROGRAMADO ACUMULADO : 100.00%
AVANCE FISICO EJECUTADO ACUMULADO :
DE LA EJECUCION FISICA DEL PROYECTO

PRIMERA VALORIZACION - ABRIL : 16.50%


SEGUNDA VALORIZACION - MAYO : 55.62%
TERCERA VALORIZACION - JUNIO : 6.20%
78.31%

DEL PROCESO CONSTRUCTIVO DE LA OBRA


METAS FISICAS DE LA OBRA "CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III:
GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE QUICHUAS - PROVINCIA DE TAYACAJA
- DEPARTAMENTO DE HUANCAVELICA"
OBRAS PROVISIONALES : S/6,464.46
OBRAS PRELIMINARES : S/8,960.83
MOVIMIENTO DE TIERRAS : S/194,736.11
OBRAS DE ARTE Y DRENAJE : S/19,254.37
CONTROL DE CALIDAD : S/490.00
MANTENIMIENTO DE MAQUINARIA : S/6,000.00
FICHA DE IDENTIFICACION DE OBRA

PROYECTO: "CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III:
GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE QUICHUAS -
PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

MITIGACION E IMPACTO AMBIENTAL : S/1,377.20

FLETE : S/3,209.53

VALORIZACIONES PROGRAMADOS
COSTO DIRECTO AVANCE FISICO AVANCE ACUMULADO
VALORIZACION OBSERVACIONES
S/ % %
VALORIZACION N° 01 INC. IGV S/30,789.06 12.80% 12.80%
VALORIZACION N° 02 INC. IGV S/118,378.61 49.22% 62.03%
VALORIZACION N° 03 INC. IGV S/91,324.84 37.97% 100.00%

VALORIZACIONES EJECUTADOS
COSTO DIRECTO AVANCE FISICO AVANCE ACUMULADO
VALORIZACION OBSERVACIONES
S/ % %

VALORIZACION N° 01 INC. IGV S/39,671.77 16.50% 16.50% La obra se encuentra con mayor avance de lo programado

VALORIZACION N° 02 INC. IGV S/133,754.65 55.62% 72.11% La obra se encuentra con mayor avance de lo programado

La obra se encuentra culminada al 100% con la funcion del


objetivo proncipal, la obra cuenta cn deductivo de 21.69% el
VALORIZACION N° 03 INC. IGV S/14,914.57 6.20% 78.31% cual
CUADRO DE RESUMEN DE OBRA
UNIDAD EJECUTORA DE INVERSIONES : MUNICIPALIDAD DISTRITAL DE QUICHUAS

"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA –


PROYECTO HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE
UCHUYMARCA DEL DISTRITO DE QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"

RESIDENTE DE OBRA : ING. ROGER BENDEZU DE LA CRUZ


SUPERVIOR DE OBRA : ING. JACK M. PUMACAHUA QUISPE
MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA
PLAZO DE EJECUCION : 60 DIAS CALENDARIOS
FECHA DE ENTREGA DE TERRENO : 12/04/2021
FECHA DE INICIO : 12/04/2021
FECHA DE TERMINO PROGRAMADO : 10/06/2021

TOTAL PROGRAMADO EJECUTADO SALDO POR


PRESUPUEST0 DEDUCTIVO DE
Descripción EXPEDIENTE 1° VALORIZACION 2° VALORIZACION 3° VALORIZACION 1° VALORIZACION 2° VALORIZACION 3° VALORIZACION OBRA
TECNICO
MONTO MONTO MONTO MONTO MONTO MONTO MONTO
% % % % % % %
S/. S/. S/. S/. S/. S/. S/. S/.
COSTO DIRECTO 240,492.50 30,789.06 118,378.61 91,324.84 39,671.77 133,754.65 14,914.57 52,151.50

GASTOS GENERALES 13,000.00 1,664.33 6,399.04 4,936.63 2,144.49 7,230.21 806.22 2,819.09

PRESUPUESTO SUB TOTAL


253,492.50 32,453.38 124,777.65 96,261.47 41,816.26 140,984.86 15,720.79 54,970.59
DE LA OBRA 12.80% 49.22% 37.97% 15.81% 55.62% 6.20% 21.69%
LIQUIDACION 0.00
EXPEDIENTE TECNICO 27,000.00
COSTO TOTAL DE OBRA 280,492.50
SUPERVISION 11,000.00
PRESUPUESTO SUB TOTAL
DE LA OBRA
240,492.50 32,453.38 124,777.65 96,261.47 S/41,816.26 140,984.86 15,720.79 54,970.59

PORCENTAJE DE AVANCE 100.00% 12.80% 49.22% 37.97% 15.81% 55.62% 6.20% 21.69%
CONTROL DE VALORIZACIONES

UNIDAD EJECUTORA DE INVERSIONES : MUNICIPALIDAD DISTRITAL DE QUICHUAS


"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III:
PROYECTO GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO
DE QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"
RESIDENTE DE OBRA ING. JACK M. PUMACAHUA QUISPE
SUPERVIOR DE OBRA ING. ROGER BENDEZU DE LA CRUZ
MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA
PLAZO DE EJECUCION : 60 DIAS CALENDARIOS
FECHA DE ENTREGA DE TERRENO : 12/04/2021
FECHA DE INICIO : 12/04/2021
FECHA DE TERMINO PROGRAMADO : 10/06/2021

PROGRAMADO EJECUTADO
N° Monto S/. Monto S/.
Valoriz. Período mes % Avance % Avance
(INC. COSTO DIRECTO + GG) (INC. COSTO DIRECTO + GG)

Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado

0 12/04/2021 Inicio 0.00 0.00 0.00% 0.00% - - 0.00% 0.00%


1 30/04/2021 Apr-2021 32,453.38 32,453.38 12.80% 12.80% 41,816.26 41,816.26 16.50% 16.50%

2 31/05/2021 May-2021 124,777.65 157,231.03 49.22% 62.03% 140,984.86 182,801.12 55.62% 72.11%
3 10/06/2021 Jun-2021 96,261.47 253,492.50 37.97% 100.00% 15,720.79 198,521.90 6.20% 78.31%
TOTAL S/. S/. 253,492.50 100.00% S/. 198,521.90 78.31%
OBRA MODALIDAD DE EJECUCION ADMINISTRACION DIRECTA
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III: GEUNOEPAMPA – NEGRO PUQUIO,
EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE
SUPERVISOR ING. JACK M. PUMACAHUA QUISPE
HUANCAVELICA" RESIDENTE DE OBRA ING. ROGER D. BENDEZU DE LA CRUZ
PROPIETARIO MUNICIPALIDAD DISTRITAL DE QUICHUAS PLAZO EJECUCIÓN 60 DIAS CALENDARIOS
UBICACIÓN C.P DE UCHUYMARCA FECHA DE PRESENTACION 30-jun-21
ETAPA DE EJECUCION TRAMOS; I: GEUNOEPAMPA – HUARISCA FECHA DE INICIO 12-abr-21
COSTO DIRECTO S/. 240,492.50 FECHA DE TÉRMINO INICIAL 10-jun-21
FECHA DE TERMINO REAL 10-jun-21

CUADRO COMPARATIVO DE
VALORIZACIONES MENSUALES DE AVANCE DE OBRA N°03

160,000.00
140,984.86

MONTO PARCIAL
140,000.00
124,777.65

120,000.00

96,261.47
100,000.00

80,000.00

60,000.00
SITUACIÓN DE LA OBRA 41,816.26
MONTO ACUMULADO. 40,000.00
32,453.38

Real 15,720.79
20,000.00
CULMINADA Y PUESTA EN FUNSION 0.00 0.00
0.00
12-Apr-21 FIN 31/04/2021 FIN 31/05/2021 FIN 10/06/2021

MESES

Row 47 Row 48

0 1 2 3 4 5 6 10

MESES 12-Apr-21 FIN 31/04/2021 FIN 31/05/2021 FIN 10/06/2021

MONTO PROG. 0.00 32,453.38 124,777.65 96,261.47

PARCIALES (S/.) REAL 0.00 41,816.26 140,984.86 15,720.79


GRAFICO DE AVANCE DE OBRA
EXPEDIENTE TECNICO VS EJECUTADO
CURVA "S"
UNIDAD EJECUTORA DE INVERSIONES : MUNICIPALIDAD DISTRITAl DE QUICHUAS
"CREACION DE CAMINOS VECINALES DE LOS TRAMOS; I: GEUNOEPAMPA – HUARISCA, II: HUARISCA – HUAYRACCASA, III:
PROYECTO GEUNOEPAMPA – NEGRO PUQUIO, EN EL ANEXO DE OCCOBAMBA DEL CENTRO POBLADO DE UCHUYMARCA DEL DISTRITO DE
QUICHUAS - PROVINCIA DE TAYACAJA - DEPARTAMENTO DE HUANCAVELICA"
RESIDENTE DE OBRA ING. ROGER D. BENDEZU DE LA CRUZ
SUPERVIOR DE OBRA ING. JACK M. PUMACAHUA QUISPE
MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA
PLAZO DE EJECUCION : 60 DIAS CALENDARIOS
FECHA DE ENTREGA DE TERRENO : 12/04/2021
FECHA DE INICIO : 12/04/2021

FECHA DE TERMINO PROGRAMADO 6/10/2021

FECHA DE TERMINO REAL DE OBRA 6/10/2021

PROGRAMADO EJECUTADO
N° Período mes
Valoriz. Monto S/. (S/IGV) % Avance Monto S/. (S/IGV) % Avance
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado

0 12/04/2021 Inicio 0.00 0.00 0.00% 0.00% - 0.00 0.00% 0.00%


1 30/04/2021 Apr-2021 32,453.38 32,453.38 12.80% 12.80% 41,816.26 41,816.26 16.50% 16.50%
2 31/05/2021 May-2021 124,777.65 157,231.03 49.22% 62.03% 140,984.86 182,801.12 55.62% 72.11%
10/06/2021 Jun-2021 96,261.47 253,492.51 37.97% 100.00% 15,720.79 198,521.90 6.20% 78.31%
3

TOTAL S/. S/. 253,492.50 100.00% S/. 198,521.90 78.31%

AVANCE PROGRAMADO VS EJECUTADO

100.00%

90.00%

80.00% 78.31%
72.11%
70.00%

62.03%
% DE AVANCE

60.00%

50.00%

40.00%
__________ PROGRAMADO
30.00%

20.00%
__________
Column GEJECUTADO
Column K
16.50%
12.80%
10.00%

0.00% 0.00%
0.00%
Inicio Apr-2021 May-2021 Jun-2021

PERIODO

ESTADO DE AVANCE LA OBRA SE ENCUENTRA CULMINADA Y OPERATIVA CON SALDO DE -21.69%