Item Descripción Und. Metrado Precio S/. Parcial S/.

01 TRABAJOS PRELIMINARES
01.01 LIMPIEZA DE TERRENO m2 336.00
01.02 TRAZO Y REPLANTEO SIN EQUIPO m2 336.00
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACION DE ZANJAS m3 94.08
03 OBRAS DE CONCRETO SIMPLE
03.01 CIMIENTOS CORRIDOS MEZCLA 1:10 C:H + 30% PG m3 75.26
03.02 CONCRETO SOBRECIMIENTO DE 1:8 C:H + 25% PM m3 48.72
03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 338.24
04 OBRAS DE CONCRETO ARMADO
04.01 CONCRETO F'C=175 KG/CM2 PARA LOSA SANITARIA m3 20.50
04.02 ACERO DE REFUERZO FY=4200 KG/CM2 kg 788.48
04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 61.88
05 ALBAÑILERIA
05.01 ELABORACION DE ADOBE 0.30x0.40x0.12 M. und 13,496.00
05.02 MURO DE ADOBE 30x40x12 CM m2 782.77
06 REVOQUES Y ENLUCIDOS
06.01 TARRAJEO INTERIOR CON MEZCLA DE MORTERO 1:5 m2 940.30
06.02 EMPASTADO DE MURO CON BARRO m2 522.76
07 PISOS Y PAVIMENTOS
07.01 PISO DE CEMENTO COLOREADO Y PULIDO m2 131.04
08 CONTRAZOCALOS
08.01 CONTRAZOCALO DE CEMENTO H=0.40m. 1:5 m 473.20
09 CARPINTERIA DE MADERA
09.01 VIGA DE MADERA 2"x3"x2.05m und 224.00
09.02 CORREAS DE MADERA 2"x2"x10' m 504.00
09.03 SUMINISTRO Y COLOCADO DE PUERTA DE MADERA TIPO TABLERO REBAJADO und 56.00
09.04 SUMINISTRO Y COLOCADO DE VENTANA DE MADERA 0.50x0.40 CON ACRILICO und 56.00
10 COBERTURA
10.01 COBERTURA DE TEJA ANDINA 1.14x0.72M E=5MM m2 424.70
11 PINTURA
11.01 PINTURA LATEX 2 MANOS EN LETRINAS m2 1,869.00
12 APARATOS SANITARIOS
12.01 SUMINISTRO Y COLOCADO DE TAZA TURCA und 56.00
12.02 SUMINISTRO Y COLOCADO DE DUCHA und 56.00
12.03 SUMIDERO DE 2", PARA DUCHA und 56.00
13 INSTALACIONES SANITARIAS
13.01 TENDIDO DE TUBERIA PVC SAL DE 4" m 280.00
13.02 TENDIDO DE TUBERIA PVC SAL DE 2" m 280.00
14 INSTALACIONES ELECTRICAS
14.01 SALIDA DE TECHO C/CABLE AWG TW 2.5MM(14)+D PVC SEL 16MM(5/8) pto 56.00
15 POZO PERCOLADOR
15.01 TRAZO Y REPLANTEO SIN EQUIPO m2 188.16
15.02 EXCAVACION DE ZANJAS m3 338.69
15.03 MAMPOSTERIA DE PIEDRA S/MORTERO m3 152.32
15.04 TAPA PARA POZO DE ABSORCION
997.92
0.84 282.24
2.13 715.68
969.02
10.30 969.02
34,764.53
181.89 13,689.04
225.28 10,975.64
29.86 10,099.85
11,862.31
338.91 6,947.66
4.14 3,264.31
26.67 1,650.34
17,916.50
0.74 9,987.04
10.13 7,929.46
19,297.41
15.28 14,367.78
9.43 4,929.63
606.72
4.63 606.72
2,574.21
5.44 2,574.21
39,584.72
29.53 6,614.72
9.38 4,727.52
340.60 19,073.60
163.73 9,168.88
23,163.14
54.54 23,163.14
11,157.93
5.97 11,157.93
14,568.40
125.18 7,010.08
96.47 5,402.32
38.50 2,156.00
1,976.80
3.68 1,030.40
3.38 946.40
2,970.80
53.05 2,970.80
35,265.20
2.59 487.33
10.30 3,488.51
128.30 19,542.66
11,746.70
Item Descripción Und. Metrado Precio S/. Parcial S/.
15.04.01 CONCRETO F'C=175 KG/CM2 PARA TAPA DE POZA DE ABSORCION m3 18.82
15.04.02
ACERO DE REFUERZO FY = 4200 KG/CM2 kg 865.48
15.04.03
ENCOFRADO Y DESENCOFRADO NORMAL m2 42.56
COSTO DIRECTO
GASTOS GENERALES 15.50%
GASTOS DE SUPERVISION 5.00%
GASTOS DE LIQUIDACION 1.50 %
GASTOS DE EXPEDIENTE TECNICO 3.50%
COSTO TOTAL DE LA OBRA
375.30 7,063.15
4.10 3,548.47
26.67 1,135.08
217,675.61
33,739.72
10,883.78
3,265.13
7,618.65
273,182.89
SON : DOSCIENTOS SETENTITRES MIL CIENTO OCHENTIDOS Y 89/100 NUEVOS SOLES