Documentos de Académico
Documentos de Profesional
Documentos de Cultura
A PROJECT REPORT
Submitted by
SAKET AGARWAL
of
BACHELOR OF COMMERCE
1
In
FINANCE
MARCH, 2010
KOLKATA
BONAFIDE CERTIFICATE
2
SIGNATURE SIGNATURE
3
ACKNOWLEDGEMENT
4
ABSTRACT
It may be arranged in many ways – and project finance is one such way. It is
the raising of funds on a limited recourse or non-recourse basis to finance an
economically separable capital investment project in which the providers of
the funds look primarily to the cash flow from the project as the source of
funds to service their loans and provide a return on their equity invested in
the project.
5
The presented case study involves a peep into Enron scandal and the way it
has impacted project finance, as after Enron project finance was widely
criticized.
Table of Contents
PAGE NO.
1. INTRODUCTION
1.1 Rationale of Project Finance
1-2
1.2 Characteristics of Project Finance
3
1.3 Basic Scheme of Project Finance
4-5
2. LITERATURE REVIEW
2.1 Definition of Project Finance
6-7
2.2 Project Financing Arrangements
8-9
2.2.1 Build Own Operate Transfer
2.2.2 Build Own Operate Structure
2.2.3 Build Lease Transfer Structure
2.3 Project Viability and Financial Modelling
10-23
2.3.1 Technical Feasibility
2.3.2 Project Construction Cost
6
2.3.3 Economic Viability
2.3.4 Adequacy of Raw Material Supplies
2.3.5 Creditworthiness
2.3.6 Financial Modelling
2.4 Project Finance Risk
24-34
2.4.1 Risk Minimization Review
2.4.2 Types Of Risks
2.5 Security Arrangements
35-39
2.5.1 Security Arrangements Covering Completion of Project
2.5.2 Direct Security Interest in Project’s Facilities
2.5.3 Security Covering Debt Service
2.5.4 Purchase And Sale Contract
2.5.5 Raw Material Supply Agreement
2.5.6 Supplemental Credit Support
2.5.7 Financial Support Agreement
2.5.8 Cash Deficiency Agreement
2.5.9 Escrow Fund
2.5.10 Insurance
2.6 Legal Structure
40-44
2.6.1 Undivided Joint Interest
2.6.2 Corporations
2.6.3 Partnerships
2.7 Sources Of Funds
45-49
7
3.2 Caution among Lenders and Investors
52-53
3.3 Project Finance And Enron Factor
53-64
3.3.1 Effect on Traditional Project Finance
3.3.2 Effect in Structured Project Finance
3.3.3 Sources of Free Cash Flow
3.3.4 Security Interests
3.3.5 How Companies Have Responded
3.3.6 Increased Transparency and Disclosure
3.3.7 Regulatory Issues
3.4 Other Lessons Learned
65-66
4. CONCLUSION
67
BIBLIOGRAPHY
68
8
9
10
11
CONTENTS
1. INTRODUCTION 4
2. LITERATURE REVIEW 6
3. METHODOLOGY 17
4. HYPOTHESIS 26
5. RESULTS 27
6. CONCLUSION 28
7. EXECUTIVE SUMMARY 30
ANNEXURE
BIBLIOGRAPHY
12
1. INTRODUCTION
13
There is a growing realization in many developing countries of the
limitations of governments in managing and financing economic activities,
particularly large infrastructure projects, Provision of infrastructure
facilities, traditionally in the government domain, is now being offered for
private sectors investments and management. This trend has been
reinforced by the resource crunch faced by many governments.
Infrastructure projects are usually characterized by large investments, long
gestation periods, and very specific domestic markets.
In project financing the project, its assets, contracts, inherent economic and
cash flows are separated from their promoters or sponsors in order to permit
credit appraisal and loan to the project, independent of the sponsors. The
assets of the specific project serve as a collateral for the loan, and all loan
repayments are made out of the cash of the project. In this sense, the loan
is said to be of non-resource to the sponsor.
14
Thus, project financing may be defined as the scheme of ‘financing of a
particular economic unit in which l lender is satisfied in looking at the cash
flows and the earnings of that economic unit as a source of funds, from
which a loan can be repaid, and to the assets of the economic unit as a
collateral for the loan. In the past, project financing was mostly used in oil
exploration and other mineral extraction through joint ventures with foreign
firms. The most recent use of project financing can be found in
infrastructure projects, particularly in power and telecommunication
projects. Project financing is made possible by combining undertakings and
various kinds of guarantees by parties who are interested in a project. It is
built in such a way that no one party alone has to assume the full credit
responsibility of the project. When all the undertakings are combined and
reviewed together, it results in an equivalent of the satisfactory credit risk
for the lenders. It is often suggested that the project financing enables a
parent company to obtain inexpensive loans without having to bear all the
risks of the project. This is not true, in practice, the parent company is
affected by the actual plight of the project, and the interests on the project
loan depend on the parents stake in the project. The traditional form of
financing is the corporate financing or the balance sheet financing. In this
case, although financing is apparently for a project, the lender looks at the
cash flows and assets of the whole company in order to service the debt and
provide security.
15
1.2 Characteristics of Project Finance
• A separate project entity is created that receives loans from lenders and
equity from sponsors.
• The project funding and all it’s other cash flows are separated from the
parent company’s balance sheet.
• Debt services and repayments entirely depend on the project’s cash flows.
Project assets are used as collateral for loan repayments.
16
Project financing is most appropriate for those projects, which require large
amount of capital expenditure and involve high risk. It is used by
companies to reduce their own risk by allocating the risk to a number of
parties.
• Finance large projects than the company’s credit and financial capability
would permit.
• Insulate the company’s balance sheet from the impact of the project.
The basic scheme of project finance has been explained with an example:
Acme Coal Co. imports coal. Energen Inc. supplies energy to consumers.
The two companies agree to build a power plant to accomplish their
respective goals. Typically, the first step would be to sign a memorandum of
understanding to set out the intentions of the two parties. This would be
followed by an agreement to form a joint venture.
17
Acme Coal and Energen form an SPV (Special Purpose Vehicle) called
Power Holdings Inc. and divide the shares between them according to their
contributions. Acme Coal, being more established, contributes more capital
and takes 70% of the shares. Energen is a smaller company and takes the
remaining 30%. The new company has no assets.
Acme Coal and Energen form Power Manage Inc., another SPV, to manage
the facility. The ultimate purpose of the two SPVs (Power Holding and
Power Manage) is primarily to protect Acme Coal and Energen. If a disaster
happens at the plant, prospective plaintiffs cannot sue Acme Coal or Energen
and target their assets because neither company owns or operates the plant.
A Sale and Purchase Agreement (SPA) between Power Manage and Acme
Coal supplies raw materials to the power plant. Electricity is then delivered
to Energen using a wholesale delivery contract. The cash flow of both Acme
Coal and Energen from this transaction will be used to repay the financiers.
18
FIGURE - I
2. LITERATURE REVIEW
19
2.1 Definition of Project Finance
--------------------------------------------------------------------------------------------
21
2.2 Project Financing Arrangements
22
It is a special financing scheme, which is designed to attract private
participation in financing constructing and operating infrastructure projects.
In BOOT scheme, a private project company builds a project, operates it for
a sufficient period of time to earn an adequate return on investment, and then
transfers it to the host government or its agency. Quite often, the value of
efficiency gain from private participation can outweigh the extra cost of
borrowing through a BOOT project, relative to direct government borrowing.
The private group usually consists of international construction contractors,
heavy equipment suppliers, and plant and system operators along with local
partners.
23
2.2.3 Build-Lease-Transfer arrangement
24
Investors are concerned about all the risks a project involves, who will bear
each of them, and whether their returns will be adequate to compensate them
for the risks they are being asked to bear. Both the sponsors and their adviser
must be thoroughly familiar with the technical aspects of the project and the
risks involved, and they must independently evaluate a projects economics
and its ability to service project related borrowings.
2.3.1.Technical Feasibility:
25
2.3.2 Project Construction Cost:
The detailed engineering and design work provides the basis for estimating
the construction costs for the project. Construction costs should include the
cost of all facilities necessary for the project’s operation as a freestanding
entity. Construction costs should include contingency factor adequate to
cover possible design errors or unforeseen costs. Project sponsors or their
advisers generally prepare a time schedule detailing the activities that must
be accomplished before and during the construction period. A quarterly
breakdown of capital expenditures normally accompanies the time schedule.
(2) The procurement lead time anticipated for major pieces of equipment and
26
The project sponsor examines the critical path of the construction schedule to
determine where the risk of delay is greatest and then assesses the potential
financial impact of any projected delay.
27
The critical issue concerning economic viability is whether the project’s
expected net present value is positive. It will be positive only if the expected
present value of the future free cash flows exceeds the expected present
value of the project’s construction costs. All the factors that can affect
project cash flows are important in making this determination. Assuming that
the project is completed on schedule and within budget, its economic
viability will depend primarily on the marketability of the projects output
(price and volume). To evaluate marketability, the sponsors arrange for a
study of projected supply and demand conditions over the expected life of
the project. The marketing study is designed to confirm that, under a
reasonable set of economic assumptions, demand will be sufficient to absorb
the planned output of the project at a price that will cover the full cost of
production, enable the project to service its debt, and provide an acceptable
rate of return to equity investors.
2) An analysis of the expected life cycle for project output, expected sales
volume, and projected prices; and
28
An independent firm of experts usually performs the study. If the project
will operate within a regulated industry, the potential impact of regulatory
decisions on production levels and prices—and, ultimately, on the
profitability of the project –must also be considered. The cost of production
will affect the pricing of the project output. Projections of operating costs are
prepared after project design work has been completed. Each cost element,
such as raw materials, labor, overhead, taxes, royalties, and maintenance
expense, must be identified and quantified. Typically, this estimation is
accomplished by dividing the cost element into fixed and variable cost
components and estimating each category separately. Each operating cost
element should be escalated over the term of the projections at a rate that
reflects the anticipated rate of inflation. From a financing standpoint, it is
important to assess the reasonableness of the cost estimates and the extent to
which the pricing, and hence the marketability, of the project output is likely
to be affected by estimated cost inflation rates. In addition to operating costs,
the project’s cost of capital must be determined. The financial adviser
typically is responsible for this task. He develops and tests various financing
plans for the project in order to arrive at an optimal financing plan that is
consistent with the business objectives of the project sponsor.
29
The project should have sufficient supplies of raw materials to enable it to
operate at design capacity over the term of the debt. Independent consultants
may be summoned to evaluate the quantity, grade, and rate of extraction that
the mineral reserves available to the project are capable of supporting. The
project should have the ability to access the raw materials through
contractual agreements like direct ownership, lease, purchase agreement etc.
2.3.5 Creditworthiness:
A project has no operating history at the time of its initial debt financing.
Consequently, the amount of debt the project can raise is a function of the
project’s expected capacity to service debt from project cash flow- or more
simply, its credit strength.
30
Thus,
31
2.4 PROJECT FINANCE RISK
Financiers are concerned with minimizing the dangers of any events that
could have a negative impact on the financial performance of the project, in
particular, events that could result in:
32
(1) The project not being completed on time, on budget, or at all;
(3) The project failing to generate sufficient revenue to service the debt; or
The minimization of such risks involves a three-step process. The first step
requires the identification and analysis of all the risks that may bear upon the
project. The second step is the allocation of those risks among the parties.
The last step involves the creation of mechanisms to manage the risks.
33
The project sponsors will usually prepare a feasibility study, e.g. as to the
construction and operation of a mine or pipeline. The financiers will
carefully review the study and may engage independent expert consultants to
supplement it. The matters of particular focus will be whether the costs of the
project have been properly assessed and whether the cash-flow streams from
the project are properly calculated. Some risks are analyzed using financial
models to determine the project's cash flow and hence the ability of the
project to meet repayment schedules. Different scenarios will be examined
by adjusting economic variables such as inflation, interest rates, exchange
rates and prices for the inputs and output of the project. Various classes of
risk that may be identified in a project financing will be discussed below.
Once the risks are identified and analyzed, they are allocated by the parties
through negotiation of the contractual framework. Ideally a risk should be
allocated to the party who is the most appropriate to bear it (i.e. who is in the
best position to manage, control and insure against it) and who has the
financial capacity to bear it. It has been observed that financiers attempt to
allocate uncontrollable risks widely and to ensure that each party has an
interest in fixing such risks. Generally, commercial risks are sought to be
allocated to the private sector and political risks to the state sector.
34
STEP 3 - Risk management
Risks must be also managed in order to minimize the possibility of the risk
event occurring and to minimize its consequences if it does occur. Financiers
need to ensure that the greater the risks that they bear, the more informed
they are and the greater their control over the project. Since they take
security over the entire project and must be prepared to step in and take it
over if the borrower defaults. This requires the financiers to be involved in
and monitor the project closely. Such risk management is facilitated by
imposing reporting obligations on the borrower and controls over project
accounts. Such measures may lead to tension between the flexibility desired
by borrower and risk management mechanisms required by the financier.
35
(ii) The operation phase; or
It is useful to divide the project in this way when looking at risks because the
nature and the allocation of risks usually change between the construction
phase and the operation phase.
36
Completion risk:
Completion risk allocation is a vital part of the risk allocation of any project.
This phase carries the greatest risk for the financier. Construction carries the
danger that the project will not be completed on time, on budget or at all
because of technical, labour, and other construction difficulties. Such delays
or cost increases may delay loan repayments and cause interest and debt to
accumulate. They may also jeopardize contracts for the sale of the project's
output and supply contacts for raw materials.
(a) Obtaining completion guarantees requiring the sponsors to pay all debts
and liquidated damages if completion does not occur by the required date;
(b) Ensuring that sponsors have a significant financial interest in the success
of the project so that they remain committed to it by insisting that sponsors
inject equity into the project;
37
Completion risk is managed during the loan period by methods such as
making pre-completion phase drawdown’s of further funds conditional on
certificates being issued by independent experts to confirm that the
construction is progressing as planned.
This is the risk that for a mining project, rail project, power station or toll
road there are inadequate inputs that can be processed or serviced to produce
an adequate return.
For example, this is the risk that there are insufficient reserves for a mine,
passengers for a railway, fuel for a power station or vehicles for a toll road.
Such resource risks are usually minimized by:
(a) Experts’ reports as to the existence of the inputs (e.g. detailed reservoir
and engineering reports which classify and quantify the reserves for a mining
project) or estimates of public users of the project based on surveys and other
empirical evidence (e.g. the number of passengers who will use a railway);
38
(b) Requiring long term supply contracts for inputs to be entered into as
protection against shortages or price fluctuations (e.g. fuel supply
agreements for a power station);
(c) Obtaining guarantees that there will be a minimum level of inputs (e.g.
from a government that a certain number of vehicles will use a toll road); and
(d) "Take or pay" off-take contacts, which require the purchaser to make
minimum payments even if the product cannot be delivered.
Operating risk
These are general risks that may affect the cash flow of the project by
increasing the operating costs or affecting the project's capacity to continue
to generate the quantity and quality of the planned output over the life of the
project. The usual way for minimizing operating risks before lending takes
place is to require the project to be operated by a reputable and financially
sound operator whose performance is secured by performance bonds.
Operating risks are managed during the loan period by requiring the
provision of detailed reports on the operations of the project and by
controlling cash-flows by requiring the proceeds of the sale of product to be
paid into a tightly regulated proceeds account to ensure that funds are used
for approved operating costs only.
39
Market / off-take risk
Obviously, the loan can only be repaid if the product that is generated can be
turned into cash. Market risk is the risk that a buyer cannot be found for the
product at a price sufficient to provide adequate cash flow to service the
debt. The best mechanism for minimizing market risk before lending takes
place is an acceptable forward sales contact entered into with a financially
sound purchaser.
These are the risks associated with the sponsors or the borrowers themselves.
The question is whether they have sufficient resources to manage the
construction and operation of the project and to efficiently resolve any
problems that may arise. Of course, credit risk is also important for the
sponsors' completion guarantees. To minimize these risks, the financiers
need to satisfy themselves that the participants in the project have the
necessary human resources, experience in past projects of this nature and are
financially strong.
40
Technical risk
Currency risk
41
(a) Matching the currencies of the sales contracts with the currencies of
supply contracts as far as possible;
(b) Denominating the loan in the most relevant foreign currency; and
These are risks that government licenses and approvals required to construct
or operate the project will not be issued (or will only be issued subject to
onerous conditions), or that the project will be subject to excessive taxation,
royalty payments, or rigid requirements as to local supply or distribution.
Such risks may be reduced by obtaining legal opinions confirming
compliance with applicable laws and ensuring that any necessary approvals
are a condition precedent to the drawdown of funds.
Political risk
42
This is the danger of political or financial instability in the host country
caused by events such as insurrections, strikes, and suspension of foreign
exchange, creeping expropriation and outright nationalization. It also
includes the risk that a government may be able to avoid its contractual
obligations through sovereign immunity doctrines. Common mechanisms for
minimizing political risk include: (a) requiring host country agreements and
assurances that project will not be interfered with;
(b) Obtaining legal opinions as to the applicable laws and the enforceability
of contracts with government entities;
(e) Establishing accounts in stable countries for the receipt of sale proceeds
from purchasers.
43
This is the risk of events which render the construction or operation of the
project impossible, either temporarily (e.g. minor floods) or permanently
(e.g. complete destruction by fire). Mechanisms for minimizing such risks
include:
(b) Allocating such risks to other parties as far as possible (e.g. to the builder
under the construction contract); and
Country Risk
Country risk includes risks of currency transfer, expropriation, war and civil
disturbances, and breach of contract by the host government. The multilateral
Investment guarantee Agency (MIGA) of the World Bank provides
guarantee against country risk for an appropriate premium. Export credit
agencies also provide such guarantees but they usually seek counter-
guarantees from the host government.
Sector Risk
44
Sector risk refers to the risk in certain sectors because of the role of
government agencies in those sectors. For example, in the power sector, the
buyer is usually a government utility agency that transmits and distributes
power. The solvency of the utility is critical for the ‘take or pay’ power
purchase agreement to have any value. For selected power projects, the
Indian government has agreed in principle to give counter guarantees to back
up state guarantees for the State Electricity Boards (SEBs), payment
obligations to private generating companies, on a specific request to the state
government concerned and subject to the state government agreeing to
certain terms and conditions. For toll roads, government support may be
necessary to enforce toll collections. Similarly, in the case of municipal
services such as water supply and solid-state disposal, the support of
municipal authorities is important. In each case, the government may
guarantee contract compliance of the respective agencies.
45
2.5 Security Arrangements
46
Arranging sufficient credit support for project debt securities is a necessary
precondition to arranging debt financing for any project. Lenders to a project
will require that security arrangements be put in place to protect them from
various risks. The contractual security arrangements apportion the risks
among the project sponsors, the purchasers of the project output, and the
other parties involved in the project. They represent a means of conveying
the credit strength of going-concern entities to support project debt.
47
2.5.2 Direct security interest in project facilities:
After the project commences operations, contracts for the purchase and sale
of the project’s output or utilization of the project’s services normally
constitute the principal security arrangements for project debt. Such contracts
are intended ensure that the project will receive revenues that are sufficient
to cover operating costs fully and meet debt service obligations in a timely
manner.
48
2.5.4 Purchase and Sale Contracts:
(a)Take-if-offered contract:
49
A Take-or-pay contract is similar to a Take-if-offered contract; it gives the
buyer the option to make cash payment in lieu of taking delivery, whereas
the take-if-offered contract requires the buyer to accept deliveries. Cash
payments are usually credited against charges for future deliveries. Like the
take-if-offered contract, a take-or-pay contract does not require the purchaser
to pay if the project is unable to deliver the output or services.
This is similar to a take-or-pay contract except that there are no ‘outs’ even
when adverse circumstances are beyond the control of the purchaser. The
purchaser must pay in all events, regardless of whether any output is
delivered. It therefore provides lenders with tighter security than other
contracts.
Step-up provisions:
50
A raw material supply agreement represents a contract to fulfill the project’s
raw material requirements. The contract specifies certain remedies when
deliveries are not made. Often both purchase and supply contracts are made
to provide credit support for a project. A supply-or-pay contract obligates the
raw material supplier to furnish the requisite amounts of the raw material
specified in the contract or else make payments to the project entity that are
sufficient to cover the project’s debt service.
51
A financial support agreement can take the form of a letter of credit or
similar guarantee provided by the project sponsors. Payments made under
the letter of credit or similar guarantee are treated as subordinated loans to
the project company. In some cases it is advantageous to purchase the
guarantee of a financially able party to provide credit support for the
obligations of a project company
It is designed to cover any cash shortfalls that would impair the project
company’s ability to meet its debt service requirements. The obligor makes a
cash payment sufficient t cover the cash deficiency. Payments made under a
cash deficiency agreement are usually credited as cash advances toward
payment for future services or product from the project.
52
2.5.10 Insurance:
Lenders typically require that insurance betaken out to protect against certain
risks of force majeure. The insurance will provide funds to restore the project
in the event of force majeure, thereby ensuring that the project remains a
viable entity. The project sponsors normally purchase commercial insurance
to cover the cost of damage caused by natural disasters. They may also
secure business interruption insurance to cover certain other risks. In
addition lenders may require the sponsors to agree contractually to provide
additional funds to the project to the extent insurance proceeds are
insufficient to restore the operations.
53
2.6 LEGAL STRUCTURE
Sponsors of projects adopt many different legal forms for the ownership of
the project. The specific form adopted for any particular project will depend
upon many factors, including:
54
undivided interest in the real and personal property constituting the project
and shares in the benefits and risks of the project in direct proportion to the
ownership percentage. The ownership interests relate to the entire assets of
the project; no participant is entitled to any particular portion of the property.
When the project is organized, the participants choose someone in their ranks
to serve as the project operator. This arrangement is particularly suitable
when one of the owners already has operations in the same industry that are
of a similar nature, or otherwise has qualified employees available. The
duties of the operator and obligations of all other parties are specified in an
operating statement. The joint venture will require each participant to
assume responsibility for raising its share of the project’s external financing
requirements. Each sponsor will be free to do so by whatever means are most
appropriate to its circumstances.
55
also provide the project sponsors with immediate cash flow to fund their
equity investments.
2.6.2 Corporation
2.6.3 Partnership:
57
They are not exposed to unlimited liability. However, there must be at least
one general partner who does have such exposure.
58
100% OWNERSHIP 100% OWNERSHIP 100% OWNERSHIP
X Y Z
100%
OWNER
59
2.7 SOURCES OF FUNDS
Financing options i.e the various sources of finance are equity, debt, Indian
and international financial institutions, multilateral institutions, export credit
agencies, GDR’s and external commercial borrowings.
In raising debt or financing the power sector projects the list of funds should
be the lowest so that the ultimate cost of electricity will be the lowest for the
end consumer. The decision of the promoter to go in for equity or debt
financing depends on various factors like go guidelines for power projects,
incentives available and return on equity as also the cost of debt vis-a vis
equity.
60
Domestic Capital market Bonds are issued by the Central / State Government
and Publish/private Ltd. Companies t augment the resources of the power
sector in the capital market. Presently, internal rates are regulated and credit
rating is mandatory if the maturity of the instruments exceeds 18 months.
NCDs with an option of buy back, debentures with equity warrants, floating
rate bonds and deep discount bonds are some of the innovative instruments
offered in the market.
The area of project financing in the Indian context is mainly limited to the
Indian Term Lending Institutions. In addition a large number of state level
institutions, finance projects of smaller size commercial banks also
participate in the term loans to a limited extent, besides meeting the working
capital requirements. As no individual FI can feed to the power sector
because of the huge funds requirements and the long gestation period of the
projects. The concept of loan syndication amongst the FIs is gaining
momentum. This also helps in sharing the risk among the FIs apart from
saving o the efforts and the cost because of the appraisal done by the leading
institution.
61
(d) Sources of international finance
Due to the domestic finance viable for the power projects, the need to tap
international markets has become inevitable which is characterized by the
long tenure of maturities and availability of various modes of finance.
Institutions like the World Bank, IFC, and ADB etc. Have traditionallybeen
financing infrastructure in developing countries. The financing comer with
restrictive covenants affordable costs, long tenure and in an assured manner.
The co-financing facility extended by some of the multilateral institutions is
gaining popularity. In many of these loans, sovereign guarantee is required.
62
(g) External commercial borrowings
GDRs present an attractive avenue of funds for the Indian companies. Indian
Companies can collect a large volume of funds in foreign currency in Euro
issues. GDRs are usually listed in Luxembourg and are traded in London in
the OTC market or among a restricted group such as Qualified Institutional
Buyers (QIBs) in the USA. The GDRs do not have a voting right; there is no
fear of management control.
63
FIGURE4: SOURCES OF FUNDS
64
3. CASE STUDY :
2001, Enron employed approximately 22,000 staff and was one of the
world's leading electricity, natural gas, communications and pulp and paper
years.
At the end of 2001 it was revealed that its reported financial condition was
sustained substantially by institutionalized, systematic, and creatively
planned accounting fraud, known as the "Enron scandal". Enron has since
become a popular symbol of willful corporate fraud and corruption. The
scandal also brought into question the accounting practices of many
corporations throughout the United States and was a factor in the creation
of the Sarbanes–Oxley Act of 2002. The scandal also caused the
dissolution of the Arthur Andersen accounting firm, affecting the wider
business world.
Enron filed for bankruptcy protection in the Southern District of New York in
late 2001 and selected Weil, Gotshal & Manges as its bankruptcy counsel.
It emerged from bankruptcy in November 2004, pursuant to a court-
approved plan of reorganization, after one of the biggest and most complex
bankruptcy cases in U.S. history. A new board of directors changed the
name of Enron to Enron Creditors Recovery Corp and focused on
reorganizing and liquidating certain operations and assets of the pre-
bankruptcy Enron. On September 7, 2006, Enron sold Prisma Energy
International Inc., its last remaining business, to Ashmore Energy
International Ltd. (now AEI).
66
3.2 CAUTION AMONG LENDERS AND INVESTORS
67
Similar to lenders and investors, companies that trade with each other are
becoming more concerned with counterparty credit risk. In evaluating the
creditworthiness of a given counterparty, they are looking at the whole
portfolio to see if one risky business such as merchant power or energy
trading—diversification benefits aside— could drag down the others.
68
The Enron bankruptcy and related events have changed neither the nature nor
the usefulness of traditional project finance, but they have led to a slowing
down of some of the more innovative forms of structured project finance.
Among the other direct and indirect effects of Enron have been increased
caution among lenders and investors toward the energy and power sectors;
increased scrutiny of off-balance sheet transactions, increased emphasis on
counterparty credit risk particularly with regard to companies involved in
merchant power and trading and deeper analysis of how companies generate
cash flow. There is increased emphasis on transparency and disclosure even
tough disclosure in traditional project finance has been more robust than in
most types of corporate finance. In the current market environment, for
reasons that extend beyond Enron, some power companies have been
cancelling projects and selling assets to reduce leverage and resorting to on
balance financing to fortify liquidity.
The combination of these events in 2001, accentuated at the end of the year
by the Enron bankruptcy, caused a dramatic change in the perception of risk
among investors, lenders, and rating agencies. In particular, these parties
began to perceive independent power producers (IPPs) riskier than they ever
had before.
70
They considered trading businesses difficult to evaluate; they suspected
earnings manipulation through the marking to market of power contracts and
off-balance-sheet vehicles; they feared sustained low power prices in the
U.S. market. After problems in countries such as Argentina, Brazil, India and
Indonesia, emerging market IPP projects began to seem more like a danger
than an opportunity. Investors and lenders began to perceive earnings in the
IPP and trading business to be less predictable and sustainable than they had
thought before. They discounted the growth prospects of these companies
and focused on liquidity and leverage in light of higher perceived risk.
They have bad exposures in foreign markets that have collapsed; they have
had to cancel advance purchase orders for turbines because of a slowing U.S.
power market; their stock prices are tumbling as a result of reduced growth
prospects; and they are facing a credit crunch from lenders, some of which
are gun-shy from recent losses related to PG&E or Enron. So, as we look at
today’s energy and power market, we see some direct effects of the Enron
bankruptcy and other situations caused by a combination of all the factors
discussed above.
But before going further, let’s look at how Enron has affected pure,
traditional project finance.
71
3.3.1 EFFECT ON TRADITIONAL PROJECT FINANCE
“Traditional” project finance is cash flow based; asset-based finance that has
little in common with Enron’s heavily criticized off- balance-sheet
partnerships. The historic elements of project finance are firmness of cash
flow, counterparty creditworthiness, ability to deal over a long time frame,
and confidence in the legal system. It is a method for monetizing cash flows,
enhancing security, and sharing or transferring risks. The Enron transactions
in question generally did not have these characteristics. They were an
attempt to unduly benefit from accounting, tax, and disclosure requirements
and definitions.
72
For example, in the case of Joint venture where a company owns 50% of a
project or less, the equity method of accounting is used for off balance-sheet
treatment. On the income statement, the company’s share of earnings from
the project is included below the line in the equity investment in
unconsolidated subsidiaries.
When a company owns more than 50% of a project, its debt is consolidated
on the balance sheet and its dividends are included in income. The minority
interest is backed out. The point to remember is that whether a project is
financed on or off the balance sheet, analysts know where to look.
Also off-balance-sheet treatment may not be the principal reason for most
project financing. It usually is motivated more by considerations such as risk
transfer or providing a way for parties with different credit rating to jointly
finance a project – whereas if all of those parties providing the financing on
their own balance sheets, they would be providing unequal amounts of
capital by virtue of their different borrowing costs. None of these
considerations have anything to do with the Enron partnerships, where 3 %
equity participation from a financial player with nothing at risk was used as a
gimmick to get assets and related debt off the balance sheet.
73
Even though traditional project finance has not been affected very much by
Enron, there certainly has been a slowing of activity in the more innovative
types of structured finance such as synthetic leasing, structured partnerships,
and equity share trusts – at least for the time being.
Even though synthetic lease are transparent and well understood, they have
an off-balance sheet element that creates headlines in today’s environment,
more of them maybe done in a year or two.
The investor market has overreacted to anything that sounds “like Enron”.
Structured and project financing techniques have been developed for sound
risk management reasons and, in my opinion, must be defended vigorously
on those grounds. I believe a prejudice against such financial structures could
have a real economic and financial cost. However if sponsors fear that the
wider market will punish them for using complex structures, they will stop
using them.
At the time of Enron scandal several companies had already made public
vows not to use any off – balance sheet structures.
74
But, rather than pandering to uninformed sentiment, one should make greater
efforts to clearly delineate the difference between legitimate non-recourse
debt and the Enron structures.
75
Immediately after Enron filed for bankruptcy protection, some questioned
whether project and structured finance would survive in its form. And
indeed, some corporations with large amounts of off- balance sheet financing
were subjected to increased scrutiny and sharply red valuations for both their
equity and their debt. In response those companies have expanded their
liquidity and reduced their debt to the extent possible. But, as time
progresses, the main fallout from Enron and the other recent market shocks
have not been so much of a turning away from project finance but rather a
greater stress on bottom-up evaluation of how companies generate recurring
free cash flow and what might affect it over time. In this process, project as
well as structured finance probably will continue to play an important role.
The change, has been that the focus has shifted from not only the project
structures, but also on how they may affect corporate level cash flow and
credit profiles, for example through springing guarantees and potential debt
acceleration, through contingent indemnification and performance
guarantees, and through the potential for joint-venture and partnership
dissolutions to create sudden changes in cash flows.
76
Power business, in part, has shifted from a contract-based business to a
trading, cash flow- based kind of business where the counterparty becomes
critical to the viability of a transaction. The security in the transaction is less
than the asset itself and more what the trading counterparty does with the
asset. That asset has an option value in the hands of a counterparty, but a far
different value if a bask has to foreclose on it—a value you would rather not
find out.
Enron’s alleged tendency to set its own rules for marking gas, electricity and
various other newer, thinly traded derivative contacts to market raises some
questions about collateral and security. Historically, the security in a power
plant financing has consisted of contracts, counterparty arrangements and
assets. But if a lender’s security depends on marking certain contracts to
market and there is some question as to the objectivity of the counterparty
that is marking them to market, that raises additional questions as to what is
an adequate sale, what is adequate collateral, how a lender takes an adequate
security interest, how a lender monitors the value of its security interest, and
what needs to be done to establish a sufficient prior lien in the cash flow
associated with the transaction. In the case of a structured project finance
transaction, the key question remains just as it always has been: whether the
security is real and whether you can get rely on it.
77
3.3.5 HOW COMPANIES HAVE RESPONDED
Some power companies have set up massive credit facilities for doing so
based on their overall corporate cash flow and creditworthiness. Another
option for a company is to borrow against a basket of power projects,
allowing the lenders to diversify their risks, but such a facility is still largely
based on the credit fundamentals of the corporation. But project financing on
an individual plant basis can be preferable to either of these approaches for
both project sponsors and lenders.
78
For example, say a company is financing ten projects and three run into
trouble. The company can make a rational economic decision as to which of
those projects are salvageable and which ones do not merit throwing in good
money after bad. It might let one go into foreclosure and be restructured and
sold. But if a company is financing ten projects together, its management
may feel compelled to artificially bolster some of its projects so that the
failure of one project does not bring the entire credit facility down. Making
such an uneconomic decision for the near term would not be in the
company’s long-term interests.
79
The major players generally are releasing much more information than
before about their businesses and financing arrangements. Similarly, an
overriding aura of conservatism in disclosure has been seen, for example, in
conference room discussions while drafting prospectuses for project finance
deals. Bankers are making extra efforts to confirm that details are being
disclosed and explained the right way. Given the current tarnishing of the
merchant power sector, they might explain further than in the past that a
company’s trading is not speculative and that it is using accepted risk
management measures such as value-at-risk (VAR). They also might break
out the percentage of sales from power sales and from “marketing”—a team
that sounds better than trading in today’ environment
Managing earnings is out and managing cash flow is in—and, that’s what the
rating agencies are looking at anyway.
80
Companies may need to reexamine their strengths and weaknesses and
refocus and simplify their basic business strategies. Their boards of directors
might become more helpful in this process with the addition of non-
executive members who understand the business.
One of the reasons Enron was left to its own devices in valuing gas,
electricity, and other types of contracts was that it became, in effect the
largest unregulated bank in the world. It was able to avoid regulation of its
activities by the Commodity Futures Trading Commission (CFTC). Partly as
a result of its own lobbying efforts, and the Federal Energy Regulation
Commission (FERC) declined to get involved as well. Therefore, it was able
to duck some of the scrutiny that regulators have directed toward commercial
and investment banks dealing in derivatives. Of course, securities analysis
had long complained about Enron’s opaque financial reporting, only to be
told in return that they just didn’t understand the business.
81
FERC will have to become more involved in trading than it has in the past.
FERC’s current emphasis is to avoid the abuse of market power in the
electricity business But today, a power company might have market power in
trading completely unrelated to market power in asset ownership. Enron
proved that they are two different things. A company can dominate trading
market without dominating the asset-ownership market. So regulatory lesson
to be learned from Enron is that today’s electricity market needs more
sophisticated oversight of both the trading function and market power.
82
3.4 OTHER LESSONS LEARNED
Among the more general lessonsfrom Enron that go beyond the realm of
structured and project finance are:
83
• Mark-to-market accounting rules can mislead investors, lenders, and
analysts as to the extent of non-recurring earnings, even in the absence of
fraud.
Among the lessons more directly related to project and structured finance are
the following:
• Having been badly burned by the Enron bankruptcy, banks and investors in
its structured and project financings, and in the energy sector generally, will
be especially conservative, and this will limit credit and capital access for
many clients in the sector, creating a genera liquidity issue for these
customers.
84
• An effort must be made by all in the project finance industry (and investor
relations) to underscore the distinction between true non-recourse structures
and Enron’s activities
• The terms “non-recourse” and “off balance sheet should remain synonyms.
Liabilities that truly have no recourse to a company’s shareholders can justly
be treated as off balance sheet. Enron appears to have violated this principle
since the undisclosed liabilities in the off- balance sheet partnerships actually
had significant recourse to Enron shareholders through share marketing
mechanisms.
• Many project finance structures are “limited” rather than “non” recourse,
and thus there is a potential grey area in which accounting rules allow off-
balance sheet treatment but there is nonetheless some contingent liability to
the parent company shareholders. Full disclosure of any potential
shareholder recourse was advisable pre-Enron and is absolutely necessary
now.
4. CONCLUSION
85
Two basic tenets of project finance:
I) The financing of hard assets that have ongoing value through economic
cycles and
To conclude, project finance is alive and well. We just need to remind a few
people of its basic fundamentals. Neither project finance nor sensible in
innovations in structured finance with sound, well explained business
reasons have been shaken by Enron.
The principle lessons learned from the Enron debacle have to do with
transparency and disclosure. When some of your businesses or your finance
structures become hard to explain, you may begin to question whether they
make sense in the first place.
86
BIBLIOGRAPHY
• Nevitt, P.K., and F.J. Fabozzi, 2000, Project Financing, 7th edition,
Euromoney Books (London, U.K.).
• Wikepedia.com - (http://en.wikipedia.org/wiki/Project_finance)
(en.wikipedia.org/wiki/Enron)
87
• www.projectfinancemagazine.com/
• www.people.hbs.edu/besty/projfinportal/
• www.pfie.com
• www.projectfinancereview .com
• www.time.com/time/2002/enron
• www.enronfraud.com/
• www.uow.edu.au/~bmartin/dissent/documents/.../citienron.html
88