PRESUPUESTO BASE (SEGÚN EXPEDIENTE TECNICO APROBADO)

ENTIDAD : MUNICIPALIDAD DISTRITAL DE CHUNGUI

PROYECTO : “INSTALACION DE SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P, EN LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO”

TIEMPO DE EJECUCIÓN : 180 DIAS CALENDARIO

PRESUPUESTO BASE PRESUPUESTO


ITEM DESCRIPCIÓN UND COEFICIENTE
METRADO PRE. UNIT. BASE DE INCIDENCIA
01 AULAS
01.01 OBRAS PRELIMINARES
01.01.01 ALQUILER DE ALMACEN mes 6.00 423.73 S/. 2,542.38 0.39%
01.01.02 CARTEL DE OBRA glb 1.00 593.22 S/. 593.22 0.09%
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DE TERRENO MANUAL m2 223.82 0.74 S/. 165.63 0.03%
01.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 300.00 1.87 S/. 561.00 0.08%
01.03 MOVIMIENTO DE TIERRAS
01.03.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 55.71 14.72 S/. 820.05 0.12%
01.03.02 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 25.85 1.44 S/. 37.22 0.01%
01.03.03 EXCAVACIONES
01.03.03.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 35.98 14.44 S/. 519.55 0.08%
01.03.03.02 EXCAVACION MANUAL DE ZAPATAS m3 30.00 14.72 S/. 441.60 0.07%
01.03.03.03 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES DE VEREDAS m3 2.24 14.44 S/. 32.35 0.00%
01.03.03.04 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS DE DRENAJE m3 5.82 14.72 S/. 85.67 0.01%
01.03.03.05 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 10.35 9.02 S/. 93.36 0.01%
01.03.03.06 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 158.60 6.02 S/. 954.77 0.14%
01.03.03.07 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 200.42 0.74 S/. 148.31 0.02%
01.03.03.08 AFIRMADO DE e=4" PARA PISOS INTERIORES Y EXTERIORES m2 119.98 24.34 S/. 2,920.31 0.44%
01.04 CONCRETO SIMPLE
01.04.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 13.82 559.63 S/. 7,734.09 1.17%
01.04.02 SUBCIMIENTO C:H=1:12+30% PG m3 15.72 525.00 S/. 8,253.00 1.25%
01.04.03 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 20.00 44.27 S/. 885.40 0.13%
01.04.04 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 5.69 559.11 S/. 3,181.34 0.48%
01.04.05 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 59.52 19.61 S/. 1,167.19 0.18%
01.04.06 FALSO PISO e= 4" ( MEZCLA 1:10 CEMENTO : HORMIGON ) m2 146.87 58.90 S/. 8,650.64 1.31%
01.04.07 CONCRETO F'C=140 KG/CM2 EN CANALETAS m3 6.11 671.93 S/. 4,105.49 0.62%
01.04.08 ENCOFRADO Y DESENCOFRADO EN CANALETAS m2 31.36 31.65 S/. 992.54 0.15%
01.04.09 JUNTAS ASFALTICAS m 3.20 7.13 S/. 22.82 0.00%
01.04.10 TUBERIA PVC SAL D=8" m 6.00 49.98 S/. 299.88 0.05%
01.05 CONCRETO ARMADO
01.05.01 VIGA DE CIMENTACION
01.05.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 4.17 691.52 S/. 2,883.64 0.44%
01.05.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 41.65 25.25 S/. 1,051.66 0.16%
01.05.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 481.42 3.71 S/. 1,786.07 0.27%
01.05.02 ZAPATAS
01.05.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 12.00 776.93 S/. 9,323.16 1.41%
01.05.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 236.87 3.71 S/. 878.79 0.13%
01.05.03 COLUMNAS
01.05.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 9.45 812.05 S/. 7,673.87 1.16%
01.05.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 85.11 30.13 S/. 2,564.36 0.39%
01.05.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,992.18 3.71 S/. 7,390.99 1.12%
01.05.04 VIGAS
01.05.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 8.56 806.43 S/. 6,903.04 1.05%
01.05.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 97.51 36.32 S/. 3,541.56 0.54%
01.05.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,114.78 3.71 S/. 4,135.83 0.63%
01.05.05 COLUMNETAS
01.05.05.01 CONCRETO fc'= 175 kg/cm2 EN COLUMNETAS m3 3.36 724.97 S/. 2,435.90 0.37%
01.05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNETAS m2 100.38 28.18 S/. 2,828.71 0.43%
01.05.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 356.52 3.71 S/. 1,322.69 0.20%
01.05.06 VIGUETAS
01.05.06.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.41 724.97 S/. 297.24 0.05%
01.05.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 8.92 28.18 S/. 251.37 0.04%
01.05.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 136.42 3.71 S/. 506.12 0.08%
01.06 ESTRUCTURA METALICA
01.06.01 TIJERAL METALICO TIPO I L=9.93 M und 6.00 2,330.51 S/. 13,983.06 2.12%
01.06.02 TIJERAL METALICO TIPO IV L=8.72 M und 3.00 2,076.27 S/. 6,228.81 0.94%
01.06.03 CORREAS METALICAS CW 64X38X0.90 m 226.12 24.92 S/. 5,634.91 0.85%
01.06.04 CORREAS METALICAS UP 90X32X0.90 MM m 46.94 23.13 S/. 1,085.72 0.16%
01.06.05 ARRIOSTRE METALICO PT 100X0.9 m 63.30 57.83 S/. 3,660.64 0.55%
01.06.06 CORREAS METALICAS DE CIERRE UP 65X32X0.90 MM m 57.18 17.80 S/. 1,017.80 0.15%
01.07 ALBAÑILERIA
01.07.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 48.22 57.40 S/. 2,767.83 0.42%
01.07.02 MURO DE LADRILLO KK DE ARCILLA DE CABEZA MEZCLA 1:4 m2 77.77 96.30 S/. 7,489.25 1.13%
01.07.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 32.90 3.71 S/. 122.06 0.02%
01.08 REVOQUES, ENLUCIDOS Y DERRAMES
01.08.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 200.58 16.69 S/. 3,347.68 0.51%
01.08.02 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 123.32 23.06 S/. 2,843.76 0.43%
01.08.03 VESTIDURAS DE DERRAMES CON BORDES BOLEADOS M : 1: 5 m 128.36 7.51 S/. 963.98 0.15%
01.08.04 BRUÑAS
01.08.04.01 BRUÑA e= 1 cm. EXTERIOR m 93.34 2.53 S/. 236.15 0.04%
01.08.04.02 BRUÑA e= 1 cm. INTERIOR m 171.85 2.53 S/. 434.78 0.07%
01.08.04.03 BRUÑA e= 1 cm. EN PISO INTERIOR Y EXTERIOR m 72.84 2.53 S/. 184.29 0.03%
01.09 CERRAMIENTO CON PANEL FIBROCEMENTO 0.00%
01.09.01 CIELORRASO CON PANEL FIBROCEMENTO 4 mm. m2 179.89 142.37 S/. 25,610.94 3.88%
01.10 PISOS Y PAVIMENTOS
01.10.01 PISO DE MADERA MACHIHEMBRADA m2 120.95 76.46 S/. 9,247.84 1.40%
01.10.02 PISO DE CONCRETO e=2", PULIDO SIN COLOREAR m2 9.00 38.12 S/. 343.08 0.05%
01.10.03 PISO CERAMICO DE COLOR CLARO 30X30CM m2 21.02 45.69 S/. 960.40 0.15%
01.10.04 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 31.56 107.22 S/. 3,383.86 0.51%
01.10.05 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 5.35 7.80 S/. 41.73 0.01%
01.11 ZOCALOS Y CONTRAZOCALOS
01.11.01 ZOCALO DE MAYOLICA BLANCA 30 X 30 CM. m2 40.70 46.22 S/. 1,881.15 0.28%
01.11.02 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.20 m. EXTERIOR m 57.30 5.47 S/. 313.43 0.05%
01.11.03 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.10 m. INTERIOR m 14.54 3.74 S/. 54.38 0.01%
01.11.04 CONTRAZOCALO DE CEDRO DE 3" RODON 1" m 54.72 16.69 S/. 913.28 0.14%
01.12 CUBIERTA Y TECHO
01.12.01 COBERTURA CON LAMINA TERMOACUSTICA m2 293.23 34.96 S/. 10,251.32 1.55%
01.12.02 CUMBRERA DENTADA m 22.54 27.64 S/. 623.01 0.09%
01.13 CARPINTERIA DE MADERA
01.13.01 PUERTA DE MADERA APANELADA m2 15.90 160.54 S/. 2,552.59 0.39%
PRESUPUESTO BASE PRESUPUESTO
ITEM DESCRIPCIÓN UND COEFICIENTE
METRADO PRE. UNIT. BASE DE INCIDENCIA
01.13.02 VENTANA DE MADERA m2 36.42 91.01 S/. 3,314.58 0.50%
01.13.03 TICERO DE MADERA CEDRO ( L= 3.00 m. ) BARNIZADO und 2.00 157.90 S/. 315.80 0.05%
01.14 CERRAJERIA
01.14.01 BISAGRA ALUMINIZADA DE 4" x 4" PESADA PARA PUERTA pza 24.00 6.45 S/. 154.80 0.02%
01.14.02 CERRADURA PARA PUERTA EXTERIOR TIPO PARCHE 2 GOLPES pza 7.00 59.54 S/. 416.78 0.06%
01.14.03 MANIJA DE 4" PARA PUERTA pza 7.00 5.27 S/. 36.89 0.01%
01.14.04 CERROJOS PARA VENTANAS DE BRONCE pza 70.00 2.98 S/. 208.60 0.03%
01.14.05 MANIJA DE BRONCE PARA PORTAÑUELAS DE VENTANAS pza 70.00 3.57 S/. 249.90 0.04%
01.14.06 BISAGRA ALUMINIZADA DE 2 1/2" x 2 1/2" PARA VENTANA pza 70.00 5.67 S/. 396.90 0.06%
01.14.07 TOPE METALICO DE FIERRO PARA VENTANA pza 70.00 3.84 S/. 268.80 0.04%
01.15 VIDRIOS, CRISTALES Y SIMILARES
01.15.01 VIDRIOS SEMIDOBLES p2 391.83 3.65 S/. 1,430.18 0.22%
01.16 PINTURA
01.16.01 PINT. LATEX 2 MANOS EN MUROS EXTERIORES m2 123.32 4.65 S/. 573.44 0.09%
01.16.02 PINT. LATEX 2 MANOS EN MUROS INTERIORES m2 187.14 4.65 S/. 870.20 0.13%
01.16.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 85.11 6.18 S/. 525.98 0.08%
01.16.04 PINTURA LATEX 2 MANOS EN COLUMNETAS m2 44.09 6.18 S/. 272.48 0.04%
01.16.05 PINTURA LATEX 2 MANOS EN VIGAS m2 97.51 6.37 S/. 621.14 0.09%
01.16.06 PINTURA BARNIZ EN PUERTAS m2 31.80 6.69 S/. 212.74 0.03%
01.16.07 PINTURA BARNIZ EN VENTANA DE MADERA m2 36.42 6.69 S/. 243.65 0.04%
01.17 VARIOS
01.17.01 JUNTA SISMICA DE 1" m 9.87 4.35 S/. 42.93 0.01%
01.17.02 PIZARRA CEMENTO 3.00 x 1.20 m. SIN TICERO und 2.00 118.88 S/. 237.76 0.04%
01.17.03 JUNTA DE DILATACION DE 1" EN VEREDA m 35.21 7.18 S/. 252.81 0.04%
01.18 INSTALACIONES SANITARIAS
01.18.01 DESAGUE Y VENTILACION
01.18.01.01 SALIDA DE DESAGUE PVC SAL D=2" pto 7.00 40.26 S/. 281.82 0.04%
01.18.01.02 SALIDA DE DESAGUE PVC SAL D=4" pto 4.00 51.85 S/. 207.40 0.03%
01.18.01.03 SUMIDEROS DE 3" pza 1.00 36.79 S/. 36.79 0.01%
01.18.01.04 REGISTRO DE BRONCE 2" pza 1.00 20.32 S/. 20.32 0.00%
01.18.01.05 REGISTRO DE BRONCE 4" pza 2.00 30.22 S/. 60.44 0.01%
01.18.02 REDES DE DISTRIBUCION
01.18.02.01 TUBERIA PVC -SAL 2" m 10.11 9.19 S/. 92.91 0.01%
01.18.02.02 TUBERIA PVC -SAL 4" m 39.81 12.76 S/. 507.98 0.08%
01.18.03 APARATOS Y ACCESORIOS SANITARIOS
01.18.03.01 INODORO TANQUE BAJO TIPO "BABY" und 4.00 289.42 S/. 1,157.68 0.18%
01.18.03.02 PAPELERA DE LOZA DE COLOR DE 15 X 15 cm pza 4.00 8.47 S/. 33.88 0.01%
01.18.03.03 CAJA DE REGISTRO 12"X24" C/TAPA DE CONCRETO pza 1.00 47.49 S/. 47.49 0.01%
01.18.04 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.18.04.01 SALIDA DE AGUA FRIA PVC pto 10.00 25.65 S/. 256.50 0.04%
01.18.04.02 TUBERIA PVC CLASE 10 - 3/4" m 30.72 5.06 S/. 155.44 0.02%
01.18.04.03 TUBERIA PVC CLASE 10 - 1/2" m 4.03 4.63 S/. 18.66 0.00%
01.18.04.04 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza 1.00 35.90 S/. 35.90 0.01%
01.18.04.05 VALVULAS DE COMPUERTA DE BRONCE DE 3/4" pza 2.00 48.60 S/. 97.20 0.01%
01.18.05 SISTEMA DE DRENAJE PLUVIAL
01.18.05.01 TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS m 30.33 16.69 S/. 506.21 0.08%
01.18.05.02 CANALETA DE FIERRO GALVANIZADO m 64.94 30.63 S/. 1,989.11 0.30%
01.18.05.03 ABRAZADERA DE FIJACION DE TUBO pza 59.00 7.06 S/. 416.54 0.06%
01.18.05.04 COLECTOR DE ZINC GALVANIZADO und 6.00 7.04 S/. 42.24 0.01%
01.18.05.05 ABRAZADERA DE FIJACION DE TUBERIA DE 3" pza 18.00 15.92 S/. 286.56 0.04%
01.19 INSTALACIONES ELECTRICAS
01.19.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 17.00 48.42 S/. 823.14 0.12%
01.19.02 SALIDA INTERRUPTOR SIMPLE pto 2.00 8.30 S/. 16.60 0.00%
01.19.03 SALIDA INTERRUPTOR DOBLE pto 5.00 10.85 S/. 54.25 0.01%
01.19.04 SALIDA TOMACORRIENTE DOBLE pto 6.00 55.14 S/. 330.84 0.05%
01.19.05 SALIDA PARA ANTENA DE TELEVISION CON PVC pto 2.00 64.08 S/. 128.16 0.02%
01.20 TABLEROS
01.20.01 TABLERO DE DISTRIBUCION TD-3 und 1.00 416.20 S/. 416.20 0.06%
01.21 ARTEFACTOS 0.00%
01.21.01 ARTEFACTO FLUORESCENTE 2/18 W und 4.00 42.01 S/. 168.04 0.03%
01.21.02 ARTEFACTO FLUORESCENTE 1/36W und 2.00 41.16 S/. 82.32 0.01%
01.21.03 ARTEFACTO FLUORESCENTE 2/36 W und 2.00 78.45 S/. 156.90 0.02%
01.21.04 ARTEFACTO FLUORESCENTE 4/36W und 8.00 35.23 S/. 281.84 0.04%
01.22 POZO PUESTA A TIERRA
01.22.01 POZO DE PUESTA A TIERRA und 1.00 402.90 S/. 402.90 0.06%
02 AREA COMPLEMENTARIA
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 248.72 0.74 S/. 184.05 0.03%
02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 290.85 1.87 S/. 543.89 0.08%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 369.18 14.72 S/. 5,434.33 0.82%
02.02.02 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 33.95 1.44 S/. 48.89 0.01%
02.02.03 EXCAVACIONES
02.02.03.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 46.92 14.44 S/. 677.52 0.10%
02.02.03.02 EXCAVACION MANUAL DE ZAPATAS m3 31.50 14.72 S/. 463.68 0.07%
02.02.03.03 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES DE VEREDAS m3 2.25 14.44 S/. 32.49 0.00%
02.02.03.04 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS DE DRENAJE m3 5.42 14.72 S/. 79.78 0.01%
02.02.03.05 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 12.23 9.02 S/. 110.31 0.02%
02.02.03.06 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 580.36 6.02 S/. 3,493.77 0.53%
02.02.03.07 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 247.78 0.74 S/. 183.36 0.03%
02.02.03.08 AFIRMADO DE e=4" PARA PISOS INTERIORES Y EXTERIORES m2 226.78 24.34 S/. 5,519.83 0.84%
02.03 CONCRETO SIMPLE
02.03.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 18.24 559.63 S/. 10,207.65 1.55%
02.03.02 SUBCIMIENTO C:H=1:12+30% PG m3 18.20 525.00 S/. 9,555.00 1.45%
02.03.03 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 21.00 44.27 S/. 929.67 0.14%
02.03.04 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 10.49 559.11 S/. 5,865.06 0.89%
02.03.05 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 113.05 19.61 S/. 2,216.91 0.34%
02.03.06 FALSO PISO e= 4" ( MEZCLA 1:10 CEMENTO : HORMIGON ) m2 178.05 58.90 S/. 10,487.15 1.59%
02.03.07 CONCRETO F'C=140 KG/CM2 EN CANALETAS m3 6.60 671.93 S/. 4,434.74 0.67%
02.03.08 ENCOFRADO Y DESENCOFRADO EN CANALETAS m2 34.02 31.65 S/. 1,076.73 0.16%
02.03.09 JUNTAS ASFALTICAS m 4.00 7.13 S/. 28.52 0.00%
02.03.10 TUBERIA PVC SAL D=8" m 6.00 49.98 S/. 299.88 0.05%
02.04 CONCRETO ARMADO
02.04.01 VIGA DE CIMENTACION
02.04.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 6.85 691.52 S/. 4,736.91 0.72%
02.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 68.49 25.25 S/. 1,729.37 0.26%
02.04.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 545.47 3.71 S/. 2,023.69 0.31%
02.04.02 ZAPATAS 0.00%
02.04.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 12.60 776.93 S/. 9,789.32 1.48%
02.04.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 250.55 3.71 S/. 929.54 0.14%
02.04.03 COLUMNAS
02.04.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 11.05 812.05 S/. 8,973.15 1.36%
PRESUPUESTO BASE PRESUPUESTO
ITEM DESCRIPCIÓN UND COEFICIENTE
METRADO PRE. UNIT. BASE DE INCIDENCIA
02.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 79.62 30.13 S/. 2,398.95 0.36%
02.04.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 2,805.55 3.71 S/. 10,408.59 1.58%
02.04.04 VIGAS
02.04.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 11.82 806.43 S/. 9,532.00 1.44%
02.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 134.17 36.32 S/. 4,873.05 0.74%
02.04.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,580.11 3.71 S/. 5,862.21 0.89%
02.04.05 COLUMNETAS
02.04.05.01 CONCRETO fc'= 175 kg/cm2 EN COLUMNETAS m3 4.67 724.97 S/. 3,385.61 0.51%
02.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNETAS m2 75.55 28.18 S/. 2,129.00 0.32%
02.04.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 543.43 3.71 S/. 2,016.13 0.31%
02.04.06 VIGUETAS
02.04.06.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.36 724.97 S/. 260.99 0.04%
02.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 5.51 28.18 S/. 155.27 0.02%
02.04.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 101.78 3.71 S/. 377.60 0.06%
02.05 ESTRUCTURA METALICA
02.05.01 TIJERAL METALICO TIPO I L=9.93 M und 6.00 2,330.51 S/. 13,983.06 2.12%
02.05.02 TIJERAL METALICO TIPO III L=7.50 M und 4.00 1,779.66 S/. 7,118.64 1.08%
02.05.03 CORREAS METALICAS CW 64X38X0.90 m 302.69 24.92 S/. 7,543.03 1.14%
02.05.04 CORREAS METALICAS UP 90X32X0.90 MM m 60.52 23.13 S/. 1,399.83 0.21%
02.05.05 ARRIOSTRE METALICO PT 100X0.9 m 71.86 57.83 S/. 4,155.66 0.63%
02.05.06 CORREAS METALICAS DE CIERRE UP 65X32X0.90 MM m 58.22 17.80 S/. 1,036.32 0.16%
02.06 ALBAÑILERIA
02.06.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 102.29 57.40 S/. 5,871.45 0.89%
02.06.02 MURO DE LADRILLO KK DE ARCILLA DE CABEZA MEZCLA 1:4 m2 120.61 96.30 S/. 11,614.74 1.76%
02.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 45.85 3.71 S/. 170.10 0.03%
02.07 REVOQUES, ENLUCIDOS Y DERRAMES 0.00%
02.07.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 285.76 16.69 S/. 4,769.33 0.72%
02.07.02 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 160.04 23.06 S/. 3,690.52 0.56%
02.07.03 VESTIDURAS DE DERRAMES CON BORDES BOLEADOS M : 1: 5 m 57.30 7.51 S/. 430.32 0.07%
02.07.04 BRUÑAS
02.07.04.01 BRUÑA e= 1 cm. EXTERIOR m 104.66 2.53 S/. 264.79 0.04%
02.07.04.02 BRUÑA e= 1 cm. INTERIOR m 162.31 2.53 S/. 410.64 0.06%
02.07.04.03 BRUÑA e= 1 cm. EN PISO INTERIOR Y EXTERIOR m 122.24 2.53 S/. 309.27 0.05%
02.08 CERRAMIENTO CON PANEL FIBROCEMENTO
02.08.01 CIELORRASO CON PANEL FIBROCEMENTO 4 mm. m2 260.42 142.37 S/. 37,076.00 5.61%
02.09 PISOS Y PAVIMENTOS
02.09.01 PISO DE MADERA MACHIHEMBRADA m2 82.64 76.46 S/. 6,318.65 0.96%
02.09.02 PISO DE CONCRETO e=2", PULIDO SIN COLOREAR m2 21.00 38.12 S/. 800.52 0.12%
02.09.03 PISO CERAMICO DE COLOR CLARO 30X30CM m2 73.42 45.69 S/. 3,354.56 0.51%
02.09.04 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 49.25 107.22 S/. 5,280.59 0.80%
02.09.05 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 7.76 7.80 S/. 60.53 0.01%
02.10 ZOCALOS Y CONTRAZOCALOS
02.10.01 ZOCALO DE MAYOLICA BLANCA 30 X 30 CM. m2 25.04 46.22 S/. 1,157.35 0.18%
02.10.02 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.20 m. EXTERIOR m 66.03 5.47 S/. 361.18 0.05%
02.10.03 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.10 m. INTERIOR m 40.77 3.74 S/. 152.48 0.02%
02.10.04 CONTRAZOCALO DE CEDRO DE 3" RODON 1" m 47.01 16.69 S/. 784.60 0.12%
02.10.05 CONTRAZOCALO DE CERAMICO H=20 CM m 13.85 12.89 S/. 178.53 0.03%
02.11 CUBIERTA Y TECHO
02.11.01 COBERTURA CON LAMINA TERMOACUSTICA m2 291.80 34.96 S/. 10,201.33 1.54%
02.11.02 CUMBRERA DENTADA m 30.25 27.64 S/. 836.11 0.13%
02.12 CARPINTERIA DE MADERA
02.12.01 PUERTA DE MADERA APANELADA m2 21.74 160.54 S/. 3,490.14 0.53%
02.12.02 VENTANA DE MADERA m2 31.52 91.01 S/. 2,868.64 0.43%
02.12.03 TICERO DE MADERA CEDRO ( L= 3.00 m. ) BARNIZADO und 1.00 157.90 S/. 157.90 0.02%
02.13 CERRAJERIA
02.13.01 BISAGRA ALUMINIZADA DE 4" x 4" PESADA PARA PUERTA pza 30.00 6.45 S/. 193.50 0.03%
02.13.02 CERRADURA PARA PUERTA EXTERIOR TIPO PARCHE 2 GOLPES pza 10.00 59.54 S/. 595.40 0.09%
02.13.03 MANIJA DE 4" PARA PUERTA pza 10.00 5.27 S/. 52.70 0.01%
02.13.04 CERROJOS PARA VENTANAS DE BRONCE pza 62.00 2.98 S/. 184.76 0.03%
02.13.05 MANIJA DE BRONCE PARA PORTAÑUELAS DE VENTANAS pza 62.00 3.57 S/. 221.34 0.03%
02.13.06 BISAGRA ALUMINIZADA DE 2 1/2" x 2 1/2" PARA VENTANA pza 62.00 5.67 S/. 351.54 0.05%
02.13.07 TOPE METALICO DE FIERRO PARA VENTANA pza 62.00 3.84 S/. 238.08 0.04%
02.14 VIDRIOS, CRISTALES Y SIMILARES
02.14.01 VIDRIOS SEMIDOBLES p2 339.17 3.65 S/. 1,237.97 0.19%
02.15 PINTURA
02.15.01 PINT. LATEX 2 MANOS EN MUROS EXTERIORES m2 160.04 4.65 S/. 744.19 0.11%
02.15.02 PINT. LATEX 2 MANOS EN MUROS INTERIORES m2 285.76 4.65 S/. 1,328.78 0.20%
02.15.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 134.17 6.18 S/. 829.17 0.13%
02.15.04 PINTURA LATEX 2 MANOS EN COLUMNETAS m2 75.55 6.18 S/. 466.90 0.07%
02.15.05 PINTURA LATEX 2 MANOS EN VIGAS m2 100.38 6.37 S/. 639.42 0.10%
02.15.06 PINTURA BARNIZ EN PUERTAS m2 43.47 6.69 S/. 290.81 0.04%
02.15.07 PINTURA BARNIZ EN VENTANA DE MADERA m2 63.04 6.69 S/. 421.74 0.06%
02.16 VARIOS
02.16.01 JUNTA SISMICA DE 1" m 16.48 4.35 S/. 71.69 0.01%
02.16.02 PIZARRA CEMENTO 3.00 x 1.20 m. SIN TICERO und 1.00 118.88 S/. 118.88 0.02%
02.16.03 JUNTA DE DILATACION DE 1" EN VEREDA m 23.29 7.18 S/. 167.22 0.03%
02.17 INSTALACIONES SANITARIAS
02.17.01 DESAGUE Y VENTILACION
02.17.01.01 SALIDA DE DESAGUE PVC SAL D=2" pto 4.00 40.26 S/. 161.04 0.02%
02.17.01.02 SALIDA DE DESAGUE PVC SAL D=4" pto 1.00 51.85 S/. 51.85 0.01%
02.17.01.03 SUMIDEROS DE 2" pza 1.00 31.84 S/. 31.84 0.00%
02.17.01.04 SUMIDEROS DE 3" pza 1.00 36.79 S/. 36.79 0.01%
02.17.01.05 REGISTRO DE BRONCE 2" pza 1.00 20.32 S/. 20.32 0.00%
02.17.01.06 REGISTRO DE BRONCE 4" pza 1.00 30.22 S/. 30.22 0.00%
02.17.02 REDES DE DISTRIBUCION
02.17.02.01 TUBERIA PVC -SAL 2" m 10.11 9.19 S/. 92.91 0.01%
02.17.02.02 TUBERIA PVC -SAL 4" m 6.12 12.76 S/. 78.09 0.01%
02.17.03 APARATOS Y ACCESORIOS SANITARIOS
02.17.03.01 INODORO TANQUE BAJO BLANCO pza 1.00 156.78 S/. 156.78 0.02%
02.17.03.02 PAPELERA DE LOZA DE COLOR DE 15 X 15 cm pza 1.00 8.47 S/. 8.47 0.00%
02.17.03.03 LAVATORIO DE PARED BLANCO 1 LLAVE pza 1.00 84.75 S/. 84.75 0.01%
02.17.03.04 LAVADERO DE COCINA DE ACERO INOXIDABLE pza 2.00 127.12 S/. 254.24 0.04%
02.17.03.05 CAJA DE REGISTRO 12"X24" C/TAPA DE CONCRETO pza 3.00 47.49 S/. 142.47 0.02%
02.17.04 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 0.00%
02.17.04.01 SALIDA DE AGUA FRIA PVC pto 4.00 25.65 S/. 102.60 0.02%
02.17.04.02 TUBERIA PVC CLASE 10 - 3/4" m 26.00 5.06 S/. 131.56 0.02%
02.17.04.03 TUBERIA PVC CLASE 10 - 1/2" m 42.00 4.63 S/. 194.46 0.03%
02.17.04.04 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza 1.00 35.90 S/. 35.90 0.01%
02.17.04.05 VALVULAS DE COMPUERTA DE BRONCE DE 3/4" pza 1.00 48.60 S/. 48.60 0.01%
02.17.05 SISTEMA DE DRENAJE PLUVIAL
02.17.05.01 TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS m 30.33 16.69 S/. 506.21 0.08%
02.17.05.02 CANALETA DE FIERRO GALVANIZADO m 73.62 30.63 S/. 2,254.98 0.34%
PRESUPUESTO BASE PRESUPUESTO
ITEM DESCRIPCIÓN UND COEFICIENTE
METRADO PRE. UNIT. BASE DE INCIDENCIA
02.17.05.03 ABRAZADERA DE FIJACION DE TUBO pza 70.00 7.06 S/. 494.20 0.07%
02.17.05.04 COLECTOR DE ZINC GALVANIZADO und 6.00 7.04 S/. 42.24 0.01%
02.17.05.05 ABRAZADERA DE FIJACION DE TUBERIA DE 3" pza 18.00 15.92 S/. 286.56 0.04%
02.18 INSTALACIONES ELECTRICAS
02.18.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 22.00 48.42 S/. 1,065.24 0.16%
02.18.02 SALIDA INTERRUPTOR SIMPLE pto 5.00 8.30 S/. 41.50 0.01%
02.18.03 SALIDA INTERRUPTOR DOBLE pto 10.00 10.85 S/. 108.50 0.02%
02.18.04 SALIDA TOMACORRIENTE DOBLE pto 20.00 55.14 S/. 1,102.80 0.17%
02.19 TABLEROS
02.19.01 TABLERO GENERAL TG und 1.00 371.03 S/. 371.03 0.06%
02.19.02 TABLERO DE DISTRIBUCION TD-1 glb 1.00 419.31 S/. 419.31 0.06%
02.19.03 TABLERO DE DISTRIBUCION TD-2 glb 1.00 357.53 S/. 357.53 0.05%
02.20 ARTEFACTOS
02.20.01 ARTEFACTO FLUORESCENTE 2/18 W und 4.00 42.01 S/. 168.04 0.03%
02.20.02 ARTEFACTO FLUORESCENTE 2/36 W und 8.00 78.45 S/. 627.60 0.10%
02.20.03 ARTEFACTO FLUORESCENTE 4/36W und 10.00 35.23 S/. 352.30 0.05%
02.21 POZO PUESTA A TIERRA
02.21.01 POZO DE PUESTA A TIERRA und 1.00 402.90 S/. 402.90 0.06%
03 TANQUE SEPTICO Y POZO PERCOLADOR
03.01 TANQUE SEPTICO
03.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.00 0.74 S/. 5.18 0.00%
03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 7.00 1.87 S/. 13.09 0.00%
03.01.03 EXCAVACION DE ESTRUCTURAS m3 10.85 14.72 S/. 159.71 0.02%
03.01.04 TERRAPLEN P/FALSO PISO C/PISON MANUAL, H=0.15 M m2 4.80 0.93 S/. 4.46 0.00%
03.01.05 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 14.10 6.02 S/. 84.88 0.01%
03.01.06 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 4.80 44.27 S/. 212.50 0.03%
03.01.07 CONCRETO F'C=175 KG/CM2 EN TANQUE SUBTERRANEO m3 4.73 700.92 S/. 3,315.35 0.50%
03.01.08 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 244.37 3.71 S/. 906.61 0.14%
03.01.09 ENCOFRADO Y DESENCOFRADO EN TANQUE ENTERRADO m2 47.29 21.69 S/. 1,025.72 0.16%
03.01.10 TARRAJEO CON IMPERMEABILIZANTE, MEZCLA E=1.5 CM m2 17.79 35.90 S/. 638.66 0.10%
03.01.11 ACCESORIOS PVC SAL EN TANQUE SEPTICO und 1.00 34.97 S/. 34.97 0.01%
03.01.12 TUBERIA PVC -SAL 4" m 7.00 32.67 S/. 228.69 0.03%
03.01.13 CAJA DE REGISTRO DE DESAGUE 12"X24" und 1.00 58.23 S/. 58.23 0.01%
03.02 POZA DE PERCOLACION
03.02.01 LIMPIEZA DE TERRENO MANUAL m2 8.65 0.74 S/. 6.40 0.00%
03.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 8.65 1.87 S/. 16.18 0.00%
03.02.03 EXCAVACION DE ESTRUCTURAS m3 17.74 14.72 S/. 261.13 0.04%
03.02.04 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 23.06 6.02 S/. 138.82 0.02%
03.02.05 CONCRETO F'C=175 KG/CM2 EN POZA DE PERCOLACION m3 1.03 700.92 S/. 721.95 0.11%
03.02.06 ENCOFRADO Y DESENCOFRADO EN POZA DE PERCOLACION m2 9.96 21.00 S/. 209.16 0.03%
03.02.07 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 42.42 3.71 S/. 157.38 0.02%
03.02.08 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 23.58 57.40 S/. 1,353.49 0.20%
03.02.09 FILTRO DE GRAVAS O CASCAJO m3 0.38 101.69 S/. 38.64 0.01%
03.02.10 CAJA DE REGISTRO DE DESAGUE 12"X24" und 1.00 58.23 S/. 58.23 0.01%
03.02.11 TUBERIA PVC -SAL 4" m 64.00 32.67 S/. 2,090.88 0.32%
04 CERCO PERIMETRICO
04.01 TRABAJOS PRELIMINARES
04.01.01 LIMPIEZA DE TERRENO MANUAL m2 71.00 0.74 S/. 52.54 0.01%
04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 78.00 1.87 S/. 145.86 0.02%
04.02 MOVIMIENTO DE TIERRAS
04.02.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 14.71 14.44 S/. 212.41 0.03%
04.02.02 EXCAVACION MANUAL DE ZAPATAS m3 4.50 14.72 S/. 66.24 0.01%
04.02.03 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 12.26 0.74 S/. 9.07 0.00%
04.02.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 2.76 9.02 S/. 24.90 0.00%
04.02.05 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 21.39 6.02 S/. 128.77 0.02%
04.03 CONCRETO SIMPLE
04.03.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 10.78 559.63 S/. 6,032.81 0.91%
04.03.02 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 2.25 559.11 S/. 1,258.00 0.19%
04.03.03 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 30.04 19.61 S/. 589.08 0.09%
04.03.04 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 3.00 44.27 S/. 132.81 0.02%
04.04 CONCRETO ARMADO
04.04.01 VIGA DE CIMENTACION
04.04.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 0.57 691.52 S/. 394.17 0.06%
04.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 9.12 25.25 S/. 230.28 0.03%
04.04.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 68.61 3.71 S/. 254.54 0.04%
04.04.02 ZAPATAS
04.04.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 1.50 776.93 S/. 1,165.40 0.18%
04.04.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 52.07 3.71 S/. 193.18 0.03%
04.04.03 COLUMNAS
04.04.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 3.32 812.05 S/. 2,696.01 0.41%
04.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 29.64 30.13 S/. 893.05 0.14%
04.04.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 414.96 3.71 S/. 1,539.50 0.23%
04.04.04 VIGAS
04.04.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 0.49 806.43 S/. 395.15 0.06%
04.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 5.28 36.32 S/. 191.77 0.03%
04.04.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 59.10 3.71 S/. 219.26 0.03%
04.04.05 VIGUETAS
04.04.05.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.06 724.97 S/. 43.50 0.01%
04.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 0.77 28.18 S/. 21.70 0.00%
04.04.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 6.42 3.71 S/. 23.82 0.00%
04.04.06 LOSA ARMADA
04.04.06.01 CONCRETO F'C=210 KG/CM2 EN LOSA ARMADA m3 1.32 806.43 S/. 1,064.49 0.16%
04.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE LOSA ARMADA m2 11.37 32.77 S/. 372.59 0.06%
04.04.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 48.43 3.71 S/. 179.68 0.03%
04.05 ALBAÑILERIA
04.05.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 10.61 57.40 S/. 609.01 0.09%
04.06 PISOS Y PAVIMENTOS
04.06.01 AFIRMADO DE 4" PARA VEREDAS m2 12.26 24.65 S/. 302.21 0.05%
04.06.02 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 12.26 107.22 S/. 1,314.52 0.20%
04.06.03 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 0.31 7.80 S/. 2.42 0.00%
04.07 PINTURA
04.07.01 PINTURA LATEX 2 MANOS EN COLUMNAS m2 33.79 6.18 S/. 208.82 0.03%
04.07.02 PINTURA LATEX 2 MANOS EN VIGAS m2 5.28 6.37 S/. 33.63 0.01%
04.07.03 PINTURA LATEX 2 MANOS EN VIGUETAS m2 0.77 6.37 S/. 4.90 0.00%
04.08 CARPINTERIA METALICA
04.08.01 PUERTA METALICA P1(3.75x3.20M) und 1.00 4,433.15 S/. 4,433.15 0.67%
04.08.02 PUERTA METALICA P2(1.10x3.20M) und 1.00 2,708.42 S/. 2,708.42 0.41%
04.08.03 MALLA METALICA COCADA 2'X2' H=2.20 M m 20.00 98.35 S/. 1,967.00 0.30%
04.09 INSTALACIONES ELECTRICAS
04.09.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 4.00 48.63 S/. 194.52 0.03%
04.09.02 ARTEFACTO FLUORESCENTE 2/36 W und 4.00 78.45 S/. 313.80 0.05%
04.10 VARIOS
PRESUPUESTO BASE PRESUPUESTO
ITEM DESCRIPCIÓN UND COEFICIENTE
METRADO PRE. UNIT. BASE DE INCIDENCIA
04.10.01 JUNTA SISMICA DE 1" m 5.00 4.35 S/. 21.75 0.00%
05 PATIO DE ENCUENTRO
05.01 TRABAJOS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO MANUAL m2 190.00 0.74 S/. 140.60 0.02%
05.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 190.00 2.82 S/. 535.80 0.08%
05.02 MOVIMIENTO DE TIERRAS
05.02.01 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 180.59 1.44 S/. 260.05 0.04%
05.02.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 234.77 6.02 S/. 1,413.32 0.21%
05.03 SEMBRADO DE AREAS VERDES
05.03.01 PREPARACION DE TIERRA DE CHACRA m2 180.56 10.02 S/. 1,809.21 0.27%
05.03.02 SEMBRADO DE GRASS AMERICANO m2 180.56 3.21 S/. 579.60 0.09%
06 BEBEDERO
06.01 MOVIMIENTO DE TIERRAS
06.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.05 14.72 S/. 0.74 0.00%
06.01.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 0.07 6.02 S/. 0.42 0.00%
06.02 OBRAS DE CONCRETO
06.02.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 0.05 559.63 S/. 27.98 0.00%
06.02.02 CONCRETO F'C=175 KG/CM2 EN BEBEDERO m3 0.27 700.92 S/. 189.25 0.03%
06.02.03 ENCOFRADO Y DESENCOFRADO EN BEBEDEROS m2 2.97 25.25 S/. 74.99 0.01%
06.02.04 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 8.85 3.71 S/. 32.83 0.00%
06.03 ALBAÑILERIA
06.03.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 0.31 57.40 S/. 17.79 0.00%
06.04 REVOQUES, ENLUCIDOS Y DERRAMES
06.04.01 TARRAJEO PRIMARIO MORTERO 1:5 m2 3.88 15.70 S/. 60.92 0.01%
06.04.02 ZOCALO DE MAYOLICA BLANCA 20 X 20 CM. m2 3.57 46.22 S/. 165.01 0.02%
06.05 SUMINISTRO E INSTALACION DE ACCESORIOS 0.00%
06.05.01 ACCESORIOS EN BEBEDERO und 1.00 115.87 S/. 115.87 0.02%
07 URINARIO
07.01 MOVIMIENTO DE TIERRAS
07.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.04 14.72 S/. 0.59 0.00%
07.01.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 0.06 6.02 S/. 0.36 0.00%
07.02 OBRAS DE CONCRETO
07.02.01 CONCRETO CICLOPEO F'C=140 KG/CM2 EN URINARIO m3 0.09 667.03 S/. 60.03 0.01%
07.02.02 ENCOFRADO Y DESENCOFRADO EN BEBEDEROS m2 0.86 25.25 S/. 21.72 0.00%
07.03 REVOQUES, ENLUCIDOS Y DERRAMES
07.03.01 TARRAJEO PRIMARIO MORTERO 1:5 m2 0.92 15.70 S/. 14.44 0.00%
07.03.02 ZOCALO DE MAYOLICA BLANCA 20 X 20 CM. m2 1.28 46.22 S/. 59.16 0.01%
07.04 SUMINISTRO E INSTALACION DE ACCESORIOS
07.04.01 ACCESORIOS SANITARIOS EN URINARIO und 2.00 71.05 S/. 142.10 0.02%
08 JUEGOS INFANTILES
08.01 TRABAJOS PRELIMINARES
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 90.00 0.74 S/. 66.60 0.01%
08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 90.00 2.82 S/. 253.80 0.04%
08.02 MOVIMIENTO DE TIERRAS
08.02.01 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 85.49 1.44 S/. 123.11 0.02%
08.02.02 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.60 14.72 S/. 38.27 0.01%
08.02.03 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 14.49 6.02 S/. 87.23 0.01%
08.03 OBRAS DE CONCRETO
08.03.01 CONCRETO F'C=140 KG/CM2 EN SARDINELES m3 2.97 667.03 S/. 1,981.08 0.30%
08.03.02 ENCOFRADO Y DESENCOFRADO EN SARDINELES m2 26.19 31.65 S/. 828.91 0.13%
08.03.03 JUNTAS ASFALTICAS m 4.40 7.13 S/. 31.37 0.00%
08.04 VARIOS
08.04.01 COLOCACION DE ARENA FINA e=0.10 M m2 85.49 31.66 S/. 2,706.61 0.41%
08.04.02 COLUMPIO und 1.00 847.46 S/. 847.46 0.13%
08.04.03 TOBOGAN und 1.00 762.71 S/. 762.71 0.12%
08.04.04 BALANCIN und 1.00 847.46 S/. 847.46 0.13%
09 EQUIPAMIENTO Y MOBILIARIO
09.01 EQUIPAMIENTO
09.01.01 TELEVISOR und 2.00 1,016.95 S/. 2,033.90 0.31%
09.01.02 REPRODUCTOR BLU RAY und 2.00 322.03 S/. 644.06 0.10%
09.02 MOBILIARIO
09.02.01 AULAS
09.02.01.01 MOBILIARIO PARA DOCENTES und 2.00 423.73 S/. 847.46 0.13%
09.02.01.02 ESTANTE DE MADERA und 2.00 211.86 S/. 423.72 0.06%
09.02.01.03 MUEBLE MOVIL PARA TV Y EQUIPO DE SONIDO und 2.00 169.49 S/. 338.98 0.05%
09.02.02 AMBIENTES COMPLEMENTARIOS
09.02.02.01 MOBILIARIO PARA COMEDOR DE NINOS und 5.00 379.64 S/. 1,898.20 0.29%
09.02.02.02 MOBILIARIO PARA DIRECCION und 1.00 788.13 S/. 788.13 0.12%
09.02.02.03 MOBILIARIO PARA TOPICO und 1.00 974.57 S/. 974.57 0.15%
10 CAPACITACION DE DOCENTES
10.01 CAPACITACIONES glb 1.00 847.46 S/. 847.46 0.13%
11 FLETE
11.01 FLETE TERRESTRE
11.01.01 FLETE glb 1.00 37,630.56 S/. 37,630.56 5.70%
11.02 FLETE RURAL
11.02.01 ACARREO DE MATERIALES glb 1.00 44,581.44 S/. 44,581.44 6.75%

COSTO DIRECTO S/. 660,329.39 100.00%


GASTOS GENERALES (8.50%) S/. 56,128.00
UTILIDAD (6%) S/. 39,619.76

SUBTOTAL S/. 756,077.15


IGV(18%) S/. 136,093.89

PRESUPUESTO DE OBRA S/. 892,171.04


SUPERVISION (2.56%) S/. 22,847.68

PRESUPUESTO TOTAL S/. 915,018.72


RESUMEN DE METRADOS FINALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO

ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL


META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO


METRADOS FINALES
Metrado Principal Ejecutado Saldo vinculante Saldo Final
ITEM DESCRIPCIÓN DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

01 AULAS
01.01 OBRAS PRELIMINARES
01.01.01 ALQUILER DE ALMACEN mes 6.00 6.00 0.00 0.00 6.00 100.00% 0.00 0.00% 0.00 0.00%
01.01.02 CARTEL DE OBRA glb 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DE TERRENO MANUAL m2 223.82 223.82 0.00 0.00 223.82 100.00% 0.00 0.00% 0.00 0.00%
01.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 300.00 300.00 0.00 0.00 300.00 100.00% 0.00 0.00% 0.00 0.00%
01.03 MOVIMIENTO DE TIERRAS
01.03.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 55.71 55.71 0.00 0.00 55.71 100.00% 0.00 0.00% 0.00 0.00%
01.03.02 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 25.85 25.85 0.00 0.00 25.85 100.00% 0.00 0.00% 0.00 0.00%
01.03.03 EXCAVACIONES
01.03.03.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 35.98 35.98 0.00 0.00 35.98 100.00% 0.00 0.00% 0.00 0.00%
01.03.03.02 EXCAVACION MANUAL DE ZAPATAS m3 30.00 30.00 0.00 0.00 30.00 100.00% 0.00 0.00% 0.00 0.00%
01.03.03.03 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES DE VEREDAS m3 2.24 2.24 0.00 0.00 2.24 100.00% 0.00 0.00% 0.00 0.00%
01.03.03.04 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS DE DRENAJE m3 5.82 5.82 0.00 0.00 5.82 100.00% 0.00 0.00% 0.00 0.00%
01.03.03.05 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 10.35 10.35 0.00 0.00 10.35 100.00% 0.00 0.00% 0.00 0.00%
01.03.03.06 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 158.60 158.60 0.00 0.00 158.60 100.00% 0.00 0.00% 0.00 0.00%
01.03.03.07 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 200.42 200.42 0.00 0.00 200.42 100.00% 0.00 0.00% 0.00 0.00%
01.03.03.08 AFIRMADO DE e=4" PARA PISOS INTERIORES Y EXTERIORES m2 119.98 119.98 0.00 0.00 119.98 100.00% 0.00 0.00% 0.00 0.00%
01.04 CONCRETO SIMPLE
01.04.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 13.82 13.82 0.00 0.00 13.82 100.00% 0.00 0.00% 0.00 0.00%
01.04.02 SUBCIMIENTO C:H=1:12+30% PG m3 15.72 15.72 0.00 0.00 15.72 100.00% 0.00 0.00% 0.00 0.00%
01.04.03 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 20.00 20.00 0.00 0.00 20.00 100.00% 0.00 0.00% 0.00 0.00%
01.04.04 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 5.69 5.69 0.00 0.00 5.69 100.00% 0.00 0.00% 0.00 0.00%
01.04.05 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 59.52 59.52 0.00 0.00 59.52 100.00% 0.00 0.00% 0.00 0.00%
01.04.06 FALSO PISO e= 4" ( MEZCLA 1:10 CEMENTO : HORMIGON ) m2 146.87 146.87 0.00 0.00 146.87 100.00% 0.00 0.00% 0.00 0.00%
01.04.07 CONCRETO F'C=140 KG/CM2 EN CANALETAS m3 6.11 6.11 0.00 0.00 6.11 100.00% 0.00 0.00% 0.00 0.00%
01.04.08 ENCOFRADO Y DESENCOFRADO EN CANALETAS m2 31.36 31.36 0.00 0.00 31.36 100.00% 0.00 0.00% 0.00 0.00%
01.04.09 JUNTAS ASFALTICAS m 3.20 3.20 0.00 0.00 3.20 100.00% 0.00 0.00% 0.00 0.00%
01.04.10 TUBERIA PVC SAL D=8" m 6.00 6.00 0.00 0.00 6.00 100.00% 0.00 0.00% 0.00 0.00%
01.05 CONCRETO ARMADO
01.05.01 VIGA DE CIMENTACION
01.05.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 4.17 4.17 0.00 0.00 4.17 100.00% 0.00 0.00% 0.00 0.00%
01.05.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 41.65 41.65 0.00 0.00 41.65 100.00% 0.00 0.00% 0.00 0.00%
01.05.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 481.42 481.42 0.00 0.00 481.42 100.00% 0.00 0.00% 0.00 0.00%
01.05.02 ZAPATAS
01.05.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 12.00 12.00 0.00 0.00 12.00 100.00% 0.00 0.00% 0.00 0.00%
01.05.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 236.87 236.87 0.00 0.00 236.87 100.00% 0.00 0.00% 0.00 0.00%
01.05.03 COLUMNAS
01.05.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 9.45 9.45 0.00 0.00 9.45 100.00% 0.00 0.00% 0.00 0.00%
01.05.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 85.11 85.11 0.00 0.00 85.11 100.00% 0.00 0.00% 0.00 0.00%
01.05.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,992.18 1,992.18 0.00 0.00 1,992.18 100.00% 0.00 0.00% 0.00 0.00%
01.05.04 VIGAS
01.05.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 8.56 8.56 0.00 0.00 8.56 100.00% 0.00 0.00% 0.00 0.00%
01.05.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 97.51 97.51 0.00 0.00 97.51 100.00% 0.00 0.00% 0.00 0.00%
01.05.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,114.78 1,114.78 0.00 0.00 1,114.78 100.00% 0.00 0.00% 0.00 0.00%
01.05.05 COLUMNETAS
01.05.05.01 CONCRETO fc'= 175 kg/cm2 EN COLUMNETAS m3 3.36 3.36 0.00 0.00 3.36 100.00% 0.00 0.00% 0.00 0.00%
01.05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNETAS m2 100.38 100.38 0.00 0.00 100.38 100.00% 0.00 0.00% 0.00 0.00%
01.05.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 356.52 356.52 0.00 0.00 356.52 100.00% 0.00 0.00% 0.00 0.00%
01.05.06 VIGUETAS
01.05.06.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.41 0.41 0.00 0.00 0.41 100.00% 0.00 0.00% 0.00 0.00%
01.05.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 8.92 8.92 0.00 0.00 8.92 100.00% 0.00 0.00% 0.00 0.00%
01.05.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 136.42 136.42 0.00 0.00 136.42 100.00% 0.00 0.00% 0.00 0.00%
01.06 ESTRUCTURA METALICA
01.06.01 TIJERAL METALICO TIPO I L=9.93 M und 6.00 6.00 0.00 0.00 6.00 66.67% 0.00 33.33% 0.00 0.00%
01.06.02 TIJERAL METALICO TIPO IV L=8.72 M und 3.00 3.00 0.00 0.00 3.00 100.00% 0.00 0.00% 0.00 0.00%
01.06.03 CORREAS METALICAS CW 64X38X0.90 m 226.12 226.12 0.00 0.00 226.12 100.00% 0.00 0.00% 0.00 0.00%
01.06.04 CORREAS METALICAS UP 90X32X0.90 MM m 46.94 46.94 0.00 0.00 46.94 66.67% 0.00 33.33% 0.00 0.00%
01.06.05 ARRIOSTRE METALICO PT 100X0.9 m 63.30 63.30 0.00 0.00 63.30 100.00% 0.00 0.00% 0.00 0.00%
01.06.06 CORREAS METALICAS DE CIERRE UP 65X32X0.90 MM m 57.18 57.18 0.00 0.00 57.18 100.00% 0.00 0.00% 0.00 0.00%
01.07 ALBAÑILERIA 0 0.00 0.00 0.00 66.67% 33.33%
RESUMEN DE METRADOS FINALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO

ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL


META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO


METRADOS FINALES
Metrado Principal Ejecutado Saldo vinculante Saldo Final
ITEM DESCRIPCIÓN DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

01.07.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 48.22 48.22 0.00 0.00 48.22 100.00% 0.00 0.00% 0.00 0.00%
01.07.02 MURO DE LADRILLO KK DE ARCILLA DE CABEZA MEZCLA 1:4 m2 77.77 77.77 0.00 0.00 77.77 100.00% 0.00 0.00% 0.00 0.00%
01.07.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 32.90 32.90 0.00 0.00 32.90 100.00% 0.00 0.00% 0.00 0.00%
01.08 REVOQUES, ENLUCIDOS Y DERRAMES
01.08.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 200.58 200.58 0.00 0.00 200.58 100.00% 0.00 0.00% 0.00 0.00%
01.08.02 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 123.32 123.32 0.00 0.00 123.32 100.00% 0.00 0.00% 0.00 0.00%
01.08.03 VESTIDURAS DE DERRAMES CON BORDES BOLEADOS M : 1: 5 m 128.36 128.36 0.00 0.00 128.36 100.00% 0.00 0.00% 0.00 0.00%
01.08.04 BRUÑAS
01.08.04.01 BRUÑA e= 1 cm. EXTERIOR m 93.34 93.34 0.00 0.00 93.34 100.00% 0.00 0.00% 0.00 0.00%
01.08.04.02 BRUÑA e= 1 cm. INTERIOR m 171.85 171.85 0.00 0.00 171.85 100.00% 0.00 0.00% 0.00 0.00%
01.08.04.03 BRUÑA e= 1 cm. EN PISO INTERIOR Y EXTERIOR m 72.84 72.84 0.00 0.00 72.84 100.00% 0.00 0.00% 0.00 0.00%
01.09 CERRAMIENTO CON PANEL FIBROCEMENTO
01.09.01 CIELORRASO CON PANEL FIBROCEMENTO 4 mm. m2 179.89 179.89 0.00 0.00 179.89 100.00% 0.00 0.00% 0.00 0.00%
01.10 PISOS Y PAVIMENTOS
01.10.01 PISO DE MADERA MACHIHEMBRADA m2 120.95 120.95 0.00 0.00 120.95 100.00% 0.00 0.00% 0.00 0.00%
01.10.02 PISO DE CONCRETO e=2", PULIDO SIN COLOREAR m2 9.00 9.00 0.00 0.00 9.00 100.00% 0.00 0.00% 0.00 0.00%
01.10.03 PISO CERAMICO DE COLOR CLARO 30X30CM m2 21.02 21.02 0.00 0.00 21.02 100.00% 0.00 0.00% 0.00 0.00%
01.10.04 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 31.56 31.56 0.00 0.00 31.56 100.00% 0.00 0.00% 0.00 0.00%
01.10.05 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 5.35 5.35 0.00 0.00 5.35 100.00% 0.00 0.00% 0.00 0.00%
01.11 ZOCALOS Y CONTRAZOCALOS
01.11.01 ZOCALO DE MAYOLICA BLANCA 30 X 30 CM. m2 40.70 40.70 0.00 0.00 40.70 100.00% 0.00 0.00% 0.00 0.00%
01.11.02 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.20 m. EXTERIOR m 57.30 57.30 0.00 0.00 57.30 100.00% 0.00 0.00% 0.00 0.00%
01.11.03 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.10 m. INTERIOR m 14.54 14.54 0.00 0.00 14.54 100.00% 0.00 0.00% 0.00 0.00%
01.11.04 CONTRAZOCALO DE CEDRO DE 3" RODON 1" m 54.72 54.72 0.00 0.00 54.72 100.00% 0.00 0.00% 0.00 0.00%
01.12 CUBIERTA Y TECHO
01.12.01 COBERTURA CON LAMINA TERMOACUSTICA m2 293.23 293.23 0.00 0.00 293.23 100.00% 0.00 0.00% 0.00 0.00%
01.12.02 CUMBRERA DENTADA m 22.54 22.54 0.00 0.00 22.54 100.00% 0.00 0.00% 0.00 0.00%
01.13 CARPINTERIA DE MADERA
01.13.01 PUERTA DE MADERA APANELADA m2 15.90 15.90 0.00 0.00 15.90 100.00% 0.00 0.00% 0.00 0.00%
01.13.02 VENTANA DE MADERA m2 36.42 36.42 0.00 0.00 36.42 100.00% 0.00 0.00% 0.00 0.00%
01.13.03 TICERO DE MADERA CEDRO ( L= 3.00 m. ) BARNIZADO und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
01.14 CERRAJERIA
01.14.01 BISAGRA ALUMINIZADA DE 4" x 4" PESADA PARA PUERTA pza 24.00 24.00 0.00 0.00 24.00 100.00% 0.00 0.00% 0.00 0.00%
01.14.02 CERRADURA PARA PUERTA EXTERIOR TIPO PARCHE 2 GOLPES pza 7.00 7.00 0.00 0.00 7.00 100.00% 0.00 0.00% 0.00 0.00%
01.14.03 MANIJA DE 4" PARA PUERTA pza 7.00 7.00 0.00 0.00 7.00 100.00% 0.00 0.00% 0.00 0.00%
01.14.04 CERROJOS PARA VENTANAS DE BRONCE pza 70.00 70.00 0.00 0.00 70.00 100.00% 0.00 0.00% 0.00 0.00%
01.14.05 MANIJA DE BRONCE PARA PORTAÑUELAS DE VENTANAS pza 70.00 70.00 0.00 0.00 70.00 100.00% 0.00 0.00% 0.00 0.00%
01.14.06 BISAGRA ALUMINIZADA DE 2 1/2" x 2 1/2" PARA VENTANA pza 70.00 70.00 0.00 0.00 70.00 100.00% 0.00 0.00% 0.00 0.00%
01.14.07 TOPE METALICO DE FIERRO PARA VENTANA pza 70.00 70.00 0.00 0.00 70.00 100.00% 0.00 0.00% 0.00 0.00%
01.15 VIDRIOS, CRISTALES Y SIMILARES
01.15.01 VIDRIOS SEMIDOBLES p2 391.83 391.83 0.00 0.00 391.83 100.00% 0.00 0.00% 0.00 0.00%
01.16 PINTURA
01.16.01 PINT. LATEX 2 MANOS EN MUROS EXTERIORES m2 123.32 123.32 0.00 0.00 123.32 100.00% 0.00 0.00% 0.00 0.00%
01.16.02 PINT. LATEX 2 MANOS EN MUROS INTERIORES m2 187.14 187.14 0.00 0.00 187.14 100.00% 0.00 0.00% 0.00 0.00%
01.16.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 85.11 85.11 0.00 0.00 85.11 100.00% 0.00 0.00% 0.00 0.00%
01.16.04 PINTURA LATEX 2 MANOS EN COLUMNETAS m2 44.09 44.09 0.00 0.00 44.09 100.00% 0.00 0.00% 0.00 0.00%
01.16.05 PINTURA LATEX 2 MANOS EN VIGAS m2 97.51 97.51 0.00 0.00 97.51 100.00% 0.00 0.00% 0.00 0.00%
01.16.06 PINTURA BARNIZ EN PUERTAS m2 31.80 31.80 0.00 0.00 31.80 100.00% 0.00 0.00% 0.00 0.00%
01.16.07 PINTURA BARNIZ EN VENTANA DE MADERA m2 36.42 36.42 0.00 0.00 36.42 100.00% 0.00 0.00% 0.00 0.00%
01.17 VARIOS
01.17.01 JUNTA SISMICA DE 1" m 9.87 9.87 0.00 0.00 9.87 100.00% 0.00 0.00% 0.00 0.00%
01.17.02 PIZARRA CEMENTO 3.00 x 1.20 m. SIN TICERO und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
01.17.03 JUNTA DE DILATACION DE 1" EN VEREDA m 35.21 35.21 0.00 0.00 35.21 100.00% 0.00 0.00% 0.00 0.00%
01.18 INSTALACIONES SANITARIAS
01.18.01 DESAGUE Y VENTILACION
01.18.01.01 SALIDA DE DESAGUE PVC SAL D=2" pto 7.00 7.00 0.00 0.00 7.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.01.02 SALIDA DE DESAGUE PVC SAL D=4" pto 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.01.03 SUMIDEROS DE 3" pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.01.04 REGISTRO DE BRONCE 2" pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.01.05 REGISTRO DE BRONCE 4" pza 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.02 REDES DE DISTRIBUCION
01.18.02.01 TUBERIA PVC -SAL 2" m 10.11 10.11 0.00 0.00 10.11 100.00% 0.00 0.00% 0.00 0.00%
RESUMEN DE METRADOS FINALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO

ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL


META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO


METRADOS FINALES
Metrado Principal Ejecutado Saldo vinculante Saldo Final
ITEM DESCRIPCIÓN DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

01.18.02.02 TUBERIA PVC -SAL 4" m 39.81 39.81 0.00 0.00 39.81 100.00% 0.00 0.00% 0.00 0.00%
01.18.03 APARATOS Y ACCESORIOS SANITARIOS
01.18.03.01 INODORO TANQUE BAJO TIPO "BABY" und 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.03.02 PAPELERA DE LOZA DE COLOR DE 15 X 15 cm pza 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.03.03 CAJA DE REGISTRO 12"X24" C/TAPA DE CONCRETO pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.04 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.18.04.01 SALIDA DE AGUA FRIA PVC pto 10.00 10.00 0.00 0.00 10.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.04.02 TUBERIA PVC CLASE 10 - 3/4" m 30.72 30.72 0.00 0.00 30.72 100.00% 0.00 0.00% 0.00 0.00%
01.18.04.03 TUBERIA PVC CLASE 10 - 1/2" m 4.03 4.03 0.00 0.00 4.03 100.00% 0.00 0.00% 0.00 0.00%
01.18.04.04 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.04.05 VALVULAS DE COMPUERTA DE BRONCE DE 3/4" pza 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.05 SISTEMA DE DRENAJE PLUVIAL
01.18.05.01 TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS m 30.33 30.33 0.00 0.00 30.33 100.00% 0.00 0.00% 0.00 0.00%
01.18.05.02 CANALETA DE FIERRO GALVANIZADO m 64.94 64.94 0.00 0.00 64.94 100.00% 0.00 0.00% 0.00 0.00%
01.18.05.03 ABRAZADERA DE FIJACION DE TUBO pza 59.00 59.00 0.00 0.00 59.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.05.04 COLECTOR DE ZINC GALVANIZADO und 6.00 6.00 0.00 0.00 6.00 100.00% 0.00 0.00% 0.00 0.00%
01.18.05.05 ABRAZADERA DE FIJACION DE TUBERIA DE 3" pza 18.00 18.00 0.00 0.00 18.00 100.00% 0.00 0.00% 0.00 0.00%
01.19 INSTALACIONES ELECTRICAS
01.19.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 17.00 17.00 0.00 0.00 17.00 100.00% 0.00 0.00% 0.00 0.00%
01.19.02 SALIDA INTERRUPTOR SIMPLE pto 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
01.19.03 SALIDA INTERRUPTOR DOBLE pto 5.00 5.00 0.00 0.00 5.00 100.00% 0.00 0.00% 0.00 0.00%
01.19.04 SALIDA TOMACORRIENTE DOBLE pto 6.00 6.00 0.00 0.00 6.00 100.00% 0.00 0.00% 0.00 0.00%
01.19.05 SALIDA PARA ANTENA DE TELEVISION CON PVC pto 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
01.20 TABLEROS
01.20.01 TABLERO DE DISTRIBUCION TD-3 und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
01.21 ARTEFACTOS
01.21.01 ARTEFACTO FLUORESCENTE 2/18 W und 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
01.21.02 ARTEFACTO FLUORESCENTE 1/36W und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
01.21.03 ARTEFACTO FLUORESCENTE 2/36 W und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
01.21.04 ARTEFACTO FLUORESCENTE 4/36W und 8.00 8.00 0.00 0.00 8.00 100.00% 0.00 0.00% 0.00 0.00%
01.22 POZO PUESTA A TIERRA 0 0.00 0.00
01.22.01 POZO DE PUESTA A TIERRA und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02 AREA COMPLEMENTARIA
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 248.72 248.72 0.00 0.00 248.72 100.00% 0.00 0.00% 0.00 0.00%
02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 290.85 290.85 0.00 0.00 290.85 100.00% 0.00 0.00% 0.00 0.00%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 369.18 369.18 0.00 0.00 369.18 100.00% 0.00 0.00% 0.00 0.00%
02.02.02 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 33.95 33.95 0.00 0.00 33.95 100.00% 0.00 0.00% 0.00 0.00%
02.02.03 EXCAVACIONES
02.02.03.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 46.92 46.92 0.00 0.00 46.92 100.00% 0.00 0.00% 0.00 0.00%
02.02.03.02 EXCAVACION MANUAL DE ZAPATAS m3 31.50 31.50 0.00 0.00 31.50 100.00% 0.00 0.00% 0.00 0.00%
02.02.03.03 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES DE VEREDAS m3 2.25 2.25 0.00 0.00 2.25 100.00% 0.00 0.00% 0.00 0.00%
02.02.03.04 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS DE DRENAJE m3 5.42 5.42 0.00 0.00 5.42 100.00% 0.00 0.00% 0.00 0.00%
02.02.03.05 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 12.23 12.23 0.00 0.00 12.23 100.00% 0.00 0.00% 0.00 0.00%
02.02.03.06 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 580.36 580.36 0.00 0.00 580.36 100.00% 0.00 0.00% 0.00 0.00%
02.02.03.07 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 247.78 247.78 0.00 0.00 247.78 100.00% 0.00 0.00% 0.00 0.00%
02.02.03.08 AFIRMADO DE e=4" PARA PISOS INTERIORES Y EXTERIORES m2 226.78 226.78 0.00 0.00 226.78 100.00% 0.00 0.00% 0.00 0.00%
02.03 CONCRETO SIMPLE
02.03.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 18.24 18.24 0.00 0.00 18.24 100.00% 0.00 0.00% 0.00 0.00%
02.03.02 SUBCIMIENTO C:H=1:12+30% PG m3 18.20 18.20 0.00 0.00 18.20 100.00% 0.00 0.00% 0.00 0.00%
02.03.03 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 21.00 21.00 0.00 0.00 21.00 100.00% 0.00 0.00% 0.00 0.00%
02.03.04 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 10.49 10.49 0.00 0.00 10.49 100.00% 0.00 0.00% 0.00 0.00%
02.03.05 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 113.05 113.05 0.00 0.00 113.05 100.00% 0.00 0.00% 0.00 0.00%
02.03.06 FALSO PISO e= 4" ( MEZCLA 1:10 CEMENTO : HORMIGON ) m2 178.05 178.05 0.00 0.00 178.05 100.00% 0.00 0.00% 0.00 0.00%
02.03.07 CONCRETO F'C=140 KG/CM2 EN CANALETAS m3 6.60 6.60 0.00 0.00 6.60 100.00% 0.00 0.00% 0.00 0.00%
02.03.08 ENCOFRADO Y DESENCOFRADO EN CANALETAS m2 34.02 34.02 0.00 0.00 34.02 100.00% 0.00 0.00% 0.00 0.00%
02.03.09 JUNTAS ASFALTICAS m 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
02.03.10 TUBERIA PVC SAL D=8" m 6.00 6.00 0.00 0.00 6.00 100.00% 0.00 0.00% 0.00 0.00%
02.04 CONCRETO ARMADO
02.04.01 VIGA DE CIMENTACION
02.04.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 6.85 6.85 0.00 0.00 6.85 100.00% 0.00 0.00% 0.00 0.00%
RESUMEN DE METRADOS FINALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO

ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL


META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO


METRADOS FINALES
Metrado Principal Ejecutado Saldo vinculante Saldo Final
ITEM DESCRIPCIÓN DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

02.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 68.49 68.49 0.00 0.00 68.49 100.00% 0.00 0.00% 0.00 0.00%
02.04.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 545.47 545.47 0.00 0.00 545.47 100.00% 0.00 0.00% 0.00 0.00%
02.04.02 ZAPATAS
02.04.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 12.60 12.60 0.00 0.00 12.60 100.00% 0.00 0.00% 0.00 0.00%
02.04.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 250.55 250.55 0.00 0.00 250.55 100.00% 0.00 0.00% 0.00 0.00%
02.04.03 COLUMNAS
02.04.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 11.05 11.05 0.00 0.00 11.05 100.00% 0.00 0.00% 0.00 0.00%
02.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 79.62 79.62 0.00 0.00 79.62 100.00% 0.00 0.00% 0.00 0.00%
02.04.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 2,805.55 2,805.55 0.00 0.00 2,805.55 100.00% 0.00 0.00% 0.00 0.00%
02.04.04 VIGAS
02.04.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 11.82 11.82 0.00 0.00 11.82 100.00% 0.00 0.00% 0.00 0.00%
02.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 134.17 134.17 0.00 0.00 134.17 100.00% 0.00 0.00% 0.00 0.00%
02.04.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,580.11 1,580.11 0.00 0.00 1,580.11 100.00% 0.00 0.00% 0.00 0.00%
02.04.05 COLUMNETAS
02.04.05.01 CONCRETO fc'= 175 kg/cm2 EN COLUMNETAS m3 4.67 4.67 0.00 0.00 4.67 100.00% 0.00 0.00% 0.00 0.00%
02.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNETAS m2 75.55 75.55 0.00 0.00 75.55 100.00% 0.00 0.00% 0.00 0.00%
02.04.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 543.43 543.43 0.00 0.00 543.43 100.00% 0.00 0.00% 0.00 0.00%
02.04.06 VIGUETAS
02.04.06.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.36 0.36 0.00 0.00 0.36 100.00% 0.00 0.00% 0.00 0.00%
02.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 5.51 5.51 0.00 0.00 5.51 100.00% 0.00 0.00% 0.00 0.00%
02.04.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 101.78 101.78 0.00 0.00 101.78 100.00% 0.00 0.00% 0.00 0.00%
02.05 ESTRUCTURA METALICA
02.05.01 TIJERAL METALICO TIPO I L=9.93 M und 6.00 6.00 0.00 0.00 6.00 100.00% 0.00 0.00% 0.00 0.00%
02.05.02 TIJERAL METALICO TIPO III L=7.50 M und 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
02.05.03 CORREAS METALICAS CW 64X38X0.90 m 302.69 302.69 0.00 0.00 302.69 100.00% 0.00 0.00% 0.00 0.00%
02.05.04 CORREAS METALICAS UP 90X32X0.90 MM m 60.52 60.52 0.00 0.00 60.52 100.00% 0.00 0.00% 0.00 0.00%
02.05.05 ARRIOSTRE METALICO PT 100X0.9 m 71.86 71.86 0.00 0.00 71.86 100.00% 0.00 0.00% 0.00 0.00%
02.05.06 CORREAS METALICAS DE CIERRE UP 65X32X0.90 MM m 58.22 58.22 0.00 0.00 58.22 100.00% 0.00 0.00% 0.00 0.00%
02.06 ALBAÑILERIA
02.06.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 102.29 102.29 0.00 0.00 102.29 100.00% 0.00 0.00% 0.00 0.00%
02.06.02 MURO DE LADRILLO KK DE ARCILLA DE CABEZA MEZCLA 1:4 m2 120.61 120.61 0.00 0.00 120.61 100.00% 0.00 0.00% 0.00 0.00%
02.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 45.85 45.85 0.00 0.00 45.85 100.00% 0.00 0.00% 0.00 0.00%
02.07 REVOQUES, ENLUCIDOS Y DERRAMES 0 0.00 0.00
02.07.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 285.76 285.76 0.00 0.00 285.76 100.00% 0.00 0.00% 0.00 0.00%
02.07.02 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 160.04 160.04 0.00 0.00 160.04 100.00% 0.00 0.00% 0.00 0.00%
02.07.03 VESTIDURAS DE DERRAMES CON BORDES BOLEADOS M : 1: 5 m 57.30 57.30 0.00 0.00 57.30 100.00% 0.00 0.00% 0.00 0.00%
02.07.04 BRUÑAS
02.07.04.01 BRUÑA e= 1 cm. EXTERIOR m 104.66 104.66 0.00 0.00 104.66 100.00% 0.00 0.00% 0.00 0.00%
02.07.04.02 BRUÑA e= 1 cm. INTERIOR m 162.31 162.31 0.00 0.00 162.31 100.00% 0.00 0.00% 0.00 0.00%
02.07.04.03 BRUÑA e= 1 cm. EN PISO INTERIOR Y EXTERIOR m 122.24 122.24 0.00 0.00 122.24 100.00% 0.00 0.00% 0.00 0.00%
02.08 CERRAMIENTO CON PANEL FIBROCEMENTO
02.08.01 CIELORRASO CON PANEL FIBROCEMENTO 4 mm. m2 260.42 260.42 0.00 0.00 260.42 100.00% 0.00 0.00% 0.00 0.00%
02.09 PISOS Y PAVIMENTOS
02.09.01 PISO DE MADERA MACHIHEMBRADA m2 82.64 82.64 0.00 0.00 82.64 100.00% 0.00 0.00% 0.00 0.00%
02.09.02 PISO DE CONCRETO e=2", PULIDO SIN COLOREAR m2 21.00 21.00 0.00 0.00 21.00 100.00% 0.00 0.00% 0.00 0.00%
02.09.03 PISO CERAMICO DE COLOR CLARO 30X30CM m2 73.42 73.42 0.00 0.00 73.42 100.00% 0.00 0.00% 0.00 0.00%
02.09.04 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 49.25 49.25 0.00 0.00 49.25 100.00% 0.00 0.00% 0.00 0.00%
02.09.05 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 7.76 7.76 0.00 0.00 7.76 100.00% 0.00 0.00% 0.00 0.00%
02.10 ZOCALOS Y CONTRAZOCALOS
02.10.01 ZOCALO DE MAYOLICA BLANCA 30 X 30 CM. m2 25.04 25.04 0.00 0.00 25.04 100.00% 0.00 0.00% 0.00 0.00%
02.10.02 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.20 m. EXTERIOR m 66.03 66.03 0.00 0.00 66.03 100.00% 0.00 0.00% 0.00 0.00%
02.10.03 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.10 m. INTERIOR m 40.77 40.77 0.00 0.00 40.77 100.00% 0.00 0.00% 0.00 0.00%
02.10.04 CONTRAZOCALO DE CEDRO DE 3" RODON 1" m 47.01 47.01 0.00 0.00 47.01 100.00% 0.00 0.00% 0.00 0.00%
02.10.05 CONTRAZOCALO DE CERAMICO H=20 CM m 13.85 13.85 0.00 0.00 13.85 100.00% 0.00 0.00% 0.00 0.00%
02.11 CUBIERTA Y TECHO
02.11.01 COBERTURA CON LAMINA TERMOACUSTICA m2 291.80 291.80 0.00 0.00 291.80 100.00% 0.00 0.00% 0.00 0.00%
02.11.02 CUMBRERA DENTADA m 30.25 30.25 0.00 0.00 30.25 100.00% 0.00 0.00% 0.00 0.00%
02.12 CARPINTERIA DE MADERA
02.12.01 PUERTA DE MADERA APANELADA m2 21.74 21.74 0.00 0.00 21.74 100.00% 0.00 0.00% 0.00 0.00%
02.12.02 VENTANA DE MADERA m2 31.52 31.52 0.00 0.00 31.52 100.00% 0.00 0.00% 0.00 0.00%
02.12.03 TICERO DE MADERA CEDRO ( L= 3.00 m. ) BARNIZADO und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.13 CERRAJERIA
RESUMEN DE METRADOS FINALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO

ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL


META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO


METRADOS FINALES
Metrado Principal Ejecutado Saldo vinculante Saldo Final
ITEM DESCRIPCIÓN DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

02.13.01 BISAGRA ALUMINIZADA DE 4" x 4" PESADA PARA PUERTA pza 30.00 30.00 0.00 0.00 30.00 100.00% 0.00 0.00% 0.00 0.00%
02.13.02 CERRADURA PARA PUERTA EXTERIOR TIPO PARCHE 2 GOLPES pza 10.00 10.00 0.00 0.00 10.00 100.00% 0.00 0.00% 0.00 0.00%
02.13.03 MANIJA DE 4" PARA PUERTA pza 10.00 10.00 0.00 0.00 10.00 100.00% 0.00 0.00% 0.00 0.00%
02.13.04 CERROJOS PARA VENTANAS DE BRONCE pza 62.00 62.00 0.00 0.00 62.00 100.00% 0.00 0.00% 0.00 0.00%
02.13.05 MANIJA DE BRONCE PARA PORTAÑUELAS DE VENTANAS pza 62.00 62.00 0.00 0.00 62.00 100.00% 0.00 0.00% 0.00 0.00%
02.13.06 BISAGRA ALUMINIZADA DE 2 1/2" x 2 1/2" PARA VENTANA pza 62.00 62.00 0.00 0.00 62.00 100.00% 0.00 0.00% 0.00 0.00%
02.13.07 TOPE METALICO DE FIERRO PARA VENTANA pza 62.00 62.00 0.00 0.00 62.00 100.00% 0.00 0.00% 0.00 0.00%
02.14 VIDRIOS, CRISTALES Y SIMILARES
02.14.01 VIDRIOS SEMIDOBLES p2 339.17 339.17 0.00 0.00 339.17 100.00% 0.00 0.00% 0.00 0.00%
02.15 PINTURA
02.15.01 PINT. LATEX 2 MANOS EN MUROS EXTERIORES m2 160.04 160.04 0.00 0.00 160.04 100.00% 0.00 0.00% 0.00 0.00%
02.15.02 PINT. LATEX 2 MANOS EN MUROS INTERIORES m2 285.76 285.76 0.00 0.00 285.76 100.00% 0.00 0.00% 0.00 0.00%
02.15.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 134.17 134.17 0.00 0.00 134.17 100.00% 0.00 0.00% 0.00 0.00%
02.15.04 PINTURA LATEX 2 MANOS EN COLUMNETAS m2 75.55 75.55 0.00 0.00 75.55 100.00% 0.00 0.00% 0.00 0.00%
02.15.05 PINTURA LATEX 2 MANOS EN VIGAS m2 100.38 100.38 0.00 0.00 100.38 100.00% 0.00 0.00% 0.00 0.00%
02.15.06 PINTURA BARNIZ EN PUERTAS m2 43.47 43.47 0.00 0.00 43.47 100.00% 0.00 0.00% 0.00 0.00%
02.15.07 PINTURA BARNIZ EN VENTANA DE MADERA m2 63.04 63.04 0.00 0.00 63.04 100.00% 0.00 0.00% 0.00 0.00%
02.16 VARIOS
02.16.01 JUNTA SISMICA DE 1" m 16.48 16.48 0.00 0.00 16.48 100.00% 0.00 0.00% 0.00 0.00%
02.16.02 PIZARRA CEMENTO 3.00 x 1.20 m. SIN TICERO und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.16.03 JUNTA DE DILATACION DE 1" EN VEREDA m 23.29 23.29 0.00 0.00 23.29 100.00% 0.00 0.00% 0.00 0.00%
02.17 INSTALACIONES SANITARIAS
02.17.01 DESAGUE Y VENTILACION
02.17.01.01 SALIDA DE DESAGUE PVC SAL D=2" pto 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.01.02 SALIDA DE DESAGUE PVC SAL D=4" pto 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.01.03 SUMIDEROS DE 2" pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.01.04 SUMIDEROS DE 3" pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.01.05 REGISTRO DE BRONCE 2" pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.01.06 REGISTRO DE BRONCE 4" pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.02 REDES DE DISTRIBUCION
02.17.02.01 TUBERIA PVC -SAL 2" m 10.11 10.11 0.00 0.00 10.11 100.00% 0.00 0.00% 0.00 0.00%
02.17.02.02 TUBERIA PVC -SAL 4" m 6.12 6.12 0.00 0.00 6.12 100.00% 0.00 0.00% 0.00 0.00%
02.17.03 APARATOS Y ACCESORIOS SANITARIOS
02.17.03.01 INODORO TANQUE BAJO BLANCO pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.03.02 PAPELERA DE LOZA DE COLOR DE 15 X 15 cm pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.03.03 LAVATORIO DE PARED BLANCO 1 LLAVE pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.03.04 LAVADERO DE COCINA DE ACERO INOXIDABLE pza 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.03.05 CAJA DE REGISTRO 12"X24" C/TAPA DE CONCRETO pza 3.00 3.00 0.00 0.00 3.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.04 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
02.17.04.01 SALIDA DE AGUA FRIA PVC pto 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.04.02 TUBERIA PVC CLASE 10 - 3/4" m 26.00 26.00 0.00 0.00 26.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.04.03 TUBERIA PVC CLASE 10 - 1/2" m 42.00 42.00 0.00 0.00 42.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.04.04 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.04.05 VALVULAS DE COMPUERTA DE BRONCE DE 3/4" pza 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.05 SISTEMA DE DRENAJE PLUVIAL
02.17.05.01 TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS m 30.33 30.33 0.00 0.00 30.33 100.00% 0.00 0.00% 0.00 0.00%
02.17.05.02 CANALETA DE FIERRO GALVANIZADO m 73.62 73.62 0.00 0.00 73.62 100.00% 0.00 0.00% 0.00 0.00%
02.17.05.03 ABRAZADERA DE FIJACION DE TUBO pza 70.00 70.00 0.00 0.00 70.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.05.04 COLECTOR DE ZINC GALVANIZADO und 6.00 6.00 0.00 0.00 6.00 100.00% 0.00 0.00% 0.00 0.00%
02.17.05.05 ABRAZADERA DE FIJACION DE TUBERIA DE 3" pza 18.00 18.00 0.00 0.00 18.00 100.00% 0.00 0.00% 0.00 0.00%
02.18 INSTALACIONES ELECTRICAS
02.18.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 22.00 22.00 0.00 0.00 22.00 100.00% 0.00 0.00% 0.00 0.00%
02.18.02 SALIDA INTERRUPTOR SIMPLE pto 5.00 5.00 0.00 0.00 5.00 100.00% 0.00 0.00% 0.00 0.00%
02.18.03 SALIDA INTERRUPTOR DOBLE pto 10.00 10.00 0.00 0.00 10.00 100.00% 0.00 0.00% 0.00 0.00%
02.18.04 SALIDA TOMACORRIENTE DOBLE pto 20.00 20.00 0.00 0.00 20.00 100.00% 0.00 0.00% 0.00 0.00%
02.19 TABLEROS
02.19.01 TABLERO GENERAL TG und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.19.02 TABLERO DE DISTRIBUCION TD-1 glb 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.19.03 TABLERO DE DISTRIBUCION TD-2 glb 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
02.20 ARTEFACTOS
02.20.01 ARTEFACTO FLUORESCENTE 2/18 W und 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
02.20.02 ARTEFACTO FLUORESCENTE 2/36 W und 8.00 8.00 0.00 0.00 8.00 100.00% 0.00 0.00% 0.00 0.00%
RESUMEN DE METRADOS FINALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO

ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL


META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO


METRADOS FINALES
Metrado Principal Ejecutado Saldo vinculante Saldo Final
ITEM DESCRIPCIÓN DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

02.20.03 ARTEFACTO FLUORESCENTE 4/36W und 10.00 10.00 0.00 0.00 10.00 100.00% 0.00 0.00% 0.00 0.00%
02.21 POZO PUESTA A TIERRA
02.21.01 POZO DE PUESTA A TIERRA und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
03 TANQUE SEPTICO Y POZO PERCOLADOR
03.01 TANQUE SEPTICO
03.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.00 7.00 0.00 0.00 7.00 100.00% 0.00 0.00% 0.00 0.00%
03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 7.00 7.00 0.00 0.00 7.00 100.00% 0.00 0.00% 0.00 0.00%
03.01.03 EXCAVACION DE ESTRUCTURAS m3 10.85 10.85 0.00 0.00 10.85 100.00% 0.00 0.00% 0.00 0.00%
03.01.04 TERRAPLEN P/FALSO PISO C/PISON MANUAL, H=0.15 M m2 4.80 4.80 0.00 0.00 4.80 100.00% 0.00 0.00% 0.00 0.00%
03.01.05 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 14.10 14.10 0.00 0.00 14.10 100.00% 0.00 0.00% 0.00 0.00%
03.01.06 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 4.80 4.80 0.00 0.00 4.80 100.00% 0.00 0.00% 0.00 0.00%
03.01.07 CONCRETO F'C=175 KG/CM2 EN TANQUE SUBTERRANEO m3 4.73 4.73 0.00 0.00 4.73 100.00% 0.00 0.00% 0.00 0.00%
03.01.08 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 244.37 244.37 0.00 0.00 244.37 100.00% 0.00 0.00% 0.00 0.00%
03.01.09 ENCOFRADO Y DESENCOFRADO EN TANQUE ENTERRADO m2 47.29 47.29 0.00 0.00 47.29 100.00% 0.00 0.00% 0.00 0.00%
03.01.10 TARRAJEO CON IMPERMEABILIZANTE, MEZCLA E=1.5 CM m2 17.79 17.79 0.00 0.00 17.79 100.00% 0.00 0.00% 0.00 0.00%
03.01.11 ACCESORIOS PVC SAL EN TANQUE SEPTICO und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
03.01.12 TUBERIA PVC -SAL 4" m 7.00 7.00 0.00 0.00 7.00 100.00% 0.00 0.00% 0.00 0.00%
03.01.13 CAJA DE REGISTRO DE DESAGUE 12"X24" und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
03.02 POZA DE PERCOLACION
03.02.01 LIMPIEZA DE TERRENO MANUAL m2 8.65 8.65 0.00 0.00 8.65 100.00% 0.00 0.00% 0.00 0.00%
03.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 8.65 8.65 0.00 0.00 8.65 100.00% 0.00 0.00% 0.00 0.00%
03.02.03 EXCAVACION DE ESTRUCTURAS m3 17.74 17.74 0.00 0.00 17.74 100.00% 0.00 0.00% 0.00 0.00%
03.02.04 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 23.06 23.06 0.00 0.00 23.06 100.00% 0.00 0.00% 0.00 0.00%
03.02.05 CONCRETO F'C=175 KG/CM2 EN POZA DE PERCOLACION m3 1.03 1.03 0.00 0.00 1.03 100.00% 0.00 0.00% 0.00 0.00%
03.02.06 ENCOFRADO Y DESENCOFRADO EN POZA DE PERCOLACION m2 9.96 9.96 0.00 0.00 9.96 100.00% 0.00 0.00% 0.00 0.00%
03.02.07 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 42.42 42.42 0.00 0.00 42.42 100.00% 0.00 0.00% 0.00 0.00%
03.02.08 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 23.58 23.58 0.00 0.00 23.58 100.00% 0.00 0.00% 0.00 0.00%
03.02.09 FILTRO DE GRAVAS O CASCAJO m3 0.38 0.38 0.00 0.00 0.38 100.00% 0.00 0.00% 0.00 0.00%
03.02.10 CAJA DE REGISTRO DE DESAGUE 12"X24" und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
03.02.11 TUBERIA PVC -SAL 4" m 64.00 64.00 0.00 0.00 64.00 100.00% 0.00 0.00% 0.00 0.00%
04 CERCO PERIMETRICO
04.01 TRABAJOS PRELIMINARES
04.01.01 LIMPIEZA DE TERRENO MANUAL m2 71.00 71.00 0.00 0.00 71.00 100.00% 0.00 0.00% 0.00 0.00%
04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 78.00 78.00 0.00 0.00 78.00 100.00% 0.00 0.00% 0.00 0.00%
04.02 MOVIMIENTO DE TIERRAS
04.02.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 14.71 14.71 0.00 0.00 14.71 100.00% 0.00 0.00% 0.00 0.00%
04.02.02 EXCAVACION MANUAL DE ZAPATAS m3 4.50 4.50 0.00 0.00 4.50 100.00% 0.00 0.00% 0.00 0.00%
04.02.03 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 12.26 12.26 0.00 0.00 12.26 100.00% 0.00 0.00% 0.00 0.00%
04.02.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 2.76 2.76 0.00 0.00 2.76 100.00% 0.00 0.00% 0.00 0.00%
04.02.05 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 21.39 21.39 0.00 0.00 21.39 100.00% 0.00 0.00% 0.00 0.00%
04.03 CONCRETO SIMPLE
04.03.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 10.78 10.78 0.00 0.00 10.78 100.00% 0.00 0.00% 0.00 0.00%
04.03.02 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 2.25 2.25 0.00 0.00 2.25 100.00% 0.00 0.00% 0.00 0.00%
04.03.03 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 30.04 30.04 0.00 0.00 30.04 100.00% 0.00 0.00% 0.00 0.00%
04.03.04 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 3.00 3.00 0.00 0.00 3.00 100.00% 0.00 0.00% 0.00 0.00%
04.04 CONCRETO ARMADO
04.04.01 VIGA DE CIMENTACION
04.04.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 0.57 0.57 0.00 0.00 0.57 100.00% 0.00 0.00% 0.00 0.00%
04.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 9.12 9.12 0.00 0.00 9.12 100.00% 0.00 0.00% 0.00 0.00%
04.04.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 68.61 68.61 0.00 0.00 68.61 100.00% 0.00 0.00% 0.00 0.00%
04.04.02 ZAPATAS
04.04.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 1.50 1.50 0.00 0.00 1.50 100.00% 0.00 0.00% 0.00 0.00%
04.04.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 52.07 52.07 0.00 0.00 52.07 100.00% 0.00 0.00% 0.00 0.00%
04.04.03 COLUMNAS
04.04.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 3.32 3.32 0.00 0.00 3.32 100.00% 0.00 0.00% 0.00 0.00%
04.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 29.64 29.64 0.00 0.00 29.64 100.00% 0.00 0.00% 0.00 0.00%
04.04.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 414.96 414.96 0.00 0.00 414.96 100.00% 0.00 0.00% 0.00 0.00%
04.04.04 VIGAS
04.04.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 0.49 0.49 0.00 0.00 0.49 100.00% 0.00 0.00% 0.00 0.00%
04.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 5.28 5.28 0.00 0.00 5.28 100.00% 0.00 0.00% 0.00 0.00%
04.04.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 59.10 59.10 0.00 0.00 59.10 100.00% 0.00 0.00% 0.00 0.00%
04.04.05 VIGUETAS
RESUMEN DE METRADOS FINALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO

ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL


META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO


METRADOS FINALES
Metrado Principal Ejecutado Saldo vinculante Saldo Final
ITEM DESCRIPCIÓN DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

04.04.05.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.06 0.06 0.00 0.00 0.06 100.00% 0.00 0.00% 0.00 0.00%
04.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 0.77 0.77 0.00 0.00 0.77 100.00% 0.00 0.00% 0.00 0.00%
04.04.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 6.42 6.42 0.00 0.00 6.42 100.00% 0.00 0.00% 0.00 0.00%
04.04.06 LOSA ARMADA
04.04.06.01 CONCRETO F'C=210 KG/CM2 EN LOSA ARMADA m3 1.32 1.32 0.00 0.00 1.32 100.00% 0.00 0.00% 0.00 0.00%
04.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE LOSA ARMADA m2 11.37 11.37 0.00 0.00 11.37 100.00% 0.00 0.00% 0.00 0.00%
04.04.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 48.43 48.43 0.00 0.00 48.43 100.00% 0.00 0.00% 0.00 0.00%
04.05 ALBAÑILERIA
04.05.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 10.61 10.61 0.00 0.00 10.61 100.00% 0.00 0.00% 0.00 0.00%
04.06 PISOS Y PAVIMENTOS
04.06.01 AFIRMADO DE 4" PARA VEREDAS m2 12.26 12.26 0.00 0.00 12.26 100.00% 0.00 0.00% 0.00 0.00%
04.06.02 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 12.26 12.26 0.00 0.00 12.26 100.00% 0.00 0.00% 0.00 0.00%
04.06.03 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 0.31 0.31 0.00 0.00 0.31 100.00% 0.00 0.00% 0.00 0.00%
04.07 PINTURA
04.07.01 PINTURA LATEX 2 MANOS EN COLUMNAS m2 33.79 33.79 0.00 0.00 33.79 100.00% 0.00 0.00% 0.00 0.00%
04.07.02 PINTURA LATEX 2 MANOS EN VIGAS m2 5.28 5.28 0.00 0.00 5.28 100.00% 0.00 0.00% 0.00 0.00%
04.07.03 PINTURA LATEX 2 MANOS EN VIGUETAS m2 0.77 0.77 0.00 0.00 0.77 100.00% 0.00 0.00% 0.00 0.00%
04.08 CARPINTERIA METALICA
04.08.01 PUERTA METALICA P1(3.75x3.20M) und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
04.08.02 PUERTA METALICA P2(1.10x3.20M) und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
04.08.03 MALLA METALICA COCADA 2'X2' H=2.20 M m 20.00 20.00 0.00 0.00 20.00 100.00% 0.00 0.00% 0.00 0.00%
04.09 INSTALACIONES ELECTRICAS
04.09.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
04.09.02 ARTEFACTO FLUORESCENTE 2/36 W und 4.00 4.00 0.00 0.00 4.00 100.00% 0.00 0.00% 0.00 0.00%
04.10 VARIOS
04.10.01 JUNTA SISMICA DE 1" m 5.00 5.00 0.00 0.00 5.00 100.00% 0.00 0.00% 0.00 0.00%
05 PATIO DE ENCUENTRO
05.01 TRABAJOS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO MANUAL m2 190.00 190.00 0.00 0.00 190.00 100.00% 0.00 0.00% 0.00 0.00%
05.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 190.00 190.00 0.00 0.00 190.00 100.00% 0.00 0.00% 0.00 0.00%
05.02 MOVIMIENTO DE TIERRAS
05.02.01 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 180.59 180.59 0.00 0.00 180.59 100.00% 0.00 0.00% 0.00 0.00%
05.02.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 234.77 234.77 0.00 0.00 234.77 100.00% 0.00 0.00% 0.00 0.00%
05.03 SEMBRADO DE AREAS VERDES
05.03.01 PREPARACION DE TIERRA DE CHACRA m2 180.56 180.56 0.00 0.00 180.56 100.00% 0.00 0.00% 0.00 0.00%
05.03.02 SEMBRADO DE GRASS AMERICANO m2 180.56 180.56 0.00 0.00 180.56 100.00% 0.00 0.00% 0.00 0.00%
06 BEBEDERO
06.01 MOVIMIENTO DE TIERRAS
06.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.05 0.05 0.00 0.00 0.05 100.00% 0.00 0.00% 0.00 0.00%
06.01.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 0.07 0.07 0.00 0.00 0.07 100.00% 0.00 0.00% 0.00 0.00%
06.02 OBRAS DE CONCRETO
06.02.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 0.05 0.05 0.00 0.00 0.05 100.00% 0.00 0.00% 0.00 0.00%
06.02.02 CONCRETO F'C=175 KG/CM2 EN BEBEDERO m3 0.27 0.27 0.00 0.00 0.27 100.00% 0.00 0.00% 0.00 0.00%
06.02.03 ENCOFRADO Y DESENCOFRADO EN BEBEDEROS m2 2.97 2.97 0.00 0.00 2.97 100.00% 0.00 0.00% 0.00 0.00%
06.02.04 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 8.85 8.85 0.00 0.00 8.85 100.00% 0.00 0.00% 0.00 0.00%
06.03 ALBAÑILERIA
06.03.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 0.31 0.31 0.00 0.00 0.31 100.00% 0.00 0.00% 0.00 0.00%
06.04 REVOQUES, ENLUCIDOS Y DERRAMES
06.04.01 TARRAJEO PRIMARIO MORTERO 1:5 m2 3.88 3.88 0.00 0.00 3.88 100.00% 0.00 0.00% 0.00 0.00%
06.04.02 ZOCALO DE MAYOLICA BLANCA 20 X 20 CM. m2 3.57 3.57 0.00 0.00 3.57 100.00% 0.00 0.00% 0.00 0.00%
06.05 SUMINISTRO E INSTALACION DE ACCESORIOS
06.05.01 ACCESORIOS EN BEBEDERO und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
07 URINARIO
07.01 MOVIMIENTO DE TIERRAS
07.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.04 0.04 0.00 0.00 0.04 100.00% 0.00 0.00% 0.00 0.00%
07.01.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 0.06 0.06 0.00 0.00 0.06 100.00% 0.00 0.00% 0.00 0.00%
07.02 OBRAS DE CONCRETO
07.02.01 CONCRETO CICLOPEO F'C=140 KG/CM2 EN URINARIO m3 0.09 0.09 0.00 0.00 0.09 100.00% 0.00 0.00% 0.00 0.00%
07.02.02 ENCOFRADO Y DESENCOFRADO EN BEBEDEROS m2 0.86 0.86 0.00 0.00 0.86 100.00% 0.00 0.00% 0.00 0.00%
07.03 REVOQUES, ENLUCIDOS Y DERRAMES
07.03.01 TARRAJEO PRIMARIO MORTERO 1:5 m2 0.92 0.92 0.00 0.00 0.92 100.00% 0.00 0.00% 0.00 0.00%
07.03.02 ZOCALO DE MAYOLICA BLANCA 20 X 20 CM. m2 1.28 1.28 0.00 0.00 1.28 100.00% 0.00 0.00% 0.00 0.00%
RESUMEN DE METRADOS FINALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO

ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL


META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO


METRADOS FINALES
Metrado Principal Ejecutado Saldo vinculante Saldo Final
ITEM DESCRIPCIÓN DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

07.04 SUMINISTRO E INSTALACION DE ACCESORIOS


07.04.01 ACCESORIOS SANITARIOS EN URINARIO und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
08 JUEGOS INFANTILES
08.01 TRABAJOS PRELIMINARES
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 90.00 90.00 0.00 0.00 90.00 100.00% 0.00 0.00% 0.00 0.00%
08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 90.00 90.00 0.00 0.00 90.00 100.00% 0.00 0.00% 0.00 0.00%
08.02 MOVIMIENTO DE TIERRAS
08.02.01 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 85.49 85.49 0.00 0.00 85.49 100.00% 0.00 0.00% 0.00 0.00%
08.02.02 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.60 2.60 0.00 0.00 2.60 100.00% 0.00 0.00% 0.00 0.00%
08.02.03 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 14.49 14.49 0.00 0.00 14.49 100.00% 0.00 0.00% 0.00 0.00%
08.03 OBRAS DE CONCRETO
08.03.01 CONCRETO F'C=140 KG/CM2 EN SARDINELES m3 2.97 2.97 0.00 0.00 2.97 100.00% 0.00 0.00% 0.00 0.00%
08.03.02 ENCOFRADO Y DESENCOFRADO EN SARDINELES m2 26.19 26.19 0.00 0.00 26.19 100.00% 0.00 0.00% 0.00 0.00%
08.03.03 JUNTAS ASFALTICAS m 4.40 4.40 0.00 0.00 4.40 100.00% 0.00 0.00% 0.00 0.00%
08.04 VARIOS
08.04.01 COLOCACION DE ARENA FINA e=0.10 M m2 85.49 85.49 0.00 0.00 85.49 100.00% 0.00 0.00% 0.00 0.00%
08.04.02 COLUMPIO und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
08.04.03 TOBOGAN und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
08.04.04 BALANCIN und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
09 EQUIPAMIENTO Y MOBILIARIO
09.01 EQUIPAMIENTO
09.01.01 TELEVISOR und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
09.01.02 REPRODUCTOR BLU RAY und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
09.02 MOBILIARIO
09.02.01 AULAS
09.02.01.01 MOBILIARIO PARA DOCENTES und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
09.02.01.02 ESTANTE DE MADERA und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
09.02.01.03 MUEBLE MOVIL PARA TV Y EQUIPO DE SONIDO und 2.00 2.00 0.00 0.00 2.00 100.00% 0.00 0.00% 0.00 0.00%
09.02.02 AMBIENTES COMPLEMENTARIOS
09.02.02.01 MOBILIARIO PARA COMEDOR DE NINOS und 5.00 5.00 0.00 0.00 5.00 100.00% 0.00 0.00% 0.00 0.00%
09.02.02.02 MOBILIARIO PARA DIRECCION und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
09.02.02.03 MOBILIARIO PARA TOPICO und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
10 CAPACITACION DE DOCENTES
10.01 CAPACITACIONES glb 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
11 FLETE
11.01 FLETE TERRESTRE
11.01.01 FLETE glb 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
11.02 FLETE RURAL 0 0.00 0.00
11.02.01 ACARREO DE MATERIALES glb 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
FORMATO N° (T-01)
RESUMEN DE METRADOS FINALES EJECUTADOS

REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP


ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN,
DISTRITO DE CHUNGUI - LA MAR – AYACUCHO
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO

Metrado Metrados Ejecutados Saldo vinculante Saldo Final


ITEM DESCRIPCION DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

01 OBRAS PRELIMINARES
01.01 CARTEL DE OBRA und 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
01.02 CAMPAMENTOS, OFICINAS Y ALMACEN PARA LA OBRA m2 200.00 200.00 0.00 0.00 200.00 100.00% 0.00 0.00% 0.00 0.00%
01.03 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA GLB 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
01.04 TRAZO Y REPLANTEO KM 8.50 8.50 0.00 0.00 8.50 100.00% 0.00 0.00% 0.00 0.00%
01.05 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL DURANTE LA EJECUCION DE LA OBRA GLB 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
01.06 TRAZO Y REPLANTEO EN PROCESO CONSTRUCTIVO KM 8.50 8.50 0.00 0.00 8.50 100.00% 0.00 0.00% 0.00 0.00%
02 MOVIMIENTO DE TIERRAS
02.01 CORTE EN MATERIAL SUELTO m3 32403.00 32403.00 0.00 0.00 32403.00 100.00% 0.00 0.00% 0.00 0.00%
02.02 PERFORACION Y DISPARO EN ROCA SUELTA m3 4190.81 4190.81 0.00 0.00 4190.81 100.00% 0.00 0.00% 0.00 0.00%
02.03 EXCAVACION, DESQUINCHE Y PEINADO DE TALUDES EN ROCA SUELTA m3 4190.81 4190.81 0.00 0.00 4190.81 100.00% 0.00 0.00% 0.00 0.00%
02.04 PERFORACION Y DISPARO EN ROCA FIJA m3 1824.35 1824.35 0.00 0.00 1824.35 100.00% 0.00 0.00% 0.00 0.00%
02.05 EXCAVACION, DESQUINCHE Y PEINADO DE TALUDES EN ROCA FIJA m3 1824.35 1824.35 0.00 0.00 1824.35 100.00% 0.00 0.00% 0.00 0.00%
02.06 RELLENO CON MATERIAL PROPIO m3 1914.80 1914.80 0.00 0.00 1914.80 100.00% 0.00 0.00% 0.00 0.00%
02.07 MEJORAMIENTO DE SUELO A NIVEL DE SUB RASANTE m3 10979.79 10979.79 0.00 0.00 10979.79 100.00% 0.00 0.00% 0.00 0.00%
03 TRATAMIENTO SUPERFICIAL BICAPA
03.01 SUB BASE (e=0.20 m) m3 11499.33 11499.33 0.00 0.00 11499.33 100.00% 0.00 0.00% 0.00 0.00%
03.02 BASE GRANULAR (e=0.20 m) m3 10692.85 10692.85 0.00 0.00 10692.85 100.00% 0.00 0.00% 0.00 0.00%
03.03 IMPRIMACION ASFALTICA m2 51461.63 51461.63 0.00 0.00 51461.63 100.00% 0.00 0.00% 0.00 0.00%
FORMATO N° (T-01)
RESUMEN DE METRADOS FINALES EJECUTADOS

REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP


ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN,
DISTRITO DE CHUNGUI - LA MAR – AYACUCHO
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO

Metrado Metrados Ejecutados Saldo vinculante Saldo Final


ITEM DESCRIPCION DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

03.04 TRATAMIENTO SUPERFICIAL BICAPA - PRIMERA CAPA m2 51206.63 51206.63 0.00 0.00 51206.63 100.00% 0.00 0.00% 0.00 0.00%
03.05 TRATAMIENTO SUPERFICIAL BICAPA - SEGUNDA CAPA m2 51206.63 51206.63 0.00 0.00 51206.63 100.00% 0.00 0.00% 0.00 0.00%
04 OBRAS DE ARTE Y DRENAJE
04.01 SUBDRENES
04.01.01 SUBDRENAJE LONGITUDINAL
04.01.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 124.80 99.84 0.00 0.00 99.84 80.00% 0.00 0.00% 24.96 20.00%
04.01.01.02 RELLENO PARA ESTRUCTURAS m3 27.60 22.08 0.00 0.00 22.08 80.00% 0.00 0.00% 5.52 20.00%
04.01.01.03 RELLENO CON MATERIAL FILTRANTE m3 76.20 60.96 0.00 0.00 60.96 80.00% 0.00 0.00% 15.24 20.00%
04.01.01.04 TUBERIA HDPE CORRUGADA 6" m 350.00 280.00 0.00 0.00 280.00 80.00% 0.00 0.00% 70.00 20.00%
04.01.01.05 TUBERIA DE VENTILACION PARA SUBDRENAJE m 14.00 11.20 0.00 0.00 11.20 80.00% 0.00 0.00% 2.80 20.00%
04.01.01.06 GEOTEXTIL NO TEJIDO m2 779.00 623.20 0.00 0.00 623.20 80.00% 0.00 0.00% 155.80 20.00%
04.01.02 SUBDRENAJE DESCARGA
04.01.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 35.70 28.56 0.00 0.00 28.56 80.00% 0.00 0.00% 7.14 20.00%
04.01.02.02 RELLENO PARA ESTRUCTURAS m3 35.70 28.56 0.00 0.00 28.56 80.00% 0.00 0.00% 7.14 20.00%
04.01.02.03 TUBERIA HDPE CORRUGADA 6" m 70.00 56.00 0.00 0.00 56.00 80.00% 0.00 0.00% 14.00 20.00%
04.01.03 CABEZAL
04.01.03.01 CONCRETO F'C=175 KG/CM2 m3 0.56 0.45 0.00 0.00 0.45 80.00% 0.00 0.00% 0.11 20.00%
04.01.03.02 ENCOFRADO Y DESENCOFRADO m2 3.36 2.69 0.00 0.00 2.69 80.00% 0.00 0.00% 0.67 20.00%
04.01.03.03 MANPOSTERIA DE PIEDRA F'C=140KG/CM2 + 30% PM. m3 1.40 1.12 0.00 0.00 1.12 80.00% 0.00 0.00% 0.28 20.00%
FORMATO N° (T-01)
RESUMEN DE METRADOS FINALES EJECUTADOS

REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP


ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN,
DISTRITO DE CHUNGUI - LA MAR – AYACUCHO
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO

Metrado Metrados Ejecutados Saldo vinculante Saldo Final


ITEM DESCRIPCION DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

04.02 CUNETAS
04.02.01 EXCAVACION DE CUNETAS m 10560.00 10560.00 0.00 0.00 10560.00 100.00% 0.00 0.00% 0.00 0.00%
04.02.02 REVESTIMIENTO DE CONCRETO EN CUNETAS m 10560.00 10560.00 0.00 0.00 10560.00 100.00% 0.00 0.00% 0.00 0.00%
04.03 ALCANTARILLAS TIPO I (22 UND)
04.03.01 DEMOLICION DE ALCANTARILLAS EXISTENTES REND=40 M3/DIA m3 157.08 157.08 0.00 0.00 157.08 100.00% 0.00 0.00% 0.00 0.00%
04.03.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 316.54 316.54 0.00 0.00 316.54 100.00% 0.00 0.00% 0.00 0.00%
04.03.03 RELLENO CON MATERIAL PROPIO COMPACTADO C/PISON m3 39.60 39.60 0.00 0.00 39.60 100.00% 0.00 0.00% 0.00 0.00%
04.03.04 RELLENO CON MATERIAL SELECCIONADO m3 26.40 26.40 0.00 0.00 26.40 100.00% 0.00 0.00% 0.00 0.00%
04.03.05 ELIMINACION DE MATERIAL EXCEDENTE m3 340.24 340.24 0.00 0.00 340.24 100.00% 0.00 0.00% 0.00 0.00%
04.03.06 SOLADO 1:10, cemento:arena m2 242.88 242.88 0.00 0.00 242.88 100.00% 0.00 0.00% 0.00 0.00%
04.03.07 MANPOSTERIA DE PIEDRA F'C=140KG/CM2 + 30% PM. m3 5.41 5.41 0.00 0.00 5.41 100.00% 0.00 0.00% 0.00 0.00%
04.03.08 CONCRETO CICLOPEO F'C=175 KG/CM2 + 30 % PM m3 179.17 179.17 0.00 0.00 179.17 100.00% 0.00 0.00% 0.00 0.00%
04.03.09 CONCRETO F'C=210 KG/CM2 m3 26.40 26.40 0.00 0.00 26.40 100.00% 0.00 0.00% 0.00 0.00%
04.03.10 ENCOFRADO Y DESENCOFRADO m2 668.10 668.10 0.00 0.00 668.10 100.00% 0.00 0.00% 0.00 0.00%
04.03.11 ACERO DE REFUERZO FY=4200 KG/CM2 kg 1829.26 1829.26 0.00 0.00 1829.26 100.00% 0.00 0.00% 0.00 0.00%
04.03.12 REVESTIMIENTO DE CEMENTO Y ARENA m2 186.78 186.78 0.00 0.00 186.78 100.00% 0.00 0.00% 0.00 0.00%
04.04 ALCANTARILLAS TIPO II (10 UND)
04.04.01 DEMOLICION DE ALCANTARILLAS EXISTENTES REND=40 M3/DIA m3 128.09 85.39 0.00 0.00 85.39 66.67% 42.70 33.33% 0.00 0.00%
04.04.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 641.25 427.50 0.00 0.00 427.50 66.67% 213.75 33.33% 0.00 0.00%
FORMATO N° (T-01)
RESUMEN DE METRADOS FINALES EJECUTADOS

REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP


ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN,
DISTRITO DE CHUNGUI - LA MAR – AYACUCHO
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO

Metrado Metrados Ejecutados Saldo vinculante Saldo Final


ITEM DESCRIPCION DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

04.04.03 RELLENO CON MATERIAL PROPIO COMPACTADO C/PISON m3 161.46 107.64 0.00 0.00 107.64 66.67% 53.82 33.33% 0.00 0.00%
04.04.04 RELLENO CON MATERIAL SELECCIONADO m3 5.85 3.92 0.00 0.00 3.92 66.67% 1.93 33.33% 0.00 0.00%
04.04.05 ELIMINACION DE MATERIAL EXCEDENTE m3 479.79 319.86 0.00 0.00 319.86 66.67% 159.93 33.33% 0.00 0.00%
04.04.06 SOLADO 1:10, cemento:arena m2 178.80 119.20 0.00 0.00 119.20 66.67% 59.60 33.33% 0.00 0.00%
04.04.07 MANPOSTERIA DE PIEDRA F'C=140KG/CM2 + 30% PM. m3 22.91 15.27 0.00 0.00 15.27 66.67% 7.64 33.33% 0.00 0.00%
04.04.08 CONCRETO F'C=210 KG/CM2 m3 108.60 72.40 0.00 0.00 72.40 66.67% 36.20 33.33% 0.00 0.00%
04.04.09 ENCOFRADO Y DESENCOFRADO m2 955.95 637.30 0.00 0.00 637.30 66.67% 318.65 33.33% 0.00 0.00%
04.04.10 ACERO DE REFUERZO FY=4200 KG/CM2 kg 6105.37 4070.25 0.00 0.00 4070.25 66.67% 2035.12 33.33% 0.00 0.00%
04.04.11 REVESTIMIENTO DE CEMENTO Y ARENA m2 395.85 263.90 0.00 0.00 263.90 66.67% 131.95 33.33% 0.00 0.00%
04.05 ALCANTARILLAS TIPO III (5 UND)
04.05.01 DEMOLICION DE ALCANTARILLAS EXISTENTES REND=40 M3/DIA m3 13.62 13.62 0.00 0.00 13.62 100.00% 0.00 0.00% 0.00 0.00%
04.05.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 255.81 255.81 0.00 0.00 255.81 100.00% 0.00 0.00% 0.00 0.00%
04.05.03 RELLENO CON MATERIAL PROPIO COMPACTADO C/PISON m3 53.82 53.82 0.00 0.00 53.82 100.00% 0.00 0.00% 0.00 0.00%
04.05.04 RELLENO CON MATERIAL SELECCIONADO m3 1.95 1.95 0.00 0.00 1.95 100.00% 0.00 0.00% 0.00 0.00%
04.05.05 ELIMINACION DE MATERIAL EXCEDENTE m3 201.99 201.99 0.00 0.00 201.99 100.00% 0.00 0.00% 0.00 0.00%
04.05.06 SOLADO 1:10, cemento:arena m2 6.86 6.86 0.00 0.00 6.86 100.00% 0.00 0.00% 0.00 0.00%
04.05.07 MANPOSTERIA DE PIEDRA F'C=140KG/CM2 + 30% PM. m3 8.46 8.46 0.00 0.00 8.46 100.00% 0.00 0.00% 0.00 0.00%
04.05.08 CONCRETO F'C=210 KG/CM2 m3 41.54 41.54 0.00 0.00 41.54 100.00% 0.00 0.00% 0.00 0.00%
04.05.09 ENCOFRADO Y DESENCOFRADO m2 370.05 370.05 0.00 0.00 370.05 100.00% 0.00 0.00% 0.00 0.00%
FORMATO N° (T-01)
RESUMEN DE METRADOS FINALES EJECUTADOS

REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP


ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN,
DISTRITO DE CHUNGUI - LA MAR – AYACUCHO
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO

Metrado Metrados Ejecutados Saldo vinculante Saldo Final


ITEM DESCRIPCION DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

04.05.10 ACERO DE REFUERZO FY=4200 KG/CM2 kg 2216.73 2216.73 0.00 0.00 2216.73 100.00% 0.00 0.00% 0.00 0.00%
04.05.11 REVESTIMIENTO DE CEMENTO Y ARENA m2 158.55 158.55 0.00 0.00 158.55 100.00% 0.00 0.00% 0.00 0.00%
04.06 MURO DE CONCRETO CICLOPEO
04.06.01 TRAZO Y REPLANTEO m2 214.20 214.20 0.00 0.00 214.20 100.00% 0.00 0.00% 0.00 0.00%
04.06.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 210.15 210.15 0.00 0.00 210.15 100.00% 0.00 0.00% 0.00 0.00%
04.06.03 REFINE Y COMPACTACION DE TERRENO m2 214.20 214.20 0.00 0.00 214.20 100.00% 0.00 0.00% 0.00 0.00%
04.06.04 RELLENO CON MATERIAL PROPIO COMPACTADO C/PISON m3 55.16 55.16 0.00 0.00 55.16 100.00% 0.00 0.00% 0.00 0.00%
04.06.05 RELLENO CON MATERIAL FILTRANTE m3 65.55 65.55 0.00 0.00 65.55 100.00% 0.00 0.00% 0.00 0.00%
04.06.06 CONCRETO CICLOPEO F'C=175 KG/CM2 + 30 % PM m3 249.05 249.05 0.00 0.00 249.05 100.00% 0.00 0.00% 0.00 0.00%
04.06.07 ENCOFRADO Y DESENCOFRADO m2 656.12 656.12 0.00 0.00 656.12 100.00% 0.00 0.00% 0.00 0.00%
04.06.08 TUBERIA DE PVC SAP 3", SUBDRENAJE m 242.40 242.40 0.00 0.00 242.40 100.00% 0.00 0.00% 0.00 0.00%
04.06.09 JUNTAS DE DILATACION m 58.15 58.15 0.00 0.00 58.15 100.00% 0.00 0.00% 0.00 0.00%
05 TRANSPORTE
05.01 TRANSPORTE DE AFIRMADO PARA D<=1 KM M3K 10692.85 10692.85 0.00 0.00 10692.85 100.00% 0.00 0.00% 0.00 0.00%
05.02 TRANSPORTE DE AFIRMADO PARA D>1 KM M3K 135299.95 135299.95 0.00 0.00 135299.95 100.00% 0.00 0.00% 0.00 0.00%
05.03 TRANSPORTE DE MATERIAL EXCEDENTE PARA D<=1 KM M3K 45368.21 45368.21 0.00 0.00 45368.21 100.00% 0.00 0.00% 0.00 0.00%
05.04 TRANSPORTE DE MATERIAL EXCEDENTE PARA D>1 KM M3K 269754.32 269754.32 0.00 0.00 269754.32 100.00% 0.00 0.00% 0.00 0.00%
06 SEÑALIZACION
06.01 SEÑALES PREVENTIVAS und 64.00 64.00 0.00 0.00 64.00 100.00% 0.00 0.00% 0.00 0.00%
FORMATO N° (T-01)
RESUMEN DE METRADOS FINALES EJECUTADOS

REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP


ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN,
DISTRITO DE CHUNGUI - LA MAR – AYACUCHO
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO

Metrado Metrados Ejecutados Saldo vinculante Saldo Final


ITEM DESCRIPCION DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

06.02 SEÑALES INFORMATIVAS und 9.00 6.04 0.00 0.00 6.04 67.11% 0.00 0.00% 2.96 32.89%
06.03 HITOS KILOMETRICOS HIT 9.00 9.00 0.00 0.00 9.00 100.00% 0.00 0.00% 0.00 0.00%
06.04 PINTADO DE LAS MARCAS EN PAVIMENTO m 21242.06 21242.06 0.00 0.00 21242.06 100.00% 0.00 0.00% 0.00 0.00%
06.05 TACHAS DELINEADORAS BIDIRECCIONALES und 2127.00 2127.00 0.00 0.00 2127.00 100.00% 0.00 0.00% 0.00 0.00%
06.06 GUARDAVIA S (INCL. TERMINAL) m 142.00 142.00 0.00 0.00 142.00 100.00% 0.00 0.00% 0.00 0.00%
06.07 PINTADO DE PARAPETOS DE MUROS Y ALCANTARILLAS m2 245.95 245.95 0.00 0.00 245.95 100.00% 0.00 0.00% 0.00 0.00%
07 REPOSICION DE CERCO Y VIVIENDAS AFECTADAS
07.01 REPOSICION DE CERCO CON MURO SECO DE PIEDRA m3 468.90 468.90 0.00 0.00 468.90 100.00% 0.00 0.00% 0.00 0.00%
07.02 REPOSICION DE VIVIENDAS AFECTADAS GLB 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
08 FLETE
08.01 FLETE TERRESTRE GLB 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
09 MITIGACION IMPACTO AMBIENTAL
09.01 PERFILADO DE BANQUETAS m2 180.00 180.00 0.00 0.00 180.00 100.00% 0.00 0.00% 0.00 0.00%
09.02 RESTAURACION DE CANTERAS m2 3500.00 3500.00 0.00 0.00 3500.00 100.00% 0.00 0.00% 0.00 0.00%
09.03 RESTAURACION DE CAMPAMENTOS Y PATIO DE MAQUINARIAS m2 2700.00 2700.00 0.00 0.00 2700.00 100.00% 0.00 0.00% 0.00 0.00%
09.04 ACONDICIONAMIENTO DE BOTADEROS m2 1296.00 1296.00 0.00 0.00 1296.00 100.00% 0.00 0.00% 0.00 0.00%
09.05 CONTROL Y EDUCACION AMBIENTAL est 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
09.06 CONTROL DE POLUCION EN OBRA m3 6810.86 6810.86 0.00 0.00 6810.86 100.00% 0.00 0.00% 0.00 0.00%
09.07 REFORESTACION Y PLANTACION DE ESPECIES NATIVAS HA 0.77 0.77 0.00 0.00 0.77 100.00% 0.00 0.00% 0.00 0.00%
FORMATO N° (T-01)
RESUMEN DE METRADOS FINALES EJECUTADOS

REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP


ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL
PROYECTO : 2224730 INSTALACION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P DE LA COMUNIDAD DE QARIN,
DISTRITO DE CHUNGUI - LA MAR – AYACUCHO
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO

Metrado Metrados Ejecutados Saldo vinculante Saldo Final


ITEM DESCRIPCION DE PARTIDA UND. Contratado Principal > Metrados Adic. Total % Metrado % Metrado %

10 CAPACITACION
10.01 CURSOS DE CAPACITACION A LA POBLACION event 1.00 1.00 0.00 0.00 1.00 100.00% 0.00 0.00% 0.00 0.00%
VALORIZACIÓN FINAL DE OBRA
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION MODALIDAD EJECUCIÓN : CONTRATA
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD DE CONTRATO : PRECIOS UNITARIOS
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL PLAZO DE EJECUCIÓN : 180 DIAS CALENDARIO
PROYECTO : 2143123 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA - VALOR REFERENCIAL : S/. 892,171.04
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO MONTO DE CONTRATO : S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL FACTOR DE RELACIÓN :1
META : 0029 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA -
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO CONTRATISTA : CONSORCIO TAWA
UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO SUPERVISIÓN : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) CONTRATADO PRINCIPAL EJECUTADO DEDUCTIVO VINCULANTE SALDO FINAL
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %

01 AULAS
01.01 OBRAS PRELIMINARES
01.01.01 ALQUILER DE ALMACEN mes 6.00 423.73 2,542.38 6.00 2542.38 100.00% 6.00 2542.38 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.01.02 CARTEL DE OBRA glb 1.00 593.22 593.22 1.00 593.22 100.00% 1.00 593.22 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DE TERRENO MANUAL m2 223.82 0.74 165.63 223.82 165.63 100.00% 223.82 165.63 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 300.00 1.87 561.00 300.00 561.00 100.00% 300.00 561.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03 MOVIMIENTO DE TIERRAS 0.00
01.03.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 55.71 14.72 820.05 55.71 820.05 100.00% 55.71 820.05 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.02 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 25.85 1.44 37.22 25.85 37.22 100.00% 25.85 37.22 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.03 EXCAVACIONES 0.00
01.03.03.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 35.98 14.44 519.55 35.98 519.55 100.00% 35.98 519.55 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.03.02 EXCAVACION MANUAL DE ZAPATAS m3 30.00 14.72 441.60 30.00 441.60 100.00% 30.00 441.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.03.03 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES DE VEREDAS m3 2.24 14.44 32.35 2.24 32.35 100.00% 2.24 32.35 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.03.04 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS DE DRENAJE m3 5.82 14.72 85.67 5.82 85.67 100.00% 5.82 85.67 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.03.05 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 10.35 9.02 93.36 10.35 93.36 100.00% 10.35 93.36 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.03.06 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 158.60 6.02 954.77 158.60 954.77 100.00% 158.60 954.77 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.03.07 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 200.42 0.74 148.31 200.42 148.31 100.00% 200.42 148.31 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.03.08 AFIRMADO DE e=4" PARA PISOS INTERIORES Y EXTERIORES m2 119.98 24.34 2,920.31 119.98 2920.31 100.00% 119.98 2920.31 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04 CONCRETO SIMPLE 0.00
01.04.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 13.82 559.63 7,734.09 13.82 7734.09 100.00% 13.82 7734.09 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.02 SUBCIMIENTO C:H=1:12+30% PG m3 15.72 525.00 8,253.00 15.72 8253.00 100.00% 15.72 8253.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.03 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 20.00 44.27 885.40 20.00 885.40 100.00% 20.00 885.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.04 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 5.69 559.11 3,181.34 5.69 3181.34 100.00% 5.69 3181.34 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.05 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 59.52 19.61 1,167.19 59.52 1167.19 100.00% 59.52 1167.19 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.06 FALSO PISO e= 4" ( MEZCLA 1:10 CEMENTO : HORMIGON ) m2 146.87 58.90 8,650.64 146.87 8650.64 100.00% 146.87 8650.64 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.07 CONCRETO F'C=140 KG/CM2 EN CANALETAS m3 6.11 671.93 4,105.49 6.11 4105.49 100.00% 6.11 4105.49 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.08 ENCOFRADO Y DESENCOFRADO EN CANALETAS m2 31.36 31.65 992.54 31.36 992.54 100.00% 31.36 992.54 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.09 JUNTAS ASFALTICAS m 3.20 7.13 22.82 3.20 22.82 100.00% 3.20 22.82 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.04.10 TUBERIA PVC SAL D=8" m 6.00 49.98 299.88 6.00 299.88 100.00% 6.00 299.88 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05 CONCRETO ARMADO
01.05.01 VIGA DE CIMENTACION
01.05.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 4.17 691.52 2,883.64 4.17 2883.64 100.00% 4.17 2883.64 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 41.65 25.25 1,051.66 41.65 1051.66 100.00% 41.65 1051.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 481.42 3.71 1,786.07 481.42 1786.07 100.00% 481.42 1786.07 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.02 ZAPATAS
01.05.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 12.00 776.93 9,323.16 12.00 9323.16 100.00% 12.00 9323.16 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 236.87 3.71 878.79 236.87 878.79 100.00% 236.87 878.79 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.03 COLUMNAS
01.05.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 9.45 812.05 7,673.87 9.45 7673.87 100.00% 9.45 7673.87 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 85.11 30.13 2,564.36 85.11 2564.36 100.00% 85.11 2564.36 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,992.18 3.71 7,390.99 1992.18 7390.99 100.00% 1992.18 7390.99 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.04 VIGAS
01.05.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 8.56 806.43 6,903.04 8.56 6903.04 100.00% 8.56 6903.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 97.51 36.32 3,541.56 97.51 3541.56 100.00% 97.51 3541.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,114.78 3.71 4,135.83 1114.78 4135.83 100.00% 1114.78 4135.83 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.05 COLUMNETAS
01.05.05.01 CONCRETO fc'= 175 kg/cm2 EN COLUMNETAS m3 3.36 724.97 2,435.90 3.36 2435.90 100.00% 3.36 2435.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNETAS m2 100.38 28.18 2,828.71 100.38 2828.71 100.00% 100.38 2828.71 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 356.52 3.71 1,322.69 356.52 1322.69 100.00% 356.52 1322.69 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.06 VIGUETAS
01.05.06.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.41 724.97 297.24 0.41 297.24 100.00% 0.41 297.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 8.92 28.18 251.37 8.92 251.37 100.00% 8.92 251.37 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.05.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 136.42 3.71 506.12 136.42 506.12 100.00% 136.42 506.12 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
VALORIZACIÓN FINAL DE OBRA
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION MODALIDAD EJECUCIÓN : CONTRATA
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD DE CONTRATO : PRECIOS UNITARIOS
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL PLAZO DE EJECUCIÓN : 180 DIAS CALENDARIO
PROYECTO : 2143123 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA - VALOR REFERENCIAL : S/. 892,171.04
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO MONTO DE CONTRATO : S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL FACTOR DE RELACIÓN :1
META : 0029 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA -
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO CONTRATISTA : CONSORCIO TAWA
UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO SUPERVISIÓN : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) CONTRATADO PRINCIPAL EJECUTADO DEDUCTIVO VINCULANTE SALDO FINAL
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01.06 ESTRUCTURA METALICA
01.06.01 TIJERAL METALICO TIPO I L=9.93 M und 6.00 2,330.51 13,983.06 6.00 13983.06 100.00% 6.00 13983.06 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.02 TIJERAL METALICO TIPO IV L=8.72 M und 3.00 2,076.27 6,228.81 3.00 6228.81 100.00% 3.00 6228.81 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.03 CORREAS METALICAS CW 64X38X0.90 m 226.12 24.92 5,634.91 226.12 5634.91 100.00% 226.12 5634.91 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.04 CORREAS METALICAS UP 90X32X0.90 MM m 46.94 23.13 1,085.72 46.94 1085.72 100.00% 46.94 1085.72 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.05 ARRIOSTRE METALICO PT 100X0.9 m 63.30 57.83 3,660.64 63.30 3660.64 100.00% 63.30 3660.64 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.06.06 CORREAS METALICAS DE CIERRE UP 65X32X0.90 MM m 57.18 17.80 1,017.80 57.18 1017.80 100.00% 57.18 1017.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07 ALBAÑILERIA
01.07.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 48.22 57.40 2,767.83 48.22 2767.83 100.00% 48.22 2767.83 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07.02 MURO DE LADRILLO KK DE ARCILLA DE CABEZA MEZCLA 1:4 m2 77.77 96.30 7,489.25 77.77 7489.25 100.00% 77.77 7489.25 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.07.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 32.90 3.71 122.06 32.90 122.06 100.00% 32.90 122.06 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08 REVOQUES, ENLUCIDOS Y DERRAMES
01.08.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 200.58 16.69 3,347.68 200.58 3347.68 100.00% 200.58 3347.68 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.02 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 123.32 23.06 2,843.76 123.32 2843.76 100.00% 123.32 2843.76 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.03 VESTIDURAS DE DERRAMES CON BORDES BOLEADOS M : 1: 5 m 128.36 7.51 963.98 128.36 963.98 100.00% 128.36 963.98 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.04 BRUÑAS 0.00
01.08.04.01 BRUÑA e= 1 cm. EXTERIOR m 93.34 2.53 236.15 93.34 236.15 100.00% 93.34 236.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.04.02 BRUÑA e= 1 cm. INTERIOR m 171.85 2.53 434.78 171.85 434.78 100.00% 171.85 434.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.08.04.03 BRUÑA e= 1 cm. EN PISO INTERIOR Y EXTERIOR m 72.84 2.53 184.29 72.84 184.29 100.00% 72.84 184.29 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.09 CERRAMIENTO CON PANEL FIBROCEMENTO
01.09.01 CIELORRASO CON PANEL FIBROCEMENTO 4 mm. m2 179.89 142.37 25,610.94 179.89 25610.94 100.00% 179.89 25610.94 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10 PISOS Y PAVIMENTOS
01.10.01 PISO DE MADERA MACHIHEMBRADA m2 120.95 76.46 9,247.84 120.95 9247.84 100.00% 120.95 9247.84 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.02 PISO DE CONCRETO e=2", PULIDO SIN COLOREAR m2 9.00 38.12 343.08 9.00 343.08 100.00% 9.00 343.08 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.03 PISO CERAMICO DE COLOR CLARO 30X30CM m2 21.02 45.69 960.40 21.02 960.40 100.00% 21.02 960.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.04 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 31.56 107.22 3,383.86 31.56 3383.86 100.00% 31.56 3383.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.10.05 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 5.35 7.80 41.73 5.35 41.73 100.00% 5.35 41.73 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.11 ZOCALOS Y CONTRAZOCALOS
01.11.01 ZOCALO DE MAYOLICA BLANCA 30 X 30 CM. m2 40.70 46.22 1,881.15 40.70 1881.15 100.00% 40.70 1881.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.11.02 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.20 m. EXTERIOR m 57.30 5.47 313.43 57.30 313.43 100.00% 57.30 313.43 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.11.03 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.10 m. INTERIOR m 14.54 3.74 54.38 14.54 54.38 100.00% 14.54 54.38 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.11.04 CONTRAZOCALO DE CEDRO DE 3" RODON 1" m 54.72 16.69 913.28 54.72 913.28 100.00% 54.72 913.28 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.12 CUBIERTA Y TECHO
01.12.01 COBERTURA CON LAMINA TERMOACUSTICA m2 293.23 34.96 10,251.32 293.23 10251.32 100.00% 293.23 10251.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.12.02 CUMBRERA DENTADA m 22.54 27.64 623.01 22.54 623.01 100.00% 22.54 623.01 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.13 CARPINTERIA DE MADERA
01.13.01 PUERTA DE MADERA APANELADA m2 15.90 160.54 2,552.59 15.90 2552.59 100.00% 15.90 2552.59 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.13.02 VENTANA DE MADERA m2 36.42 91.01 3,314.58 36.42 3314.58 100.00% 36.42 3314.58 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.13.03 TICERO DE MADERA CEDRO ( L= 3.00 m. ) BARNIZADO und 2.00 157.90 315.80 2.00 315.80 100.00% 2.00 315.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14 CERRAJERIA
01.14.01 BISAGRA ALUMINIZADA DE 4" x 4" PESADA PARA PUERTA pza 24.00 6.45 154.80 24.00 154.80 100.00% 24.00 154.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.02 CERRADURA PARA PUERTA EXTERIOR TIPO PARCHE 2 GOLPES pza 7.00 59.54 416.78 7.00 416.78 100.00% 7.00 416.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.03 MANIJA DE 4" PARA PUERTA pza 7.00 5.27 36.89 7.00 36.89 100.00% 7.00 36.89 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.04 CERROJOS PARA VENTANAS DE BRONCE pza 70.00 2.98 208.60 70.00 208.60 100.00% 70.00 208.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.05 MANIJA DE BRONCE PARA PORTAÑUELAS DE VENTANAS pza 70.00 3.57 249.90 70.00 249.90 100.00% 70.00 249.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.06 BISAGRA ALUMINIZADA DE 2 1/2" x 2 1/2" PARA VENTANA pza 70.00 5.67 396.90 70.00 396.90 100.00% 70.00 396.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.14.07 TOPE METALICO DE FIERRO PARA VENTANA pza 70.00 3.84 268.80 70.00 268.80 100.00% 70.00 268.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.15 VIDRIOS, CRISTALES Y SIMILARES
01.15.01 VIDRIOS SEMIDOBLES p2 391.83 3.65 1,430.18 391.83 1430.18 100.00% 391.83 1430.18 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.16 PINTURA
01.16.01 PINT. LATEX 2 MANOS EN MUROS EXTERIORES m2 123.32 4.65 573.44 123.32 573.44 100.00% 123.32 573.44 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.16.02 PINT. LATEX 2 MANOS EN MUROS INTERIORES m2 187.14 4.65 870.20 187.14 870.20 100.00% 187.14 870.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.16.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 85.11 6.18 525.98 85.11 525.98 100.00% 85.11 525.98 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.16.04 PINTURA LATEX 2 MANOS EN COLUMNETAS m2 44.09 6.18 272.48 44.09 272.48 100.00% 44.09 272.48 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.16.05 PINTURA LATEX 2 MANOS EN VIGAS m2 97.51 6.37 621.14 97.51 621.14 100.00% 97.51 621.14 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
VALORIZACIÓN FINAL DE OBRA
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION MODALIDAD EJECUCIÓN : CONTRATA
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD DE CONTRATO : PRECIOS UNITARIOS
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL PLAZO DE EJECUCIÓN : 180 DIAS CALENDARIO
PROYECTO : 2143123 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA - VALOR REFERENCIAL : S/. 892,171.04
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO MONTO DE CONTRATO : S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL FACTOR DE RELACIÓN :1
META : 0029 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA -
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO CONTRATISTA : CONSORCIO TAWA
UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO SUPERVISIÓN : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) CONTRATADO PRINCIPAL EJECUTADO DEDUCTIVO VINCULANTE SALDO FINAL
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
01.16.06 PINTURA BARNIZ EN PUERTAS m2 31.80 6.69 212.74 31.80 212.74 100.00% 31.80 212.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.16.07 PINTURA BARNIZ EN VENTANA DE MADERA m2 36.42 6.69 243.65 36.42 243.65 100.00% 36.42 243.65 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.17 VARIOS
01.17.01 JUNTA SISMICA DE 1" m 9.87 4.35 42.93 9.87 42.93 100.00% 9.87 42.93 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.17.02 PIZARRA CEMENTO 3.00 x 1.20 m. SIN TICERO und 2.00 118.88 237.76 2.00 237.76 100.00% 2.00 237.76 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.17.03 JUNTA DE DILATACION DE 1" EN VEREDA m 35.21 7.18 252.81 35.21 252.81 100.00% 35.21 252.81 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18 INSTALACIONES SANITARIAS
01.18.01 DESAGUE Y VENTILACION
01.18.01.01 SALIDA DE DESAGUE PVC SAL D=2" pto 7.00 40.26 281.82 7.00 281.82 100.00% 7.00 281.82 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.01.02 SALIDA DE DESAGUE PVC SAL D=4" pto 4.00 51.85 207.40 4.00 207.40 100.00% 4.00 207.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.01.03 SUMIDEROS DE 3" pza 1.00 36.79 36.79 1.00 36.79 100.00% 1.00 36.79 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.01.04 REGISTRO DE BRONCE 2" pza 1.00 20.32 20.32 1.00 20.32 100.00% 1.00 20.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.01.05 REGISTRO DE BRONCE 4" pza 2.00 30.22 60.44 2.00 60.44 100.00% 2.00 60.44 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.02 REDES DE DISTRIBUCION
01.18.02.01 TUBERIA PVC -SAL 2" m 10.11 9.19 92.91 10.11 92.91 100.00% 10.11 92.91 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.02.02 TUBERIA PVC -SAL 4" m 39.81 12.76 507.98 39.81 507.98 100.00% 39.81 507.98 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.03 APARATOS Y ACCESORIOS SANITARIOS
01.18.03.01 INODORO TANQUE BAJO TIPO "BABY" und 4.00 289.42 1,157.68 4.00 1157.68 100.00% 4.00 1157.68 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.03.02 PAPELERA DE LOZA DE COLOR DE 15 X 15 cm pza 4.00 8.47 33.88 4.00 33.88 100.00% 4.00 33.88 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.03.03 CAJA DE REGISTRO 12"X24" C/TAPA DE CONCRETO pza 1.00 47.49 47.49 1.00 47.49 100.00% 1.00 47.49 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.04 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
01.18.04.01 SALIDA DE AGUA FRIA PVC pto 10.00 25.65 256.50 10.00 256.50 100.00% 10.00 256.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.04.02 TUBERIA PVC CLASE 10 - 3/4" m 30.72 5.06 155.44 30.72 155.44 100.00% 30.72 155.44 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.04.03 TUBERIA PVC CLASE 10 - 1/2" m 4.03 4.63 18.66 4.03 18.66 100.00% 4.03 18.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.04.04 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza 1.00 35.90 35.90 1.00 35.90 100.00% 1.00 35.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.04.05 VALVULAS DE COMPUERTA DE BRONCE DE 3/4" pza 2.00 48.60 97.20 2.00 97.20 100.00% 2.00 97.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.05 SISTEMA DE DRENAJE PLUVIAL
01.18.05.01 TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS m 30.33 16.69 506.21 30.33 506.21 100.00% 30.33 506.21 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.05.02 CANALETA DE FIERRO GALVANIZADO m 64.94 30.63 1,989.11 64.94 1989.11 100.00% 64.94 1989.11 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.05.03 ABRAZADERA DE FIJACION DE TUBO pza 59.00 7.06 416.54 59.00 416.54 100.00% 59.00 416.54 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.05.04 COLECTOR DE ZINC GALVANIZADO und 6.00 7.04 42.24 6.00 42.24 100.00% 6.00 42.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.18.05.05 ABRAZADERA DE FIJACION DE TUBERIA DE 3" pza 18.00 15.92 286.56 18.00 286.56 100.00% 18.00 286.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.19 INSTALACIONES ELECTRICAS
01.19.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 17.00 48.42 823.14 17.00 823.14 100.00% 17.00 823.14 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.19.02 SALIDA INTERRUPTOR SIMPLE pto 2.00 8.30 16.60 2.00 16.60 100.00% 2.00 16.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.19.03 SALIDA INTERRUPTOR DOBLE pto 5.00 10.85 54.25 5.00 54.25 100.00% 5.00 54.25 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.19.04 SALIDA TOMACORRIENTE DOBLE pto 6.00 55.14 330.84 6.00 330.84 100.00% 6.00 330.84 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.19.05 SALIDA PARA ANTENA DE TELEVISION CON PVC pto 2.00 64.08 128.16 2.00 128.16 100.00% 2.00 128.16 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.20 TABLEROS
01.20.01 TABLERO DE DISTRIBUCION TD-3 und 1.00 416.20 416.20 1.00 416.20 100.00% 1.00 416.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.21 ARTEFACTOS
01.21.01 ARTEFACTO FLUORESCENTE 2/18 W und 4.00 42.01 168.04 4.00 168.04 100.00% 4.00 168.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.21.02 ARTEFACTO FLUORESCENTE 1/36W und 2.00 41.16 82.32 2.00 82.32 100.00% 2.00 82.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.21.03 ARTEFACTO FLUORESCENTE 2/36 W und 2.00 78.45 156.90 2.00 156.90 100.00% 2.00 156.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.21.04 ARTEFACTO FLUORESCENTE 4/36W und 8.00 35.23 281.84 8.00 281.84 100.00% 8.00 281.84 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
01.22 POZO PUESTA A TIERRA
01.22.01 POZO DE PUESTA A TIERRA und 1.00 402.90 402.90 1.00 402.90 100.00% 1.00 402.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02 AREA COMPLEMENTARIA
02.01 TRABAJOS PRELIMINARES
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 248.72 0.74 184.05 248.72 184.05 100.00% 248.72 184.05 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 290.85 1.87 543.89 290.85 543.89 100.00% 290.85 543.89 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 369.18 14.72 5,434.33 369.18 5434.33 100.00% 369.18 5434.33 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.02 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 33.95 1.44 48.89 33.95 48.89 100.00% 33.95 48.89 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.03 EXCAVACIONES
VALORIZACIÓN FINAL DE OBRA
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION MODALIDAD EJECUCIÓN : CONTRATA
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD DE CONTRATO : PRECIOS UNITARIOS
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL PLAZO DE EJECUCIÓN : 180 DIAS CALENDARIO
PROYECTO : 2143123 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA - VALOR REFERENCIAL : S/. 892,171.04
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO MONTO DE CONTRATO : S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL FACTOR DE RELACIÓN :1
META : 0029 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA -
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO CONTRATISTA : CONSORCIO TAWA
UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO SUPERVISIÓN : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) CONTRATADO PRINCIPAL EJECUTADO DEDUCTIVO VINCULANTE SALDO FINAL
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
02.02.03.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 46.92 14.44 677.52 46.92 677.52 100.00% 46.92 677.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.03.02 EXCAVACION MANUAL DE ZAPATAS m3 31.50 14.72 463.68 31.50 463.68 100.00% 31.50 463.68 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.03.03 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES DE VEREDAS m3 2.25 14.44 32.49 2.25 32.49 100.00% 2.25 32.49 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.03.04 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS DE DRENAJE m3 5.42 14.72 79.78 5.42 79.78 100.00% 5.42 79.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.03.05 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 12.23 9.02 110.31 12.23 110.31 100.00% 12.23 110.31 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.03.06 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 580.36 6.02 3,493.77 580.36 3493.77 100.00% 580.36 3493.77 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.03.07 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 247.78 0.74 183.36 247.78 183.36 100.00% 247.78 183.36 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.03.08 AFIRMADO DE e=4" PARA PISOS INTERIORES Y EXTERIORES m2 226.78 24.34 5,519.83 226.78 5519.83 100.00% 226.78 5519.83 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03 CONCRETO SIMPLE
02.03.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 18.24 559.63 10,207.65 18.24 10207.65 100.00% 18.24 10207.65 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03.02 SUBCIMIENTO C:H=1:12+30% PG m3 18.20 525.00 9,555.00 18.20 9555.00 100.00% 18.20 9555.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03.03 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 21.00 44.27 929.67 21.00 929.67 100.00% 21.00 929.67 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03.04 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 10.49 559.11 5,865.06 10.49 5865.06 100.00% 10.49 5865.06 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03.05 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 113.05 19.61 2,216.91 113.05 2216.91 100.00% 113.05 2216.91 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03.06 FALSO PISO e= 4" ( MEZCLA 1:10 CEMENTO : HORMIGON ) m2 178.05 58.90 10,487.15 178.05 10487.15 100.00% 178.05 10487.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03.07 CONCRETO F'C=140 KG/CM2 EN CANALETAS m3 6.60 671.93 4,434.74 6.60 4434.74 100.00% 6.60 4434.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03.08 ENCOFRADO Y DESENCOFRADO EN CANALETAS m2 34.02 31.65 1,076.73 34.02 1076.73 100.00% 34.02 1076.73 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03.09 JUNTAS ASFALTICAS m 4.00 7.13 28.52 4.00 28.52 100.00% 4.00 28.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.03.10 TUBERIA PVC SAL D=8" m 6.00 49.98 299.88 6.00 299.88 100.00% 6.00 299.88 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04 CONCRETO ARMADO
02.04.01 VIGA DE CIMENTACION
02.04.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 6.85 691.52 4,736.91 6.85 4736.91 100.00% 6.85 4736.91 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 68.49 25.25 1,729.37 68.49 1729.37 100.00% 68.49 1729.37 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 545.47 3.71 2,023.69 545.47 2023.69 100.00% 545.47 2023.69 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.02 ZAPATAS
02.04.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 12.60 776.93 9,789.32 12.60 9789.32 100.00% 12.60 9789.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 250.55 3.71 929.54 250.55 929.54 100.00% 250.55 929.54 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.03 COLUMNAS
02.04.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 11.05 812.05 8,973.15 11.05 8973.15 100.00% 11.05 8973.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 79.62 30.13 2,398.95 79.62 2398.95 100.00% 79.62 2398.95 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 2,805.55 3.71 10,408.59 2805.55 10408.59 100.00% 2805.55 10408.59 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.04 VIGAS
02.04.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 11.82 806.43 9,532.00 11.82 9532.00 100.00% 11.82 9532.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 134.17 36.32 4,873.05 134.17 4873.05 100.00% 134.17 4873.05 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,580.11 3.71 5,862.21 1580.11 5862.21 100.00% 1580.11 5862.21 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.05 COLUMNETAS
02.04.05.01 CONCRETO fc'= 175 kg/cm2 EN COLUMNETAS m3 4.67 724.97 3,385.61 4.67 3385.61 100.00% 4.67 3385.61 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNETAS m2 75.55 28.18 2,129.00 75.55 2129.00 100.00% 75.55 2129.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 543.43 3.71 2,016.13 543.43 2016.13 100.00% 543.43 2016.13 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.06 VIGUETAS
02.04.06.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.36 724.97 260.99 0.36 260.99 100.00% 0.36 260.99 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 5.51 28.18 155.27 5.51 155.27 100.00% 5.51 155.27 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.04.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 101.78 3.71 377.60 101.78 377.60 100.00% 101.78 377.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.05 ESTRUCTURA METALICA
02.05.01 TIJERAL METALICO TIPO I L=9.93 M und 6.00 2,330.51 13,983.06 6.00 13983.06 100.00% 6.00 13983.06 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.05.02 TIJERAL METALICO TIPO III L=7.50 M und 4.00 1,779.66 7,118.64 4.00 7118.64 100.00% 4.00 7118.64 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.05.03 CORREAS METALICAS CW 64X38X0.90 m 302.69 24.92 7,543.03 302.69 7543.03 100.00% 302.69 7543.03 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.05.04 CORREAS METALICAS UP 90X32X0.90 MM m 60.52 23.13 1,399.83 60.52 1399.83 100.00% 60.52 1399.83 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.05.05 ARRIOSTRE METALICO PT 100X0.9 m 71.86 57.83 4,155.66 71.86 4155.66 100.00% 71.86 4155.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.05.06 CORREAS METALICAS DE CIERRE UP 65X32X0.90 MM m 58.22 17.80 1,036.32 58.22 1036.32 100.00% 58.22 1036.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.06 ALBAÑILERIA
02.06.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 102.29 57.40 5,871.45 102.29 5871.45 100.00% 102.29 5871.45 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.06.02 MURO DE LADRILLO KK DE ARCILLA DE CABEZA MEZCLA 1:4 m2 120.61 96.30 11,614.74 120.61 11614.74 100.00% 120.61 11614.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 45.85 3.71 170.10 45.85 170.10 100.00% 45.85 170.10 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.07 REVOQUES, ENLUCIDOS Y DERRAMES
VALORIZACIÓN FINAL DE OBRA
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION MODALIDAD EJECUCIÓN : CONTRATA
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD DE CONTRATO : PRECIOS UNITARIOS
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL PLAZO DE EJECUCIÓN : 180 DIAS CALENDARIO
PROYECTO : 2143123 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA - VALOR REFERENCIAL : S/. 892,171.04
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO MONTO DE CONTRATO : S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL FACTOR DE RELACIÓN :1
META : 0029 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA -
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO CONTRATISTA : CONSORCIO TAWA
UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO SUPERVISIÓN : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) CONTRATADO PRINCIPAL EJECUTADO DEDUCTIVO VINCULANTE SALDO FINAL
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
02.07.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 285.76 16.69 4,769.33 285.76 4769.33 100.00% 285.76 4769.33 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.07.02 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 160.04 23.06 3,690.52 160.04 3690.52 100.00% 160.04 3690.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.07.03 VESTIDURAS DE DERRAMES CON BORDES BOLEADOS M : 1: 5 m 57.30 7.51 430.32 57.30 430.32 100.00% 57.30 430.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.07.04 BRUÑAS
02.07.04.01 BRUÑA e= 1 cm. EXTERIOR m 104.66 2.53 264.79 104.66 264.79 100.00% 104.66 264.79 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.07.04.02 BRUÑA e= 1 cm. INTERIOR m 162.31 2.53 410.64 162.31 410.64 100.00% 162.31 410.64 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.07.04.03 BRUÑA e= 1 cm. EN PISO INTERIOR Y EXTERIOR m 122.24 2.53 309.27 122.24 309.27 100.00% 122.24 309.27 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.08 CERRAMIENTO CON PANEL FIBROCEMENTO
02.08.01 CIELORRASO CON PANEL FIBROCEMENTO 4 mm. m2 260.42 142.37 37,076.00 260.42 37076.00 100.00% 260.42 37076.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.09 PISOS Y PAVIMENTOS
02.09.01 PISO DE MADERA MACHIHEMBRADA m2 82.64 76.46 6,318.65 82.64 6318.65 100.00% 82.64 6318.65 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.09.02 PISO DE CONCRETO e=2", PULIDO SIN COLOREAR m2 21.00 38.12 800.52 21.00 800.52 100.00% 21.00 800.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.09.03 PISO CERAMICO DE COLOR CLARO 30X30CM m2 73.42 45.69 3,354.56 73.42 3354.56 100.00% 73.42 3354.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.09.04 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 49.25 107.22 5,280.59 49.25 5280.59 100.00% 49.25 5280.59 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.09.05 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 7.76 7.80 60.53 7.76 60.53 100.00% 7.76 60.53 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.10 ZOCALOS Y CONTRAZOCALOS
02.10.01 ZOCALO DE MAYOLICA BLANCA 30 X 30 CM. m2 25.04 46.22 1,157.35 25.04 1157.35 100.00% 25.04 1157.35 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.10.02 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.20 m. EXTERIOR m 66.03 5.47 361.18 66.03 361.18 100.00% 66.03 361.18 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.10.03 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.10 m. INTERIOR m 40.77 3.74 152.48 40.77 152.48 100.00% 40.77 152.48 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.10.04 CONTRAZOCALO DE CEDRO DE 3" RODON 1" m 47.01 16.69 784.60 47.01 784.60 100.00% 47.01 784.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.10.05 CONTRAZOCALO DE CERAMICO H=20 CM m 13.85 12.89 178.53 13.85 178.53 100.00% 13.85 178.53 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.11 CUBIERTA Y TECHO
02.11.01 COBERTURA CON LAMINA TERMOACUSTICA m2 291.80 34.96 10,201.33 291.80 10201.33 100.00% 291.80 10201.33 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.11.02 CUMBRERA DENTADA m 30.25 27.64 836.11 30.25 836.11 100.00% 30.25 836.11 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.12 CARPINTERIA DE MADERA
02.12.01 PUERTA DE MADERA APANELADA m2 21.74 160.54 3,490.14 21.74 3490.14 100.00% 21.74 3490.14 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.12.02 VENTANA DE MADERA m2 31.52 91.01 2,868.64 31.52 2868.64 100.00% 31.52 2868.64 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.12.03 TICERO DE MADERA CEDRO ( L= 3.00 m. ) BARNIZADO und 1.00 157.90 157.90 1.00 157.90 100.00% 1.00 157.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.13 CERRAJERIA
02.13.01 BISAGRA ALUMINIZADA DE 4" x 4" PESADA PARA PUERTA pza 30.00 6.45 193.50 30.00 193.50 100.00% 30.00 193.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.13.02 CERRADURA PARA PUERTA EXTERIOR TIPO PARCHE 2 GOLPES pza 10.00 59.54 595.40 10.00 595.40 100.00% 10.00 595.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.13.03 MANIJA DE 4" PARA PUERTA pza 10.00 5.27 52.70 10.00 52.70 100.00% 10.00 52.70 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.13.04 CERROJOS PARA VENTANAS DE BRONCE pza 62.00 2.98 184.76 62.00 184.76 100.00% 62.00 184.76 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.13.05 MANIJA DE BRONCE PARA PORTAÑUELAS DE VENTANAS pza 62.00 3.57 221.34 62.00 221.34 100.00% 62.00 221.34 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.13.06 BISAGRA ALUMINIZADA DE 2 1/2" x 2 1/2" PARA VENTANA pza 62.00 5.67 351.54 62.00 351.54 100.00% 62.00 351.54 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.13.07 TOPE METALICO DE FIERRO PARA VENTANA pza 62.00 3.84 238.08 62.00 238.08 100.00% 62.00 238.08 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.14 VIDRIOS, CRISTALES Y SIMILARES
02.14.01 VIDRIOS SEMIDOBLES p2 339.17 3.65 1,237.97 339.17 1237.97 100.00% 339.17 1237.97 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.15 PINTURA
02.15.01 PINT. LATEX 2 MANOS EN MUROS EXTERIORES m2 160.04 4.65 744.19 160.04 744.19 100.00% 160.04 744.19 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.15.02 PINT. LATEX 2 MANOS EN MUROS INTERIORES m2 285.76 4.65 1,328.78 285.76 1328.78 100.00% 285.76 1328.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.15.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 134.17 6.18 829.17 134.17 829.17 100.00% 134.17 829.17 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.15.04 PINTURA LATEX 2 MANOS EN COLUMNETAS m2 75.55 6.18 466.90 75.55 466.90 100.00% 75.55 466.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.15.05 PINTURA LATEX 2 MANOS EN VIGAS m2 100.38 6.37 639.42 100.38 639.42 100.00% 100.38 639.42 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.15.06 PINTURA BARNIZ EN PUERTAS m2 43.47 6.69 290.81 43.47 290.81 100.00% 43.47 290.81 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.15.07 PINTURA BARNIZ EN VENTANA DE MADERA m2 63.04 6.69 421.74 63.04 421.74 100.00% 63.04 421.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.16 VARIOS
02.16.01 JUNTA SISMICA DE 1" m 16.48 4.35 71.69 16.48 71.69 100.00% 16.48 71.69 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.16.02 PIZARRA CEMENTO 3.00 x 1.20 m. SIN TICERO und 1.00 118.88 118.88 1.00 118.88 100.00% 1.00 118.88 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.16.03 JUNTA DE DILATACION DE 1" EN VEREDA m 23.29 7.18 167.22 23.29 167.22 100.00% 23.29 167.22 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17 INSTALACIONES SANITARIAS
02.17.01 DESAGUE Y VENTILACION
02.17.01.01 SALIDA DE DESAGUE PVC SAL D=2" pto 4.00 40.26 161.04 4.00 161.04 100.00% 4.00 161.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.01.02 SALIDA DE DESAGUE PVC SAL D=4" pto 1.00 51.85 51.85 1.00 51.85 100.00% 1.00 51.85 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.01.03 SUMIDEROS DE 2" pza 1.00 31.84 31.84 1.00 31.84 100.00% 1.00 31.84 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
VALORIZACIÓN FINAL DE OBRA
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION MODALIDAD EJECUCIÓN : CONTRATA
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD DE CONTRATO : PRECIOS UNITARIOS
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL PLAZO DE EJECUCIÓN : 180 DIAS CALENDARIO
PROYECTO : 2143123 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA - VALOR REFERENCIAL : S/. 892,171.04
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO MONTO DE CONTRATO : S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL FACTOR DE RELACIÓN :1
META : 0029 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA -
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO CONTRATISTA : CONSORCIO TAWA
UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO SUPERVISIÓN : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) CONTRATADO PRINCIPAL EJECUTADO DEDUCTIVO VINCULANTE SALDO FINAL
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
02.17.01.04 SUMIDEROS DE 3" pza 1.00 36.79 36.79 1.00 36.79 100.00% 1.00 36.79 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.01.05 REGISTRO DE BRONCE 2" pza 1.00 20.32 20.32 1.00 20.32 100.00% 1.00 20.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.01.06 REGISTRO DE BRONCE 4" pza 1.00 30.22 30.22 1.00 30.22 100.00% 1.00 30.22 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.02 REDES DE DISTRIBUCION
02.17.02.01 TUBERIA PVC -SAL 2" m 10.11 9.19 92.91 10.11 92.91 100.00% 10.11 92.91 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.02.02 TUBERIA PVC -SAL 4" m 6.12 12.76 78.09 6.12 78.09 100.00% 6.12 78.09 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.03 APARATOS Y ACCESORIOS SANITARIOS
02.17.03.01 INODORO TANQUE BAJO BLANCO pza 1.00 156.78 156.78 1.00 156.78 100.00% 1.00 156.78 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.03.02 PAPELERA DE LOZA DE COLOR DE 15 X 15 cm pza 1.00 8.47 8.47 1.00 8.47 100.00% 1.00 8.47 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.03.03 LAVATORIO DE PARED BLANCO 1 LLAVE pza 1.00 84.75 84.75 1.00 84.75 100.00% 1.00 84.75 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.03.04 LAVADERO DE COCINA DE ACERO INOXIDABLE pza 2.00 127.12 254.24 2.00 254.24 100.00% 2.00 254.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.03.05 CAJA DE REGISTRO 12"X24" C/TAPA DE CONCRETO pza 3.00 47.49 142.47 3.00 142.47 100.00% 3.00 142.47 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.04 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
02.17.04.01 SALIDA DE AGUA FRIA PVC pto 4.00 25.65 102.60 4.00 102.60 100.00% 4.00 102.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.04.02 TUBERIA PVC CLASE 10 - 3/4" m 26.00 5.06 131.56 26.00 131.56 100.00% 26.00 131.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.04.03 TUBERIA PVC CLASE 10 - 1/2" m 42.00 4.63 194.46 42.00 194.46 100.00% 42.00 194.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.04.04 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza 1.00 35.90 35.90 1.00 35.90 100.00% 1.00 35.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.04.05 VALVULAS DE COMPUERTA DE BRONCE DE 3/4" pza 1.00 48.60 48.60 1.00 48.60 100.00% 1.00 48.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.05 SISTEMA DE DRENAJE PLUVIAL
02.17.05.01 TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS m 30.33 16.69 506.21 30.33 506.21 100.00% 30.33 506.21 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.05.02 CANALETA DE FIERRO GALVANIZADO m 73.62 30.63 2,254.98 73.62 2254.98 100.00% 73.62 2254.98 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.05.03 ABRAZADERA DE FIJACION DE TUBO pza 70.00 7.06 494.20 70.00 494.20 100.00% 70.00 494.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.05.04 COLECTOR DE ZINC GALVANIZADO und 6.00 7.04 42.24 6.00 42.24 100.00% 6.00 42.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.17.05.05 ABRAZADERA DE FIJACION DE TUBERIA DE 3" pza 18.00 15.92 286.56 18.00 286.56 100.00% 18.00 286.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.18 INSTALACIONES ELECTRICAS
02.18.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 22.00 48.42 1,065.24 22.00 1065.24 100.00% 22.00 1065.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.18.02 SALIDA INTERRUPTOR SIMPLE pto 5.00 8.30 41.50 5.00 41.50 100.00% 5.00 41.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.18.03 SALIDA INTERRUPTOR DOBLE pto 10.00 10.85 108.50 10.00 108.50 100.00% 10.00 108.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.18.04 SALIDA TOMACORRIENTE DOBLE pto 20.00 55.14 1,102.80 20.00 1102.80 100.00% 20.00 1102.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.19 TABLEROS
02.19.01 TABLERO GENERAL TG und 1.00 371.03 371.03 1.00 371.03 100.00% 1.00 371.03 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.19.02 TABLERO DE DISTRIBUCION TD-1 glb 1.00 419.31 419.31 1.00 419.31 100.00% 1.00 419.31 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.19.03 TABLERO DE DISTRIBUCION TD-2 glb 1.00 357.53 357.53 1.00 357.53 100.00% 1.00 357.53 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.20 ARTEFACTOS
02.20.01 ARTEFACTO FLUORESCENTE 2/18 W und 4.00 42.01 168.04 4.00 168.04 100.00% 4.00 168.04 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.20.02 ARTEFACTO FLUORESCENTE 2/36 W und 8.00 78.45 627.60 8.00 627.60 100.00% 8.00 627.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.20.03 ARTEFACTO FLUORESCENTE 4/36W und 10.00 35.23 352.30 10.00 352.30 100.00% 10.00 352.30 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
02.21 POZO PUESTA A TIERRA
02.21.01 POZO DE PUESTA A TIERRA und 1.00 402.90 402.90 1.00 402.90 100.00% 1.00 402.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03 TANQUE SEPTICO Y POZO PERCOLADOR
03.01 TANQUE SEPTICO
03.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.00 0.74 5.18 7.00 5.18 100.00% 7.00 5.18 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 7.00 1.87 13.09 7.00 13.09 100.00% 7.00 13.09 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.03 EXCAVACION DE ESTRUCTURAS m3 10.85 14.72 159.71 10.85 159.71 100.00% 10.85 159.71 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.04 TERRAPLEN P/FALSO PISO C/PISON MANUAL, H=0.15 M m2 4.80 0.93 4.46 4.80 4.46 100.00% 4.80 4.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.05 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 14.10 6.02 84.88 14.10 84.88 100.00% 14.10 84.88 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.06 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 4.80 44.27 212.50 4.80 212.50 100.00% 4.80 212.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.07 CONCRETO F'C=175 KG/CM2 EN TANQUE SUBTERRANEO m3 4.73 700.92 3,315.35 4.73 3315.35 100.00% 4.73 3315.35 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.08 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 244.37 3.71 906.61 244.37 906.61 100.00% 244.37 906.61 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.09 ENCOFRADO Y DESENCOFRADO EN TANQUE ENTERRADO m2 47.29 21.69 1,025.72 47.29 1025.72 100.00% 47.29 1025.72 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.10 TARRAJEO CON IMPERMEABILIZANTE, MEZCLA E=1.5 CM m2 17.79 35.90 638.66 17.79 638.66 100.00% 17.79 638.66 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.11 ACCESORIOS PVC SAL EN TANQUE SEPTICO und 1.00 34.97 34.97 1.00 34.97 100.00% 1.00 34.97 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.12 TUBERIA PVC -SAL 4" m 7.00 32.67 228.69 7.00 228.69 100.00% 7.00 228.69 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.13 CAJA DE REGISTRO DE DESAGUE 12"X24" und 1.00 58.23 58.23 1.00 58.23 100.00% 1.00 58.23 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02 POZA DE PERCOLACION
VALORIZACIÓN FINAL DE OBRA
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION MODALIDAD EJECUCIÓN : CONTRATA
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD DE CONTRATO : PRECIOS UNITARIOS
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL PLAZO DE EJECUCIÓN : 180 DIAS CALENDARIO
PROYECTO : 2143123 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA - VALOR REFERENCIAL : S/. 892,171.04
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO MONTO DE CONTRATO : S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL FACTOR DE RELACIÓN :1
META : 0029 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA -
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO CONTRATISTA : CONSORCIO TAWA
UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO SUPERVISIÓN : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) CONTRATADO PRINCIPAL EJECUTADO DEDUCTIVO VINCULANTE SALDO FINAL
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
03.02.01 LIMPIEZA DE TERRENO MANUAL m2 8.65 0.74 6.40 8.65 6.40 100.00% 8.65 6.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 8.65 1.87 16.18 8.65 16.18 100.00% 8.65 16.18 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.03 EXCAVACION DE ESTRUCTURAS m3 17.74 14.72 261.13 17.74 261.13 100.00% 17.74 261.13 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.04 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 23.06 6.02 138.82 23.06 138.82 100.00% 23.06 138.82 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.05 CONCRETO F'C=175 KG/CM2 EN POZA DE PERCOLACION m3 1.03 700.92 721.95 1.03 721.95 100.00% 1.03 721.95 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.06 ENCOFRADO Y DESENCOFRADO EN POZA DE PERCOLACION m2 9.96 21.00 209.16 9.96 209.16 100.00% 9.96 209.16 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.07 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 42.42 3.71 157.38 42.42 157.38 100.00% 42.42 157.38 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.08 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 23.58 57.40 1,353.49 23.58 1353.49 100.00% 23.58 1353.49 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.09 FILTRO DE GRAVAS O CASCAJO m3 0.38 101.69 38.64 0.38 38.64 100.00% 0.38 38.64 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.10 CAJA DE REGISTRO DE DESAGUE 12"X24" und 1.00 58.23 58.23 1.00 58.23 100.00% 1.00 58.23 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
03.02.11 TUBERIA PVC -SAL 4" m 64.00 32.67 2,090.88 64.00 2090.88 100.00% 64.00 2090.88 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04 CERCO PERIMETRICO
04.01 TRABAJOS PRELIMINARES
04.01.01 LIMPIEZA DE TERRENO MANUAL m2 71.00 0.74 52.54 71.00 52.54 100.00% 71.00 52.54 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 78.00 1.87 145.86 78.00 145.86 100.00% 78.00 145.86 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.02 MOVIMIENTO DE TIERRAS
04.02.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 14.71 14.44 212.41 14.71 212.41 100.00% 14.71 212.41 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.02.02 EXCAVACION MANUAL DE ZAPATAS m3 4.50 14.72 66.24 4.50 66.24 100.00% 4.50 66.24 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.02.03 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 12.26 0.74 9.07 12.26 9.07 100.00% 12.26 9.07 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.02.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 2.76 9.02 24.90 2.76 24.90 100.00% 2.76 24.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.02.05 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 21.39 6.02 128.77 21.39 128.77 100.00% 21.39 128.77 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.03 CONCRETO SIMPLE
04.03.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 10.78 559.63 6,032.81 10.78 6032.81 100.00% 10.78 6032.81 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.03.02 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 2.25 559.11 1,258.00 2.25 1258.00 100.00% 2.25 1258.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.03.03 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 30.04 19.61 589.08 30.04 589.08 100.00% 30.04 589.08 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.03.04 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 3.00 44.27 132.81 3.00 132.81 100.00% 3.00 132.81 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04 CONCRETO ARMADO
04.04.01 VIGA DE CIMENTACION
04.04.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 0.57 691.52 394.17 0.57 394.17 100.00% 0.57 394.17 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 9.12 25.25 230.28 9.12 230.28 100.00% 9.12 230.28 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 68.61 3.71 254.54 68.61 254.54 100.00% 68.61 254.54 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.02 ZAPATAS
04.04.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 1.50 776.93 1,165.40 1.50 1165.40 100.00% 1.50 1165.40 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 52.07 3.71 193.18 52.07 193.18 100.00% 52.07 193.18 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.03 COLUMNAS
04.04.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 3.32 812.05 2,696.01 3.32 2696.01 100.00% 3.32 2696.01 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 29.64 30.13 893.05 29.64 893.05 100.00% 29.64 893.05 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 414.96 3.71 1,539.50 414.96 1539.50 100.00% 414.96 1539.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.04 VIGAS
04.04.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 0.49 806.43 395.15 0.49 395.15 100.00% 0.49 395.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 5.28 36.32 191.77 5.28 191.77 100.00% 5.28 191.77 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 59.10 3.71 219.26 59.10 219.26 100.00% 59.10 219.26 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.05 VIGUETAS
04.04.05.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.06 724.97 43.50 0.06 43.50 100.00% 0.06 43.50 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 0.77 28.18 21.70 0.77 21.70 100.00% 0.77 21.70 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 6.42 3.71 23.82 6.42 23.82 100.00% 6.42 23.82 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.06 LOSA ARMADA
04.04.06.01 CONCRETO F'C=210 KG/CM2 EN LOSA ARMADA m3 1.32 806.43 1,064.49 1.32 1064.49 100.00% 1.32 1064.49 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE LOSA ARMADA m2 11.37 32.77 372.59 11.37 372.59 100.00% 11.37 372.59 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.04.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 48.43 3.71 179.68 48.43 179.68 100.00% 48.43 179.68 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.05 ALBAÑILERIA
04.05.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 10.61 57.40 609.01 10.61 609.01 100.00% 10.61 609.01 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.06 PISOS Y PAVIMENTOS
04.06.01 AFIRMADO DE 4" PARA VEREDAS m2 12.26 24.65 302.21 12.26 302.21 100.00% 12.26 302.21 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.06.02 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 12.26 107.22 1,314.52 12.26 1314.52 100.00% 12.26 1314.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
VALORIZACIÓN FINAL DE OBRA
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION MODALIDAD EJECUCIÓN : CONTRATA
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD DE CONTRATO : PRECIOS UNITARIOS
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL PLAZO DE EJECUCIÓN : 180 DIAS CALENDARIO
PROYECTO : 2143123 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA - VALOR REFERENCIAL : S/. 892,171.04
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO MONTO DE CONTRATO : S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL FACTOR DE RELACIÓN :1
META : 0029 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA -
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO CONTRATISTA : CONSORCIO TAWA
UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO SUPERVISIÓN : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) CONTRATADO PRINCIPAL EJECUTADO DEDUCTIVO VINCULANTE SALDO FINAL
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
04.06.03 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 0.31 7.80 2.42 0.31 2.42 100.00% 0.31 2.42 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.07 PINTURA
04.07.01 PINTURA LATEX 2 MANOS EN COLUMNAS m2 33.79 6.18 208.82 33.79 208.82 100.00% 33.79 208.82 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.07.02 PINTURA LATEX 2 MANOS EN VIGAS m2 5.28 6.37 33.63 5.28 33.63 100.00% 5.28 33.63 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.07.03 PINTURA LATEX 2 MANOS EN VIGUETAS m2 0.77 6.37 4.90 0.77 4.90 100.00% 0.77 4.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.08 CARPINTERIA METALICA
04.08.01 PUERTA METALICA P1(3.75x3.20M) und 1.00 4,433.15 4,433.15 1.00 4433.15 100.00% 1.00 4433.15 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.08.02 PUERTA METALICA P2(1.10x3.20M) und 1.00 2,708.42 2,708.42 1.00 2708.42 100.00% 1.00 2708.42 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.08.03 MALLA METALICA COCADA 2'X2' H=2.20 M m 20.00 98.35 1,967.00 20.00 1967.00 100.00% 20.00 1967.00 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.09 INSTALACIONES ELECTRICAS
04.09.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 4.00 48.63 194.52 4.00 194.52 100.00% 4.00 194.52 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.09.02 ARTEFACTO FLUORESCENTE 2/36 W und 4.00 78.45 313.80 4.00 313.80 100.00% 4.00 313.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
04.10 VARIOS
04.10.01 JUNTA SISMICA DE 1" m 5.00 4.35 21.75 5.00 21.75 100.00% 5.00 21.75 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05 PATIO DE ENCUENTRO
05.01 TRABAJOS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO MANUAL m2 190.00 0.74 140.60 190.00 140.60 100.00% 190.00 140.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 190.00 2.82 535.80 190.00 535.80 100.00% 190.00 535.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.02 MOVIMIENTO DE TIERRAS
05.02.01 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 180.59 1.44 260.05 180.59 260.05 100.00% 180.59 260.05 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.02.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 234.77 6.02 1,413.32 234.77 1413.32 100.00% 234.77 1413.32 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.03 SEMBRADO DE AREAS VERDES
05.03.01 PREPARACION DE TIERRA DE CHACRA m2 180.56 10.02 1,809.21 180.56 1809.21 100.00% 180.56 1809.21 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
05.03.02 SEMBRADO DE GRASS AMERICANO m2 180.56 3.21 579.60 180.56 579.60 100.00% 180.56 579.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06 BEBEDERO
06.01 MOVIMIENTO DE TIERRAS
06.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.05 14.72 0.74 0.05 0.74 100.00% 0.05 0.74 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.01.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 0.07 6.02 0.42 0.07 0.42 100.00% 0.07 0.42 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02 OBRAS DE CONCRETO
06.02.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 0.05 559.63 27.98 0.05 27.98 100.00% 0.05 27.98 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02.02 CONCRETO F'C=175 KG/CM2 EN BEBEDERO m3 0.27 700.92 189.25 0.27 189.25 100.00% 0.27 189.25 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02.03 ENCOFRADO Y DESENCOFRADO EN BEBEDEROS m2 2.97 25.25 74.99 2.97 74.99 100.00% 2.97 74.99 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.02.04 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 8.85 3.71 32.83 8.85 32.83 100.00% 8.85 32.83 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.03 ALBAÑILERIA
06.03.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 0.31 57.40 17.79 0.31 17.79 100.00% 0.31 17.79 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.04 REVOQUES, ENLUCIDOS Y DERRAMES
06.04.01 TARRAJEO PRIMARIO MORTERO 1:5 m2 3.88 15.70 60.92 3.88 60.92 100.00% 3.88 60.92 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.04.02 ZOCALO DE MAYOLICA BLANCA 20 X 20 CM. m2 3.57 46.22 165.01 3.57 165.01 100.00% 3.57 165.01 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
06.05 SUMINISTRO E INSTALACION DE ACCESORIOS
06.05.01 ACCESORIOS EN BEBEDERO und 1.00 115.87 115.87 1.00 115.87 100.00% 1.00 115.87 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07 URINARIO
07.01 MOVIMIENTO DE TIERRAS
07.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.04 14.72 0.59 0.04 0.59 100.00% 0.04 0.59 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.01.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 0.06 6.02 0.36 0.06 0.36 100.00% 0.06 0.36 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.02 OBRAS DE CONCRETO
07.02.01 CONCRETO CICLOPEO F'C=140 KG/CM2 EN URINARIO m3 0.09 667.03 60.03 0.09 60.03 100.00% 0.09 60.03 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.02.02 ENCOFRADO Y DESENCOFRADO EN BEBEDEROS m2 0.86 25.25 21.72 0.86 21.72 100.00% 0.86 21.72 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.03 REVOQUES, ENLUCIDOS Y DERRAMES
07.03.01 TARRAJEO PRIMARIO MORTERO 1:5 m2 0.92 15.70 14.44 0.92 14.44 100.00% 0.92 14.44 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.03.02 ZOCALO DE MAYOLICA BLANCA 20 X 20 CM. m2 1.28 46.22 59.16 1.28 59.16 100.00% 1.28 59.16 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
07.04 SUMINISTRO E INSTALACION DE ACCESORIOS
07.04.01 ACCESORIOS SANITARIOS EN URINARIO und 2.00 71.05 142.10 2.00 142.10 100.00% 2.00 142.10 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08 JUEGOS INFANTILES
08.01 TRABAJOS PRELIMINARES
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 90.00 0.74 66.60 90.00 66.60 100.00% 90.00 66.60 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
VALORIZACIÓN FINAL DE OBRA
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION MODALIDAD EJECUCIÓN : CONTRATA
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD DE CONTRATO : PRECIOS UNITARIOS
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL PLAZO DE EJECUCIÓN : 180 DIAS CALENDARIO
PROYECTO : 2143123 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA - VALOR REFERENCIAL : S/. 892,171.04
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO MONTO DE CONTRATO : S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL FACTOR DE RELACIÓN :1
META : 0029 MEJORAMIENTO Y REHABILITACIÓN TROCHA CARROZABLE TIXIBAMBA - SAN JUAN DE CACHIMINA - MOYABAMBA -
CHINCHIBAMBA - VILLA AURORA, DISTRITO DE CHUNGUI - LA MAR – AYACUCHO CONTRATISTA : CONSORCIO TAWA
UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO SUPERVISIÓN : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) CONTRATADO PRINCIPAL EJECUTADO DEDUCTIVO VINCULANTE SALDO FINAL
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado % Metrado Valorizado % Metrado Valorizado % Metrado Valorizado %
08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 90.00 2.82 253.80 90.00 253.80 100.00% 90.00 253.80 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.02 MOVIMIENTO DE TIERRAS
08.02.01 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 85.49 1.44 123.11 85.49 123.11 100.00% 85.49 123.11 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.02.02 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.60 14.72 38.27 2.60 38.27 100.00% 2.60 38.27 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.02.03 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 14.49 6.02 87.23 14.49 87.23 100.00% 14.49 87.23 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.03 OBRAS DE CONCRETO
08.03.01 CONCRETO F'C=140 KG/CM2 EN SARDINELES m3 2.97 667.03 1,981.08 2.97 1981.08 100.00% 2.97 1981.08 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.03.02 ENCOFRADO Y DESENCOFRADO EN SARDINELES m2 26.19 31.65 828.91 26.19 828.91 100.00% 26.19 828.91 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.03.03 JUNTAS ASFALTICAS m 4.40 7.13 31.37 4.40 31.37 100.00% 4.40 31.37 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.04 VARIOS
08.04.01 COLOCACION DE ARENA FINA e=0.10 M m2 85.49 31.66 2,706.61 85.49 2706.61 100.00% 85.49 2706.61 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.04.02 COLUMPIO und 1.00 847.46 847.46 1.00 847.46 100.00% 1.00 847.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.04.03 TOBOGAN und 1.00 762.71 762.71 1.00 762.71 100.00% 1.00 762.71 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
08.04.04 BALANCIN und 1.00 847.46 847.46 1.00 847.46 100.00% 1.00 847.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09 EQUIPAMIENTO Y MOBILIARIO
09.01 EQUIPAMIENTO
09.01.01 TELEVISOR und 2.00 1,016.95 2,033.90 2.00 2033.90 100.00% 2.00 2033.90 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.01.02 REPRODUCTOR BLU RAY und 2.00 322.03 644.06 2.00 644.06 100.00% 2.00 644.06 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.02 MOBILIARIO
09.02.01 AULAS
09.02.01.01 MOBILIARIO PARA DOCENTES und 2.00 423.73 847.46 2.00 847.46 100.00% 2.00 847.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.02.01.02 ESTANTE DE MADERA und 2.00 211.86 423.72 2.00 423.72 100.00% 2.00 423.72 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.02.01.03 MUEBLE MOVIL PARA TV Y EQUIPO DE SONIDO und 2.00 169.49 338.98 2.00 338.98 100.00% 2.00 338.98 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.02.02 AMBIENTES COMPLEMENTARIOS
09.02.02.01 MOBILIARIO PARA COMEDOR DE NINOS und 5.00 379.64 1,898.20 5.00 1898.20 100.00% 5.00 1898.20 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.02.02.02 MOBILIARIO PARA DIRECCION und 1.00 788.13 788.13 1.00 788.13 100.00% 1.00 788.13 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
09.02.02.03 MOBILIARIO PARA TOPICO und 1.00 974.57 974.57 1.00 974.57 100.00% 1.00 974.57 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
10 CAPACITACION DE DOCENTES
10.01 CAPACITACIONES glb 1.00 847.46 847.46 1.00 847.46 100.00% 1.00 847.46 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11 FLETE
11.01 FLETE TERRESTRE
11.01.01 FLETE glb 1.00 37,630.56 37,630.56 1.00 37630.56 100.00% 1.00 37630.56 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%
11.02 FLETE RURAL
11.02.01 ACARREO DE MATERIALES glb 1.00 44,581.44 44,581.44 1.00 44581.44 100.00% 1.00 44581.44 100.00% 0.00 0.00 0.00% 0.00 0.00 0.00%

COSTO DIRECTO S/. 660,329.39 S/. 660,329.39 100.00% S/. 660,329.39 100.00% S/. 0.00 0.00% S/. 0.00 0.00%
GASTOS GENERALES (8.50% CD) S/. 56,128.00 S/. 56,128.00 S/. 56,128.00 S/. 0.00 S/. 0.00
UTILIDAD (6% CD) S/. 39,619.76 S/. 39,619.76 S/. 39,619.76 S/. 0.00 S/. 0.00
SUB TOTAL S/. 756,077.15 S/. 756,077.15 S/. 756,077.15 S/. 0.00 S/. 0.00
VALORIZACIÓN CONTRACTUAL = SUB TOTAL x FACTOR DE RELACIÓN (FR= 1.00000) S/. 756,077.15 S/. 756,077.15 S/. 756,077.15 S/. 0.00 S/. 0.00
IGV (18%) S/. 136,093.89 S/. 136,093.89 S/. 136,093.89 S/. 0.00 S/. 0.00
TOTAL VALORIZADO S/. 892,171.04 S/. 892,171.04 S/. 892,171.04 S/. 0.00 S/. 0.00
PORCENTAJE DE AVANCE (%) 100.00% 100.00% 0.00% 0.00%
RESUMEN DE VALORIZACIONES MENSUALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD EJEC. : CONTRATA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL SISTEMA DE CONTRATO: : PRECIOS UNITARIOS
PROYECTO : 2224730 MEJOTRAMIENTO DEL SERVICIO EDUCACION INICIAL EN 04 I.E.I. DEL AMBITO DEL DISTRITO DE CHUNGUI - LA MAR – AYACUCHO PLAZO DE EJECUCIÓN: : 180 DIAS CALENDARIO
VALOR REFERENCIAL: S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL MONTO DE CONTRATO: S/. 892,171.04
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION FACTOR DE RELACIÓN: 1.00000

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO CONTRATISTA: : CONSORCIO TAWA


SUPERVISIÓN: : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) VALORIZ. N° 01 VALORIZ. N° 02 VALORIZ. N° 03 VALORIZ. N° 04 VALORIZ. N° 05 VALORIZ. N° 06 VALORIZ. N° 07 VALORIZ. N° 08 VALORIZ. N° 09 VALORIZ. N° 10 TOTAL VALORIZADO
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado %

01 AULAS
01.01 OBRAS PRELIMINARES 0 0.00 0.00 0.00
01.01.01 ALQUILER DE ALMACEN mes 6.00 423.73 2,542.38 1.00 423.73 1.00 423.73 1.00 423.73 1.00 423.73 1.00 423.73 1.00 423.73 1.00 423.73 0.00 0.00 0.00 -1.00 -423.73 6.00 2542.38 1.00
01.01.02 CARTEL DE OBRA glb 1.00 593.22 593.22 1.00 593.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 593.22 1.00
01.02 TRABAJOS PRELIMINARES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02.01 LIMPIEZA DE TERRENO MANUAL m2 223.82 0.74 165.63 223.82 165.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 223.82 165.63 1.00
01.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 300.00 1.87 561.00 300.00 561.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 300.00 561.00 1.00
01.03 MOVIMIENTO DE TIERRAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.03.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 55.71 14.72 820.05 55.71 820.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 55.71 820.05 1.00
01.03.02 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 25.85 1.44 37.22 0.00 0.00 25.85 37.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.85 37.22 1.00
01.03.03 EXCAVACIONES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.03.03.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 35.98 14.44 519.55 26.54 383.24 9.44 136.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 35.98 519.55 1.00
01.03.03.02 EXCAVACION MANUAL DE ZAPATAS m3 30.00 14.72 441.60 30.00 441.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.00 441.60 1.00
01.03.03.03 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES DE VEREDAS m3 2.24 14.44 32.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.24 32.35 0.00 0.00 2.24 32.35 1.00
01.03.03.04 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS DE DRENAJE m3 5.82 14.72 85.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.82 85.67 0.00 0.00 5.82 85.67 1.00
01.03.03.05 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 10.35 9.02 93.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.35 93.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.35 93.36 1.00
01.03.03.06 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 158.60 6.02 954.77 158.60 954.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 158.60 954.77 1.00
01.03.03.07 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 200.42 0.74 148.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 200.42 148.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 200.42 148.31 1.00
01.03.03.08 AFIRMADO DE e=4" PARA PISOS INTERIORES Y EXTERIORES m2 119.98 24.34 2,920.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 91.00 2214.94 0.00 0.00 0.00 0.00 0.00 0.00 28.98 705.37 0.00 0.00 119.98 2920.31 1.00
01.04 CONCRETO SIMPLE 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.04.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 13.82 559.63 7,734.09 0.00 0.00 13.82 7734.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.06 13.82 7734.09 1.00
01.04.02 SUBCIMIENTO C:H=1:12+30% PG m3 15.72 525.00 8,253.00 0.00 0.00 15.72 8253.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.26 15.72 8253.00 1.00
01.04.03 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 20.00 44.27 885.40 0.00 0.00 20.00 885.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.00 885.40 1.00
01.04.04 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 5.69 559.11 3,181.34 0.00 0.00 5.69 3181.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.11 5.69 3181.34 1.00
01.04.05 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 59.52 19.61 1,167.19 0.00 0.00 59.52 1167.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 59.52 1167.19 1.00
01.04.06 FALSO PISO e= 4" ( MEZCLA 1:10 CEMENTO : HORMIGON ) m2 146.87 58.90 8,650.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 146.87 8650.64 0.00 0.00 146.87 8650.64 1.00
01.04.07 CONCRETO F'C=140 KG/CM2 EN CANALETAS m3 6.11 671.93 4,105.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.11 4105.49 0.00 0.00 6.11 4105.49 1.00
01.04.08 ENCOFRADO Y DESENCOFRADO EN CANALETAS m2 31.36 31.65 992.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31.36 992.54 0.00 0.00 31.36 992.54 1.00
01.04.09 JUNTAS ASFALTICAS m 3.20 7.13 22.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.20 22.82 0.00 0.00 3.20 22.82 1.00
01.04.10 TUBERIA PVC SAL D=8" m 6.00 49.98 299.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 299.88 0.00 0.00 6.00 299.88 1.00
01.05 CONCRETO ARMADO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.05.01 VIGA DE CIMENTACION 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.05.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 4.17 691.52 2,883.64 0.00 0.00 0.00 0.00 4.17 2883.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.01 4.17 2883.64 1.00
01.05.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 41.65 25.25 1,051.66 0.00 0.00 0.00 0.00 41.65 1051.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 41.65 1051.66 1.00
01.05.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 481.42 3.71 1,786.07 481.42 1786.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 481.42 1786.07 1.00
01.05.02 ZAPATAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.05.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 12.00 776.93 9,323.16 0.00 0.00 12.00 9323.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.00 9323.16 1.00
01.05.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 236.87 3.71 878.79 236.87 878.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.01 236.87 878.79 1.00
01.05.03 COLUMNAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.05.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 9.45 812.05 7,673.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.02 4888.54 0.00 0.00 0.00 0.00 0.00 0.00 3.43 2785.33 0.00 0.00 9.45 7673.87 1.00
01.05.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 85.11 30.13 2,564.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49.87 1502.58 0.00 0.00 0.00 0.00 0.00 0.00 35.24 1061.78 0.00 0.00 85.11 2564.36 1.00
01.05.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,992.18 3.71 7,390.99 1992.18 7390.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 1992.18 7390.99 1.00
01.05.04 VIGAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.05.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 8.56 806.43 6,903.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.79 3862.80 3.77 3040.24 0.00 0.00 0.00 0.00 0.00 8.56 6903.04 1.00
01.05.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 97.51 36.32 3,541.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.98 1778.95 48.53 1762.61 0.00 0.00 0.00 0.00 0.00 97.51 3541.56 1.00
01.05.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,114.78 3.71 4,135.83 0.00 0.00 500.00 1855.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1114.78 4135.83 0.00 0.00 0.00 -500.00 -1855.00 1114.78 4135.83 1.00
01.05.05 COLUMNETAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.05.05.01 CONCRETO fc'= 175 kg/cm2 EN COLUMNETAS m3 3.36 724.97 2,435.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.22 884.46 0.00 0.00 0.00 0.00 0.00 0.00 2.14 1551.44 0.00 0.00 3.36 2435.90 1.00
01.05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNETAS m2 100.38 28.18 2,828.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.92 1012.23 0.00 0.00 0.00 0.00 0.00 0.00 64.46 1816.48 0.00 0.00 100.38 2828.71 1.00
01.05.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 356.52 3.71 1,322.69 0.00 0.00 356.52 1322.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.02 356.52 1322.69 1.00
01.05.06 VIGUETAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.05.06.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.41 724.97 297.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.41 297.24 0.00 0.00 0.41 297.24 1.00
01.05.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 8.92 28.18 251.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.92 251.37 0.00 0.00 8.92 251.37 1.00
01.05.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 136.42 3.71 506.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 136.42 506.12 0.00 0.00 136.42 506.12 1.00
01.06 ESTRUCTURA METALICA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.06.01 TIJERAL METALICO TIPO I L=9.93 M und 6.00 2,330.51 13,983.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 13983.06 0.00 0.00 6.00 13983.06 1.00
01.06.02 TIJERAL METALICO TIPO IV L=8.72 M und 3.00 2,076.27 6,228.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 6228.81 0.00 0.00 3.00 6228.81 1.00
01.06.03 CORREAS METALICAS CW 64X38X0.90 m 226.12 24.92 5,634.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 226.12 5634.91 0.00 0.00 226.12 5634.91 1.00
01.06.04 CORREAS METALICAS UP 90X32X0.90 MM m 46.94 23.13 1,085.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 46.94 1085.72 0.00 0.00 46.94 1085.72 1.00
01.06.05 ARRIOSTRE METALICO PT 100X0.9 m 63.30 57.83 3,660.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 63.30 3660.64 0.00 0.00 63.30 3660.64 1.00
01.06.06 CORREAS METALICAS DE CIERRE UP 65X32X0.90 MM m 57.18 17.80 1,017.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.18 1017.80 0.00 0.00 57.18 1017.80 1.00
01.07 ALBAÑILERIA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.07.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 48.22 57.40 2,767.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.62 1757.59 0.00 0.00 0.00 0.00 0.00 0.00 17.60 1010.24 0.00 0.00 48.22 2767.83 1.00
01.07.02 MURO DE LADRILLO KK DE ARCILLA DE CABEZA MEZCLA 1:4 m2 77.77 96.30 7,489.25 0.00 0.00 0.00 0.00 0.00 0.00 9.62 926.36 32.60 3139.38 0.00 0.00 0.00 0.00 0.00 0.00 35.55 3423.47 0.00 0.05 77.77 7489.25 1.00
01.07.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 32.90 3.71 122.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.90 122.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.90 122.06 1.00
01.08 REVOQUES, ENLUCIDOS Y DERRAMES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.08.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 200.58 16.69 3,347.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 141.12 2355.29 59.46 992.39 0.00 0.00 200.58 3347.68 1.00
01.08.02 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 123.32 23.06 2,843.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 123.32 2843.76 0.00 0.00 123.32 2843.76 1.00
01.08.03 VESTIDURAS DE DERRAMES CON BORDES BOLEADOS M : 1: 5 m 128.36 7.51 963.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 128.36 963.98 0.00 0.00 128.36 963.98 1.00
01.08.04 BRUÑAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.08.04.01 BRUÑA e= 1 cm. EXTERIOR m 93.34 2.53 236.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 93.34 236.15 0.00 0.00 93.34 236.15 1.00
01.08.04.02 BRUÑA e= 1 cm. INTERIOR m 171.85 2.53 434.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 120.23 304.18 51.62 130.60 0.00 0.00 171.85 434.78 1.00
01.08.04.03 BRUÑA e= 1 cm. EN PISO INTERIOR Y EXTERIOR m 72.84 2.53 184.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 72.84 184.29 0.00 0.00 72.84 184.29 1.00
RESUMEN DE VALORIZACIONES MENSUALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD EJEC. : CONTRATA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL SISTEMA DE CONTRATO: : PRECIOS UNITARIOS
PROYECTO : 2224730 MEJOTRAMIENTO DEL SERVICIO EDUCACION INICIAL EN 04 I.E.I. DEL AMBITO DEL DISTRITO DE CHUNGUI - LA MAR – AYACUCHO PLAZO DE EJECUCIÓN: : 180 DIAS CALENDARIO
VALOR REFERENCIAL: S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL MONTO DE CONTRATO: S/. 892,171.04
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION FACTOR DE RELACIÓN: 1.00000

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO CONTRATISTA: : CONSORCIO TAWA


SUPERVISIÓN: : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) VALORIZ. N° 01 VALORIZ. N° 02 VALORIZ. N° 03 VALORIZ. N° 04 VALORIZ. N° 05 VALORIZ. N° 06 VALORIZ. N° 07 VALORIZ. N° 08 VALORIZ. N° 09 VALORIZ. N° 10 TOTAL VALORIZADO
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado %
01.09 CERRAMIENTO CON PANEL FIBROCEMENTO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.09.01 CIELORRASO CON PANEL FIBROCEMENTO 4 mm. m2 179.89 142.37 25,610.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 179.89 25610.94 179.89 25610.94 1.00
01.10 PISOS Y PAVIMENTOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.10.01 PISO DE MADERA MACHIHEMBRADA m2 120.95 76.46 9,247.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 120.95 9247.84 120.95 9247.84 1.00
01.10.02 PISO DE CONCRETO e=2", PULIDO SIN COLOREAR m2 9.00 38.12 343.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.00 343.08 0.00 0.00 9.00 343.08 1.00
01.10.03 PISO CERAMICO DE COLOR CLARO 30X30CM m2 21.02 45.69 960.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.02 960.40 0.00 0.00 21.02 960.40 1.00
01.10.04 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 31.56 107.22 3,383.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31.56 3383.86 0.00 0.00 31.56 3383.86 1.00
01.10.05 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 5.35 7.80 41.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.35 41.73 0.00 0.00 5.35 41.73 1.00
01.11 ZOCALOS Y CONTRAZOCALOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.11.01 ZOCALO DE MAYOLICA BLANCA 30 X 30 CM. m2 40.70 46.22 1,881.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 40.70 1881.15 0.00 0.00 40.70 1881.15 1.00
01.11.02 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.20 m. EXTERIOR m 57.30 5.47 313.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.30 313.43 0.00 0.00 57.30 313.43 1.00
01.11.03 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.10 m. INTERIOR m 14.54 3.74 54.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.54 54.38 0.00 0.00 14.54 54.38 1.00
01.11.04 CONTRAZOCALO DE CEDRO DE 3" RODON 1" m 54.72 16.69 913.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 54.72 913.28 54.72 913.28 1.00
01.12 CUBIERTA Y TECHO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.12.01 COBERTURA CON LAMINA TERMOACUSTICA m2 293.23 34.96 10,251.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 293.23 10251.32 0.00 0.00 293.23 10251.32 1.00
01.12.02 CUMBRERA DENTADA m 22.54 27.64 623.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.54 623.01 0.00 0.00 22.54 623.01 1.00
01.13 CARPINTERIA DE MADERA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.13.01 PUERTA DE MADERA APANELADA m2 15.90 160.54 2,552.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.90 2552.59 15.90 2552.59 1.00
01.13.02 VENTANA DE MADERA m2 36.42 91.01 3,314.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36.42 3314.58 36.42 3314.58 1.00
01.13.03 TICERO DE MADERA CEDRO ( L= 3.00 m. ) BARNIZADO und 2.00 157.90 315.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 315.80 2.00 315.80 1.00
01.14 CERRAJERIA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.14.01 BISAGRA ALUMINIZADA DE 4" x 4" PESADA PARA PUERTA pza 24.00 6.45 154.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.00 154.80 24.00 154.80 1.00
01.14.02 CERRADURA PARA PUERTA EXTERIOR TIPO PARCHE 2 GOLPES pza 7.00 59.54 416.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 416.78 7.00 416.78 1.00
01.14.03 MANIJA DE 4" PARA PUERTA pza 7.00 5.27 36.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 36.89 7.00 36.89 1.00
01.14.04 CERROJOS PARA VENTANAS DE BRONCE pza 70.00 2.98 208.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.00 208.60 70.00 208.60 1.00
01.14.05 MANIJA DE BRONCE PARA PORTAÑUELAS DE VENTANAS pza 70.00 3.57 249.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.00 249.90 70.00 249.90 1.00
01.14.06 BISAGRA ALUMINIZADA DE 2 1/2" x 2 1/2" PARA VENTANA pza 70.00 5.67 396.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.00 396.90 70.00 396.90 1.00
01.14.07 TOPE METALICO DE FIERRO PARA VENTANA pza 70.00 3.84 268.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.00 268.80 70.00 268.80 1.00
01.15 VIDRIOS, CRISTALES Y SIMILARES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.15.01 VIDRIOS SEMIDOBLES p2 391.83 3.65 1,430.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 391.83 1430.18 391.83 1430.18 1.00
01.16 PINTURA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.16.01 PINT. LATEX 2 MANOS EN MUROS EXTERIORES m2 123.32 4.65 573.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 123.32 573.44 123.32 573.44 1.00
01.16.02 PINT. LATEX 2 MANOS EN MUROS INTERIORES m2 187.14 4.65 870.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 187.14 870.20 187.14 870.20 1.00
01.16.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 85.11 6.18 525.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 85.11 525.98 85.11 525.98 1.00
01.16.04 PINTURA LATEX 2 MANOS EN COLUMNETAS m2 44.09 6.18 272.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 44.09 272.48 44.09 272.48 1.00
01.16.05 PINTURA LATEX 2 MANOS EN VIGAS m2 97.51 6.37 621.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.51 621.14 97.51 621.14 1.00
01.16.06 PINTURA BARNIZ EN PUERTAS m2 31.80 6.69 212.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31.80 212.74 31.80 212.74 1.00
01.16.07 PINTURA BARNIZ EN VENTANA DE MADERA m2 36.42 6.69 243.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36.42 243.65 36.42 243.65 1.00
01.17 VARIOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.17.01 JUNTA SISMICA DE 1" m 9.87 4.35 42.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.87 42.93 0.00 0.00 9.87 42.93 1.00
01.17.02 PIZARRA CEMENTO 3.00 x 1.20 m. SIN TICERO und 2.00 118.88 237.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 237.76 0.00 0.00 2.00 237.76 1.00
01.17.03 JUNTA DE DILATACION DE 1" EN VEREDA m 35.21 7.18 252.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.21 252.81 0.00 0.00 35.21 252.81 1.00
01.18 INSTALACIONES SANITARIAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.18.01 DESAGUE Y VENTILACION 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.18.01.01 SALIDA DE DESAGUE PVC SAL D=2" pto 7.00 40.26 281.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 281.82 0.00 0.00 7.00 281.82 1.00
01.18.01.02 SALIDA DE DESAGUE PVC SAL D=4" pto 4.00 51.85 207.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 207.40 0.00 0.00 4.00 207.40 1.00
01.18.01.03 SUMIDEROS DE 3" pza 1.00 36.79 36.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 36.79 0.00 0.00 1.00 36.79 1.00
01.18.01.04 REGISTRO DE BRONCE 2" pza 1.00 20.32 20.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 20.32 0.00 0.00 1.00 20.32 1.00
01.18.01.05 REGISTRO DE BRONCE 4" pza 2.00 30.22 60.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 60.44 0.00 0.00 2.00 60.44 1.00
01.18.02 REDES DE DISTRIBUCION 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.18.02.01 TUBERIA PVC -SAL 2" m 10.11 9.19 92.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.11 92.91 0.00 0.00 10.11 92.91 1.00
01.18.02.02 TUBERIA PVC -SAL 4" m 39.81 12.76 507.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39.81 507.98 0.00 0.00 39.81 507.98 1.00
01.18.03 APARATOS Y ACCESORIOS SANITARIOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.18.03.01 INODORO TANQUE BAJO TIPO "BABY" und 4.00 289.42 1,157.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 1157.68 4.00 1157.68 1.00
01.18.03.02 PAPELERA DE LOZA DE COLOR DE 15 X 15 cm pza 4.00 8.47 33.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 33.88 4.00 33.88 1.00
01.18.03.03 CAJA DE REGISTRO 12"X24" C/TAPA DE CONCRETO pza 1.00 47.49 47.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 47.49 1.00 47.49 1.00
01.18.04 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.18.04.01 SALIDA DE AGUA FRIA PVC pto 10.00 25.65 256.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 256.50 0.00 0.00 10.00 256.50 1.00
01.18.04.02 TUBERIA PVC CLASE 10 - 3/4" m 30.72 5.06 155.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.72 155.44 0.00 0.00 30.72 155.44 1.00
01.18.04.03 TUBERIA PVC CLASE 10 - 1/2" m 4.03 4.63 18.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.03 18.66 0.00 0.00 4.03 18.66 1.00
01.18.04.04 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza 1.00 35.90 35.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 35.90 0.00 0.00 1.00 35.90 1.00
01.18.04.05 VALVULAS DE COMPUERTA DE BRONCE DE 3/4" pza 2.00 48.60 97.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 97.20 0.00 0.00 2.00 97.20 1.00
01.18.05 SISTEMA DE DRENAJE PLUVIAL 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.18.05.01 TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS m 30.33 16.69 506.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.33 506.21 0.00 0.00 30.33 506.21 1.00
01.18.05.02 CANALETA DE FIERRO GALVANIZADO m 64.94 30.63 1,989.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.94 1989.11 0.00 0.00 64.94 1989.11 1.00
01.18.05.03 ABRAZADERA DE FIJACION DE TUBO pza 59.00 7.06 416.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 59.00 416.54 0.00 0.00 59.00 416.54 1.00
01.18.05.04 COLECTOR DE ZINC GALVANIZADO und 6.00 7.04 42.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 42.24 0.00 0.00 6.00 42.24 1.00
01.18.05.05 ABRAZADERA DE FIJACION DE TUBERIA DE 3" pza 18.00 15.92 286.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.00 286.56 0.00 0.00 18.00 286.56 1.00
01.19 INSTALACIONES ELECTRICAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.19.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 17.00 48.42 823.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.00 823.14 17.00 823.14 1.00
01.19.02 SALIDA INTERRUPTOR SIMPLE pto 2.00 8.30 16.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 16.60 2.00 16.60 1.00
01.19.03 SALIDA INTERRUPTOR DOBLE pto 5.00 10.85 54.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.00 54.25 5.00 54.25 1.00
01.19.04 SALIDA TOMACORRIENTE DOBLE pto 6.00 55.14 330.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 330.84 6.00 330.84 1.00
01.19.05 SALIDA PARA ANTENA DE TELEVISION CON PVC pto 2.00 64.08 128.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 128.16 2.00 128.16 1.00
RESUMEN DE VALORIZACIONES MENSUALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD EJEC. : CONTRATA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL SISTEMA DE CONTRATO: : PRECIOS UNITARIOS
PROYECTO : 2224730 MEJOTRAMIENTO DEL SERVICIO EDUCACION INICIAL EN 04 I.E.I. DEL AMBITO DEL DISTRITO DE CHUNGUI - LA MAR – AYACUCHO PLAZO DE EJECUCIÓN: : 180 DIAS CALENDARIO
VALOR REFERENCIAL: S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL MONTO DE CONTRATO: S/. 892,171.04
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION FACTOR DE RELACIÓN: 1.00000

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO CONTRATISTA: : CONSORCIO TAWA


SUPERVISIÓN: : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) VALORIZ. N° 01 VALORIZ. N° 02 VALORIZ. N° 03 VALORIZ. N° 04 VALORIZ. N° 05 VALORIZ. N° 06 VALORIZ. N° 07 VALORIZ. N° 08 VALORIZ. N° 09 VALORIZ. N° 10 TOTAL VALORIZADO
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado %
01.20 TABLEROS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.20.01 TABLERO DE DISTRIBUCION TD-3 und 1.00 416.20 416.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 416.20 0.00 0.00 1.00 416.20 1.00
01.21 ARTEFACTOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.21.01 ARTEFACTO FLUORESCENTE 2/18 W und 4.00 42.01 168.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 168.04 4.00 168.04 1.00
01.21.02 ARTEFACTO FLUORESCENTE 1/36W und 2.00 41.16 82.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 82.32 2.00 82.32 1.00
01.21.03 ARTEFACTO FLUORESCENTE 2/36 W und 2.00 78.45 156.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 156.90 2.00 156.90 1.00
01.21.04 ARTEFACTO FLUORESCENTE 4/36W und 8.00 35.23 281.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 281.84 8.00 281.84 1.00
01.22 POZO PUESTA A TIERRA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.22.01 POZO DE PUESTA A TIERRA und 1.00 402.90 402.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 402.90 1.00 402.90 1.00
02 AREA COMPLEMENTARIA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01 TRABAJOS PRELIMINARES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01.01 LIMPIEZA DE TERRENO MANUAL m2 248.72 0.74 184.05 0.00 0.00 248.72 184.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 248.72 184.05 1.00
02.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 290.85 1.87 543.89 0.00 0.00 290.85 543.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 290.85 543.89 1.00
02.02 MOVIMIENTO DE TIERRAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 369.18 14.72 5,434.33 0.00 0.00 369.18 5434.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 369.18 5434.33 1.00
02.02.02 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 33.95 1.44 48.89 0.00 0.00 33.95 48.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33.95 48.89 1.00
02.02.03 EXCAVACIONES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02.03.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 46.92 14.44 677.52 0.00 0.00 0.00 0.00 46.92 677.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 46.92 677.52 1.00
02.02.03.02 EXCAVACION MANUAL DE ZAPATAS m3 31.50 14.72 463.68 0.00 0.00 0.00 0.00 31.50 463.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31.50 463.68 1.00
02.02.03.03 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES DE VEREDAS m3 2.25 14.44 32.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.25 32.49 0.00 0.00 2.25 32.49 1.00
02.02.03.04 EXCAVACION MANUAL DE ZANJAS PARA CANALETAS DE DRENAJE m3 5.42 14.72 79.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.42 79.78 0.00 0.00 5.42 79.78 1.00
02.02.03.05 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 12.23 9.02 110.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.23 110.31 12.23 110.31 0.00 0.00 0.00 0.00 0.00 -12.23 -110.31 12.23 110.31 1.00
02.02.03.06 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 580.36 6.02 3,493.77 0.00 0.00 580.36 3493.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 580.36 3493.77 1.00
02.02.03.07 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 247.78 0.74 183.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 247.78 183.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 247.78 183.36 1.00
02.02.03.08 AFIRMADO DE e=4" PARA PISOS INTERIORES Y EXTERIORES m2 226.78 24.34 5,519.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 226.78 5519.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 226.78 5519.83 1.00
02.03 CONCRETO SIMPLE 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 18.24 559.63 10,207.65 0.00 0.00 0.00 0.00 18.24 10207.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.24 10207.65 1.00
02.03.02 SUBCIMIENTO C:H=1:12+30% PG m3 18.20 525.00 9,555.00 0.00 0.00 0.00 0.00 18.20 9555.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.20 9555.00 1.00
02.03.03 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 21.00 44.27 929.67 0.00 0.00 0.00 0.00 21.00 929.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.00 929.67 1.00
02.03.04 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 10.49 559.11 5,865.06 0.00 0.00 0.00 0.00 0.00 0.00 10.49 5864.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 10.49 5865.06 1.00
02.03.05 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 113.05 19.61 2,216.91 0.00 0.00 0.00 0.00 0.00 0.00 113.05 2216.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 113.05 2216.91 1.00
02.03.06 FALSO PISO e= 4" ( MEZCLA 1:10 CEMENTO : HORMIGON ) m2 178.05 58.90 10,487.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.35 5733.92 0.00 0.00 0.00 0.00 0.00 0.00 80.70 4753.23 0.00 0.00 178.05 10487.15 1.00
02.03.07 CONCRETO F'C=140 KG/CM2 EN CANALETAS m3 6.60 671.93 4,434.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.60 4434.74 0.00 0.00 6.60 4434.74 1.00
02.03.08 ENCOFRADO Y DESENCOFRADO EN CANALETAS m2 34.02 31.65 1,076.73 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 34.02 1076.73 0.00 0.00 34.02 1076.73 1.00
02.03.09 JUNTAS ASFALTICAS m 4.00 7.13 28.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 28.52 0.00 0.00 4.00 28.52 1.00
02.03.10 TUBERIA PVC SAL D=8" m 6.00 49.98 299.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 299.88 0.00 0.00 6.00 299.88 1.00
02.04 CONCRETO ARMADO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04.01 VIGA DE CIMENTACION 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 6.85 691.52 4,736.91 0.00 0.00 0.00 0.00 0.00 0.00 6.85 4736.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.86 6.85 4736.91 1.00
02.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 68.49 25.25 1,729.37 0.00 0.00 0.00 0.00 0.00 0.00 68.49 1729.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.06 68.49 1729.37 1.00
02.04.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 545.47 3.71 2,023.69 0.00 0.00 0.00 0.00 200.00 742.00 345.47 1281.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 545.47 2023.69 1.00
02.04.02 ZAPATAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 12.60 776.93 9,789.32 0.00 0.00 0.00 0.00 5.40 4195.42 7.20 5593.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.60 9789.32 1.00
02.04.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 250.55 3.71 929.54 0.00 0.00 0.00 0.00 250.55 929.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.01 250.55 929.54 1.00
02.04.03 COLUMNAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 11.05 812.05 8,973.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.20 8282.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.85 690.24 11.05 8973.15 1.00
02.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 79.62 30.13 2,398.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 73.53 2215.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.09 183.49 79.62 2398.95 1.00
02.04.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 2,805.55 3.71 10,408.59 0.00 0.00 0.00 0.00 1000.00 3710.00 1805.55 6698.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2805.55 10408.59 1.00
02.04.04 VIGAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 11.82 806.43 9,532.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.17 4975.67 5.65 4556.33 0.00 0.00 0.00 0.00 0.00 11.82 9532.00 1.00
02.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 134.17 36.32 4,873.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 63.02 2288.89 71.15 2584.17 0.00 0.00 0.00 0.00 0.00 134.17 4873.05 1.00
02.04.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 1,580.11 3.71 5,862.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 500.00 1855.00 0.00 0.00 1580.11 5862.21 0.00 0.00 0.00 -500.00 -1855.00 1580.11 5862.21 1.00
02.04.05 COLUMNETAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04.05.01 CONCRETO fc'= 175 kg/cm2 EN COLUMNETAS m3 4.67 724.97 3,385.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.67 3385.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.67 3385.61 1.00
02.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE COLUMNETAS m2 75.55 28.18 2,129.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 75.55 2129.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 75.55 2129.00 1.00
02.04.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 543.43 3.71 2,016.13 0.00 0.00 0.00 0.00 0.00 0.00 543.43 2016.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 543.43 2016.13 1.00
02.04.06 VIGUETAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04.06.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.36 724.97 260.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.36 260.99 0.00 0.00 0.36 260.99 1.00
02.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 5.51 28.18 155.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.51 155.27 0.00 0.00 5.51 155.27 1.00
02.04.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 101.78 3.71 377.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 101.78 377.60 0.00 0.00 101.78 377.60 1.00
02.05 ESTRUCTURA METALICA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.05.01 TIJERAL METALICO TIPO I L=9.93 M und 6.00 2,330.51 13,983.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 13983.06 0.00 0.00 6.00 13983.06 1.00
02.05.02 TIJERAL METALICO TIPO III L=7.50 M und 4.00 1,779.66 7,118.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 7118.64 0.00 0.00 4.00 7118.64 1.00
02.05.03 CORREAS METALICAS CW 64X38X0.90 m 302.69 24.92 7,543.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 302.69 7543.03 0.00 0.00 302.69 7543.03 1.00
02.05.04 CORREAS METALICAS UP 90X32X0.90 MM m 60.52 23.13 1,399.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 60.52 1399.83 0.00 0.00 60.52 1399.83 1.00
02.05.05 ARRIOSTRE METALICO PT 100X0.9 m 71.86 57.83 4,155.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71.86 4155.66 0.00 0.00 71.86 4155.66 1.00
02.05.06 CORREAS METALICAS DE CIERRE UP 65X32X0.90 MM m 58.22 17.80 1,036.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 58.22 1036.32 0.00 0.00 58.22 1036.32 1.00
02.06 ALBAÑILERIA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.06.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 102.29 57.40 5,871.45 0.00 0.00 0.00 0.00 0.00 0.00 64.12 3680.52 38.17 2190.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 102.29 5871.45 1.00
02.06.02 MURO DE LADRILLO KK DE ARCILLA DE CABEZA MEZCLA 1:4 m2 120.61 96.30 11,614.74 0.00 0.00 0.00 0.00 0.00 0.00 86.99 8377.61 26.24 2526.91 0.00 0.00 0.00 0.00 0.00 0.00 7.38 710.69 0.00 -0.47 120.61 11614.74 1.00
02.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 45.85 3.71 170.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 45.85 170.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 45.85 170.10 1.00
02.07 REVOQUES, ENLUCIDOS Y DERRAMES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.07.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA m2 285.76 16.69 4,769.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 285.76 4769.33 0.00 0.00 0.00 285.76 4769.33 1.00
02.07.02 TARRAJEO EN EXTERIORES CON CEMENTO-ARENA m2 160.04 23.06 3,690.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 65.66 1514.12 94.38 2176.40 0.00 0.00 160.04 3690.52 1.00
RESUMEN DE VALORIZACIONES MENSUALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD EJEC. : CONTRATA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL SISTEMA DE CONTRATO: : PRECIOS UNITARIOS
PROYECTO : 2224730 MEJOTRAMIENTO DEL SERVICIO EDUCACION INICIAL EN 04 I.E.I. DEL AMBITO DEL DISTRITO DE CHUNGUI - LA MAR – AYACUCHO PLAZO DE EJECUCIÓN: : 180 DIAS CALENDARIO
VALOR REFERENCIAL: S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL MONTO DE CONTRATO: S/. 892,171.04
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION FACTOR DE RELACIÓN: 1.00000

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO CONTRATISTA: : CONSORCIO TAWA


SUPERVISIÓN: : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) VALORIZ. N° 01 VALORIZ. N° 02 VALORIZ. N° 03 VALORIZ. N° 04 VALORIZ. N° 05 VALORIZ. N° 06 VALORIZ. N° 07 VALORIZ. N° 08 VALORIZ. N° 09 VALORIZ. N° 10 TOTAL VALORIZADO
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado %
02.07.03 VESTIDURAS DE DERRAMES CON BORDES BOLEADOS M : 1: 5 m 57.30 7.51 430.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.30 430.32 0.00 0.00 57.30 430.32 1.00
02.07.04 BRUÑAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.07.04.01 BRUÑA e= 1 cm. EXTERIOR m 104.66 2.53 264.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.65 123.08 56.01 141.71 0.00 0.00 104.66 264.79 1.00
02.07.04.02 BRUÑA e= 1 cm. INTERIOR m 162.31 2.53 410.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 162.31 410.64 0.00 0.00 0.00 162.31 410.64 1.00
02.07.04.03 BRUÑA e= 1 cm. EN PISO INTERIOR Y EXTERIOR m 122.24 2.53 309.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 122.24 309.27 0.00 0.00 122.24 309.27 1.00
02.08 CERRAMIENTO CON PANEL FIBROCEMENTO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.08.01 CIELORRASO CON PANEL FIBROCEMENTO 4 mm. m2 260.42 142.37 37,076.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 260.42 37076.00 260.42 37076.00 1.00
02.09 PISOS Y PAVIMENTOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.09.01 PISO DE MADERA MACHIHEMBRADA m2 82.64 76.46 6,318.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 82.64 6318.65 82.64 6318.65 1.00
02.09.02 PISO DE CONCRETO e=2", PULIDO SIN COLOREAR m2 21.00 38.12 800.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.00 800.52 0.00 0.00 21.00 800.52 1.00
02.09.03 PISO CERAMICO DE COLOR CLARO 30X30CM m2 73.42 45.69 3,354.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 73.42 3354.56 0.00 0.00 73.42 3354.56 1.00
02.09.04 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 49.25 107.22 5,280.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 49.25 5280.59 0.00 0.00 49.25 5280.59 1.00
02.09.05 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 7.76 7.80 60.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.76 60.53 0.00 0.00 7.76 60.53 1.00
02.10 ZOCALOS Y CONTRAZOCALOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.10.01 ZOCALO DE MAYOLICA BLANCA 30 X 30 CM. m2 25.04 46.22 1,157.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.04 1157.35 0.00 0.00 25.04 1157.35 1.00
02.10.02 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.20 m. EXTERIOR m 66.03 5.47 361.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 66.03 361.18 0.00 0.00 66.03 361.18 1.00
02.10.03 CONTRAZOCALO DE CEMENTO S/COLOREAR h=0.10 m. INTERIOR m 40.77 3.74 152.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 40.77 152.48 0.00 0.00 40.77 152.48 1.00
02.10.04 CONTRAZOCALO DE CEDRO DE 3" RODON 1" m 47.01 16.69 784.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 47.01 784.60 47.01 784.60 1.00
02.10.05 CONTRAZOCALO DE CERAMICO H=20 CM m 13.85 12.89 178.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.85 178.53 0.00 0.00 13.85 178.53 1.00
02.11 CUBIERTA Y TECHO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.11.01 COBERTURA CON LAMINA TERMOACUSTICA m2 291.80 34.96 10,201.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 291.80 10201.33 0.00 0.00 291.80 10201.33 1.00
02.11.02 CUMBRERA DENTADA m 30.25 27.64 836.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.25 836.11 0.00 0.00 30.25 836.11 1.00
02.12 CARPINTERIA DE MADERA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.12.01 PUERTA DE MADERA APANELADA m2 21.74 160.54 3,490.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.74 3490.14 21.74 3490.14 1.00
02.12.02 VENTANA DE MADERA m2 31.52 91.01 2,868.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 31.52 2868.64 31.52 2868.64 1.00
02.12.03 TICERO DE MADERA CEDRO ( L= 3.00 m. ) BARNIZADO und 1.00 157.90 157.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 157.90 1.00 157.90 1.00
02.13 CERRAJERIA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.13.01 BISAGRA ALUMINIZADA DE 4" x 4" PESADA PARA PUERTA pza 30.00 6.45 193.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.00 193.50 30.00 193.50 1.00
02.13.02 CERRADURA PARA PUERTA EXTERIOR TIPO PARCHE 2 GOLPES pza 10.00 59.54 595.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 595.40 10.00 595.40 1.00
02.13.03 MANIJA DE 4" PARA PUERTA pza 10.00 5.27 52.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 52.70 10.00 52.70 1.00
02.13.04 CERROJOS PARA VENTANAS DE BRONCE pza 62.00 2.98 184.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.00 184.76 62.00 184.76 1.00
02.13.05 MANIJA DE BRONCE PARA PORTAÑUELAS DE VENTANAS pza 62.00 3.57 221.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.00 221.34 62.00 221.34 1.00
02.13.06 BISAGRA ALUMINIZADA DE 2 1/2" x 2 1/2" PARA VENTANA pza 62.00 5.67 351.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.00 351.54 62.00 351.54 1.00
02.13.07 TOPE METALICO DE FIERRO PARA VENTANA pza 62.00 3.84 238.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.00 238.08 62.00 238.08 1.00
02.14 VIDRIOS, CRISTALES Y SIMILARES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.14.01 VIDRIOS SEMIDOBLES p2 339.17 3.65 1,237.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 339.17 1237.97 339.17 1237.97 1.00
02.15 PINTURA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.15.01 PINT. LATEX 2 MANOS EN MUROS EXTERIORES m2 160.04 4.65 744.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 160.04 744.19 160.04 744.19 1.00
02.15.02 PINT. LATEX 2 MANOS EN MUROS INTERIORES m2 285.76 4.65 1,328.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 285.76 1328.78 285.76 1328.78 1.00
02.15.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 134.17 6.18 829.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 134.17 829.17 134.17 829.17 1.00
02.15.04 PINTURA LATEX 2 MANOS EN COLUMNETAS m2 75.55 6.18 466.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 75.55 466.90 75.55 466.90 1.00
02.15.05 PINTURA LATEX 2 MANOS EN VIGAS m2 100.38 6.37 639.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.38 639.42 100.38 639.42 1.00
02.15.06 PINTURA BARNIZ EN PUERTAS m2 43.47 6.69 290.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 43.47 290.81 43.47 290.81 1.00
02.15.07 PINTURA BARNIZ EN VENTANA DE MADERA m2 63.04 6.69 421.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 63.04 421.74 63.04 421.74 1.00
02.16 VARIOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.16.01 JUNTA SISMICA DE 1" m 16.48 4.35 71.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.48 71.69 0.00 0.00 16.48 71.69 1.00
02.16.02 PIZARRA CEMENTO 3.00 x 1.20 m. SIN TICERO und 1.00 118.88 118.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 118.88 0.00 0.00 1.00 118.88 1.00
02.16.03 JUNTA DE DILATACION DE 1" EN VEREDA m 23.29 7.18 167.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.29 167.22 0.00 0.00 23.29 167.22 1.00
02.17 INSTALACIONES SANITARIAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.17.01 DESAGUE Y VENTILACION 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.17.01.01 SALIDA DE DESAGUE PVC SAL D=2" pto 4.00 40.26 161.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 161.04 0.00 0.00 4.00 161.04 1.00
02.17.01.02 SALIDA DE DESAGUE PVC SAL D=4" pto 1.00 51.85 51.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 51.85 0.00 0.00 1.00 51.85 1.00
02.17.01.03 SUMIDEROS DE 2" pza 1.00 31.84 31.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 31.84 0.00 0.00 1.00 31.84 1.00
02.17.01.04 SUMIDEROS DE 3" pza 1.00 36.79 36.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 36.79 0.00 0.00 1.00 36.79 1.00
02.17.01.05 REGISTRO DE BRONCE 2" pza 1.00 20.32 20.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 20.32 0.00 0.00 1.00 20.32 1.00
02.17.01.06 REGISTRO DE BRONCE 4" pza 1.00 30.22 30.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 30.22 0.00 0.00 1.00 30.22 1.00
02.17.02 REDES DE DISTRIBUCION 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.17.02.01 TUBERIA PVC -SAL 2" m 10.11 9.19 92.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.11 92.91 0.00 0.00 10.11 92.91 1.00
02.17.02.02 TUBERIA PVC -SAL 4" m 6.12 12.76 78.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.12 78.09 0.00 0.00 6.12 78.09 1.00
02.17.03 APARATOS Y ACCESORIOS SANITARIOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.17.03.01 INODORO TANQUE BAJO BLANCO pza 1.00 156.78 156.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 156.78 1.00 156.78 1.00
02.17.03.02 PAPELERA DE LOZA DE COLOR DE 15 X 15 cm pza 1.00 8.47 8.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 8.47 1.00 8.47 1.00
02.17.03.03 LAVATORIO DE PARED BLANCO 1 LLAVE pza 1.00 84.75 84.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 84.75 1.00 84.75 1.00
02.17.03.04 LAVADERO DE COCINA DE ACERO INOXIDABLE pza 2.00 127.12 254.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 254.24 2.00 254.24 1.00
02.17.03.05 CAJA DE REGISTRO 12"X24" C/TAPA DE CONCRETO pza 3.00 47.49 142.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 142.47 3.00 142.47 1.00
02.17.04 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.17.04.01 SALIDA DE AGUA FRIA PVC pto 4.00 25.65 102.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 102.60 0.00 0.00 4.00 102.60 1.00
02.17.04.02 TUBERIA PVC CLASE 10 - 3/4" m 26.00 5.06 131.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.00 131.56 0.00 0.00 26.00 131.56 1.00
02.17.04.03 TUBERIA PVC CLASE 10 - 1/2" m 42.00 4.63 194.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42.00 194.46 0.00 0.00 42.00 194.46 1.00
02.17.04.04 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza 1.00 35.90 35.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 35.90 0.00 0.00 1.00 35.90 1.00
02.17.04.05 VALVULAS DE COMPUERTA DE BRONCE DE 3/4" pza 1.00 48.60 48.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 48.60 0.00 0.00 1.00 48.60 1.00
02.17.05 SISTEMA DE DRENAJE PLUVIAL 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.17.05.01 TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS m 30.33 16.69 506.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.33 506.21 0.00 0.00 30.33 506.21 1.00
02.17.05.02 CANALETA DE FIERRO GALVANIZADO m 73.62 30.63 2,254.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 73.62 2254.98 0.00 0.00 73.62 2254.98 1.00
RESUMEN DE VALORIZACIONES MENSUALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD EJEC. : CONTRATA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL SISTEMA DE CONTRATO: : PRECIOS UNITARIOS
PROYECTO : 2224730 MEJOTRAMIENTO DEL SERVICIO EDUCACION INICIAL EN 04 I.E.I. DEL AMBITO DEL DISTRITO DE CHUNGUI - LA MAR – AYACUCHO PLAZO DE EJECUCIÓN: : 180 DIAS CALENDARIO
VALOR REFERENCIAL: S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL MONTO DE CONTRATO: S/. 892,171.04
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION FACTOR DE RELACIÓN: 1.00000

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO CONTRATISTA: : CONSORCIO TAWA


SUPERVISIÓN: : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) VALORIZ. N° 01 VALORIZ. N° 02 VALORIZ. N° 03 VALORIZ. N° 04 VALORIZ. N° 05 VALORIZ. N° 06 VALORIZ. N° 07 VALORIZ. N° 08 VALORIZ. N° 09 VALORIZ. N° 10 TOTAL VALORIZADO
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado %
02.17.05.03 ABRAZADERA DE FIJACION DE TUBO pza 70.00 7.06 494.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.00 494.20 0.00 0.00 70.00 494.20 1.00
02.17.05.04 COLECTOR DE ZINC GALVANIZADO und 6.00 7.04 42.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 42.24 0.00 0.00 6.00 42.24 1.00
02.17.05.05 ABRAZADERA DE FIJACION DE TUBERIA DE 3" pza 18.00 15.92 286.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.00 286.56 0.00 0.00 18.00 286.56 1.00
02.18 INSTALACIONES ELECTRICAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.18.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 22.00 48.42 1,065.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.00 1065.24 22.00 1065.24 1.00
02.18.02 SALIDA INTERRUPTOR SIMPLE pto 5.00 8.30 41.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.00 41.50 5.00 41.50 1.00
02.18.03 SALIDA INTERRUPTOR DOBLE pto 10.00 10.85 108.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 108.50 10.00 108.50 1.00
02.18.04 SALIDA TOMACORRIENTE DOBLE pto 20.00 55.14 1,102.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.00 1102.80 20.00 1102.80 1.00
02.19 TABLEROS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.19.01 TABLERO GENERAL TG und 1.00 371.03 371.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 371.03 1.00 371.03 1.00
02.19.02 TABLERO DE DISTRIBUCION TD-1 glb 1.00 419.31 419.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 419.31 1.00 419.31 1.00
02.19.03 TABLERO DE DISTRIBUCION TD-2 glb 1.00 357.53 357.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 357.53 1.00 357.53 1.00
02.20 ARTEFACTOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.20.01 ARTEFACTO FLUORESCENTE 2/18 W und 4.00 42.01 168.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 168.04 4.00 168.04 1.00
02.20.02 ARTEFACTO FLUORESCENTE 2/36 W und 8.00 78.45 627.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 627.60 8.00 627.60 1.00
02.20.03 ARTEFACTO FLUORESCENTE 4/36W und 10.00 35.23 352.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 352.30 10.00 352.30 1.00
02.21 POZO PUESTA A TIERRA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.21.01 POZO DE PUESTA A TIERRA und 1.00 402.90 402.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 402.90 1.00 402.90 1.00
03 TANQUE SEPTICO Y POZO PERCOLADOR 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01 TANQUE SEPTICO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.00 0.74 5.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 5.18 0.00 0.00 7.00 5.18 1.00
03.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 7.00 1.87 13.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 13.09 0.00 0.00 7.00 13.09 1.00
03.01.03 EXCAVACION DE ESTRUCTURAS m3 10.85 14.72 159.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.85 159.71 0.00 0.00 10.85 159.71 1.00
03.01.04 TERRAPLEN P/FALSO PISO C/PISON MANUAL, H=0.15 M m2 4.80 0.93 4.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.80 4.46 0.00 0.00 4.80 4.46 1.00
03.01.05 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 14.10 6.02 84.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.10 84.88 0.00 0.00 14.10 84.88 1.00
03.01.06 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 4.80 44.27 212.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.80 212.50 0.00 0.00 4.80 212.50 1.00
03.01.07 CONCRETO F'C=175 KG/CM2 EN TANQUE SUBTERRANEO m3 4.73 700.92 3,315.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.73 3315.35 0.00 0.00 4.73 3315.35 1.00
03.01.08 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 244.37 3.71 906.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 244.37 906.61 0.00 0.00 244.37 906.61 1.00
03.01.09 ENCOFRADO Y DESENCOFRADO EN TANQUE ENTERRADO m2 47.29 21.69 1,025.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 47.29 1025.72 0.00 0.00 47.29 1025.72 1.00
03.01.10 TARRAJEO CON IMPERMEABILIZANTE, MEZCLA E=1.5 CM m2 17.79 35.90 638.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.79 638.66 0.00 0.00 17.79 638.66 1.00
03.01.11 ACCESORIOS PVC SAL EN TANQUE SEPTICO und 1.00 34.97 34.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 34.97 0.00 0.00 1.00 34.97 1.00
03.01.12 TUBERIA PVC -SAL 4" m 7.00 32.67 228.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.00 228.69 0.00 0.00 7.00 228.69 1.00
03.01.13 CAJA DE REGISTRO DE DESAGUE 12"X24" und 1.00 58.23 58.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 58.23 0.00 0.00 1.00 58.23 1.00
03.02 POZA DE PERCOLACION 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02.01 LIMPIEZA DE TERRENO MANUAL m2 8.65 0.74 6.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.65 6.40 0.00 0.00 8.65 6.40 1.00
03.02.02 TRAZO Y REPLANTEO PRELIMINAR m2 8.65 1.87 16.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.65 16.18 0.00 0.00 8.65 16.18 1.00
03.02.03 EXCAVACION DE ESTRUCTURAS m3 17.74 14.72 261.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.74 261.13 0.00 0.00 17.74 261.13 1.00
03.02.04 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 23.06 6.02 138.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.06 138.82 0.00 0.00 23.06 138.82 1.00
03.02.05 CONCRETO F'C=175 KG/CM2 EN POZA DE PERCOLACION m3 1.03 700.92 721.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.03 721.95 0.00 0.00 1.03 721.95 1.00
03.02.06 ENCOFRADO Y DESENCOFRADO EN POZA DE PERCOLACION m2 9.96 21.00 209.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.96 209.16 0.00 0.00 9.96 209.16 1.00
03.02.07 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 42.42 3.71 157.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42.42 157.38 0.00 0.00 42.42 157.38 1.00
03.02.08 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 23.58 57.40 1,353.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.58 1353.49 0.00 0.00 23.58 1353.49 1.00
03.02.09 FILTRO DE GRAVAS O CASCAJO m3 0.38 101.69 38.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.38 38.64 0.00 0.00 0.38 38.64 1.00
03.02.10 CAJA DE REGISTRO DE DESAGUE 12"X24" und 1.00 58.23 58.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 58.23 0.00 0.00 1.00 58.23 1.00
03.02.11 TUBERIA PVC -SAL 4" m 64.00 32.67 2,090.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.00 2090.88 0.00 0.00 64.00 2090.88 1.00
04 CERCO PERIMETRICO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01 TRABAJOS PRELIMINARES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.01 LIMPIEZA DE TERRENO MANUAL m2 71.00 0.74 52.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71.00 52.54 0.00 0.00 71.00 52.54 1.00
04.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 78.00 1.87 145.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 78.00 145.86 0.00 0.00 78.00 145.86 1.00
04.02 MOVIMIENTO DE TIERRAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.01 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS CORRIDOS m3 14.71 14.44 212.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.71 212.41 0.00 0.00 14.71 212.41 1.00
04.02.02 EXCAVACION MANUAL DE ZAPATAS m3 4.50 14.72 66.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.50 66.24 0.00 0.00 4.50 66.24 1.00
04.02.03 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 12.26 0.74 9.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.26 9.07 0.00 0.00 12.26 9.07 1.00
04.02.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 2.76 9.02 24.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.76 24.90 0.00 0.00 2.76 24.90 1.00
04.02.05 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 21.39 6.02 128.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.39 128.77 0.00 0.00 21.39 128.77 1.00
04.03 CONCRETO SIMPLE 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 10.78 559.63 6,032.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.78 6032.81 0.00 0.00 10.78 6032.81 1.00
04.03.02 CONCRETO DE SOBRECIMIENTO C:H = 1:8 + 25% P.M. m3 2.25 559.11 1,258.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.25 1258.00 0.00 0.00 2.25 1258.00 1.00
04.03.03 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 30.04 19.61 589.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 30.04 589.08 0.00 0.00 30.04 589.08 1.00
04.03.04 SOLADO PARA ZAPATAS e=0.075 m. C:H, 1:12 m2 3.00 44.27 132.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 132.81 0.00 0.00 3.00 132.81 1.00
04.04 CONCRETO ARMADO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.01 VIGA DE CIMENTACION 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.01.01 CONCRETO fc'= 175 kg/cm2 PARA VIGA DE CIMENTACION m3 0.57 691.52 394.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.57 394.17 0.00 0.00 0.57 394.17 1.00
04.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGA DE CIMENTACION m2 9.12 25.25 230.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.12 230.28 0.00 0.00 9.12 230.28 1.00
04.04.01.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 68.61 3.71 254.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 68.61 254.54 0.00 0.00 68.61 254.54 1.00
04.04.02 ZAPATAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02.01 CONCRETO fc'= 210 kg/cm2 PARA ZAPATAS m3 1.50 776.93 1,165.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.50 1165.40 0.00 0.00 1.50 1165.40 1.00
04.04.02.02 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 52.07 3.71 193.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 52.07 193.18 0.00 0.00 52.07 193.18 1.00
04.04.03 COLUMNAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.03.01 CONCRETO fc'= 210 kg/cm2 DE COLUMNAS m3 3.32 812.05 2,696.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.32 2696.01 0.00 0.00 3.32 2696.01 1.00
04.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE COLUMNAS m2 29.64 30.13 893.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29.64 893.05 0.00 0.00 29.64 893.05 1.00
04.04.03.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 414.96 3.71 1,539.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 414.96 1539.50 0.00 0.00 414.96 1539.50 1.00
04.04.04 VIGAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.04.01 CONCRETO fc'= 210 kg/cm2 DE VIGAS m3 0.49 806.43 395.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.49 395.15 0.00 0.00 0.49 395.15 1.00
RESUMEN DE VALORIZACIONES MENSUALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD EJEC. : CONTRATA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL SISTEMA DE CONTRATO: : PRECIOS UNITARIOS
PROYECTO : 2224730 MEJOTRAMIENTO DEL SERVICIO EDUCACION INICIAL EN 04 I.E.I. DEL AMBITO DEL DISTRITO DE CHUNGUI - LA MAR – AYACUCHO PLAZO DE EJECUCIÓN: : 180 DIAS CALENDARIO
VALOR REFERENCIAL: S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL MONTO DE CONTRATO: S/. 892,171.04
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION FACTOR DE RELACIÓN: 1.00000

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO CONTRATISTA: : CONSORCIO TAWA


SUPERVISIÓN: : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) VALORIZ. N° 01 VALORIZ. N° 02 VALORIZ. N° 03 VALORIZ. N° 04 VALORIZ. N° 05 VALORIZ. N° 06 VALORIZ. N° 07 VALORIZ. N° 08 VALORIZ. N° 09 VALORIZ. N° 10 TOTAL VALORIZADO
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado %
04.04.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA DE VIGAS m2 5.28 36.32 191.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 191.77 0.00 0.00 5.28 191.77 1.00
04.04.04.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 59.10 3.71 219.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 59.10 219.26 0.00 0.00 59.10 219.26 1.00
04.04.05 VIGUETAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.05.01 CONCRETO fc'= 175 kg/cm2 DE VIGUETAS m3 0.06 724.97 43.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.06 43.50 0.00 0.00 0.06 43.50 1.00
04.04.05.02 ENCOFRADO Y DESENCOFRADO NORMAL DE VIGUETAS m2 0.77 28.18 21.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.77 21.70 0.00 0.00 0.77 21.70 1.00
04.04.05.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 6.42 3.71 23.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.42 23.82 0.00 0.00 6.42 23.82 1.00
04.04.06 LOSA ARMADA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.06.01 CONCRETO F'C=210 KG/CM2 EN LOSA ARMADA m3 1.32 806.43 1,064.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.32 1064.49 0.00 0.00 1.32 1064.49 1.00
04.04.06.02 ENCOFRADO Y DESENCOFRADO NORMAL DE LOSA ARMADA m2 11.37 32.77 372.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.37 372.59 0.00 0.00 11.37 372.59 1.00
04.04.06.03 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 48.43 3.71 179.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.43 179.68 0.00 0.00 48.43 179.68 1.00
04.05 ALBAÑILERIA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.05.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 10.61 57.40 609.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.61 609.01 0.00 0.00 10.61 609.01 1.00
04.06 PISOS Y PAVIMENTOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.06.01 AFIRMADO DE 4" PARA VEREDAS m2 12.26 24.65 302.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.26 302.21 0.00 0.00 12.26 302.21 1.00
04.06.02 VEREDA DE CONCRETO fc'= 140 kg/cm2, e= 0.15 m. + SARDINEL m2 12.26 107.22 1,314.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.26 1314.52 0.00 0.00 12.26 1314.52 1.00
04.06.03 ENCOFRADO Y DESENCOFRADO NORMAL DE VEREDA m2 0.31 7.80 2.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.31 2.42 0.00 0.00 0.31 2.42 1.00
04.07 PINTURA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.07.01 PINTURA LATEX 2 MANOS EN COLUMNAS m2 33.79 6.18 208.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33.79 208.82 33.79 208.82 1.00
04.07.02 PINTURA LATEX 2 MANOS EN VIGAS m2 5.28 6.37 33.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.28 33.63 5.28 33.63 1.00
04.07.03 PINTURA LATEX 2 MANOS EN VIGUETAS m2 0.77 6.37 4.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.77 4.90 0.77 4.90 1.00
04.08 CARPINTERIA METALICA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.08.01 PUERTA METALICA P1(3.75x3.20M) und 1.00 4,433.15 4,433.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 4433.15 0.00 0.00 1.00 4433.15 1.00
04.08.02 PUERTA METALICA P2(1.10x3.20M) und 1.00 2,708.42 2,708.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 2708.42 0.00 0.00 1.00 2708.42 1.00
04.08.03 MALLA METALICA COCADA 2'X2' H=2.20 M m 20.00 98.35 1,967.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.00 1967.00 0.00 0.00 20.00 1967.00 1.00
04.09 INSTALACIONES ELECTRICAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.09.01 SALIDA DE CENTRO DE ALUMBRADO EMPOTRADO pto 4.00 48.63 194.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 194.52 4.00 194.52 1.00
04.09.02 ARTEFACTO FLUORESCENTE 2/36 W und 4.00 78.45 313.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 313.80 4.00 313.80 1.00
04.10 VARIOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.10.01 JUNTA SISMICA DE 1" m 5.00 4.35 21.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.00 21.75 5.00 21.75 1.00
05 PATIO DE ENCUENTRO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01 TRABAJOS PRELIMINARES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.01 LIMPIEZA DE TERRENO MANUAL m2 190.00 0.74 140.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 190.00 140.60 0.00 0.00 190.00 140.60 1.00
05.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 190.00 2.82 535.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 190.00 535.80 0.00 0.00 190.00 535.80 1.00
05.02 MOVIMIENTO DE TIERRAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.01 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 180.59 1.44 260.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 180.59 260.05 0.00 0.00 180.59 260.05 1.00
05.02.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 234.77 6.02 1,413.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 234.77 1413.32 0.00 0.00 234.77 1413.32 1.00
05.03 SEMBRADO DE AREAS VERDES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.01 PREPARACION DE TIERRA DE CHACRA m2 180.56 10.02 1,809.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 180.56 1809.21 0.00 0.00 180.56 1809.21 1.00
05.03.02 SEMBRADO DE GRASS AMERICANO m2 180.56 3.21 579.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 180.56 579.60 0.00 0.00 180.56 579.60 1.00
06 BEBEDERO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01 MOVIMIENTO DE TIERRAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.05 14.72 0.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 0.74 0.00 0.00 0.05 0.74 1.00
06.01.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 0.07 6.02 0.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07 0.42 0.00 0.00 0.07 0.42 1.00
06.02 OBRAS DE CONCRETO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01 CIMIENTO CORRIDO C:H = 1:10 + 30% P.G. m3 0.05 559.63 27.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.05 27.98 0.00 0.00 0.05 27.98 1.00
06.02.02 CONCRETO F'C=175 KG/CM2 EN BEBEDERO m3 0.27 700.92 189.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.27 189.25 0.00 0.00 0.27 189.25 1.00
06.02.03 ENCOFRADO Y DESENCOFRADO EN BEBEDEROS m2 2.97 25.25 74.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.97 74.99 0.00 0.00 2.97 74.99 1.00
06.02.04 ACERO Fy= 4,200 kg/cm2, GRADO 60 kg 8.85 3.71 32.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.85 32.83 0.00 0.00 8.85 32.83 1.00
06.03 ALBAÑILERIA 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.01 MURO DE LADRILLO KK DE ARCILLA DE SOGA MEZCLA 1:4 m2 0.31 57.40 17.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.31 17.79 0.00 0.00 0.31 17.79 1.00
06.04 REVOQUES, ENLUCIDOS Y DERRAMES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.04.01 TARRAJEO PRIMARIO MORTERO 1:5 m2 3.88 15.70 60.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.88 60.92 0.00 0.00 3.88 60.92 1.00
06.04.02 ZOCALO DE MAYOLICA BLANCA 20 X 20 CM. m2 3.57 46.22 165.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.57 165.01 0.00 0.00 3.57 165.01 1.00
06.05 SUMINISTRO E INSTALACION DE ACCESORIOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.05.01 ACCESORIOS EN BEBEDERO und 1.00 115.87 115.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 115.87 0.00 0.00 1.00 115.87 1.00
07 URINARIO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01 MOVIMIENTO DE TIERRAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 0.04 14.72 0.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.59 0.00 0.00 0.04 0.59 1.00
07.01.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 0.06 6.02 0.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.06 0.36 0.00 0.00 0.06 0.36 1.00
07.02 OBRAS DE CONCRETO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.01 CONCRETO CICLOPEO F'C=140 KG/CM2 EN URINARIO m3 0.09 667.03 60.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.09 60.03 0.00 0.00 0.09 60.03 1.00
07.02.02 ENCOFRADO Y DESENCOFRADO EN BEBEDEROS m2 0.86 25.25 21.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.86 21.72 0.00 0.00 0.86 21.72 1.00
07.03 REVOQUES, ENLUCIDOS Y DERRAMES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.03.01 TARRAJEO PRIMARIO MORTERO 1:5 m2 0.92 15.70 14.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.92 14.44 0.00 0.00 0.92 14.44 1.00
07.03.02 ZOCALO DE MAYOLICA BLANCA 20 X 20 CM. m2 1.28 46.22 59.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.28 59.16 0.00 0.00 1.28 59.16 1.00
07.04 SUMINISTRO E INSTALACION DE ACCESORIOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.04.01 ACCESORIOS SANITARIOS EN URINARIO und 2.00 71.05 142.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 142.10 0.00 0.00 2.00 142.10 1.00
08 JUEGOS INFANTILES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01 TRABAJOS PRELIMINARES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 90.00 0.74 66.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 90.00 66.60 0.00 0.00 90.00 66.60 1.00
08.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 90.00 2.82 253.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 90.00 253.80 0.00 0.00 90.00 253.80 1.00
08.02 MOVIMIENTO DE TIERRAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.01 CORTE SUPERFICIAL MANUAL, e=0.10 m. m2 85.49 1.44 123.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 85.49 123.11 0.00 0.00 85.49 123.11 1.00
08.02.02 EXCAVACION MANUAL EN TERRENO NORMAL m3 2.60 14.72 38.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.60 38.27 0.00 0.00 2.60 38.27 1.00
RESUMEN DE VALORIZACIONES MENSUALES EJECUTADOS
REFERENCIA : A.D.S. N° 012-2014-MDCH-LM/CEP
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE CHUNGUI
FUNCION : 22 EDUCACION
DIVISION FUNCIONAL : 047 EDUCACION BASICA MODALIDAD EJEC. : CONTRATA
GRUPO FUNCIONAL : 0103 EDUCACION INICIAL SISTEMA DE CONTRATO: : PRECIOS UNITARIOS
PROYECTO : 2224730 MEJOTRAMIENTO DEL SERVICIO EDUCACION INICIAL EN 04 I.E.I. DEL AMBITO DEL DISTRITO DE CHUNGUI - LA MAR – AYACUCHO PLAZO DE EJECUCIÓN: : 180 DIAS CALENDARIO
VALOR REFERENCIAL: S/. 892,171.04
ACTIVIDAD/OBRA : 4000017 INSTALACION DE INFRAESTRUCTURA DE EDUCACION INICIAL MONTO DE CONTRATO: S/. 892,171.04
META : 0036 MEJORAMIENTO DE LA CALIDAD DE EDUCACION FACTOR DE RELACIÓN: 1.00000

UBICACIÓN : QARIN-CHUNGUI-LA MAR-AYACUCHO CONTRATISTA: : CONSORCIO TAWA


SUPERVISIÓN: : ING. SERGIO EDUARDO AVALOS ANCCO

PRESUPUESTO (Valor referencial) VALORIZ. N° 01 VALORIZ. N° 02 VALORIZ. N° 03 VALORIZ. N° 04 VALORIZ. N° 05 VALORIZ. N° 06 VALORIZ. N° 07 VALORIZ. N° 08 VALORIZ. N° 09 VALORIZ. N° 10 TOTAL VALORIZADO
ITEM DESCRIPCIÓN DE PARTIDA
Und. Metrado P. Unit. P. Parcial Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado Metrado Valorizado %
08.02.03 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m. m3 14.49 6.02 87.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.49 87.23 0.00 0.00 14.49 87.23 1.00
08.03 OBRAS DE CONCRETO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.01 CONCRETO F'C=140 KG/CM2 EN SARDINELES m3 2.97 667.03 1,981.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.97 1981.08 0.00 0.00 2.97 1981.08 1.00
08.03.02 ENCOFRADO Y DESENCOFRADO EN SARDINELES m2 26.19 31.65 828.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.19 828.91 0.00 0.00 26.19 828.91 1.00
08.03.03 JUNTAS ASFALTICAS m 4.40 7.13 31.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.40 31.37 0.00 0.00 4.40 31.37 1.00
08.04 VARIOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.01 COLOCACION DE ARENA FINA e=0.10 M m2 85.49 31.66 2,706.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 85.49 2706.61 0.00 0.00 85.49 2706.61 1.00
08.04.02 COLUMPIO und 1.00 847.46 847.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 847.46 0.00 0.00 1.00 847.46 1.00
08.04.03 TOBOGAN und 1.00 762.71 762.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 762.71 0.00 0.00 1.00 762.71 1.00
08.04.04 BALANCIN und 1.00 847.46 847.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 847.46 0.00 0.00 1.00 847.46 1.00
09 EQUIPAMIENTO Y MOBILIARIO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01 EQUIPAMIENTO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01.01 TELEVISOR und 2.00 1,016.95 2,033.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 2033.90 2.00 2033.90 1.00
09.01.02 REPRODUCTOR BLU RAY und 2.00 322.03 644.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 644.06 2.00 644.06 1.00
09.02 MOBILIARIO 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.01 AULAS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.01.01 MOBILIARIO PARA DOCENTES und 2.00 423.73 847.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 847.46 2.00 847.46 1.00
09.02.01.02 ESTANTE DE MADERA und 2.00 211.86 423.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 423.72 2.00 423.72 1.00
09.02.01.03 MUEBLE MOVIL PARA TV Y EQUIPO DE SONIDO und 2.00 169.49 338.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 338.98 2.00 338.98 1.00
09.02.02 AMBIENTES COMPLEMENTARIOS 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.02.02.01 MOBILIARIO PARA COMEDOR DE NINOS und 5.00 379.64 1,898.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.00 1898.20 5.00 1898.20 1.00
09.02.02.02 MOBILIARIO PARA DIRECCION und 1.00 788.13 788.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 788.13 1.00 788.13 1.00
09.02.02.03 MOBILIARIO PARA TOPICO und 1.00 974.57 974.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 974.57 1.00 974.57 1.00
10 CAPACITACION DE DOCENTES 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01 CAPACITACIONES glb 1.00 847.46 847.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 847.46 1.00 847.46 1.00
11 FLETE 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01 FLETE TERRESTRE 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.01.01 FLETE glb 1.00 37,630.56 37,630.56 0.16 5924.68 0.17 6548.99 0.32 12001.46 0.29 10759.46 0.03 962.49 0.11 4308.70 0.00 0.00 0.00 0.00 0.00 -0.08 -2875.22 1.00 37630.56 1.00
11.02 FLETE RURAL 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11.02.01 ACARREO DE MATERIALES glb 1.00 44,581.44 44,581.44 0.10 4244.04 0.12 5249.28 0.24 10908.00 0.17 7356.00 0.28 12457.32 0.35 15576.00 0.00 0.00 0.00 0.00 0.00 -0.25 -11209.19 1.00 44581.44 1.00

COSTO DIRECTO (CD) S/. 660,329.39 S/. 24,567.79 S/. 55,822.65 S/. 58,679.00 S/. 61,661.20 S/. 63,910.32 S/. 33,325.06 S/. 22,365.12 S/. 9,476.66 S/. 222,124.93 S/. 108,396.69 S/. 660,329.39 ###
GASTOS GENERALES (8.50% CD) 56,128.00 2,088.26 4,744.93 4,987.71 5,241.20 5,432.38 2,832.63 1,901.04 805.52 18,880.62 9,213.72 56,128.00 ###
UTILIDAD (6% CD) 39,619.76 1,474.07 3,349.36 3,520.74 3,699.67 3,834.62 1,999.50 1,341.91 568.60 13,327.50 6,503.80 39,619.76 ###
SUB TOTAL 756,077.15 28,130.12 63,916.93 67,187.45 70,602.07 73,177.32 38,157.19 25,608.06 10,850.77 254,333.05 124,114.21 756,077.15 ###
VALORIZACIÓN CONTRACTUAL = SUB TOTAL x FR (1.00000) S/. 756,077.15 S/. 28,130.12 S/. 63,916.93 S/. 67,187.45 S/. 70,602.07 S/. 73,177.32 S/. 38,157.19 S/. 25,608.06 S/. 10,850.77 S/. 254,333.05 S/. 124,114.21 S/. 756,077.15 ###
IGV (18%) 136,093.89 5,063.42 11,505.05 12,093.74 12,708.37 13,171.92 6,868.29 4,609.45 1,953.14 45,779.95 22,340.56 136,093.89 ###
TOTAL VALORIZADO S/. 892,171.04 S/. 33,193.54 S/. 75,421.98 S/. 79,281.20 S/. 83,310.43 S/. 86,349.24 S/. 45,025.48 S/. 30,217.51 S/. 12,803.91 S/. 300,113.00 S/. 146,454.77 S/. 892,171.04 ###
% DE AVANCE MENSUAL 3.72% 8.45% 8.89% 9.34% 9.68% 5.05% 3.39% 1.44% 33.64% 16.42% 100.00%
% DE AVANCE ACUMULADO 3.72% 12.17% 21.06% 30.40% 40.08% 45.12% 48.51% 49.95% 83.58% 100.00% 100.00%
RESUMEN DE PRESUPUESTO
PROYECTO : “INSTALCION DE LOS SERVICIOS EDUCATIVOS EN LA I.E.I. N° 421-Mx/P, EN LA COMUNIDAD DE QARIN, DISTRITO DE CHUNGUI - LA
MAR – AYACUCHO”

UBICACION : QARIN - CHUNGUI - LA MAR - AYACUCHO


ENTIDAD EJEC. : MUNICIPALIDAD PROVINCIAL DE CHUNGUI

ITEM DESCRIPCIÓN COSTO DIRECTO

001 AULAS 226,919.16


002 AREA COMPLEMENTARIA 285,719.32
003 TANQUE SEPTICO Y POZO PERCOLADOR 11,740.31
004 CERCO PERIMETRICO 30,644.73
005 PATIO DE ENCUENTRO 4,738.58
006 BEBEDERO 685.80
007 URINARIO 298.40
008 JUEGOS INFANTILES 8,574.61
009 EQUIPAMIENTO Y MOBILIARIO 7,949.02
010 CAPACITACION DE DOCENTES 847.46
011 FLETE 82,212.00

COSTO DIRECTO S/. 660,329.39


GASTOS GENERALES (8.50%) S/. 56,128.00
UTILIDAD (6.00%) S/. 39,619.76
SUB TOTAL S/. 756,077.15
I.G.V. 18.00% S/. 136,093.89
PRESUPUESTO TOTAL S/. 892,171.04
CALENDARIO DE AVANCE DE OBRA PROGRAMADO

MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 TOTAL
PART DESCRIPCION PARCIAL
12 AL 30/06/14 01 AL 31/07/14 01 AL 30/08/14 1 AL 30/09/14 1 AL 31/10/14 1 AL 30/11/14 1 AL 31/12/14 1 AL 31/01/15 1 AL 28/02/15 1 AL 08/03/15
01 OBRAS PROVISIONALES 19,033.77 4,523.64 2,618.95 0.00 0.00 4,130.93 2,272.01 0.00 3,717.84 1,770.40 0.00 19,033.77
02 TRABAJOS PRELIMINARES 108,865.16 23,218.12 46,624.09 20,325.39 3,178.62 3,119.18 3,071.25 2,896.61 2,796.52 2,659.20 976.17 108,865.16
03 MOVIMIENTO DE TIERRAS (0+000.00 - 28+500) 1,297,913.07 50,096.42 80,035.20 79,099.61 159,072.31 209,296.15 202,509.07 195,748.70 193,666.27 104,847.78 23,541.55 1,297,913.07
04 SUPERFICIE DE RODADURA - PAVIMENTO E=0.15M 575,853.43 0.00 0.00 0.00 0.00 37,151.83 58,823.74 97,213.97 193,189.54 148,341.97 41,132.39 575,853.43
05 OBRAS DE ARTE Y ESTRUCTURAS DE DRENAJE 847,699.55 0.00 0.00 36,458.83 80,232.85 122,397.17 305,286.24 219,136.71 67,045.12 15,087.59 2,055.05 847,699.55
06 SEÑALIZACION VERTICAL 56,832.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,006.96 35,586.19 19,239.16 56,832.32
07 MITIGACION AMBIENTAL 59,824.67 0.00 0.00 0.00 0.00 0.00 5,564.90 4,476.00 806.45 31,485.42 17,491.90 59,824.67
08 PRUEBAS, ENSAYOS Y CONTROL DE CALIDAD 10,661.96 0.00 452.54 434.37 284.08 1,390.64 2,034.94 2,013.52 1,797.36 1,645.70 608.79 10,661.96
09 CAPACITACION DE LOS COMITÉS DE MANTENIMIENTO Y SENSIBILIZACION SOCIAL 3,700.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,378.57 1,321.43 3,700.00
10 OTROS 2,898.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,863.12 1,035.07 2,898.19
11 FLETE 129,920.38 0.00 14,319.81 34,416.24 28,654.47 15,298.33 11,336.52 11,217.19 11,097.86 3,579.95 0.00 129,920.38

COSTO DIRECTO 3,113,202.50 77,838.18 144,050.60 170,734.44 271,422.34 392,784.24 590,898.67 532,702.71 476,123.91 349,245.91 107,401.51 3,113,202.50
GASTOS GENERALES (8.50 %) 264,622.21 5,826.07 10,781.96 12,779.20 20,315.54 29,399.28 44,227.84 39,871.96 35,637.13 26,140.51 8,038.83 233,018.32
UTILIDAD (6 %) 186,792.15 3,891.91 7,202.53 8,536.72 13,571.12 19,639.21 29,544.93 26,635.14 23,806.20 17,462.30 5,370.08 155,660.13
SUB TOTAL 3,564,616.86 87,556.15 162,035.09 192,050.37 305,308.99 441,822.74 664,671.45 599,209.80 535,567.23 392,848.71 120,810.42 3,501,880.95
FACTOR DE RELACION 1.00 3,564,616.86 87,556.15 162,035.09 192,050.37 305,308.99 441,822.74 664,671.45 599,209.80 535,567.23 392,848.71 120,810.42 3,501,880.95
IGV (18%) 641,631.04 15,760.11 29,166.32 34,569.07 54,955.62 79,528.09 119,640.86 107,857.76 96,402.10 70,712.77 21,745.88 630,338.57
VALOR REFERENCIAL CONTRATO 4,206,247.90 103,316.26 191,201.41 226,619.43 360,264.61 521,350.83 784,312.31 707,067.57 631,969.33 463,561.48 142,556.29 4,132,219.52

TOTAL PRESUPUESTO 4,206,247.90 103,316.26 191,201.41 226,619.43 360,264.61 521,350.83 784,312.31 707,067.57 631,969.33 463,561.48 142,556.29 4,132,219.52
DESEMBOLSO MENSUAL ACUMULADO DEL PROYECTO 103,316.26 294,517.67 521,137.10 881,401.71 1,402,752.54 2,187,064.85 2,894,132.41 3,526,101.74 3,989,663.22 4,132,219.52
PORCENTAJE MENSUAL 2.46% 4.55% 5.39% 8.56% 12.39% 18.65% 16.81% 15.02% 11.02% 3.39% 98.24%
PORCENTAJE MENSUAL ACUMULADO 2.46% 7.00% 12.39% 20.95% 33.35% 52.00% 68.81% 83.83% 94.85% 98.24%
CALENDARIO DE AVANCE DE OBRA PROGRAMADO

MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 TOTAL
PART DESCRIPCION PARCIAL
12 AL 30/06/14 01 AL 31/07/14 01 AL 30/08/14 1 AL 30/09/14 1 AL 31/10/14 1 AL 30/11/14 1 AL 31/12/14 1 AL 31/01/15 1 AL 28/02/15 1 AL 08/03/15
01 OBRAS PROVISIONALES 19,033.77 4,523.64 2,618.95 0.00 0.00 4,130.93 2,272.01 0.00 3,717.84 1,770.40 0.00 19,033.77
02 TRABAJOS PRELIMINARES 108,865.16 23,218.12 46,624.09 20,325.39 3,178.62 3,119.18 3,071.25 2,896.61 2,796.52 2,659.20 976.17 108,865.16
03 MOVIMIENTO DE TIERRAS (0+000.00 - 28+500) 1,297,913.07 50,096.42 80,035.20 79,099.61 159,072.31 209,296.15 202,509.07 195,748.70 193,666.27 104,847.78 23,541.55 1,297,913.07
04 SUPERFICIE DE RODADURA - PAVIMENTO E=0.15M 575,853.43 0.00 0.00 0.00 0.00 37,151.83 58,823.74 97,213.97 193,189.54 148,341.97 41,132.39 575,853.43
05 OBRAS DE ARTE Y ESTRUCTURAS DE DRENAJE 847,699.55 0.00 0.00 36,458.83 80,232.85 122,397.17 305,286.24 219,136.71 67,045.12 15,087.59 2,055.05 847,699.55
06 SEÑALIZACION VERTICAL 56,832.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,006.96 35,586.19 19,239.16 56,832.32
07 MITIGACION AMBIENTAL 59,824.67 0.00 0.00 0.00 0.00 0.00 5,564.90 4,476.00 806.45 31,485.42 17,491.90 59,824.67
08 PRUEBAS, ENSAYOS Y CONTROL DE CALIDAD 10,661.96 0.00 452.54 434.37 284.08 1,390.64 2,034.94 2,013.52 1,797.36 1,645.70 608.79 10,661.96
09 CAPACITACION DE LOS COMITÉS DE MANTENIMIENTO Y SENSIBILIZACION SOCIAL 3,700.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2,378.57 1,321.43 3,700.00
10 OTROS 2,898.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,863.12 1,035.07 2,898.19
11 FLETE 129,920.38 0.00 14,319.81 34,416.24 28,654.47 15,298.33 11,336.52 11,217.19 11,097.86 3,579.95 0.00 129,920.38

COSTO DIRECTO 3,113,202.50 77,838.18 144,050.60 170,734.44 271,422.34 392,784.24 590,898.67 532,702.71 476,123.91 349,245.91 107,401.51 3,113,202.50
GASTOS GENERALES (8.50 %) 264,622.21 5,826.07 10,781.96 12,779.20 20,315.54 29,399.28 44,227.84 39,871.96 35,637.13 26,140.51 8,038.83 233,018.32
UTILIDAD (6 %) 186,792.15 3,891.91 7,202.53 8,536.72 13,571.12 19,639.21 29,544.93 26,635.14 23,806.20 17,462.30 5,370.08 155,660.13
SUB TOTAL 3,564,616.86 87,556.15 162,035.09 192,050.37 305,308.99 441,822.74 664,671.45 599,209.80 535,567.23 392,848.71 120,810.42 3,501,880.95
FACTOR DE RELACION 1.00 3,564,616.86 87,556.15 162,035.09 192,050.37 305,308.99 441,822.74 664,671.45 599,209.80 535,567.23 392,848.71 120,810.42 3,501,880.95
IGV (18%) 641,631.04 15,760.11 29,166.32 34,569.07 54,955.62 79,528.09 119,640.86 107,857.76 96,402.10 70,712.77 21,745.88 630,338.57
VALOR REFERENCIAL CONTRATO 4,206,247.90 103,316.26 191,201.41 226,619.43 360,264.61 521,350.83 784,312.31 707,067.57 631,969.33 463,561.48 142,556.29 4,132,219.52

TOTAL PRESUPUESTO 4,206,247.90 103,316.26 191,201.41 226,619.43 360,264.61 521,350.83 784,312.31 707,067.57 631,969.33 463,561.48 142,556.29 4,132,219.52
DESEMBOLSO MENSUAL ACUMULADO DEL PROYECTO 103,316.26 294,517.67 521,137.10 881,401.71 1,402,752.54 2,187,064.85 2,894,132.41 3,526,101.74 3,989,663.22 4,132,219.52
PORCENTAJE MENSUAL 2.46% 4.55% 5.39% 8.56% 12.39% 18.65% 16.81% 15.02% 11.02% 3.39% 98.24%
PORCENTAJE MENSUAL ACUMULADO 2.46% 7.00% 12.39% 20.95% 33.35% 52.00% 68.81% 83.83% 94.85% 98.24%