Cronograma Financiero F. 20201104 192848 166
Cronograma Financiero F. 20201104 192848 166
Obra: MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD PEATONAL EN LA 2DA CUADRA DE LA CALLE ROSARIO,DELDISTRITO DE GROCIO PRADO - PROVINCIA DE CHINCHA - DEPARTAMENTO DE ICA
Fecha Ago-20
1.01.01 CARTEL DE OBRA DE 3.60X2.40M und 1.00 800.00 800.00 1.00 S/.800.00 100.00% 0.00 S/.0.00 0.00%
1.01.02 ALMACEN Y GUARDIANIA mes 1.00 1,200.00 1,200.00 1.00 S/.1,200.00 100.00% 0.00 S/.0.00 0.00%
1.02.01 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS Y EQUIPOS Glb 1.00 2,500.00 2,500.00 1.00 S/.2,500.00 100.00% 0.00 S/.0.00 0.00%
1.03 DEMOLICIONES
1.03.01 DEMOLICION DE VEREDA EXISTENTE m3 32.19 111.99 3,604.96 32.19 S/.3,604.96 100.00% 0.00 S/.0.00 0.00%
1.03.02 ELIMINACION DE MATERIAL EXCEDENTE m3 45.06 21.88 985.91 45.06 S/.985.91 100.00% 0.00 S/.0.00 0.00%
2.01 EQUIPOS DE DE PROTECCION INDIVIDUAL und 10.00 350.00 3,500.00 5.00 S/.1,750.00 50.00% 5.00 S/.1,750.00 50.00%
2.02 EQUIPOS DE DE PROTECCION COLECTIVA und 1.00 3,000.00 3,000.00 1.00 S/.3,000.00 100.00% 0.00 S/.0.00 0.00%
2.03 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 2,500.00 2,500.00 1.00 S/.2,500.00 100.00% 0.00 S/.0.00 0.00%
2.04 RECURSOS PARA RESPUESTAS ANTE EMERGENCIA EN SEGURIDAD Y SALUD und 1.00 620.00 620.00 1.00 S/.620.00 100.00% 0.00 S/.0.00 0.00%
3 CONSTRUCCION DE VEREDA
3.01.01 LIMPIEZA DE TERRENO m2 629.86 1.49 938.49 629.86 S/.938.49 100.00% 0.00 S/.0.00 0.00%
3.01.02 TRAZO NIVELADO Y REPLANTEO m2 629.86 1.69 1,064.46 629.86 S/.1,064.46 100.00% 0.00 S/.0.00 0.00%
3.01.03 TRAZO NIVELADO Y REPLANTEO DURANTE EL PROCESO m2 629.86 1.69 1,064.46 629.86 S/.1,064.46 100.00%
3.01.04 NIVELACION DE CONEXIONES DOMICILIARIAS - AGUA und 12.00 162.97 1,955.64 12.00 S/.1,955.64 100.00% 0.00 S/.0.00 0.00%
3.01.05 NIVELACION DE CONEXIONES DOMICILIARIAS - DESAGUE und 11.00 162.97 1,792.67 11.00 S/.1,792.67 100.00% 0.00 S/.0.00 0.00%
3.02.01 CORTE MANUAL DE TERRENO m3 69.28 29.33 2,031.98 69.28 S/.2,031.98 100.00% 0.00 S/.0.00 0.00%
3.02.02 REFINE, NIVELACION Y COMPACTACION DE SUBRASANTE m2 629.86 4.21 2,651.71 629.86 S/.2,651.71 100.00% 0.00 S/.0.00 0.00%
3.02.03 BASE GRANULAR DE 0.10M m2 629.86 14.15 8,912.52 629.86 S/.8,912.52 100.00% 0.00 S/.0.00 0.00%
3.02.04 ACARREO DE MATERIAL EXCEDENTE A ZONA DE ELIMINACION m3 90.07 21.88 1,970.73 90.07 S/.1,970.73 100.00% 0.00 S/.0.00 0.00%
3.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=0.50KM m3 90.07 21.88 1,970.73 90.07 S/.1,970.73 100.00% 0.00 S/.0.00 0.00%
03.03.01 CONCRETO EN VEREDAS FC=175 KG/CM2 m2 629.86 56.26 35,435.92 629.86 S/.35,435.92 100.00% 0.00 S/.0.00 0.00%
03.03.02 ENCOFRADO Y DESENCOFRADO m2 139.59 42.79 5,973.06 139.59 S/.5,973.06 100.00% 0.00 S/.0.00 0.00%
3.04 VARIOS
03.04.01 JUNTAS ASFALTICAS m 130.80 6.90 902.52 130.80 S/.902.52 100.00% 0.00 S/.0.00 0.00%
03.04.02 BRUÑADO m 311.52 2.53 788.15 311.52 S/.788.15 100.00% 0.00 S/.0.00 0.00%
4 CONSTRUCCION DE RAMPA
4.01.01 LIMPIEZA DE TERRENO m2 34.80 1.49 51.85 34.80 S/.51.85 100.00% 0.00 S/.0.00 0.00%
4.01.02 TRAZO NIVELADO Y REPLANTEO m2 34.80 1.69 58.81 34.80 S/.58.81 100.00% 0.00 S/.0.00 0.00%
4.02.01 CORTE MANUAL DE TERRENO m3 4.26 29.33 124.95 4.26 S/.124.95 100.00% 0.00 S/.0.00 0.00%
4.02.02 REFINE, NIVELACION Y COMPACTACION DE SUBRASANTE m2 34.80 4.21 146.51 34.80 S/.146.51 100.00% 0.00 S/.0.00 0.00%
4.02.03 BASE GRANULAR DE 0.10M m2 34.80 14.15 492.42 34.80 S/.492.42 100.00% 0.00 S/.0.00 0.00%
4.02.04 ACARREO DE MATERIAL EXCEDENTE A ZONA DE ELIMINACION m3 6.38 21.88 139.59 6.38 S/.139.59 100.00% 0.00 S/.0.00 0.00%
4.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=0.50KM m3 10.21 21.88 223.39 10.21 S/.223.39 100.00% 0.00 S/.0.00 0.00%
4.03.01 CONCRETO EN RAMPAS FC=175 KG/CM2 m3 34.80 368.03 12,807.44 34.80 S/.12,807.44 100.00% 0.00 S/.0.00 0.00%
4.03.02 ENCOFRADO Y DESENCOFRADO m2 21.04 42.79 900.30 21.04 S/.900.30 100.00% 0.00 S/.0.00 0.00%
4.04 VARIOS
04.04.01 JUNTAS ASFALTICAS m 105.20 6.90 725.88 105.20 S/.725.88 100.00% 0.00 S/.0.00 0.00%
04.04.02 BRUÑADO m 60.00 2.53 151.80 60.00 S/.151.80 100.00% 0.00 S/.0.00 0.00%
4.05 PINTURA
5.05.01 PINTURA PARA RAMPA m 105.20 3.47 365.04 105.20 S/.365.04 100.00% 0.00 S/.0.00 0.00%
Página 1
CALENDARIO DE AVANCE DE OBRA VALORIZADO
Obra: MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD PEATONAL EN LA 2DA CUADRA DE LA CALLE ROSARIO,DELDISTRITO DE GROCIO PRADO - PROVINCIA DE CHINCHA - DEPARTAMENTO DE ICA
Fecha Ago-20
05.01.01 LIMPIEZA DE TERRENO m2 223.47 1.49 332.97 0.00 S/.0.00 0.00% 223.47 S/.332.97 100.00%
05.01.02 TRAZO NIVELADO Y REPLANTEO - SARDINELES m 558.68 1.69 944.17 0.00 S/.0.00 0.00% 558.68 S/.944.17 100.00%
05.01.03 TRAZO NIVELADO Y REPLANTEO DURANTE EL PROCESO - SARDINELES m 558.68 1.69 944.17 0.00 S/.0.00 0.00% 558.68 S/.944.17 100.00%
06.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 29.33 33.23 974.64 0.00 S/.0.00 0.00% 29.33 S/.974.64 100.00%
06.02.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=0.5KM m3 38.13 21.88 834.28 0.00 S/.0.00 0.00% 38.13 S/.834.28 100.00%
05.03.01 CONCRETO PARA SARDINEL f'c=175kg/cm2 m3 29.33 368.03 10,794.32 0.00 S/.0.00 0.00% 29.33 S/.10,794.32 100.00%
05.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 46.59 53.90 2,511.20 0.00 S/.0.00 0.00% 46.59 S/.2,511.20 100.00%
05.03.03 ACERO F'Y=4200 kg/cm2 kg 770.64 5.27 4,061.27 0.00 S/.0.00 0.00% 770.64 S/.4,061.27 100.00%
5.04 JUNTAS
05.04.01 JUNTAS ASFALTICAS CADA 3M ml 27.75 6.90 191.48 0.00 S/.0.00 0.00% 27.75 S/.191.48 100.00%
5.05 PINTURA
05.05.01 PINTURA EN SARDINEL ml 558.68 3.47 1,938.62 0.00 S/.0.00 0.00% 558.68 S/.1,938.62 100.00%
06 MOBILIARIO URBANO
06.01 SUMINISTRO E INSTALACION DE DE TACHOS DE BASURA und 6.00 525.05 3,150.30 0.00 S/.0.00 0.00% 6.00 S/.3,150.30 100.00%
07.01 AGUA
07.01.01 REPOSICION DE MARCOS Y TAPAS DE AGUA und 12.00 52.91 634.92 0.00 S/.0.00 0.00% 12.00 S/.634.92 100.00%
07.02 DESAGUE
07.02.01 REPOSICION DE MARCOS Y TAPAS DE DESAGUE und 11.00 73.01 803.11 0.00 S/.0.00 0.00% 11.00 S/.803.11 100.00%
08 AREAS VERDES
08.01 LIMPIEZA DE TERRENO m2 278.81 1.49 415.43 0.00 S/.0.00 0.00% 278.81 S/.415.43 100.00%
08.02 CORTE DE MATERIAL SUELTO EN JARDINERAS m3 41.82 29.33 1,226.58 0.00 S/.0.00 0.00% 41.82 S/.1,226.58 100.00%
08.03 PREPRACION DE TIERRA DE CHACRA m2 278.81 7.05 1,965.61 0.00 S/.0.00 0.00% 278.81 S/.1,965.61 100.00%
08.04 SEMBRADO DE GRASS -8inc/suministro y colocacion) m2 278.81 25.88 7,215.60 0.00 S/.0.00 0.00% 278.81 S/.7,215.60 100.00%
08.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D=0.5KM m3 54.37 21.88 1,189.62 0.00 S/.0.00 0.00% 54.37 S/.1,189.62 100.00%
09.01 ELABORACION DEL PLAN PARA VIGILANCIA, PREVENCION Y CONTROL DEL COVID-19 glb 1.00 3,500.00 3,500.00 1.00 S/.3,500.00 100.00% 0.00 S/.0.00 0.00%
09.02 LIMPIEZA Y DESINFECCION DE OBRA mes 1.00 1,294.90 1,294.90 0.50 S/.647.45 50.00% 0.50 S/.647.45 50.00%
09.03 EVALUACION DE LA CONDICION DE SALUD DEL TRABAJADOR und 1.00 1,416.90 1,416.90 1.00 S/.1,416.90 100.00% 0.00 S/.0.00 0.00%
09.04 LAVADO Y DESINFECCION DE MANOS (OBLIGATORIO) mes 1.00 1,161.00 1,161.00 0.50 S/.580.50 50.00% 0.50 S/.580.50 50.00%
09.05 SENSIBILIZACION DE LA PREVENCION DEL CONTAGIO COVID-19 EN OBRA glb 1.00 1,130.00 1,130.00 0.50 S/.565.00 50.00% 0.50 S/.565.00 50.00%
09.06 MEDIDAS PREVENTIVAS COLECTIVAS glb 1.00 3,180.00 3,180.00 0.50 S/.1,590.00 50.00% 0.50 S/.1,590.00 50.00%
09.07 MEDIDAS PREVENTIVAS PERSONAL mes 1.00 3,792.50 3,792.50 0.50 S/.1,896.25 50.00% 0.50 S/.1,896.25 50.00%
10.01 PREFESIONAL DE SEGURIDAD Y SALUD mes 1.00 4,500.00 4,500.00 0.50 S/.2,250.00 50.00% 0.50 S/.2,250.00 50.00%
11.01 MITIGACION DE IMPACTO AMBIENTAL EN OBRA glb 1.00 3,000.00 3,000.00 0.50 S/.1,500.00 50.00% 0.50 S/.1,500.00 50.00%
69.23% 100.00%
Página 2
CALENDARIO DE AVANCE DE OBRA VALORIZADO
Obra: MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD PEATONAL EN LA 2DA CUADRA DE LA CALLE ROSARIO,DELDISTRITO DE GROCIO PRADO - PROVINCIA DE CHINCHA - DEPARTAMENTO DE ICA
Fecha Ago-20
Página 3