HW2
Autonomous Maintenance
and
Preventive Maintenance
by
Cost ($)
Degree of PM
At minimum level of PM , breakdown cost is very high and decreasing when level of PM
is higher finally at some point we reach the minimum total maintenance cost.
Repair Program
Objective is to get equipment back into operation as quickly as possible and also
control cost of repairs crews , the operation of repair shops.
- Control the investment in replacement spare parts / standby or backup machines.
Cost of
interruptions to
production
= 9.375 or 10 crews
PM database requirements
- Detailed record history must be maintained on each machine
includes dates and frequency of breakdowns, descriptions of malfunction and cost of
repairs.
- Machine spec/checklists for PM inspection.
- Computer database or kept in plastic pocket on a machine.
Formula
1 0.2
2 0.3
3 0.5
B1 = 4(0.2) = 0.8
B2 = 4(0.2+0.3) + 0.8(0.2) = 2.16
B3 = 4(0.2+0.3+0.5) + 2.16(0.2) + 0.8(0.3) = 4.672
We can see that PM every 2 weeks is the best solution to minimize the cost.