5 TABLA DE D E S C R I P C I Ó N DE RUBROS, UNIDADES, CANTIDADES Y PRECIOS

ITEM DESCRIPCION UNIDAD CANTIDAD PRECIO PRECIO


UNITARIO TOTAL

PRELIMINARES
302-1 DESBROCE, DESBOSQUE Y LIMPIEZA HA 0,30 2.592,59 777,78
DESALOJO DE MATERIAL O R G Á N I C O M3 900,00 6,99 6.291,00
EXCAVACION PARA ENCAUSAMIENTO DEL RIO M3 1.837,00 6,27 11.517,99
18.586,77

INFRAESTRUCTURA
307-2( EXCAVACION Y RELLENO PARA PUENTES M3 1.479,18 18,52 27.394,41
P I L O T E P R E F A B R I C A D O 0,50x0,50 ( I N C L U Y E P I L O T E DE P R U E B A ) M 496,00 264,26 131.072,96
HORMIGON NO ESTRUCTURAL CLASE " E " ( f ' c = 1 4 0 kg/cm2) P A R A
REPLANTILLOS M3 21,57 153,29 3.306,47
HORMIGON ESTRUCTURAL CLASE " A " ( f ' c = 2 8 0 kg/cm2) (INC. E N C O F R A D O )
503 (1) ( e s t r i b o s , d i a f r a g m a s ) M3 344,46 260,32 89.669,83
504(1) A C E R O D E R E F U E R Z O F Y = 4 2 0 0 K G / C M 2 KG 35.443,02 1,99 70.531,61
M A T E R I A L F I L T R A N T E ( P I E D R A N.4) M3 90,00 33,35 3.001,50
T U B O PVC 4 " (DRENES) M 75,00 5,53 414,75
PROVISION E INSTALACION DE G E O T E X T I L N T 2000 M2 941,00 3,28 3.086,48
E N R O C A D O PARA P R O T E C C I O N DE PUENTES Y RIVERAS DE RIOS M3 861,50 38,19 32.900,69
361.378,69

SUPERESTRUCTURA
P L A C A S DE N E O P R E N O (50x50x4 c m Shore 70) U 10,00 405,33 4.053,30
VIGA TIPO CALIFORNIA DE H O R M I G O N PRECOMPRIMIDO (PRETENSADO)
f ' c = 4 5 0 k g / c m 2 , L = 4 0 m , A l t u r a = 1,85 m U 5,00 30.065,67 150.328,35
L O S E T A DE H O R M I G O N P R E C O M P R I M I D O ( P R E T E N S A D O ) f ' c = 4 5 0 kg/cm2,
(1,54x1,00x0,08) U 265,00 144,25 38.226,25
504(1) A C E R O D E R E F U E R Z O F Y = 4 2 0 0 K G / C M 2 KG 16.880,71 1,99 33.592,61
HORMIGON ESTRUCTURAL CLASE " A " ( f ' c = 3 5 0 kg/cm2) (INC. E N C O F R A D O )
(losa d e tablero) M3 67,40 272,34 18.355,72
BARANDALES DE H O R M I G O N M 80,00 155,82 12.465,60
A C E R A H O R M I G O N A R M A D O C L A S E " B " f ' c = 2 1 0 kg/cm2 VH=0.10 m3/m2 M2 104,00 55,36 5.757,44
J U N T A DE EXPANSION M 22,00 344,48 7.578,56
T U B O S PVC 2 " (DRENES) M 8,00 6,49 51,92
405-l(: A S F A L T O MC-250 P A R A I M P R I M A C I O N Lt 524,88 1,20 629,86
C A P A DE R O D A D U R A DE H O R M I G O N A S F A L T I C O M E Z C L A D O EN P L A N T A
405-5 E=5.0 C M M2 324,00 15,53 5.031,72
276.071,32

VIAS DE A C C E S O
304-l(; M A T E R I A L DE P R E S T A M O IMPORTADO M3 462,52 19,09 8.829,51
403-1 SUB-BASE CLASE 3 M3 426,94 25,30 10.801,58
404-1 BASE CLASE 1 M3 246,66 28,40 7.005,14
B O R D I L L O C U N E T A f e = 210 kg/cm2 VH=0.16 m3/m M 206,00 28,19 5.807,14
A C E R A S H.S. C L A S E " C " ( 1 8 0 k g / c m 2 ) M2 258,00 29,01 7.484,58
B O R D I L L O f e = 2 1 0 kg/cm2 V H = 0 . 0 5 m3/m M 206,00 18,73 3.858,38
405-l(: A S F A L T O MC-250 P A R A I M P R I M A C I O N Lt 1.360,80 1,20 1.632,96
C A P A DE R O D A D U R A DE H O R M I G O N A S F A L T I C O M E Z C L A D O EN P L A N T A
405-5 E=7.5 C M M2 840,00 18,47 15.514,80
S E Ñ A L DE DECISION DE DESTINO U 4,00 148,17 592,68
61.526,77

MEDIO AMBIENTE
CABINA SANITARIA PORTATIL MES 5,00 410,30 2.051,50
C O N T R O L DE P O L V O (AGUA) M3 75,00 6,93 519,75
C H A R L A S DE C O N C I E N T I Z A C I O N DIA 1,00 276,33 276,33
VOLANTES INFORMATIVAS U 2.902,00 1,07 3.105,14
REUNION INFORMATIVA C O N LA C O M U N I D A D U 1,00 658,80 658,80
LETRERO PREVENTIVO 750X 750 U 2,00 148,49 296,98
S E Ñ A L P U E N T E EN C O N S T R U C C I O N 7 5 0 X 7 5 0 U 2,00 148,49 296,98
S E Ñ A L DE P E L I G R O 750 X 7 5 0 U 1,00 148,49 148,49
S E Ñ A L HOMBRES TRABAJANDO 750 X 750 U 2,00 148,49 296,98
RECIPIENTE PARA DESECHOS SOLIDOS U 2,00 46,01 92,02
7.742,97

TOTAL 725.306,53
SON: SETECIENTOS V E I N T I C I N C O MIL T R E C I E N T O S S E I S D O L A R E S C O N 53/100 SIN IVA