VALORIZACION MANO DE OBRA

Presupuesto VEREDAS DE CONCRETO MZ L'

MAESTRO VICENTE VALORIZACION N°01


Lugar ICA - ICA - SUBTANJALLA ACTUAL
VALORIZACION ANTERIOR ACUMULADO SALDO
Fri 12 May
Item Descripción
Und. Metrado Precio (S/.) Parcial (S/.) Metrado % Parcial Metrado % Parcial Metrado % Parcial Metrado % Parcial

01 VEREDAS
01.01 OBRAS PRELIMINARES
01.01.01 TRAZO Y REPLANTEO DURANTE LA OBRA m2 31.20 2.50 78.00 0.00 0.00% S/. - 31.20 100.00% S/. 78.00 31.20 100.00% S/. 78.00 0.00 0.00% S/. -
01.02 MOVIMIENTO DE TIERRAS
01.02.01 EXCAVACION DE ZANJAS m3 5.76 13.00 74.88 0.00 0.00% S/. - 5.76 100.00% S/. 74.88 5.76 100.00% S/. 74.88 0.00 0.00% S/. -
01.02.02 CONFORMACION DE LA BASE GRANULAR m2 31.20 4.82 150.45 0.00 0.00% S/. - 31.20 100.00% S/. 150.45 31.20 100.00% S/. 150.45 0.00 0.00% S/. -
01.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 4.81 10.50 50.51 0.00 0.00% S/. - 4.81 100.00% S/. 50.51 4.81 100.00% S/. 50.51 0.00 0.00% S/. -
01.03 VEREDAS Y RAMPAS DE CONCRETO
01.03.01 ENCOFRADO Y DESENCOFRADO m2 9.71 12.32 119.63 0.00 0.00% S/. - 9.71 100.00% S/. 119.63 9.71 100.00% S/. 119.63 0.00 0.00% S/. -
01.03.02 CONCRETO F'C=175KG/CM2, FROTACHADO Y BRUÑADO m2 31.20 18.20 567.84 0.00 0.00% S/. - 31.20 100.00% S/. 567.84 31.20 100.00% S/. 567.84 0 0.00% S/. -
01.03.03 JUNTAS ASFALTICAS m 7.80 2.50 19.50 0.00 0.00% S/. - 7.80 100.00% S/. 19.50 7.80 100.00% S/. 19.50 0 0.00% S/. -
01.03.04 CURADO DE CONCRETO EN VEREDAS Y RAMPAS m2 31.20 1.00 31.20 0.00 0.00% S/. - 31.20 100.00% S/. 31.20 31.20 100.00% S/. 31.20 0.00 0.00% S/. -

M O COSTO DIRECTO 1,092.00 0.00 1,092.01 1,092.00 0.00


F. GARANTIA 5.00% 54.60 0.00 54.60 54.60 0.00

TOTAL 1,037.40 0.00 1,037.41 1,037.40 0.00


CONTRATISTA VICENTE

OBRA VEREDAS DE CONCRETO MZ L'

UBICACIÓN PRADOS DEL ESTE

VALORIZACION N° 1

FECHA DE VALORIZACION 5/12/2017

COSTO DIRECTO S/. 1,092.01

FONDO DE GARANTIA -5% S/. 54.60

SUB TOTAL S/. 1,037.41

I.G.V. 18% S/. -

TOTAL S/. 1,037.41