*PRELIMINARES
1 MATERIALES:
2 MANO DE OBRA:
2.1 Capataz 2.00 dia 1,726.73 3,453.46
2.2 Peon (2 hombres/dia) 2.00 dia 575.13 2,300.52
SUB-TOTAL 5,753.98
3 EQUIPOS O HERRAMIENTAS:
3.1 Pala R.D.$460.00 V.U.= 6 meses 2.00 ud 6.43 12.87
2.02 Carretilla R.D.$3,656.82 V.U.= 6 meses 2.00 ud 51.15 102.30
2.03 Pico R.D.$504.00 V.U.= 6 meses 2.00 ud 7.05 14.10
2.04 Hacha R.D.$442.50 V.U.= 6 meses 2.00 ud 6.19 12.38
SUB-TOTAL 141.65
4 MISCELANEOS
Bote producto de limpieza (Camion de 6.00 m3 )
4.1 12.00 m2 30.83 370.00
Alquiler=R.D.$1,850.00/viaje
Demolicion de piso existente
4.2 3.00 m3 603.89 1,811.66
Volumen= 30x0.10 = 3.00 m3
Bote producto de demolicion (40 % esponjamiento)
4.3 4.20 m3 30.83 129.50
Volumen= 3x1.4 = 4.20 m3
SUB-TOTAL 2,311.16
TOTAL 8,206.79
COSTO R.D.$/M2 27.36
1 MATERIALES:
1.1 Madera 64.90 Pie2 43.50 2823.15
1.2 Clavos Corrientes 12.00 lb 23.25 279.00
1.3 Zinc Ancanalado Calibre 34 4.25 ud 160.00 680.00
1.4 Clavos de Zinc 2.50 lb 36.00 90.00
1.5 Plywood de 4'x 8' de 3/4" 2.67 ud 1255.00 3346.67
1.6 Candado 1.00 ud 457.84 457.84
1.7 Pestillo 1.00 ud 102.66 102.66
1.8 Bisagras 2.00 ud 225.38 450.76
1.9 Porta Candado 1.00 ud 149.00 149.00
SUB-TOTAL 8,379.08
2 MANO DE OBRA:
2.1 Carpintero 2da Categoria 3.00 dia 1,095.81 3,287.43
2.2 Ayudante de Carpintero 3.00 dia 739.84 2,219.52
2.3 Replanteo, hormigon en hoyos, excavacion, bote. 1.00 p.a. 2,000.00 2,000.00
2.4 Salida de Interruptor doble 1.00 ud 800.00 800.00
2.5 Salida de Tomacorriente 1.00 ud 800.00 800.00
24 Salida Luz de Techo 2.00 ud 800.00 1,600.00
SUB-TOTAL 10,706.95
3 EQUIPOS O HERRAMIENTAS:
3.1 5% de la Mano de Obra 5.00% % 10,706.95 535.35
SUB-TOTAL 535.35
TOTAL 19,621.37
COSTO TOTAL R.D.$/M2 1,257.16
1 de 3
Constructora YONIGA SRL.xlsx
ANALISIS PARA LA CONSTRUCCION VIVENDA YONIGA
REPLANTEO
No. DESCRIPCION Ctd. Ud. P.U. R.D.$ Valor R.D.$
AREA DE REPLANTEO 77.72 M2
1 MATERIALES:
1.1 Madera 31.53 Pie2 43.50 1,371.70
1.2 Clavos Corrientes 6.00 lb 23.25 139.50
1.3 Cal (fda 50 lb) 2.00 fda 350.00 700.00
1.4 Hilo 1.50 lb 100.00 150.00
SUB-TOTAL 2,361.20
2 MANO DE OBRA:
2.1 Capataz 1.00 dia 1,726.73 1,726.73
2.2 Carpintero 2da Categoria 1.00 dia 1,095.81 1,095.81
2.3 Ayudante De Carpintero 1.00 dia 739.84 739.84
2.4 Topografo 1.00 dia 2,500.00 2,500.00
2.5 Ayudante de Topografo 1.00 dia 740.00 740.00
24 Peon 1.00 dia 575.13 575.13
SUB-TOTAL 7,377.51
3 EQUIPOS O HERRAMIENTAS:
3.1 Estacion Topografica 1.00 dia 20,000.00 20,000.00
3.2 Cinta (10usos) R.D.$444.36 1.00 ud 44.44 44.44
SUB-TOTAL 20,044.44
TOTAL 29,783.15
COSTO TOTAL R.D.$/M2 383.19
*MOVIMIENTO DE TIERRA
RELLENO DE REPOSICION
No. DESCRIPCION Ctd. Ud. P.U. R.D.$ Valor R.D.$
1 MATERIALES:
2 MANO DE OBRA:
2.1 Paleo 1.00 m3 31.95 31.95
2.2 Compactacion 1.00 m3 57.51 57.51
SUB-TOTAL 89.46
3 EQUIPOS O HERRAMIENTAS:
3.1 Pala 1.00 m3 0.92 0.92
3.2 Pison metalico 1.00 m3 2.63 2.63
SUB-TOTAL 3.55
Costo RD$/M3 93.01
2 de 3
Constructora YONIGA SRL.xlsx
ANALISIS PARA LA CONSTRUCCION VIVENDA YONIGA
1 MATERIALES:
1.1 Suministro de Caliche (+30% alb.) 1.30 m3 500.00 650.00
1.2 Agua 75.00 gl. 1.00 75.00
SUB-TOTAL 725.00
2 MANO DE OBRA:
2.1 Carretillero 1.00 dia 575.13 575.13
2.2 Paleo 1.00 dia 575.13 575.13
2.3 Aguatero y tendedor 1.00 dia 575.13 575.13
2.4 Compactador 1.00 dia 575.13 575.13
SUB-TOTAL 2,300.52
Rendimiento 6.00 m3/dia
SUB-TOTAL 383.42
3 EQUIPOS O HERRAMIENTAS:
3.1 Carretilla R.D.$3,656.82 V.U.= 500 /m3 1.00 m3 7.31 7.31
3.2 Pala R.D.$920.00 V.U.= 500 /m3 1.00 m3 1.84 1.84
3.3 Pison Metalico
R.D.$1,314.00 V.U.= 500 /m3 1.00 m3 2.63 2.63
3.4 Manguera R.D.$845.00 V.U.= 1000 /m3 1.00 m3 0.85 0.85
SUB-TOTAL 12.6
Costo RD$/m3 1,121.05