Está en la página 1de 1

PROYECTO:

SERVICIO DE GESTIÓN, MEJORAMIENTO Y CONSERVACIÓN VIAL POR NIVELES DE SERVICIO DEL CORREDOR
VIAL PRO REGIÓN PUNO- PAQUETE 03: PE-34R, PE-3SQ Y PE-3SR
(RUTA 09: TRAMO T3,T4 (KM 04+086 - KM 35+000) = KM 34+500
PRESUPUESTOS
CONTRATISTA SUB-CONTRATISTA
Item Descripción Und. Metrado
Metrado Precio S/. Parcial S/. P.U P. Parcial S/. DIFERENCIA
Replanteado
1 TRABAJOS PRELIMINARES 168,212.03 109,140.85 59,071.18
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS
glb 1 132,400.00 132,400.00 1.00 72,250.00 72,250.00

1.02 TOPOGRAFIA Y GEOREFERENCIANCION km 30.41 1,177.64 35,812.03 34.50 1,069.30 36,890.85


2 MOVIMIENTO DE TIERRAS 1,931,007.02 1,281,382.31 649,624.71
2.01 PERFILADO DE LA SUPERFICIE SIN APORTE DE
m2 210,566.38 3.74 787,518.26 210,566.38 3.85 810,680.56
MATERIAL GRANULAR
2.02 TERRAPLENES m3 25,637.35 44.6 1,143,488.76 25,637.35 18.36 470,701.75
3 BASES Y SUB BASES 4,076,103.71 1,201,382.28 2,874,721.43
3.01 SUELO ESTABILIZADO CON CEMENTO m3 41,327.22 98.63 4,076,103.71 41,327.22 29.07 1,201,382.28
4 PAVIMENTOS 2,510,524.29 2,677,038.66 -166,514.37
4.01 IMPRIMACION ASFALTICA m2 182,982.82 4.03 737,420.76 182,982.82 3.15 576,395.88
4.02 OTTA SEAL m2 182,982.82 9.69 1,773,103.53 182,982.82 11.48 2,100,642.77
5 OBRAS DE ARTE Y DRENAJE 117,360.61 77,831.28 39,529.33
5.01 ALCANTARILLADO TMC D 36" und 6 5,124.44 30,746.64 6.00 4,355.74 26,134.44
5.02 ALCANTARILLADO TMC D 48" und 2 7,242.74 14,485.48 2.00 6,156.30 12,312.60
5.03 CUNETA REVESTIDA DE CONCRETO m 147 490.67 72,128.49 147.00 267.92 39,384.24
5.04 SUB DREN m 59.29 0.00
6 SEÑALIZACION Y SEGURIDAD VIAL 98,960.90 109,558.19 -10,597.29
6.01 SEÑALES PREVENTIVAS und 55 437.97 24,088.35 55.00 352.75 19,401.25
6.02 SEÑALES REGLAMENTARIAS und 497.51 0.00
6.03 SEÑALES INFORMATIVAS und 3.66 583.46 2,135.46 3.66 492.92 1,804.09
6.04 POSTE DELINEADOR und 245 128.9 31,580.50 245.00 107.87 26,428.15
6.05 MARCAS EN EL PAVIMENTO m2 6,122.00 5.84 35,752.48 6,122.00 8.93 54,669.46
6.06 POSTE DE KILOMETRAJE und 31 78.71 2,440.01 31.00 161.16 4,995.96
6.07 GIBAS O RESALTO m 6.2 478.08 2,964.10 6.20 364.40 2,259.28
7 PROTECCION AMBIENTAL 12,295.15 11,006.90 1,288.25
7.01 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN
m3 217.48 11.37 2,472.75 217.48 9.78 2,126.95
DME
7.02 PROGRAMA DE ABANDONO AMBIENTAL glb 1 6,500.00 6,500.00 1.00 5,843.75 5,843.75
7.03 PROGRAMA DE MONITOREO AMBIENTAL glb 1 3,322.40 3,322.40 1.00 3,036.20 3,036.20
COSTO DIRECTO 8,914,463.71 5,467,340.47 3,447,123.24
GASTOS GENERALES 447,194.19 0.00
UTILIDAD 626,071.86 0.00
SUB TOTAL 9,987,729.76 5,467,340.47
I.G.V. (20.23%) (18%) 1,803,086.96 984,121.28
PRESUPUESTO TOTAL 11,790,816.72 6,451,461.75

Long. 34.50
Costo x Km S/186,998.89