METRADO DE CARGAS PARA UNA EDIFICACION

PRIMER PISO veces cantidad largo y ancho X


COLUMNA C1 1 22 0.20 0.30
COLUMNA C2 1 2 0.25 0.25
VIGA P. 30X.60 ENTRE EJES A-A Y B-B 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES E-E Y F-F 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES B-B Y C-C 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES D-D Y E-E 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES C-C Y D-D 1 4 0.30 0.60
VIGAS S .25X.40 ENTRE EJES 1-1 Y 2-2 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 2-2 Y 3-3 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 3-3 Y 4-4 1 6 0.25 0.40
LOSA
1 1 19.70 9.80
1° espesor 0.2
TABIQUERIA ENTRE EJES A-A Y B-B 1 1 20.00 0.15
TABIQUERIA ENTRE EJES E-E Y F-F 1 1 19.30 0.15
TABIQUERIA ENTRE EJES B-B Y C-C 1 1 17.60 0.15
TABIQUERIA ENTRE EJES D-D Y E-E 1 1 14.85 0.15
TABIQUERIA ENTRE EJES C-C Y D-D 1 1 18.10 0.15
TABIQUERIA ENTRE EJES 1-1 Y 2-2 1 1 13.00 0.15
TABIQUERIA ENTRE EJES 2-2 Y 3-3 1 1 15.83 0.15
TABIQUERIA ENTRE EJES 3-3 Y 4-4 1 1 16.65 0.15
ACABADOS 1 1 21.00 10.00
DESCUENTO ACABADOS 1 -1 1.00 3.60
SOBRECARGAS BAÑOS 1 3 2.20 1.60
TOTAL PESO DEL 1 PISO

SEGUNDO PISO veces cantidad largo y ancho X


COLUMNA C1 1 22 0.20 0.30
COLUMNA C2 1 2 0.25 0.25
VIGA P. 30X.60 ENTRE EJES A-A Y B-B 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES E-E Y F-F 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES B-B Y C-C 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES D-D Y E-E 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES C-C Y D-D 1 4 0.30 0.60
VIGAS S .25X.40 ENTRE EJES 1-1 Y 2-2 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 2-2 Y 3-3 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 3-3 Y 4-4 1 6 0.25 0.40
LOSA
1 1 19.70 9.80
2° espesor 0.2
TABIQUERIA ENTRE EJES A-A Y B-B 1 1 20.00 0.15
TABIQUERIA ENTRE EJES E-E Y F-F 1 1 19.30 0.15
TABIQUERIA ENTRE EJES B-B Y C-C 1 1 17.60 0.15

TABIQUERIA ENTRE EJES D-D Y E-E 1 1 14.85 0.15


TABIQUERIA ENTRE EJES C-C Y D-D 1 1 18.10 0.15
TABIQUERIA ENTRE EJES 1-1 Y 2-2 1 1 13.00 0.15
TABIQUERIA ENTRE EJES 2-2 Y 3-3 1 1 15.83 0.15
TABIQUERIA ENTRE EJES 3-3 Y 4-4 1 1 16.65 0.15
ACABADOS 1 1 21.00 10.00
DESCUENTO ACABADOS 1 -1 1.00 3.60
SOBRECARGAS BAÑOS 1 3 2.20 1.60
TOTAL PESO DEL 2 PISO

TERCER PISO veces cantidad largo y ancho X


COLUMNA C1 1 22 0.20 0.30
COLUMNA C2 1 2 0.25 0.25
VIGA P. 30X.60 ENTRE EJES A-A Y B-B 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES E-E Y F-F 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES B-B Y C-C 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES D-D Y E-E 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES C-C Y D-D 1 4 0.30 0.60
VIGAS S .25X.40 ENTRE EJES 1-1 Y 2-2 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 2-2 Y 3-3 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 3-3 Y 4-4 1 6 0.25 0.40
LOSA
1 1 19.70 9.80
3° espesor 0.2
TABIQUERIA ENTRE EJES A-A Y B-B 1 1 20.00 0.15
TABIQUERIA ENTRE EJES E-E Y F-F 1 1 19.30 0.15
TABIQUERIA ENTRE EJES B-B Y C-C 1 1 17.60 0.15
TABIQUERIA ENTRE EJES D-D Y E-E 1 1 14.85 0.15
TABIQUERIA ENTRE EJES C-C Y D-D 1 1 18.10 0.15
TABIQUERIA ENTRE EJES 1-1 Y 2-2 1 1 13.00 0.15
TABIQUERIA ENTRE EJES 2-2 Y 3-3 1 1 15.83 0.15
TABIQUERIA ENTRE EJES 3-3 Y 4-4 1 1 16.65 0.15
ACABADOS 1 1 21.00 10.00
DESCUENTO ACABADOS 1 -1 1.00 3.60
SOBRECARGAS BAÑOS 1 3 2.20 1.60
TOTAL PESO DEL 3 PISO

CUARTO PISO veces cantidad largo y ancho X


COLUMNA C1 1 22 0.20 0.30
COLUMNA C2 1 2 0.25 0.25
VIGA P. 30X.60 ENTRE EJES A-A Y B-B 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES E-E Y F-F 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES B-B Y C-C 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES D-D Y E-E 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES C-C Y D-D 1 4 0.30 0.60
VIGAS S .25X.40 ENTRE EJES 1-1 Y 2-2 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 2-2 Y 3-3 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 3-3 Y 4-4 1 6 0.25 0.40
LOSA
1 1 19.70 9.80
4° espesor 0.2
TABIQUERIA ENTRE EJES A-A Y B-B 1 1 20.00 0.15
TABIQUERIA ENTRE EJES E-E Y F-F 1 1 19.30 0.15
TABIQUERIA ENTRE EJES B-B Y C-C 1 1 17.60 0.15
TABIQUERIA ENTRE EJES D-D Y E-E 1 1 14.85 0.15
TABIQUERIA ENTRE EJES C-C Y D-D 1 1 18.10 0.15
TABIQUERIA ENTRE EJES 1-1 Y 2-2 1 1 13.00 0.15
TABIQUERIA ENTRE EJES 2-2 Y 3-3 1 1 15.83 0.15
TABIQUERIA ENTRE EJES 3-3 Y 4-4 1 1 16.65 0.15
ACABADOS 1 1 21.00 10.00
DESCUENTO ACABADOS 1 -1 1.00 3.60
SOBRECARGAS BAÑOS 1 3 2.20 1.60
TOTAL PESO DEL 4 PISO

QUINTO PISO veces cantidad largo y ancho X


COLUMNA C1 1 22 0.20 0.30
COLUMNA C2 1 2 0.25 0.25
VIGA P. 30X.60 ENTRE EJES A-A Y B-B 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES E-E Y F-F 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES B-B Y C-C 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES D-D Y E-E 1 4 0.30 0.60
VIGA P. 30X.60 ENTRE EJES C-C Y D-D 1 4 0.30 0.60
VIGAS S .25X.40 ENTRE EJES 1-1 Y 2-2 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 2-2 Y 3-3 1 6 0.25 0.40
VIGAS S .25X.40 ENTRE EJES 3-3 Y 4-4 1 6 0.25 0.40
LOSA
1 1 19.70 9.80
5° espesor 0.2
TABIQUERIA ENTRE EJES A-A Y B-B 1 1 20.00 0.15
TABIQUERIA ENTRE EJES E-E Y F-F 1 1 19.30 0.15
TABIQUERIA ENTRE EJES B-B Y C-C 1 1 17.60 0.15
TABIQUERIA ENTRE EJES D-D Y E-E 1 1 14.85 0.15
TABIQUERIA ENTRE EJES C-C Y D-D 1 1 18.10 0.15
TABIQUERIA ENTRE EJES 1-1 Y 2-2 1 1 13.00 0.15
TABIQUERIA ENTRE EJES 2-2 Y 3-3 1 1 15.83 0.15
TABIQUERIA ENTRE EJES 3-3 Y 4-4 1 1 16.65 0.15
ACABADOS 1 1 21.00 10.00
DESCUENTO ACABADOS 1 -1 1.00 3.60
SOBRECARGAS BAÑOS 1 3 2.20 1.60
TOTAL PESO DEL 5 PISO

RESUMEN DE METRADO DE CARGAS

1° NIVEL 2° NIVEL 3° NIVEL 4° NIVEL


VIGAS PRINCIPALES 34.04 34.04 34.04 34.04
VIGAS SECUNDARIAS 14.11 14.11 14.11 14.11
COLUMNAS 9.92 9.36 9.36 9.36
ALIGERADO 57.92 57.92 57.92 57.92
TABIQUERIA 2.03 2.03 2.03 2.03
ACABADOS 20.64 20.64 20.64 20.64
SOBRECARGAS S/C 3.168 3.168 3.168 3.168
Wi 141.83 141.27 141.27 141.27
GAS PARA UNA EDIFICACION
altura CARGA UNITARIA NORMA E. 020 parcial unidad total
2.86 2.400 Tn/m3 9.06 tn
2.86 2.400 Tn/m3 0.86 tn
4.50 2.400 Tn/m3 7.78 tn
4.50 2.400 Tn/m3 7.78 tn
3.75 2.400 Tn/m3 6.48 tn
3.75 2.400 Tn/m3 6.48 tn
3.20 2.400 Tn/m3 5.53 tn
3.05 2.400 Tn/m3 4.39 tn
3.15 2.400 Tn/m3 4.54 tn
3.60 2.400 Tn/m3 5.18 tn
CARGA UNITARIA ALIGERADO NORMA E. 020 parcial unidad
0.3 Tn/m2 57.92 tn 141.83
0.1 Tn/m2 0.30 tn
0.1 Tn/m2 0.29 tn
0.1 Tn/m2 0.26 tn
0.1 Tn/m2 0.22 tn
0.1 Tn/m2 0.27 tn
0.1 Tn/m2 0.20 tn
0.1 Tn/m2 0.24 tn
0.1 Tn/m2 0.25 tn
0.1 Tn/m2 21.00 tn
0.1 Tn/m2 -0.36 tn
0.3 Tn/m2 3.168 tn
SO tn 141.83

altura CARGA UNITARIA NORMA E. 020 parcial unidad total


2.70 2.400 Tn/m3 8.55 tn
2.70 2.400 Tn/m3 0.81 tn
4.50 2.400 Tn/m3 7.78 tn
4.50 2.400 Tn/m3 7.78 tn
3.75 2.400 Tn/m3 6.48 tn
3.75 2.400 Tn/m3 6.48 tn
3.20 2.400 Tn/m3 5.53 tn
3.05 2.400 Tn/m3 4.39 tn
3.15 2.400 Tn/m3 4.54 tn
3.60 2.400 Tn/m3 5.18 tn
CARGA UNITARIA ALIGERADO NORMA E. 020 parcial unidad
0.3 Tn/m2 57.92 tn 141.27
0.1 Tn/m2 0.30 tn
0.1 Tn/m2 0.29 tn
0.1 Tn/m2 0.26 tn
141.27

0.1 Tn/m2 0.22 tn


0.1 Tn/m2 0.27 tn
0.1 Tn/m2 0.20 tn
0.1 Tn/m2 0.24 tn
0.1 Tn/m2 0.25 tn
0.1 Tn/m2 21.00 tn
0.1 Tn/m2 -0.36 tn
0.3 Tn/m2 3.168 tn
SO tn 141.27

altura CARGA UNITARIA NORMA E. 020 parcial unidad total


2.70 2.400 Tn/m3 8.55 tn
2.70 2.400 Tn/m3 0.81 tn
4.50 2.400 Tn/m3 7.78 tn
4.50 2.400 Tn/m3 7.78 tn
3.75 2.400 Tn/m3 6.48 tn
3.75 2.400 Tn/m3 6.48 tn
3.20 2.400 Tn/m3 5.53 tn
3.05 2.400 Tn/m3 4.39 tn
3.15 2.400 Tn/m3 4.54 tn
3.60 2.400 Tn/m3 5.18 tn
CARGA UNITARIA ALIGERADO NORMA E. 020 parcial unidad
0.3 Tn/m2 57.92 tn 141.27
0.1 Tn/m2 0.30 tn
0.1 Tn/m2 0.29 tn
0.1 Tn/m2 0.26 tn
0.1 Tn/m2 0.22 tn
0.1 Tn/m2 0.27 tn
0.1 Tn/m2 0.20 tn
0.1 Tn/m2 0.24 tn
0.1 Tn/m2 0.25 tn
0.1 Tn/m2 21.00 tn
0.1 Tn/m2 -0.36 tn
0.3 Tn/m2 3.168 tn
SO tn 141.27

altura CARGA UNITARIA NORMA E. 020 parcial unidad total


2.70 2.400 Tn/m3 8.55 tn
2.70 2.400 Tn/m3 0.81 tn
4.50 2.400 Tn/m3 7.78 tn
4.50 2.400 Tn/m3 7.78 tn
3.75 2.400 Tn/m3 6.48 tn
3.75 2.400 Tn/m3 6.48 tn
3.20 2.400 Tn/m3 5.53 tn
3.05 2.400 Tn/m3 4.39 tn
3.15 2.400 Tn/m3 4.54 tn
3.60 2.400 Tn/m3 5.18 tn
CARGA UNITARIA ALIGERADO NORMA E. 020 parcial unidad
0.3 Tn/m2 57.92 tn 141.27
0.1 Tn/m2 0.30 tn
0.1 Tn/m2 0.29 tn
0.1 Tn/m2 0.26 tn
0.1 Tn/m2 0.22 tn
0.1 Tn/m2 0.27 tn
0.1 Tn/m2 0.20 tn
0.1 Tn/m2 0.24 tn
0.1 Tn/m2 0.25 tn
0.1 Tn/m2 21.00 tn
0.1 Tn/m2 -0.36 tn
0.3 Tn/m2 3.168 tn
SO tn 141.27

altura CARGA UNITARIA NORMA E. 020 parcial unidad total


2.70 2.400 Tn/m3 8.55 tn
2.70 2.400 Tn/m3 0.81 tn
4.50 2.400 Tn/m3 7.78 tn
4.50 2.400 Tn/m3 7.78 tn
3.75 2.400 Tn/m3 6.48 tn
3.75 2.400 Tn/m3 6.48 tn
3.20 2.400 Tn/m3 5.53 tn
3.05 2.400 Tn/m3 4.39 tn
3.15 2.400 Tn/m3 4.54 tn
3.60 2.400 Tn/m3 5.18 tn
CARGA UNITARIA ALIGERADO NORMA E. 020 parcial unidad
0.3 Tn/m2 57.92 tn 141.27
0.1 Tn/m2 0.30 tn
0.1 Tn/m2 0.29 tn
0.1 Tn/m2 0.26 tn
0.1 Tn/m2 0.22 tn
0.1 Tn/m2 0.27 tn
0.1 Tn/m2 0.20 tn
0.1 Tn/m2 0.24 tn
0.1 Tn/m2 0.25 tn
0.1 Tn/m2 21.00 tn
0.1 Tn/m2 -0.36 tn
0.3 Tn/m2 3.168 tn
SO tn 141.27

5° NIVEL
34.04
14.11
9.36
57.92
2.03
20.64
3.168
141.27