ANALISIS DE CONCRETOS

CONCRETO 1 : 2 : 2 Fc = 4000 psi


MATERIALES UND CANT Vr.UNIT Vr.TOTAL
CEMENTO KGR 425.00 500 212,500.00
ARENA M3 0.67 60,000 40,200.00
TRITURADO M3 0.67 70,000 46,900.00
AGUA LTR 240.00 10 2,400.00
MEZCLADORA C DIA 0.18 100,000 18,000.00
DESPERDICIO UND 5% 15,100.00
COSTO POR M3 335,100.00

CONCRETO 1 : 2 : 3 Fc = 3000 psi


MATERIALES UND CANT Vr.UNIT Vr.TOTAL
CEMENTO KGR 350.00 500 175,000.00
ARENA M3 0.56 60,000 33,600.00
TRITURADO M3 0.84 70,000 58,450.00
AGUA LTR 240.00 10 2,400.00
MEZCLADORA C DIA 0.18 100,000 18,000.00
DESPERDICIO UND 5% 13,473.00
COSTO POR M3 300,923.00

CONCRETO 1 : 3 : 3 Fc = 2000 psi


MATERIALES UND CANT Vr.UNIT Vr.TOTAL
CEMENTO KGR 300.00 500 150,000.00
ARENA M3 0.72 60,000 43,200.00
TRITURADO M3 0.72 70,000 50,400.00
AGUA LTR 240.00 10 2,400.00
MEZCLADORA C DIA 0.18 100,000 18,000.00
DESPERDICIO UND 5% 12,300.00
COSTO POR M3 276,300.00

COSTO DIRECTO MORTEROS

MORTERO 1 : 4
MATERIALES UND CANT Vr.UNIT Vr.TOTAL
CEMENTO KGR 365.00 500 182,500
ARENA BLANCA M3 1.16 60,000 69,600
AGUA LTR 240.00 10 2,400
DESPERDICIO UND 5% 12,725
COSTO POR M3 267,225
MORTERO 1 : 4 IMPERMEABILIZADO
MATERIALES UND CANT Vr.UNIT Vr.TOTAL
CEMENTO KGR 365.00 500 182,500.00
ARENA BLANCA M3 1.16 60,000 69,600.00
AGUA LTR 240.00 10 2,400.00
SIKA 1 KGR 20.00 8,000 160,000.00
DESPERDICIO UND 5% 20,725.00
COSTO POR M3 435,225.00

MORTERO 1 : 3
MATERIALES UND CANT Vr.UNIT Vr.TOTAL
CEMENTO KGR 454.00 500 227,000.00
ARENA BLANCA M3 1.09 60,000 65,400.00
AGUA LTR 245.00 10 2,450.00
DESPERDICIO UND 5% 14,742.50
COSTO POR M3 309,592.50

MORTERO 1 : 3 IMPERMEABILIZADO
MATERIALES UND CANT Vr.UNIT Vr.TOTAL
CEMENTO KGR 454.00 500 227,000.00
ARENA BLANCA M3 1.09 60,000 65,400.00
AGUA LTR 245.00 10 2,450.00
SIKA 1 KGR 20.00 8,000 160,000.00
DESPERDICIO UND 5% 22,742.50
COSTO POR M3 477,592.50

MORTERO 1 : 2
MATERIALES UND CANT Vr.UNIT Vr.TOTAL
CEMENTO KGR 610.00 500 305,000.00
ARENA BLANCA M3 0.97 65,000 63,050.00
AGUA LTR 220.00 10 2,200.00
DESPERDICIO UND 5% 18,512.50
COSTO POR M3 388,762.50

COSTO DIRECTO FORMALETA

FORMALETA
MATERIALES UND CANT Vr.UNIT Vr.TOTAL
TABLA ORDINA UND 1.00 1,500.00 1,500.00
LISTON ORDINA UND 1.00 1,500.00 1,500.00
GUADUAS UND 1.00 1,000.00 1,000.00
PUNTILLAS KG 0.10 2,500.00 250.00
ALAMBRE DE A KG 0.20 2,000.00 400.00
DESPERDICIO UND 5% 232.50
COSTO POR M3 4,882.50
ANALISIS DE PRECIOS UNITARIOS

ANALISIS DE CUADRILLAS

CUADRILLA DE DEMOLICIONES JNAL COSTOS DIRECTOS

DESCRIPCION CANT. UND VR. UNITARIO MATERIAL EQUIPO M. OBRA OTRO

OFICIAL DE OBRA
INC PRESTACIONES 1.00 DIA 65,000.00 65,000.00
OBRERO INC
PRESTACIONES 4.00 DIA 50,000.00 200,000.00

CUADRILLA DE
DEMOLICIONES 265,000.0 /JNAL 0.00 0.00 265,000.00 0.00

CUADRILLA DE ALBAÑILERIA Y ACABADOS JNAL COSTOS DIRECTOS

DESCRIPCION CANT. UND VR. UNITARIO MATERIAL EQUIPO M. OBRA OTRO


MAESTRO DE
OBRA INC
PRESTACIONES 1.00 DIA 95,000.00 95,000.00

OFICIAL DE OBRA
INC PRESTACIONES 1.00 DIA 65,000.00 65,000.00
OBRERO INC
PRESTACIONES 1.00 DIA 50,000.00 50,000.00

CUADRILLA DE
ALBAÑILERIA Y
ACABADOS 210,000.0 /JNAL 0.00 0.00 210,000.00 0.00

CUADRILLA DE EXCAVACIONES Y RELLENOS JNAL COSTOS DIRECTOS

DESCRIPCION CANT. UND VR. UNITARIO MATERIAL EQUIPO M. OBRA OTRO


MAESTRO DE
OBRA INC
PRESTACIONES 1.00 DIA 95,000.00 95,000.00
OBRERO INC
PRESTACIONES 4.00 DIA 50,000.00 200,000.00
CUADRILLA DE
EXCAVACIONES Y
RELLENOS 295,000.0 /JNAL 0.00 0.00 295,000.00 0.00

CUADRILLA DE CONCRETOS JNAL COSTOS DIRECTOS

DESCRIPCION CANT. UND VR. UNITARIO MATERIAL EQUIPO M. OBRA OTRO


MAESTRO DE
OBRA INC
PRESTACIONES 1.00 DIA 95,000.00 95,000.00
OFICIAL INC
PRESTACIONES 2.00 DIA 65,000.00 130,000.00
OBRERO INC
PRESTACIONES 2.00 DIA 50,000.00 100,000.00

CUADRILLA DE
CONCRETOS 325,000.0 /JNAL 0.00 0.00 325,000.00 0.00

CUADRILLA DE ESTUCO Y PINTURA JNAL COSTOS DIRECTOS

DESCRIPCION CANT. UND VR. UNITARIO MATERIAL EQUIPO M. OBRA OTRO


MAESTRO DE
OBRA INC
PRESTACIONES 1.00 DIA 95,000.00 95,000.00
OBRERO INC
PRESTACIONES 4.00 DIA 50,000.00 200,000.00

CUADRILLA DE
ESTUCO Y PINTURA 295,000.0 /JNAL 0.00 0.00 295,000.00 0.00

CUADRILLA DE INSTALACIONES ELECTRICAS JNAL COSTOS DIRECTOS

DESCRIPCION CANT. UND VR. UNITARIO MATERIAL EQUIPO M. OBRA OTRO


TECNICO
ELECTRICISTA INC
PRESTACIONES 1.00 DIA 95,000.00 95,000.00
OFICIAL INC
PRESTACIONES 1.00 DIA 65,000.00 65,000.00
OBRERO INC
PRESTACIONES 2.00 DIA 50,000.00 100,000.00
CUADRILLA DE
INSTALACIONES
ELECTRICAS 260,000.0 /JNAL 0.00 0.00 260,000.00 0.00

CUADRILLA DE INSTALADORES CARPINTERIA EN ALUMINIO O MADERA JNAL COSTOS DIRECTOS

DESCRIPCION CANT. UND VR. UNITARIO MATERIAL EQUIPO M. OBRA OTRO


MAESTRO DE
OBRA INC
PRESTACIONES 1.00 DIA 95,000.00 95,000.00
OFICIAL INC
PRESTACIONES 1.00 DIA 65,000.00 65,000.00
CUADRILLA DE
INSTALADORES
CARPINTERIA EN
ALUMINIO O
MADERA 160,000.0 /JNAL 0.00 0.00 160,000.00 0.00

FORMALETA COMUN M2 COSTOS DIRECTOS

DESCRIPCION CANT. UND VR. UNITARIO MATERIAL EQUIPO M. OBRA OTRO


TABLA ORDINARIA 2.00 UND 7,000.00 14,000.00
LISTON ORDINARIO 2.000 UND 8,000.00 16,000.00
GUADUA 1.000 UND 7,000.00 7,000.00
PUNTILLAS 0.20 KG 3,000.00 600.00
ALAMBRE DE AMAR 0.20 KG 3,000.00 600.00

FORMALETA COMU 38,200.0 /M2 38,200.00 0.00 0.00 0.00

MORTERO 1:3 M3 COSTOS DIRECTOS

DESCRIPCION CANT. UND VR. UNITARIO MATERIAL EQUIPO M. OBRA OTRO


CEMENTO GRIS 450.00 KG 530.00 238,500.00
ARENA BLANCA 1.050 M3 40,000.00 42,000.00
AGUA 180.000 LTR 20.00 3,600.00

MORTERO 1:3 284,100.0 /M3 284,100.00 0.00 0.00 0.00


185 * 5 925
muros 1er piso
1
1
1.13
0.66
3
0.27
0.97
3.98
1.55
0.7
1.73
0.7
0.97
2.56
1
0.4
0.85
2.56
1
1.86
2.02
1.6
2
2.81
0.34
1.17
1.51
1
1.75
2.5
1.64
1.29
0.55
0.6
2.89
3.12
0.82
0.72
0.57
1.33
1.9
2.13
1.4
0.98
4
4
10
total m 62
por la altura 2.5
total 155.6
mas 10 m 10
total muros 1er
piso m4 165.6

total muros 1er


y 2do piso 327.245

estuco interior1piso
1
1.13
0.66
1.4
0.98
3.3
0.27
0.97
1.52
2.5
1.65
0.7
1.73
0.7
0.97
0.4
2.75
0.85
2.75
0.7
0.8
2.9
2
1.95
1.51
3.33
1.51
1.17
2.3
2.3
1.7
2.42
1.5
1.7
1.84
0.57
1.61
1.5
7
0.55
total 67.09

por la h 2.5
total 167.725

8
2.28
0.9
0.9
1.26
2.06
2.18
total 1er piso
m2 185.305

estuco exterior 1piso


1
1.13
0.66
3.3
0.27
0.97
1.52

1.65
0.7
1.73
0.7
0.97
0.4
0.85
2.9
2
1.95
1.51
1.51
1.17
1.17
0.57
1.61
0.98
0.98
0.98
0.7
0.4
total 34.28
por la h 2.5
total 85.7
8
2.28
0.9
0.9
1.26

2.06
2.18
total 1er piso
m2 exterior 103.28

ventana metalica vidrio 3mm


1.95 0.4 0.78
1.87 0.4 0.748
1 1.7 1.7
1 1.7 1.7
1.26 1.7 2.142
0.85 0.4 0.34
1.26 1.7 2.142
2.03 1.6 3.248
1.95 1.6 3.12
2.19 1.6 3.504
1.09 1.6 1.744
1.98 1.6 3.168
total 24.336

ventana cocina antepecho en forja


0.51 1.9 0.969
total por 6
unidades 6 5.814

electrico
toma doble
1
1
4
1
1
3
2
2
1
1
4
1

1
1
2
1
2
total doble 29

COLUMNAh7,40 COLUMNAh 6,50


FLEJES FLEJES
18 18
8 8
7 7
8 8
8 8
3 3
8 8
9 7
10 8
8 8
4 3
5
3
99 86

ELECTRICO
6.7 1.89 2.71
0.81 1.8 2
2.67 1.9 1.2
2.81 1.2 1.25
1.89 1 1.2
1.8 1.8 0.8
0.58 0.72 1.2
1.2 2 2.06
1.36 0.71 0.74
0.56 1.2 0.34
1.8 3.3 0.7
2.66 1.42 1.2
3 1.2 1.53
3.7 2.26 1.8
1.26 1.84 2.5
1.2 1.8 3.44
1.18 1.76 1.2
0.52 1.8 5
1.8 1.8 1.24
1.03 1.2 3
1.2 3.4 1.64
2.11 1.2 1.8
1.8 3.16 3
1.51 0.4 2
1.8 1.54 0.95
1.51 0.75 1.6
1.8 3.16 1.53
50.26 46.21 47.63
TOTAL 1er y 2do PISO
TOTAL ELECTRICO N12
muros 2dopiso cubiertas teja eternit
0.56 cubierta 1 91
0.83 cubierta 2 44
2.38 total m2 135
3.64
0.26
0.4
0.61 cubierta policarbonato
1.75 cubierta 3 11
0.98 cubierta zona bbq 5.5
0.37 cubierta acceso ppal 12
0.89 ajuste 1.5
0.68 total m2 30
2.77
0.42
0.57
1.8 superboard o rh exteriores
1.8 balcon jacuzzi 10
2.03 sala y balcon alcoba 17
3.09 cocina 10.6
3 baño 1 2.2
1 baño 2 3.21
0.8 baño 3 3.21
1.7 jaccuzi 12.5
0.72 total m2 58.72
1.97
1.1
2.03
1.8 cielo raso panel yeso
1.5 1er piso 115
2.22 2do piso 113
2.36 total m2 228
1.16
0.21
0.71
2.36 cartera de cubierta en rh
0.75 9.38
1.4 1.78
0.5 5.86
1.66 6.17
1.93 6.9
1.1 9.38
1.07 11.68
0.6 4.52
1.11 1.35
2.76 2.77
0.31 2.82
0.6 0.54
2 5.5
4.9 total ml 68.65
1.7
15.42 2.8

total m 58.49
por altura 2.5 enchapes baños
total 146.225 baño 1 lineal 5.48
mas 15,42m 15.42 baño2 lineal 6.55

total muros
2do piso m2 161.645 baño 3 lineal 6.55
jacuzzi 3 paredes 9.5
total ml 28.08

por altura 2.5


total m2 70.2

estuco interior 2piso pasamanos en madera internos casa


0.83 3.52
3.28 5.3
3.64 1.63
3.13 5.9
4.33 5.18
1.03 total Ml 21.53
1.97
0.72
3.13
2.16
1.69 instalacion hidrahulica
1.69 3
0.8 4.9
0.8 0.8
3.74 0.9
2 2.1
1.53 3
2.22 1
3.81 5
1.2 4.7
3.81 2.8
0.77 1.5
0.71 3
3.17 1
1.07 6.3
1.07 3.5
4.74 0.4
6.6 0.5
1.7 3
5.1 5
1.12 2.5
1.84 1.8
0.68 0.6
0.89 2.35
0.98 1.62
1.75 0.38
1.3 1
8.53 72.47 1
h 2.5 1
181.175 1.85
mas 8.53 2
total 2do
piso m2 189.705 1.8
0.6
total 1er y 2do piso
hidrahulica 70.9

estuco interior
1er piso 185.305 llaves de paso
2do piso 189.705 1er piso 5
total 375.01 2do piso 3
total 8

hidrahulica T"
1er piso 16
2do piso 5
estuco interior 2piso total 21
0.83
3.64
0.72 Punto hidrahulico
2 8
2.22 21
0.71 23
3.17 1
1.07 1
1.07 Total 54
6.6
1.7
5.1 sanitaria de 4"
1.12 4.6
1.84 8.7
0.68 0.77
0.89 2.5
0.98 1.1
1.3 1.12
1.4 1.95
0.21 4.3
2 1.28
0.67 1
0.57 2.5
0.42 2
0.77 Total 31.82
0.41
total 42.09
por la h 2.5 sanitaria de 3"
total 105.225 0.76
2.28 0.51
1.97 0.81
1.53 1
1.75 0.6
1.4 0.52
2.07 1.03
4.9 2.12
3 1.25
total 2do
piso m2 124.125 1.03
1.15

1
2.62
estuco exterior 1.66
1er piso 103.28 1.28
2do piso 124.125 Total 17.34
total 227.405

Ventana con celosia en madera vidrio 4mm


2.01 5 10.05
2.56 5 12.8
2.62 3 7.86
total 30.71

puerta corrediza vidrio 4mm


1.98 2.2 4.356
1.41 2.2 3.102
2.26 2.2 4.972
1.44 2.2 3.168
1.58 2.2 3.476
total 19.074

closeths
1.73 2.2 3.806

2.44 2.2 5.368


2.64 2.2 5.808
2.43 2.2 5.346
total 20.328

electrico electrico
apagador doble apagador sencillo
1 2
1 1
1 1
1 1
1 1
1 1
1 1
1 1
2 total apagador sencillo 9
1
1

total
apagador
doble 12 panel led
led de 12w
2
2
1
1
2
2
2
5
1
1
1
2
led de 12w 22

viga de cimentacion viga de entrepiso


5.75 120.64
4.44 volado 2 piso 1.68
3.76 total 122.32
2.84
7.92
2.71 phr c 2,20x80x2.5mm
3.88 3.62 5
11.77 5.04 4
11.85 2.69 2
4.17 3.898 2
9.72 7 2
12 5.85 1
11 3.95 1
9.69 2.12 1
4.42 total
11.16
3.56
6.88

total v
cimentacion 120.64

1.65 1.2
1.8 3
1.78 1.09
1.2 1.2
2.21 2
5 1.14
2.55 1.2
0.3 1.1
1.2 1.8
2.9 3.35
3.55 1.5
1.2 1.2
1.23 2
1.2 1.8
1.8 1.78
2.3 1.8
1.58 1
1.8 1.8
1.8 1.15
1.2 1
1.8 1.2
1.2 3.6
0.6 2.15
1.8 1.2
2.8 1.85
3.38 1.8
1.85 13.3
51.68 57.21
TOTAL 1er y 2do PISO 252.99
NEVERA 3
LAVADORA 6
DUCHA 1 5
DUCHA2 12
DUCHA 3 3
DUCHA 4 3
JACUZZI 8
TOTAL ELECTRICO N12 292.99

DUCHA 1 5
DUCHA2 12
DUCHA 3 3
DUCHA 4 3
JACUZZI 8
N10 31
BORDILLOS ETAPA 1
Piso ceramico interiores CANT
1er piso 119 bordillo banca 1
2do piso 100 bordilo banca 2
219 bordillo banca 3
ajuste 14 4 bordillo banca 4
total 233 bordilo lateral der. Con borde de bancas 1,2,3,4

bordillo banca 5
Piso antideslizante bordillo banca 6
patio 3.21 3 bordilo banca 7
baño 1 2.25 bordillo ateral izq. Con bordes de bancas 5,6,7
baño 2 3.23
baño 3 3.23 TOTAL ML BORDILLOS=
jaccuzi 12.82
balcon jacuzzi 10.5 2 banca 8 y 9
balcon alcoba 2piso 3.5 TOTAL=
balcon 1 piso sala 2.6 1 Division curva de contencion
balcon 1 piso alcoba 3.9 TOTAL=
45.24
ajuste 8 TOTAL=
total 53.24
muro de ladrillo sala y comedor
5.7 5 28.5
2.25 2.5 5.625
34.125
electrico
apagador triple
1 piso 1
2 piso 1
total apagador tripe 2

panel led
led de 8w
1
1
1
2
2
1
1
1
2
2
1
2
led de 8w 17
phr c 2,20x80x2.5mm
18.1
20.16
5.38
7.796
14
5.85
3.95
2.12
77.356
AREA NETA CONSTRUIDA AREA NETA CONSTRUIDA
VALOR UND VIA ANDENES
39.3 ML ZONA AREA UND ZONA
30.5 ML 1 217 MT² 4
13.5 ML 2 3434 MT² 5
23.8 ML 3 1012 MT² 6
107.1 ML 4 342 TOTAL=
5 450
12.2 ML 6 480
12.2 ML 7 220
27.7 ML 8 680
52.1 ML 9 150
10 140
159.2 11 152

66.4 ML
66.4 ML
39.5 ML
39.5 ML

265.1 ML TOTAL= 4663 MT²


REA NETA CONSTRUIDA

AREA UND
125 MT²
216 MT²
487 MT²
828 MT²
VIVIENDA FAMILIAR EL COROSO-BARRANQUITO- LA FLORIDA 2018
PASTO - MUNICIPIO DE NARIÑO
PROYECTO CASA CAMPESTRE DIAZ GUERRERO
Item Descripción Unidad Cantidad Valor Unit. Valor Parcial
1 PRELIMINARES

1.1 1 400,000
Campamento reutilizacion de material existente Global $400,000
1.2 Desarme de casa existente M2 1 1,000,000 $1,000,000
SUBTOTAL $1,400,000

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


2 IMPLEMENTACION DE VIA
2.01 Remplanteo y trazado Global 1 500,000 $500,000
SUBTOTAL $500,000

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


3 CIMENTACION
3.01 Nivelacion zona bbq M2 63 10,000 $630,000
3.02 Relleno con material de sitio M3 56 12,000 $672,000
M3 121 71,984
3.04 Vigas Cimentacion 30x25 Concreto 3000 psi $8,684,112
3.05 Concreto simple para solado de Vigas 6cm M3 160 32,230 $5,156,774
SUBTOTAL $15,142,886

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


4 ESTRUCTURA

4.1 Columnas h 6,20m DE 30x30 zapata 1,20


concreto 3000 Psi Unidad 8 859,193 $ 6,873,543
4.2 Columnas h 5,30m DE 30x30 zapata 1,20
concreto 3000 Psi Unidad 17 766,124 $ 13,024,104
4.3 Vigas entrepiso 2 piso y viga cinta de cubierta
30x30 concreto 3000 Psi Ml 244 74,300 $ 18,129,200
4.4 PHR de cubierta C 2.20x80X2.5 Ml 77 31,350 $ 2,413,950
4.5 Viga IPE 160MM Ml 24 59,950 $ 1,438,800
4.6 Metaldeck 2 calibre 22 losa h 0.10m M2 129 105,280 $ 13,581,120
4.8 extructura escalera metalica en viga sanca +
escalones en madera 1,20x0,35 H, 2.50 Unidad 18 210,000 $ 3,780,000
SUBTOTAL $ 59,240,718

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


5 MAMPOSTERIA Y PAÑETES
5.1 Muros ladrillo común M2 327 34,217 $ 11,197,425
5.2 Afinado muros interiores y exteriores M3 602 10,150 $ 6,110,300
5.3 Pañete E= 2CM M3 602 16,484 $ 9,923,085
5.4 Lavadero zona de ropas Ml 1.0 300,000 $ 300,000
5.5 Chimenea h. 7m Unidad 1.0 971,050 $ 971,050
SUBTOTAL $ 28,501,860

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


6 CUBIERTA

6.3 Suministro e instalacion Teja eternit odulada


n#6 terminada en color terracota M2 135 35,946 $ 4,852,710

6.4 Policarbonato cristal cubierta 3 zona bbq y


acceso principal M3 30.00 100,250 $ 3,007,500
SUBTOTAL $ 7,860,210

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


7 CIELO RASO

Cielo raso exterior en RH color blanco exteriores


7.1 de balcones, cocina, zona de ropas y baños M2 59 49,140 $ 2,885,507
7.2 Cielo raso de interiores en panel yeso M3 228 39,889 $ 9,094,578
7.4 Cartera Cielo raso en RH e=.15cm Ml 69 25,150 $ 1,726,548
SUBTOTAL $ 13,706,632

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


8 INSTALACIONES HIDRAULICAS
Suministro y tendido de red de 1/2" Ml 71 5,000 $ 354,500
8.2 Llave de Paso de 1/2 incluye caja plastica Unidad 8 $ 24,268 $ 194,140
8.3 UNION EN T 1/2 Unidad 21 $ 500 $ 10,500
8.4 Codos 90 1/2 PLG Unidad 23 $ 300 $ 6,900
8.6 Codos 45 1/2 PLG Unidad 1 $ 300 $ 300
8.5 Punto hidraulico 1/2 pvc Unidad 26 $ 50,579 $ 1,315,041
8.7 Contador de registro -acometida ppl.( Mtrs) Unidad 1 $ 700,000 $ 700,000
SUBTOTAL $ 2,581,381

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


9 INSTALACIONES SANITARIAS
9.1 Suministro deTendido de red de 4plg Ml 32 $ 20,974 $ 667,386
9.2 Suministro deTendido de red 3plg Ml 17 $ 13,834 $ 239,878
9.3 Union en T de 3" Unidad 10 $ 4,500 $ 45,000
9.4 Codos 90 de 3" Unidad 13 $ 4,500 $ 58,500
9.5 Codo 45 de 3" Unidad 1 $ 4,500 $ 4,500
9.6 Union en T de 4" Unidad 2 $ 4,500 $ 9,000
9.7 Codos 90 de 4" Unidad 3 $ 4,500 $ 13,500
9.8 Reducion 4X3 Unidad 3 $ 8,500 $ 25,500
9.9 Suministro rejilla sifon con sosco de 3"
VALVULA ANTIRRETORNO PVC SANITARIA Unidad 6 $ 11,140 $ 66,840
9.10 Caja de inspeccion 60x60cm Unidad 4 $ 364,836 $ 1,459,345
9.11 Punto sanitario Pto 20 $ 58,775 $ 1,175,490
9.12 Pozo septico (volumen 3000Litros- largo2,20-
prof 1,20-ancho 1,20) Unidad 1 $ 1,143,350 $ 1,143,350
SUBTOTAL $ 4,908,289

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


10 INSTALACIONES PLUVIALES
10.1 Bajante blanco x3m unidad 8 45,000 $ 360,000
10.2 Union bajante Unidad 6 3,500 $ 21,000
10.3 soporte de bajante Unidad 24 1,200 $ 28,800
10.4 codo bajante 45" Unidad 2 5,000 $ 10,000
10.6 Tanque de reserva 500L Unidad 1 130,000 $ 130,000
SUBTOTAL $ 549,800

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


11 INSTALACION ELECTRICA
11.1 Suministro contador electrico monofasico Unidad 1 50,000 $ 50,000
Suministro e instalacion Tablero de distribucion
11.2 8 circuitos Unidad 1 338,550 $ 338,550
11.3 Suministro alambre de cobre centelsa.#12. ROLLO 8 98,000 $ 784,000
11.4 Suministro alambre de cobre centelsa.#10 Ml 31 2,000 $ 62,000
11.6 Tubo conduit 1/2" Ml 293 800 $ 234,400

11.7 Punto y suministro de tomacorrientes doble Unidad 29 37,825 $ 1,096,925


11.8 Punto y suministro interruptor sencillo Unidad 9 36,825 $ 331,425
11.9 Punto y suministro interruptor doble Unidad 12 39,825 $ 477,900
11.10 Punto y suministro interruptor triple Unidad 2 44,825 $ 89,650
11.11 Punto y suministro interruptor conmutable Unidad 2 41,825 $ 83,650
11.12 Punto y Suministro panel led 8w Unidad 17 28,900 $ 491,300
11.13 Punto y Suministro panel led 12 w Unidad 22 31,400 $ 690,800
11.14 Punto y suministro de Ducha Unidad 4 130,625 $ 522,500
SUBTOTAL $ 5,253,100

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


12 ENCHAPES

12.2 Enchape de baños (en jacuzzi solo tres paredes) M2 70 47,508 $ 3,325,525
12.3 Enchape de cocina ( pared lavaplatos) M2 5 47,508 $ 237,538
12.4 Cenefa de cocina tipo diseño 25X35 Unidad 2 52,418 $ 104,835
12.5 Enchape lavadero (pared 1,20x0,70) M2 3.0 33,548 $ 100,643
SUBTOTAL $ 3,768,540
Item Descripción Unidad Cantidad Valor Unit. Valor Parcial
13 CERAMICAS Y PISOS
13.1 Piso ceramico interiores M2 233 43,674 $ 10,175,974
13.2 Piso ceramico trafico pesado para garaje M2 23 44,514 $ 1,023,822
13.3 Piso antideslizante baños, zona de ropa y balcones M2 53 39,224 $ 2,088,270
SUBTOTAL $ 13,288,067

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


14 ESTUCOS Y PINTURAS
14.1 Estuco Interior M2 375 16,552 $ 6,207,091
14.2 Estuco exterior M2 227 18,372 $ 4,177,839
14.3 Pintura muros exteriores blanco koraza M2 227 11,586 $ 2,634,625
14.4 Pintura muros interiores vinilo tipo 2 blanca M2 375 10,626 $ 3,984,709
SUBTOTAL $ 17,004,264

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


15 APARATOS SANITARIOS
15.1 Kit sanitario baños Unidad 4 280,000 $ 1,120,000
Tina francesa 2 personas hidromasaje 1,81X1,23
15.2 prof 58cm Unidad 1 2,500,000 $ 2,500,000
SUBTOTAL $ 3,620,000

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


16 CARPINTERIA METALICA

16.1 Elaboracion e instalacion de porton acceso a $ 1,000,000


finca. Unidad 1 $ 1,000,000
16.2 Elaboracion e instalacion de porton garaje casa. $ 1,100,000
Unidad 1 $ 1,100,000
16.2 Chapas Yale de seguridad Unidad 1 $ 90,000 $ 90,000
Elaboracion e instalacion de divisiones de baño
16.3 en acrilico $ 1,120,000
Unidad 4 $ 280,000
16.4 Ventana metalica M2 24 $ 180,000 $ 4,380,480
16.5 Ventana con celosia M3 31 $ 200,000 $ 6,142,000
16.6 Ventana cocina antepecho en forja M4 6 $ 220,000 $ 1,279,080
16.7 Puerta corrediza vidrio 4mm M3 19 $ 250,000 $ 4,768,500
SUBTOTAL $ 19,880,060

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


17 CARPINTERIA EN MADERA
17.1 Cocina integral prefabricado en melamina Unidad 1 2,500,000 $ 2,500,000
17.2 Barra en madera Unidad 1 280,000 $ 280,000
17.3 Mini bar Unidad 1 1,000,000 $ 1,000,000
17.4 Closeth empotrados en melamina M2 20 320,000 $ 6,504,960
17.5 Porton pricipal en madera Unidad 1 700,000 $ 700,000
17.6 Puertas de habitaciones y baños entamboradas Unidad 12 320,000 $ 3,840,000
17.7 Pasamanos de balcones Ml 22 260,000 $ 5,720,000
SUBTOTAL $ 20,544,960

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


18 EQUIPOS ESPECIALES
Acuario en vidrio incluye mueble en madera.
18.1 1,70x1,00x0,60 Unidad 1 1,000,000 $ 1,000,000
SUBTOTAL $ 1,000,000

Item Descripción Unidad Cantidad Valor Unit. Valor Parcial


19 ASEO
19.1 Acarreos Unidad 3 100,000 $ 300,000
19.2 Aseo general obra Jornal 5 50,000 $ 250,000
SUBTOTAL $ 550,000

COSTO DIRECTO $ 219,300,766


COSTO INDIRECTO $ 17,544,061
ADMINISTRACION $ 6,579,023 3%
IMPREVISTOS $ 6,579,023 3%
UTILIDAD $ 4,386,015 2%
COSTO TOTAL $ 236,844,827

ultima actualizacion 12/16/2020 14:23

CONTRATANTE CONTRATISTA
* ANEXO
A.1 IMPLEMENTACION DE VIA
A.1.1 Remplanteo y trazado de via (176ml x3m) global 1 500,000 $500,000
A.1.2 Alquiler de maquina global 1 1,500,000 $1,500,000
A.1.3 Alisado con Recebo 7cm m2 528 10,035 $5,298,480
A.1.4 Placa huella en adoquin(20X10cm) 50 cm de ancho ml 176 57,477 $10,115,930
TOTAL $16,914,410
24
bajante x 3m 49500
soporte bajante 1900
union bajante 3700
codo bajante 45 5200
codo bajante 90 5950
$ 219,300,766
NRO. ITEM: no tiene para este presupuesto
ITEM: toma corriente GFCI
UNIDAD DE
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Pulidora dia 1 0.008 $ 50,000 $ 400
Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 1,050

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL

toma corriente GFCI und 1 $ 45,000 $ 45,000


Caja, Curva,
Adaptador,
Terminales GLB 1.000 1 $ 1,500 $ 1,500
desperdicio glb 1 0.05 $ 1,500 $ 75
SUBTOTAL $ 46,575

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
INSTALACIONES
ELECTRICAS HC 1 0.02 $ 260,000 $ 5,200
SUBTOTAL $ 5,200

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.01 $ 100,000 $ 1,000
TRANSPORTE VIAJE 0.1 $ 10,000 $ 1,000
ALIMENTACION und 0.2 $ 13,000 $ 2,600
SUBTOTAL 4,600

COSTO DIRECTO $ 57,425

NRO. ITEM: 11.7


ITEM:
UNIDAD DE Punto y suministro de tomacorrientes doble
MEDIDA: und
FECHA: 12/16/2020 14:23
EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Pulidora dia 1 0.008 $ 50,000 $ 400
Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 1,050

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL

toma corrinte doble


con polo a tierra und 1 $ 16,000 $ 16,000
Caja, Curva,
Adaptador,
Terminales GLB 1.000 1 $ 1,500 $ 1,500
desperdicio glb 1 0.05 $ 1,500 $ 75
SUBTOTAL $ 17,575

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO

CUADRILLA DE
INSTALACIONES
ELECTRICAS HC 1 0.06 $ 260,000 $ 15,600
SUBTOTAL $ 15,600

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.2 $ 13,000 $ 2,600
SUBTOTAL 3,600

COSTO DIRECTO $ 37,825

NRO. ITEM: 11.8


ITEM:
UNIDAD DE Punto y suministro interruptor sencillo
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Pulidora dia 1 0.008 $ 50,000 $ 400
Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 1,050
MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
Caja, Curva,
Adaptador, sencillo
interruptor und 1 $ 15,000 $ 15,000
Terminales GLB 1.000 1 $ 1,500 $ 1,500
desperdicio glb 1 0.05 $ 1,500 $ 75
SUBTOTAL $ 16,575

MANO DE OBRA
CUADRILLA DE
DESCRIPCION
INSTALACIONES UND CANT. RENDIMIENTOV/R UNITARIOV/R PARCIAL
ELECTRICAS HC 1 0.06 $ 260,000 $ 15,600
SUBTOTAL $ 15,600

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.2 $ 13,000 $ 2,600
SUBTOTAL 3,600

COSTO DIRECTO $ 36,825

NRO. ITEM: 11.9


ITEM:
UNIDAD DE Punto y suministro interruptor doble
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Pulidora dia 1 0.008 $ 50,000 $ 400
Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 1,050

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
Caja, Curva,
interruptor doble
Adaptador, und 1 $ 18,000 $ 18,000
Terminales GLB 1.000 1 $ 1,500 $ 1,500
desperdicio glb 1 0.05 $ 1,500 $ 75
SUBTOTAL $ 19,575

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
INSTALACIONES
ELECTRICAS HC 1 0.06 $ 260,000 $ 15,600
SUBTOTAL $ 15,600

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.2 $ 13,000 $ 2,600
SUBTOTAL 3,600

COSTO DIRECTO $ 39,825

NRO. ITEM: 11.10


ITEM:
UNIDAD DE Punto y suministro interruptor triple
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Pulidora dia 1 0.008 $ 50,000 $ 400
Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 1,050

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
Caja, Curva,
Adaptador, triple
interruptor und 1 $ 23,000 $ 23,000
Terminales GLB 1.000 1 $ 1,500 $ 1,500
desperdicio glb 1 0.05 $ 1,500 $ 75
SUBTOTAL $ 24,575

MANO DE OBRA
CUADRILLA DE
DESCRIPCION
INSTALACIONES UND CANT. RENDIMIENTOV/R UNITARIOV/R PARCIAL
ELECTRICAS HC 1 0.06 $ 260,000 $ 15,600
SUBTOTAL $ 15,600

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.2 $ 13,000 $ 2,600
SUBTOTAL 3,600
COSTO DIRECTO $ 44,825

NRO. ITEM: 11.11


ITEM:
UNIDAD DE Punto y suministro interruptor conmutable
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Pulidora dia 1 0.008 $ 50,000 $ 400
Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 1,050

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL

Caja, interruptor
Curva,
conmutable
Adaptador, und 1 $ 20,000 $ 20,000
Terminales GLB 1.000 1 $ 1,500 $ 1,500
desperdicio glb 1 0.05 $ 1,500 $ 75
SUBTOTAL $ 21,575

MANO DE OBRA
CUADRILLA DE
DESCRIPCION
INSTALACIONES UND CANT. RENDIMIENTOV/R UNITARIOV/R PARCIAL
ELECTRICAS HC 1 0.06 $ 260,000 $ 15,600
SUBTOTAL $ 15,600

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.2 $ 13,000 $ 2,600
SUBTOTAL 3,600

COSTO DIRECTO $ 41,825

NRO. ITEM: 11.2


ITEM: Suministro e instalacion Tablero de distribucion 8 circuitos
UNIDAD DE
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO

Herramienta menor Glb $1 $0 $ 1,300 $ 650

SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
Tablero 2 fases 6
circuitos UND 1 0 $ 89,000 $ 89,000
Breaker UND 8 0 $ 9,000 $ 72,000

Accesorios instalación GLB 1 0 $ 5,000 $ 5,000


desperdicio GLB 1 0.05 $ 166,000 $ 8,300

SUBTOTAL $ 174,300

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO

CUADRILLA DE
INSTALACIONES
ELECTRICAS HC 1 0.6 $ 260,000.00 $ 156,000.00

SUBTOTAL $ 156,000.00

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.04 $ 100,000 $ 4,000
TRANSPORTE VIAJE 0.1 $ 10,000 $ 1,000
ALIMENTACION und 0.2 $ 13,000 $ 2,600
SUBTOTAL 7,600

COSTO DIRECTO $ 338,550

NRO. ITEM: 11.12


ITEM: Punto y Suministro panel led 8w
UNIDAD DE
MEDIDA: und
FECHA: 12/16/2020 14:23
EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta menor Glb 0.500 0.000 $ 2,000 $ 1,000
SUBTOTAL $ 1,000

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
Luminaria led 8w 1 $ 9,000 $ 9,000
SUBTOTAL $ 9,000

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO

CUADRILLA DE
INSTALACIONES
ELECTRICAS HC 1 0.06 $ 260,000 $ 15,600
SUBTOTAL $ 15,600

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.01 $ 100,000 $ 1,000
TRANSPORTE VIAJE 0.1 $ 10,000 $ 1,000
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 3,300

COSTO DIRECTO $ 28,900

NRO. ITEM: 11.14


ITEM: Punto y suministro de Ducha
UNIDAD DE
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Pulidora dia 1 0.008 $ 50,000 $ 400
Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 1,050

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
ducha electrica und 1 0 $ 65,000 $ 65,000
llave agua de ducha und 1 0 $ 25,000 $ 25,000
tubo conduit 1/2" ML 10.000 1 $ 800 $ 8,000
Caja, Curva,
Adaptador,
Terminales GLB 1.000 1 $ 1,500 $ 1,500
desperdicio glb 1 0.05 $ 9,500 $ 475
SUBTOTAL $ 99,975

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
INSTALACIONES
ELECTRICAS HC 1 0.1 $ 260,000 $ 26,000
SUBTOTAL $ 26,000

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.2 $ 13,000 $ 2,600
SUBTOTAL 3,600

COSTO DIRECTO $ 130,625

NRO. ITEM: 11.13


ITEM: Punto y Suministro panel led 12 w
UNIDAD DE
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta menor Glb 0.500 0.000 $ 2,000 $ 1,000
SUBTOTAL $ 1,000

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
Luminaria led 12w 1 $ 11,500 $ 11,500
SUBTOTAL $ 11,500

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
INSTALACIONES
ELECTRICAS HC 1 0.06 $ 260,000 $ 15,600
SUBTOTAL $ 15,600

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.01 $ 100,000 $ 1,000
TRANSPORTE VIAJE 0.1 $ 10,000 $ 1,000
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 3,300

COSTO DIRECTO $ 31,400


tubo connduit de 1/2"
NRO. ITEM: 8.2
ITEM: Llave de Paso de 1/2 incluye caja plastica
UNIDAD DE
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO

Herramienta
menor Glb $1 $0 $ 1,300 $ 650

SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
Llave de
paso 1/2" UND 1 - 7,800 7,800
Soldadura
PVC líquida
1/4 Gl UND 0 - 50,000 1,250
Limpiador
PVC 1/4 Gl UND 0 - 26,000 650
Adaptador
macho 1/2" UND 2 - 600 1,200
Cinta Teflón GLB 1 0.50 500 250

caja Registro
llave de paso
PVC 20*20 und 1 - 10,000 10,000

desperdicio GLB 1 0.05 3,350 168


SUBTOTAL 21,318

MANO DE OBRA
CUADRILL
A DE
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
ALBAÑILER
IA Y
ACABADOS HC 1 0.1 $ 0.00 $ 0.00 no colocar porque ya esta el punto hidraulico a

SUBTOTAL $ 0.00

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTA $ 1,300
CION und 0.1 $ 13,000
SUBTOTAL 2,300

COSTO DIRECTO $ 24,268

NRO. ITEM: 8.5


ITEM: Punto hidraulico 1/2 pvc
UNIDAD DE
MEDIDA: und
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO

Herramienta
menor Glb 0.500 0.000 $ 1,300.00 $ 650.00

SUBTOTAL $ 650.00

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
Soldadura
PVC líquida Tubería PVC
1/4 Gl UND 0.010 0.00 50,000.00 $ 500.00 presión 1/2"
Limpiador
PVC 1/4 Gl UND 0.010 0.00 17,000.00 $ 170.00
Cinta Teflón GLB 1.000 0.00 500.00 $ 500.00

desperdicio GLB 1 0.05 $ 1,170.00 $ 58.50

SUBTOTAL $ 1,229

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO

CUADRILL
A DE
ALBAÑILER
IA Y
ACABADOS HC 1 0.22 $ 210,000.00 $ 46,200.00

SUBTOTAL $ 46,200.00
TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.007 $ 100,000 $ 700
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTA $ 1,300
CION und 0.1 $ 13,000
SUBTOTAL 2,500

COSTO DIRECTO $ 50,579

sanitaria

NRO. ITEM: 9.1


ITEM: Suministro deTendido de red de 4plg
UNIDAD DE
MEDIDA: ML
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO

Herramienta
menor Glb 0.500 0.000 $ 1,300.00 $ 650.00

SUBTOTAL $ 650.00

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
Tubo
sanitario PVC
4" ML 1.000 0 14,000.00 14000
Soldadura
PVC líquida
1/4 Gl UND 0.030 0.00 50,000.00 $ 1,500.00
Limpiador
PVC 1/4 Gl UND 0.070 0.00 17,000.00 $ 1,190.00

desperdicio GLB 1 0.02 $ 16,690.00 $ 333.80


SUBTOTAL $ 17,023.80

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILL
A DE
ALBAÑILER
IA Y
ACABADOS HC 1 0.01 $ 0.00 $ 0.00 no colocar porque ya esta el punto hidraulico a
SUBTOTAL $ 0.00

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.01 $ 100,000 $ 1,000
TRANSPORTE VIAJE 0.1 $ 10,000 $ 1,000
ALIMENTA $ 1,300
CION und 0.1 $ 13,000
SUBTOTAL 3,300

COSTO DIRECTO $ 20,974

NRO. ITEM: 9.2


ITEM: Suministro deTendido de red 3plg
UNIDAD DE
MEDIDA: ML
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.500 0.000 $ 1,300.00 $ 650.00
SUBTOTAL $ 650.00

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
Tubo
sanitario PVC
3" ML 1.000 0 7,000 7,000
Soldadura
PVC líquida
1/4 Gl UND 0.030 0.00 50,000 1,500
Limpiador
PVC 1/4 Gl UND 0.070 0.00 17,000 1,190

desperdicio GLB 1 0.02 9,690 194

SUBTOTAL $ 9,883.80

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO

CUADRILL
A DE
ALBAÑILER
IA Y
ACABADOS HC 1 0.01 $ 0.00 $ 0.00 no colocar porque ya esta el punto hidraulico a

SUBTOTAL $ 0.00

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.01 $ 100,000 $ 1,000
TRANSPORTE VIAJE 0.1 $ 10,000 $ 1,000
ALIMENTA $ 1,300
CION und 0.1 $ 13,000
SUBTOTAL 3,300

COSTO DIRECTO $ 13,834

No ITEM: 9.9de 3" VALVULA ANTIRRETORNO


Suministro rejilla sifon con sosco
ITEM: PVC SANITARIA
UNIDAD DE
MEDIDA: Unidad
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO

Herramienta
menor Glb 0.500 0.000 $ 1,300.00 $ 650

SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
Soldadura
PVC líquida
1/4 Gl UND 0.010 0.00 50,000 500
Limpiador
PVC 1/4 Gl UND 0.020 0.00 17,000 340
codo sifon de
3" UND 1 0 $ 3,000 $ 3,000

rejilla plastica
con sosco UND 1 0 $ 4,000 $ 4,000
desperdicio GLB 1 0.05 $ 7,000 $ 350
SUBTOTAL $ 8,190

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO

CUADRILL
A DE
ALBAÑILER
IA Y
ACABADOS HC 1 0.08 $ 0.00 $ 0.00 no colocar porque ya esta el punto hidraulico a

SUBTOTAL $ 0.00

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTA $ 1,300
CION und 0.1 $ 13,000
SUBTOTAL 2,300

COSTO DIRECTO $ 11,140

NRO. ITEM: 9.10


ITEM: Caja de inspeccion 60x60cm
UNIDAD DE
MEDIDA: Unidad
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
Ladrillo
bloque
panela UND 88 0 $ 550 $ 48,400
Mortero 1:3
para pega y
repello M3 0.1 0 $ 309,593 $ 30,959
Concreto
3000 psi
para piso y
tapa M3 0.3 0 $ 300,923 $ 90,277
Acero
refuerzo
60000 psi KG 12.5 0 $ 3,000 $ 37,500
Alambre de
amarre KG 0.375 0 $ 10,000 $ 3,750
Cemento
gris para
esmaltado KG 10 0 $ 800 $ 8,000
Agua LTR 75 0 $ 20 $ 1,500
Formaleta
común M2 1 0 $ 22,000 $ 22,000
desperdicio GLB 2 0.1 $ 31,500 $ 6,300
SUBTOTAL $ 248,686

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
ALBAÑILER
IA Y
ACABADOS HC 1 0.5 $ 210,000 $ 105,000
SUBTOTAL $ 105,000

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.02 $ 100,000 $ 2,000
TRANSPORTE VIAJE 0.2 $ 10,000 $ 2,000
ALIMENTA $ 6,500
CION und 0.5 $ 13,000
SUBTOTAL 10,500

COSTO DIRECTO $ 364,836

NRO. ITEM: 9.11


ITEM: Punto sanitario
UNIDAD DE
MEDIDA: Pto
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
Soldadura
PVC líquida
1/4 Gl UND 0.070 0.00 $ 50,000 $ 3,500
Limpiador
PVC 1/4 Gl UND 0.070 0.00 $ 17,000 $ 1,190
desperdicio GLB 1 0.05 $ 4,690 $ 235
SUBTOTAL $ 4,925

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
ALBAÑILER
IA Y
ACABADOS HC 1 0.24 $ 210,000 $ 50,400
SUBTOTAL $ 50,400

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.001 $ 100,000 $ 100
TRANSPORTE VIAJE 0.01 $ 10,000 $ 100
ALIMENTA $ 2,600
CION und 0.2 $ 13,000
SUBTOTAL 2,800

COSTO DIRECTO $ 58,775

NRO. ITEM: 9.12

Pozo septico (volumen 3000Litros- largo2,20-prof 1,20-ancho


ITEM: 1,20)
UNIDAD DE
MEDIDA: Unidad
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 650
MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
Ladrillo
bloque
panela UND 280 0 $ 550 $ 154,000
Mortero 1:3
para pega y
repello M3 1 0 $ 309,593 $ 309,593
Concreto
3000 psi
para piso y
tapa M3 0.8 0 $ 300,923 $ 240,738

malla
electrosolda
da m2 2 0 $ 12,000 $ 24,000
Alambre de
amarre KG 0.1 0 $ 10,000 $ 1,000
Cemento
gris para
esmaltado KG 150 0 $ 800 $ 120,000
Agua LTR 75 0 $ 20 $ 1,500
Formaleta
común M2 1 0 $ 22,000 $ 22,000
clavos und 100 0 $ 15 $ 1,500
tubo pvc de
4" entrada ml 1 0 $ 14,000 $ 14,000
tubo pvc de
3" de salida ml 8 0 $ 7,000 $ 56,000
desperdicio GLB 2 0.1 $ 143,500 $ 28,700

SUBTOTAL $ 243,700

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
ALBAÑILER
IA Y
ACABADOS HC 1 4 $ 210,000 $ 840,000
SUBTOTAL $ 840,000

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.1 $ 100,000 $ 10,000
TRANSPORTE VIAJE 1 $ 10,000 $ 10,000
ALIMENTA $ 39,000
CION und 3 $ 13,000
SUBTOTAL 59,000
COSTO DIRECTO $ 1,143,350

instalaciones pluviales

NRO. ITEM: 10.1


ITEM: Bajante blanco x3m
UNIDAD DE
MEDIDA: ML
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
CANAL
TIPO
AMAZONAS ML 1.000 0 $ 75,000 $ 75,000
desperdicio GLB 1 0.01 $ 75,000 $ 750
SUBTOTAL $ 75,750

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
ALBAÑILER
IA Y
ACABADOS HC 1 0.1 $ 210,000 $ 21,000
SUBTOTAL $ 21,000

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTA $ 3,900
CION und 0.3 $ 13,000
SUBTOTAL 4,900

COSTO DIRECTO $ 102,300


que ya esta el punto hidraulico aparte
ML 3.000 0 1,500.00 4500
que ya esta el punto hidraulico aparte
que ya esta el punto hidraulico aparte
que ya esta el punto hidraulico aparte
malla
electrosoldada
(6x2,35=14,1m2) precio 60.000

regla de 3 14,1=60.000
NRO. ITEM: 14.1
ITEM: Estuco Interior
UNIDAD DE
MEDIDA: M2
FECHA: 3/2/2018 20:28

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
Andamio dia 1 1 $ 450 $ 450
SUBTOTAL $ 1,100

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO

Estuco Estuco Interior 25 Kg Estuka Dos Ea2207


plastico para
interiores kg 0.05 0 $ 41,000 $ 2,050

Lija de agua
#400 y 150 Cuadro 0.45 0 $ 1,200 $ 540
Andamio
metalico
tubular U/Dia 0.2 0 $ 7,000 $ 1,400

Desperdicio Glb 1 0.06 $ 5,780 $ 347


SUBTOTAL $ 4,337

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILL
A DE
ESTUCO Y
PINTURA HC 1 0.035 $ 295,000 $ 10,325
SUBTOTAL $ 10,325

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.002 $ 100,000 $ 200
TRANSPORTE VIAJE 0.02 $ 10,000 $ 200
ALIMENTA $ 390
CION und 0.03 $ 13,000
SUBTOTAL 790

COSTO DIRECTO $ 16,552


NRO. ITEM: 14.2
ITEM: Estuco exterior
UNIDAD DE
MEDIDA: M2
FECHA: 3/2/2018 20:28

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Andamio dia 1 1 $ 450 $ 450
Herramienta
menor Glb 0.400 0.000 $ 1,300 $ 520
SUBTOTAL $ 970

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO

Estuco
plastico para
interiores Galon 0.4 0 $ 10,000 $ 4,000 Sika Estuka Acrilico 5/1 * 30 Kg 2

Lija de agua
#400 y 150 Cuadro 0.45 0 $ 1,200 $ 540
Andamio
metalico
tubular U/Dia 0.2 0 $ 7,000 $ 1,400

Desperdicio Glb 1 0.06 $ 5,780 $ 347


SUBTOTAL $ 6,287

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILL
A DE
ESTUCO Y
PINTURA HC 1 0.035 $ 295,000 $ 10,325
SUBTOTAL $ 10,325

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.002 $ 100,000 $ 200
TRANSPORTE VIAJE 0.02 $ 10,000 $ 200
ALIMENTA $ 390
CION und 0.03 $ 13,000
SUBTOTAL 790

COSTO DIRECTO $ 18,372


NRO. ITEM: 14.4
ITEM: Pintura muros interiores vinilo tipo 2 blanca
UNIDAD DE
MEDIDA: m2
FECHA: 3/2/2018 20:28

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Andamio dia 1 1 $ 450 $ 450
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 1,100

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO

Pintura tipo 2 Galón 0.025 5 $ 58,000 $ 1,450

Lija de agua
#400 y 150 Cuadro 0.09 2 $ 1,200 $ 108

Desperdicio Glb 1 0.05 $ 2,552 $ 128


SUBTOTAL $ 1,686

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILL
A DE
ESTUCO Y
PINTURA HC 1 0.012 $ 295,000 $ 3,540
SUBTOTAL $ 3,540

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.002 $ 100,000 $ 200
TRANSPORTE VIAJE 0.02 $ 10,000 $ 200
ALIMENTA $ 3,900
CION und 0.3 $ 13,000
SUBTOTAL 4,300

COSTO DIRECTO $ 10,626


NRO. ITEM: 14.4
ITEM: Pintura muros exteriores blanco koraza
UNIDAD DE
MEDIDA: m2
FECHA: 3/2/2018 20:28

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Andamio dia 1 1 $ 450 $ 450
Herramienta
menor Glb 0.700 0.000 $ 1,300 $ 910
SUBTOTAL $ 1,360

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO

Pintura tipo 2 Galón 0.03 5 $ 65,000 $ 1,950

Lija de agua
#400 y 150 Cuadro 0.09 2 $ 1,200 $ 108

Desperdicio Glb 1 0.05 $ 2,552 $ 128


SUBTOTAL $ 2,186

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILL
A DE
ESTUCO Y
PINTURA HC 1 0.012 $ 295,000 $ 3,540
SUBTOTAL $ 3,540

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.003 $ 100,000 $ 300
TRANSPORTE VIAJE 0.03 $ 10,000 $ 300
ALIMENTA $ 3,900
CION und 0.3 $ 13,000
SUBTOTAL 4,500

COSTO DIRECTO $ 11,586


stuco Interior 25 Kg Estuka Dos Ea2207664acu Nuevo

41000
ika Estuka Acrilico 5/1 * 30 Kg 218248 $ 50,000
NRO. ITEM: fachaleta no se usa para este presupuesto

ITEM:
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO

Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650


Andamio dia 1 1 $ 325 $ 325
SUBTOTAL $ 975

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
fachaleta M² 1.000 9.000 $ 48,000 $ 48,000
Waipe Kg 0.100 0.000 $ 5,500 $ 550
Pegante kg 0.400 0.000 $ 13,500 $ 5,400
Emboquillador Kg 0.165 0.000 $ 5,500 $ 908
SUBTOTAL $ 54,858

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.07 $ 210,000 $ 14,700
ACABADOS
SUBTOTAL $ 14,700

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.01 $ 100,000 $ 1,000
TRANSPORTE VIAJE 0.1 $ 10,000 $ 1,000
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 3,300

COSTO DIRECTO $ 73,833

NRO. ITEM: 12.2

ITEM: Enchape de baños (en jacuzzi solo tres paredes)


UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23
EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO

Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650


SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
enchape negro coroM² 1.000 9.000 $ 23,000 $ 23,000
Waipe Kg 0.100 0.000 $ 5,500 $ 550
Pegante kg 0.400 0.000 $ 13,500 $ 5,400
Emboquillador Kg 0.165 0.000 $ 5,500 $ 908
SUBTOTAL $ 29,858

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.07 $ 210,000 $ 14,700
ACABADOS
SUBTOTAL $ 14,700

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 2,300

COSTO DIRECTO $ 47,508

NRO. ITEM: pizarra negra no se usa para este presupuesto


ITEM:
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO

Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650


Andamio dia 1 1 $ 450 $ 450
SUBTOTAL $ 1,100
MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
piedra pizarra
negra natural M² 1.000 9.000 $ 100,000 $ 100,000
Waipe Kg 0.100 0.000 $ 4,100 $ 410
Pegante kg 0.400 0.000 $ 13,500 $ 5,400
Emboquillador Kg 0.165 0.000 $ 5,174 $ 854
SUBTOTAL $ 106,664

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.07 $ 210,000 $ 14,700
ACABADOS
SUBTOTAL $ 14,700

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.01 $ 100,000 $ 1,000
TRANSPORTE VIAJE 0.1 $ 10,000 $ 1,000
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 3,300

COSTO DIRECTO $ 125,764

NRO. ITEM: 13.1


ITEM: Piso ceramico interiores
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO

Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650


SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
ceramica 40x40 M² 1.000 1.000 $ 20,000 $ 20,200
Waipe Kg 0.100 0.000 $ 4,100 $ 410
Pegante kg 0.400 0.000 $ 13,500 $ 5,400
Emboquillador Kg 0.165 0.000 $ 5,174 $ 854
SUBTOTAL $ 26,864
MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO

CUADRILLA DE
ALBAÑILERIA Y HC 1 0.066 $ 210,000 $ 13,860
ACABADOS

SUBTOTAL $ 13,860

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 2,300

COSTO DIRECTO $ 43,674

NRO. ITEM: 13.3


ITEM: Piso antideslizante baños, zona de ropa y balcones
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO

Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650


SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
ceramica 40x40 M² 1.000 9.000 $ 15,000 $ 16,350
Waipe Kg 0.100 0.000 $ 4,100 $ 410
Pegante kg 0.400 0.000 $ 13,500 $ 5,400
Emboquillador Kg 0.165 0.000 $ 5,174 $ 854
SUBTOTAL $ 23,014

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.066 $ 210,000 $ 13,860
ACABADOS
SUBTOTAL $ 13,860
TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.002 $ 100,000 $ 200
TRANSPORTE VIAJE 0.02 $ 10,000 $ 200
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 1,700

COSTO DIRECTO $ 39,224

NRO. ITEM: 12.3


ITEM: Enchape de cocina ( pared lavaplatos)
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO

Herramienta menor Glb 0.500 0.000 $ 1,300 $ 650


SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
enchape blanco cor M² 1.000 9.000 $ 18,000 $ 18,000
Waipe Kg 0.100 0.000 $ 5,500 $ 550
Pegante kg 0.400 0.000 $ 13,500 $ 5,400
Emboquillador Kg 0.165 0.000 $ 5,500 $ 908
SUBTOTAL $ 24,858

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.066 $ 210,000 $ 13,860
ACABADOS
SUBTOTAL $ 13,860

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.002 $ 100,000 $ 200
TRANSPORTE VIAJE 0.02 $ 10,000 $ 200
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 1,700
COSTO DIRECTO $ 41,068

NRO. ITEM: 12.4


ITEM: Cenefa de cocina tipo diseño 25X35
UNIDAD DE
MEDIDA: unidad
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO

Herramienta menor Glb 0.200 0.000 $ 1,300 $ 260


SUBTOTAL $ 260

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
cenefa tipo diseño unidad 1 0 35,000 35,000
Waipe Kg 0.100 0.000 $ 5,500 $ 550
Pegante kg 0.400 0.000 $ 13,500 $ 5,400
Emboquillador Kg 0.165 0.000 $ 5,500 $ 908
SUBTOTAL $ 41,858

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.04 $ 210,000 $ 8,400
ACABADOS
SUBTOTAL $ 8,400

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.003 $ 100,000 $ 300
TRANSPORTE VIAJE 0.03 $ 10,000 $ 300
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 1,900

COSTO DIRECTO $ 52,418

NRO. ITEM: 12.5


ITEM: Enchape lavadero (pared 1,20x0,70)
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO

Herramienta menor Glb 0.100 0.000 $ 1,300 $ 130


SUBTOTAL $ 130

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
enchape blanco ecoM² 1.000 9.000 $ 11,000 $ 11,000
Waipe Kg 0.100 0.000 $ 5,500 $ 550
Pegante kg 0.400 0.000 $ 13,500 $ 5,400
Emboquillador Kg 0.165 0.000 $ 5,500 $ 908
SUBTOTAL $ 17,858

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.066 $ 210,000 $ 13,860
ACABADOS
SUBTOTAL $ 13,860

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.002 $ 100,000 $ 200
TRANSPORTE VIAJE 0.02 $ 10,000 $ 200
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 1,700

COSTO DIRECTO $ 33,548


No item 7.1
ITEM: Cielo raso en pvc.-color blanco
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.800 0.000 $ 2,000 $ 1,600
Andamio dia 1 1 $ 450 $ 450
SUBTOTAL $ 2,050

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL

Cielo raso en pvc.-


color blanco M² 1 9.000 $ 35,000 $ 35,000
Omega ml 1 0.000 $ 1,300 $ 1,300
Angulos und 1 0.000 $ 400 $ 400
Viguetas ml 1 0.000 $ 1,300 $ 1,300
Tornillo driwalt und 20 0.000 $ 30 $ 600
clavos und 6 0.000 $ 15 $ 90
SUBTOTAL $ 38,690

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.08 $ 210,000 $ 16,800
ACABADOS
SUBTOTAL $ 16,800

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.001 $ 100,000 $ 100
TRANSPORTE VIAJE 0.01 $ 10,000 $ 100

$ 1,300
ALIMENTACION und 0.1 $ 13,000
SUBTOTAL 1,500

COSTO DIRECTO $ 59,040

NRO. ITEM: 7.4


ITEM: Cartera Cielo raso en RH e=.15cm
UNIDAD DE
MEDIDA: ml
FECHA:

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta menor Glb $1 $0 $ 1,300 $ 650
Andamio dia $1 $1 $ 500 $ 500
SUBTOTAL $ 1,150

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
lamina de RH
6mm UND 0.15 40000 6000
Accesorios UND 1 3000 3000
Tornillos und 10 25 250
Cinta Malla glb 0.1 15000 1500
SUBTOTAL 10750

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.055 $ 210,000.00 $ 11,550
ACABADOS

SUBTOTAL $ 11,550

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.002 $ 100,000 $ 200
TRANSPORTE VIAJE 0.02 $ 10,000 $ 200

$ 1,300
ALIMENTACION und 0.1 $ 13,000
SUBTOTAL 1,700

COSTO DIRECTO $ 25,150

No item 7.2
ITEM: Cielo raso de interiores en panel yeso
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.800 0.000 $ 2,000 $ 1,600
Andamio dia 1 1 $ 450 $ 450
SUBTOTAL $ 2,050

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
Cielo raso de
interiores en panel
yeso M² 0.41 2.000 $ 22,000 $ 9,200
Omega ml 1 9.000 $ 1,300 $ 1,417
Angulos und 1 9.000 $ 400 $ 436
Viguetas ml 1 9.000 $ 1,300 $ 1,417
Tornillo driwalt und 20 9.000 $ 30 $ 654
mastique und 0.05 9.000 $ 32,000 $ 1,744
estuco en polvo ml 0.05 9.000 $ 38,000 $ 2,071
pintura blanca m2 0.03 9.000 $ 110,000 $ 3,597
cinta malla ml 0.01 9.000 $ 30,000 $ 327
cinta papel ml 0.01 9.000 $ 30,000 $ 327
clavos und 6 9.000 $ 15 $ 98
SUBTOTAL $ 21,289

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.071 $ 210,000 $ 14,910
ACABADOS
SUBTOTAL $ 14,910

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.003 $ 100,000 $ 300
TRANSPORTE VIAJE 0.03 $ 10,000 $ 300

$ 1,040
ALIMENTACION und 0.08 $ 13,000
SUBTOTAL 1,640

COSTO DIRECTO $ 39,889

No item 7.1
Cielo raso exterior en RH color blanco exteriores de balcones,
ITEM: cocina, zona de ropas y baños
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.800 0.000 $ 2,000 $ 1,600
Andamio dia 1 1 $ 450 $ 450
SUBTOTAL $ 2,050

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL

Cielo raso exterior


en RH color blanco
exteriores de
balcones, cocina,
zona de ropas y
baños M² 0.41 3.000 $ 40,000 $ 16,892
Omega ml 1 9.000 $ 1,300 $ 1,417
Angulos und 1 9.000 $ 400 $ 436
Viguetas ml 1 9.000 $ 1,300 $ 1,417
Tornillo driwalt und 20 9.000 $ 30 $ 654
mastique und 0.05 9.000 $ 32,000 $ 1,744
estuco en polvo ml 0.05 9.000 $ 38,000 $ 2,071
pintura blanca m2 0.03 9.000 $ 110,000 $ 3,597
cinta malla ml 0.01 9.000 $ 30,000 $ 327
cinta papel ml 0.01 9.000 $ 30,000 $ 327
clavos und 6.00 9.000 $ 15 $ 98
SUBTOTAL $ 28,980

MANO DE OBRA
DESCRIPCION UND V/R UNITARIO V/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.08 $ 210,000 $ 16,800
ACABADOS
SUBTOTAL $ 16,800

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.002 $ 100,000 $ 200
TRANSPORTE VIAJE 0.02 $ 10,000 $ 200

$ 910
ALIMENTACION und 0.07 $ 13,000
SUBTOTAL 1,310

COSTO DIRECTO $ 49,140


omega 2,44m 3000 1350
angulo 1800
viguetas 2,4 3000
tornillos driw 30
clavo 15
Suministro e instalacion Teja eternit odulada n#6 terminada en
ITEM: color terracota
UNIDAD DE
MEDIDA: m2 Teja Termoacustica UPV
FECHA: 12/16/2020 14:23 215000

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.500 0.000 $ 1,500 $ 750
Andamio dia 1 1 $ 450 $ 450
SUBTOTAL $ 1,200

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R PARCIAL

Teja eternit odulada


n#6 M² 1.000 2.000 $ 16,800 $ 17,136
amarres und 4.000 0.000 $ 100 $ 400
SUBTOTAL $ 17,536

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.071 $ 210,000 $ 14,910
ACABADOS
SUBTOTAL $ 14,910

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 2,300

COSTO DIRECTO $ 35,946

ITEM: vidrio templado


UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23
EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.500 0.000 $ 1,500 $ 750
Andamio dia 1 1 $ 450 $ 450
SUBTOTAL $ 1,200

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
vidrio templado de
6mm M² 1.000 9.000 $ 98,000 $ 92,000
liston madera
achapo
terminado ml 1.000 0.000 $ 20,000 $ 20,000
dilatador de
aluminio und 2.000 0.000 $ 3,500 $ 7,000
SUBTOTAL $ 119,000

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.08 $ 210,000 $ 16,800
ACABADOS
SUBTOTAL $ 16,800

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.007 $ 100,000 $ 700
TRANSPORTE VIAJE 0.1 $ 10,000 $ 1,000
ALIMENTACION und 0.1 $ 13,000 $ 1,300
SUBTOTAL 3,000

COSTO DIRECTO $ 140,000

N# ITEM: 6.4
ITEM: Policarbonato cristal cubierta 3 zona bbq y acceso principal
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.300 0.000 $ 1,500 $ 450
Andamio dia 1 1 $ 400 $ 400
SUBTOTAL $ 850

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
POLICARBONATO
CRISTAL M² 1.000 9.000 $ 52,000 $ 52,000
perfil aluminio
rectangular
colmena ml 1.000 0.000 $ 12,000 $ 12,000
tornillo negro
para cubierta und 4.000 0.000 $ 600 $ 2,400
hualla tension und 1.600 0.000 $ 10,000 $ 16,000
soportes y
pernos de hualla unid 6.000 0.000 $ 3,500 $ 21,000
SUBTOTAL $ 66,400

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA DE
ALBAÑILERIA Y HC 1 0.14 $ 210,000 $ 29,400
ACABADOS
SUBTOTAL $ 29,400

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACION und 0.2 $ 13,000 $ 2,600
SUBTOTAL 3,600

COSTO DIRECTO $ 100,250


eja Termoacustica UPVC FORTE 5.9 x 0.94m espesor 2.5mm 
38.800 m2
NRO. ITEM: 5.1
ITEM: Muros ladrillo común
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.200 0.000 $ 1,300 $ 260
SUBTOTAL $ 260

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
ladrillo
bloque
panela und 36 0 $ 500 $ 18,000
mortero 1:4 m3 0.03 0.00 $ 267,225 $ 8,017
desperdicio glb 1 0.03 $ 8,017 $ 241
SUBTOTAL $ 26,257

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
ALBAÑILERI HC 1 0.031 $ 210,000 $ 6,510
AY
ACABADOS
SUBTOTAL $ 6,510

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.001 $ 100,000 $ 100
TRANSPORTE VIAJE 0.005 $ 10,000 $ 50
ALIMENTACI $ 1,040
ON und 0.08 $ 13,000
SUBTOTAL 1,190

COSTO DIRECTO $ 34,217

NRO. ITEM: 5.2


ITEM: Afinado muros interiores y exteriores

UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.100 0.000 $ 1,300 $ 130
SUBTOTAL $ 130

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
mortero 1:4 m3 0.02 0.00 $ 200,000 $ 4,000
desperdicio glb 1 0.08 $ 4,000 $ 320
SUBTOTAL $ 4,320

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
ALBAÑILERI HC 1 0.02 $ 210,000 $ 4,200
AY
ACABADOS
SUBTOTAL $ 4,200

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.001 $ 100,000 $ 100
TRANSPORTE VIAJE 0.01 $ 10,000 $ 100
ALIMENTACI $ 1,300
ON und 0.1 $ 13,000
SUBTOTAL 1,500

COSTO DIRECTO $ 10,150

NRO. ITEM: 5.3


ITEM: Pañete E= 2CM
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.200 0.000 $ 1,300 $ 260
SUBTOTAL $ 260
MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
MORTERO 1
:3 m3 0.03 0.00 $ 309,593 $ 9,288
desperdicio glb 1 0.02 $ 9,288 $ 186
SUBTOTAL $ 9,474

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
ALBAÑILERI HC 1 0.025 $ 210,000 $ 5,250
AY
ACABADOS
SUBTOTAL $ 5,250

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.001 $ 100,000 $ 100
TRANSPORTE VIAJE 0.01 $ 10,000 $ 100
ALIMENTACI $ 1,300
ON und 0.1 $ 13,000
SUBTOTAL 1,500

COSTO DIRECTO $ 16,484

NRO. ITEM: NO PARA ESTE PRESUPUESTO


ITEM: #NAME?
UNIDAD DE
MEDIDA: ml
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.500 0.000 $ 2,000 $ 1,000

SUBTOTAL $ 1,000

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
adoquin
20x10 M3 12.5 0.2 $ 1,500 $ 18,788
malla
electrosoldada
arena M3 0.2 0 $ 65,000 $ 13,000 6mx2.35
desperdicio glb 0.1 0.5 $ 31,788 $ 1,589
varilla 3/8 x
6mtrs
SUBTOTAL $ 33,377 1m

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
CONCRETO
S HC 1 0.052 ### $ 16,900
SUBTOTAL $ 16,900

TRANSPORTE
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACI $ 5,200
ON und 0.4 $ 13,000
SUBTOTAL $ 6,200

COSTO DIRECTO $ 57,477

NRO. ITEM: #NAME?


ITEM: #NAME?
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.400 0.000 $ 2,000 $ 800

SUBTOTAL $ 800

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIO V/R PARCIAL
recebo M3 0.1 30 $ 15,000 $ 1,950
SUBTOTAL $ 1,950

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
EXCAVACIO
NES Y
RELLENOS HC 1 0.013 ### $ 3,835
SUBTOTAL $ 3,835

TRANSPORTE
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.01 $ 100,000 $ 1,000
TRANSPORTE VIAJE 0.05 $ 10,000 $ 500
ALIMENTACI $ 1,950
ON und 0.15 $ 13,000
SUBTOTAL $ 3,450

COSTO DIRECTO $ 10,035

NRO. ITEM: 5.5


ITEM: Chimenea h. 7m
UNIDAD DE
MEDIDA: m2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO
ladrillo
bloque
panela m2 13.2 0 $ 19,000 $ 250,800
mortero 1:3 m3 13.2 0.00 $ 10,000 $ 132,000
formaleta m2 2 1.00 $ 6,000 $ 12,000
trampa
metalica unidad 1 0.00 $ 50,000 $ 50,000
desperdicio glb 1 0.05 $ 132,000 $ 6,600
$ 451,400
MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
ALBAÑILERI HC 1 2.3 $ 210,000 $ 483,000
AY
ACABADOS
SUBTOTAL $ 483,000

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIOV/R PARCIAL
ACARREO GLB 0.05 $ 100,000 $ 5,000
TRANSPORTE VIAJE 0.5 $ 10,000 $ 5,000
ALIMENTACI $ 26,000
ON und 2 $ 13,000
SUBTOTAL 36,000

COSTO DIRECTO $ 971,050


65,000 4.450m2

8700
1450
NRO. ITEM: 3.05
ITEM: Concreto simple para solado de Vigas 6cm
UNIDAD DE
MEDIDA: ml
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.500 0.000 $ 1,500 $ 750
SUBTOTAL $ 750

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
concreto de
3000PIS M3 0.05 0 $ 276,300 $ 13,815
Formaleta
común M2 0.3 0 $ 15,000 $ 4,500
desperdicio glb 1 0.009 $ 18,315 $ 165
SUBTOTAL $ 18,480

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA
DE
CONCRETOS HC 1 0.03 $ 325,000 $ 9,750
SUBTOTAL $ 9,750

TRANSPORTE
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 10,000 500
ALIMENTACIO 3,000
N und 0.2 15,000
SUBTOTAL 4,000

COSTO DIRECTO $ 32,230

NRO. ITEM: 3.04

ITEM: Vigas Cimentacion 30x25 Concreto 3000 psi

UNIDAD DE
MEDIDA: ml
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.500 0.000 $ 1,500 $ 750
Vibrador de
Concreto DIA 1 0.02 $ 60,000 $ 1,200
SUBTOTAL $ 1,950

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
concreto de
3000PIS M3 0.075 0 $ 300,923 $ 22,569
Hierro n#4 Ml 4 0 $ 4,830 $ 19,320
Formaleta
común M2 1 0 $ 15,000 $ 15,000
desperdicio glb 1 0.05 $ 56,889 $ 2,844
SUBTOTAL $ 59,734

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA
DE
CONCRETOS HC 1 0.03 $ 325,000 $ 9,750
SUBTOTAL $ 9,750

TRANSPORTE
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 10,000 500
ALIMENTACIO 1,500
N und 0.1 15,000
SUBTOTAL 2,500

COSTO DIRECTO $ 71,984

NRO. ITEM: 4.1

ITEM: Columnas h 6,20m DE 30x30 zapata 1,20 concreto 3000 Psi

UNIDAD DE
MEDIDA: ML
FECHA: 12/16/2020 14:23
EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
concreto de
3000 PSI M3 0.666 0 $ 300,923 $ 200,415
flejes und 99 0 $ 2,100 $ 207,900
hierro n#4 und 19 0 $ 14,500 $ 275,500
Formaleta
común M2 7 0 $ 4,883 $ 34,178
malla
electrosoldada m2 1 0 $ 5,500 $ 5,500
desperdicio glb 1 0.005 $ 510,141 $ 2,551
SUBTOTAL $ 726,043

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA
DE
CONCRETOS HC 1 0.4 $ 325,000 $ 130,000
SUBTOTAL $ 130,000

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 10,000 500
ALIMENTACIO
N und 0.1 15,000 1,500
SUBTOTAL 2,500

COSTO DIRECTO $ 859,193

NRO. ITEM: 4.2


ITEM: Columnas h 5,30m DE 30x30 zapata 1,20 concreto 3000 Psi
UNIDAD DE
MEDIDA: m3
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
concreto de
3000 PSI M3 0.585 0 $ 300,923 $ 176,040
flejes und 86 0 $ 2,100 $ 180,600
hierro n#4 und 18 0 $ 14,500 $ 261,000
Formaleta
común M2 7 0 $ 4,883 $ 34,178
malla
electrosoldada m2 1 0 $ 5,500 $ 5,500
desperdicio glb 1 0.005 $ 471,266 $ 2,356
SUBTOTAL $ 659,674

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA
DE
CONCRETOS hc 1 0.32 $ 325,000 $ 104,000
SUBTOTAL $ 104,000

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 10,000 500
ALIMENTACIO
N und 0.1 15,000 800
SUBTOTAL 1,800

COSTO DIRECTO $ 766,124

NRO. ITEM: 4.4


ITEM: PHR de cubierta C 2.20x80X2.5
UNIDAD DE
MEDIDA: ml
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.500 0.000 $ 1,500 $ 750
SUBTOTAL $ 750
MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
PHR c ml 1 0 $ 23,350 $ 23,350
platina und 1 0 $ 700 $ 700
anclaje
expansivo und} 1 0 $ 1,500 $ 1,500
SUBTOTAL $ 25,550

MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA
DE
CONCRETOS HC 1 0.01 $ 325,000 $ 3,250
SUBTOTAL $ 3,250

TRANSPORTE
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 10,000 500
ALIMENTACIO 800
N und 0.1 15,000
SUBTOTAL 1,800

COSTO DIRECTO $ 31,350

NRO. ITEM: 4.5


ITEM: Viga IPE 160MM
UNIDAD DE
MEDIDA: ml
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.500 0.000 $ 1,500 $ 750
SUBTOTAL $ 750

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
viga IPE ml 1 0 $ 52,000 $ 52,000
platina und 1 0 $ 700 $ 700
anclaje
expansivo 1 0 $ 1,500 $ 1,500
SUBTOTAL $ 54,200
MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA
DE
CONCRETOS HC 1 0.01 $ 325,000 $ 3,250
SUBTOTAL $ 3,250

TRANSPORTE
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 10,000 500
ALIMENTACIO 1,500
N und 0.1 15,000
SUBTOTAL 2,500

COSTO DIRECTO $ 59,950

NRO. ITEM: 4.6


ITEM: Metaldeck 2 calibre 22 losa h 0.10m
UNIDAD DE
MEDIDA: M2
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650

gato hidrahulico Glb 0.500 0.000 $ 2,500 $ 1,250


SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. DESP.% V/R UNITARIOV/R PARCIAL
metaldeck M2 1 0 $ 33,500 $ 33,500
anclaje
expansivo unidad 1 0 $ 1,500 $ 1,500
malla
electrosoldada m2 1 0 $ 5,500 $ 5,500
concreto de
3000PSI M3 0.1 0 $ 276,300 $ 27,630
desperdicio glb 0.05 $ 68,130 $ 3,407
SUBTOTAL $ 68,130
MANO DE OBRA
DESCRIPCION UND V/R UNITARIOV/R PARCIAL
CANT. RENDIMIENTO
CUADRILLA
DE
CONCRETOS HC 1 0.1 $ 325,000 $ 32,500

SUBTOTAL $ 32,500

TRANSPORTE
DESCRIPCION UND CANT. DISTANCIA V/R UNITARIOV/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.05 10,000 500
ALIMENTACION und 0.2 15,000 3,000
SUBTOTAL 4,000

COSTO DIRECTO $ 105,280


barilla valor medida

barilla n#3 o 8500 3m


barilla n#4 14,500 3m
No item 16.5

ITEM: Puerta corrediza vidrio 4mm


UNIDAD DE
MEDIDA: ml
FECHA: 12/16/2020 14:23

EQUIPO
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
Herramienta
menor Glb 0.500 0.000 $ 1,300 $ 650
SUBTOTAL $ 650

MATERIALES
DESCRIPCION UND CANT. V/R PARCIAL
DESP.% V/R UNITARIO

tubo aluminio Ml 1 9.000 $ 6,400 $ 6,400

soporte techo ml 1.5 0.000 $ 1,900 $ 2,850


chazo
concreto ml 6 0.000 $ 180 $ 1,080
Tornillo
driwalt und 6 0.000 $ 30 $ 180
clavos und 6 0.000 $ 15 $ 90
SUBTOTAL $ 10,600

MANO DE OBRA
DESCRIPCION UND CANT. RENDIMIENTO V/R PARCIAL
V/R UNITARIO
CUADRILLA
DE
ALBAÑILERI HC 1 0.03 $ 210,000 $ 6,300
AY
ACABADOS
SUBTOTAL $ 6,300

TRANSPORTE/ALIMENTACION
DESCRIPCION UND CANT. DISTANCIAV/R UNITARIO V/R PARCIAL
ACARREO GLB 0.005 $ 100,000 $ 500
TRANSPORTE VIAJE 0.07 $ 10,000 $ 700
ALIMENTACI $ 1,300
ON und 0.1 $ 13,000
SUBTOTAL 2,500

COSTO DIRECTO $ 20,050


LISTA DE PRECIOS UNITARIOS 2014

CODIGO DESCRIPCION PRODUCTO UNIDAD $ UNITAR


1 accesorio codo 90 PVC 4" sanitario un $5,120
2 accesorio codo PVC 2" sanitario un $1,500
3 accesorio codo PVC 3" sanitario un $2,920
4 accesorio sifón PVC 2" sanitaria un $2,560
5 accesorio Tee PVC 4" sanitaria un $6,300
6 accesorio unión 90 PVC 4" sanitaria un $2,850
7 accesorio unión PVC 2" sanitaria un $950
8 accesorio unión PVC 3" sanitaria un $1,420
9 accesorio Yee PVC 2" sanitaria un $2,500
10 accesorio Yee PVC 4x2" sanitaria un $8,350
11 accesorios PVC 1/2" un $200
12 accesorios PVC 3/4" un $300
13 acero de refuerzo Fy=60.000 psi ¼" kg $2,250
14 acero de refuerzo Fy=60.000 psi ¾" kg $2,250
15 acero de refuerzo Fy=60.000 psi 5/8" kg $2,250
16 acero de refuerzo Fy=60.000 psi ½" kg $2,250
17 acero de refuerzo Fy=60.000 psi 3/8" kg $2,250
18 acople grival 1/2 " un $2,000
19 agua lt $20
20 alambre de aluminio No. 8 ml $350
21 alambre de amarre kg $1,780
22 alambre de cobre No. 10 ml $720
23 alambre de cobre No. 12 ml $390
24 alambre de cobre No. 14 duplex ml $400
25 alambre de cobre No. 14 x 1 ml $195
26 alambre de cobre No. 6 ml $800
27 alambre teléfono 2 ml $350
28 Amarra para teja AC un $85
29 arena blanca m3 $20,000
30 arena negra estructural m3 $26,000
31 breaker 20 A Luminex un $6,500
32 breaker 40 A Luminex un $6,500
33 buje sanitario 4"x2" Gerfor un $3,560
34 caballete en AC Eternit un $13,580
35 caja toma estufa 4x10 un $1,500
36 caja octogonal lámina un $450
37 caja rectangular interruptor 4x4 un $850
38 caolín kg $250
39 cemento blanco kg $700
40 cemento gris kg $410
41 cerámica 0.20 x 0.20 baño m2 $15,000
42 cerámica 0.30 x 0.30 tráfico 3 m2 $18,500
43 cerámica 0.30 x 0.30 tráfico 4 m2 $20,000
44 cerradura Gato para puerta de madera un $18,000
45 cerradura Yale doble seguro un $48,650
46 chapa para cortina en lámina un $14,200
47 chapa puerta de baño un $14,200
48 cinta de teflón rollo un $400

LISTA DE PRECIOS UNITARIOS

CODIGO DESCRIPCION PRODUCTO UNIDAD $ UNITAR


49 clavos 3", 4" y 5" lb $900
50 color mineral F-130 lb $2,500
51 dilatación en bronce ml $3,000
52 dilatación en madera 0.02x0.05x2.50m un $850
53 dilatación en vidrio 4 mm. ml $550
54 esmalte uso exterior gln $35,000
55 esterilla de guadua m2 $4,000
56 granito No. 2 kg $252
57 grapas para aligflex caja $10,650
58 gravilla 1/2" fundición placa aligerada m3 $30,000
59 gravilla 3/4" fundición placa aligerada m3 $28,000
60 grifo 1/2" un $6,500
61 guadua un $4,000
62 hidralit para ladrillo visto kg $7,500
63 interruptor luminex conmutable un $4,000
64 interruptor luminex doble un $5,500
65 interruptor luminex sencillo un $3,750
66 ladrillo común un $300
67 lavamanos completo un $62,300
68 lavaplatos con escurridero un $85,000
69 limpiador PVC ¼ pavco ¼ $18,000
70 listón 0.04x.08x2.50 m ordinario un $4,000
71 listón 0.04x.08x2.50 m ordinario seco un $4,500
72 llave de paso 1/2" bola italiana un $6,500
73 malla cielo raso plástica x 1.80m ml $1,550
74 malla electrosoldada h-050 2.4mx6.00m (.15x.15) m2 $1,850
75 malla electrosoldada h-084 2.4mx6.00m (.15x.25) m2 $1,630
76 manguera conduflex instal. eléctricas ml $450
77 manija corriente para puerta un $1,500
78 manija para portón un $3,900
79 marmol-plast. instalado colores m2 25000
80 marmolina blanca kg $250
81 mezclador cuello cisne Grival lavaplatos un $75,000
82 mezclador ducha Grival un $50,000
83 plafón cerámico un $950
84 portón metálico en lámina 1.25 x 2.40 un $175,000
85 promical saco x 25 kg. un $4,300
86 puertas en ángulo m2 $47,000
87 Rejilla 10x20xsal 2" un $4,500
88 puertas en madera pandala 0.70x2.10 un $175,000
89 puertas en madera pandala 0.90x2.10 un $185,000
90 rajón de piedra m3 $22,000
91 recebo puesto en obra m3 $15,000
92 rejilla 2" un $900
93 rieles en pandala 2.50 x 0.09 un $1,800
94 sanitario blanco un $143,000
95 sika 1 impermeabilizante mortero kg $4,200

LISTA DE PRECIOS UNITARIOS

CODIGO DESCRIPCION PRODUCTO UNIDAD $ UNITAR


96 sika Plastocret Dm impermeabilizante concreto kg $4,500
97 soldadura PVC ¼ de galón Pavco ¼ $31,000
98 tabla común un $4,000
99 Tablero 2 contadores un $35,000
100 tablero de distribución 2 circuitos un $5,500
101 tablero de distribución 4 circuitos un $7,500
102 tablero de distribución 6 circuitos un $10,500
103 Tableta de gress m2 $10,000
104 tablón madera ordinaria un $7,000
105 teja asbesto cemento 2.65 un $29,000
106 teja asbesto cemento No. 5 un $42,000
107 tela Aligflex de a=1.25m para casetón ml $1,750
108 thiner gln $7,000
109 toma especial un $9,500
110 toma teléfono un $6,250
111 tomacorriente doble luminex un $4,500
112 triturado no seleccionado m3 $30,000
113 triturado seleccionado 1" m3 $35,000
114 tubería conduit pvc 1/2 "x 3m un $3,500
115 tubería conduit pvc 3/4 "x 3m un $4,000
116 tubería CPVC 1/2" agua cal. Pavco ml $8,250
117 tubería PVC 1/2" presión Pavco ml $850
118 tubería PVC 2" sanitaria Gerfor ml $4,560
119 tubería PVC 3" aguas lluvias x 5m ml $3,960
120 tubería PVC 3" sanitaria Gerfor ml $5,750
121 tubería PVC 4" sanitaria Gerfor ml $10,650
122 tubería PVC 6" sanitaria Gerfor ml $22,000
123 tubería ventilación 3" Tubosa un $8,000
124 válvula cheque 1/2" Red & White un $18,500
125 varenga 0.02x0.04x2.50 un $900
126 varenga 0.04x0.03x2.50 un $850
127 varenga 0.04x0.04x2.50 un $950
128 ventanas en ángulo m2 $28,000
129 lámina cal. 18 m2 $45,000
130 vidrio 4mm bronce m2 $19,500
131 vidrio 4mm claro m2 $22,000
132 vidrio 5mm m2 $20,500
133 vidrio reflectivo 4mm m2 $39,000
134 vinilo tipo 1 Viniltex Pintuco gln $35,000
135 vinilo tipo 3 gln $12,500
136 vinisol 2 mm. m2 $14,500
137 Estuco profesional kg $8,640
138 teja de zinc un $9,620
139 Saco cemento x 50 k un $23,500
140 Tablon de Gress M2 $14,200
141 Llave de Paso Bola Italiana Un $6,500