ANALISIS DE BÁSICOS
Análisis: 302-CIM-01-292 M3
CONCRETO DE F'c=150 KG/CM2. HECHO EN OBRA, T.M.A=19 MM, RESISTENCIA NORMAL
MATERIALES
301-ARE-0101 ARENA M3 $201.15 * 0.540000 $108.62 6.60%
358-AGU-0101 AGUA DE TOMA M3 $45.00 * 0.250000 $11.25 0.68%
302-CEM-0102 CEMENTO (GRIS) PORTLAND TIPO II TON $2,586.21 * 0.310000 $801.73 48.71%
PUZOLANICO, TONELADA
301-GRA-0401 GRAVA DE MINA T.M.A. 19 MM Ø (3/4), M3 M3 $531.61 * 0.640000 $340.23 20.67%
ANALISIS DE BÁSICOS
Análisis: 302-CIM-01-294 M3
CONCRETO DE F'c=250 KG/CM2. HECHO EN OBRA, T.M.A=19 MM, RESISTENCIA NORMAL
MATERIALES
301-ARE-0101 ARENA M3 $201.15 * 0.530000 $106.61 5.78%
301-GRA-0401 GRAVA DE MINA T.M.A. 19 MM Ø (3/4), M3 M3 $531.61 * 0.630000 $334.91 18.15%
358-AGU-0101 AGUA DE TOMA M3 $45.00 * 0.230000 $10.35 0.56%
302-CEM-0102 CEMENTO (GRIS) PORTLAND TIPO II TON $2,586.21 * 0.390000 $1008.62 54.68%
PUZOLANICO, TONELADA
ANALISIS DE BÁSICOS
Análisis: 302-CIM-01-544 M3
MORTERO CEMENTO ARENA EN PROPORCION DE 1:5, INCLUYE: MATERRIALES, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
301-ARE-0101 ARENA M3 $201.15 * 1.220000 $245.40 20.62%
302-CEM-0102 CEMENTO (GRIS) PORTLAND TIPO II TON $2,586.21 * 0.360000 $931.04 78.24%
PUZOLANICO, TONELADA
358-AGU-0101 AGUA DE TOMA M3 $45.00 * 0.300000 $13.50 1.13%
ANALISIS DE BÁSICOS
ANALISIS DE BÁSICOS
ANALISIS DE BÁSICOS
ANALISIS DE BÁSICOS
ANALISIS DE BÁSICOS
ANALISIS DE BÁSICOS
ANALISIS DE BÁSICOS
ANALISIS DE BÁSICOS
ANALISIS DE BÁSICOS
Análisis: MABA0002 M2
CIMBRA COMUN EN CIMENTACION.
MATERIALES
MMAD0046 MADERA PINO DE 3a DUELA 1" X 4" PT $12.00 * 2.000000 $24.00 15.50%
MBROCHA BROCHA DE 6" PZA $68.00 * 0.007000 $0.48 0.31%
MCLA0021 CLAVO KG $20.00 * 0.110000 $2.20 1.42%
MALA0180 ALAMBRE RECOCIDO No. 18 KG $20.69 * 0.300000 $6.21 4.01%
TABLA-2 TABLA DE 30 CM DE 3RA DE PINO PZA $90.00 * 1.300000 $117.00 75.56%
DIESEL DIESEL LTO $16.54 * 0.300000 $4.96 3.20%
ANALISIS DE BÁSICOS
Análisis: MABA0007 M3
MORTERO CEMENTO-ARENA 1:4
MATERIALES
301-ARE-0101 ARENA M3 $201.15 * 1.200000 $241.38 18.72%
302-CEM-0102 CEMENTO (GRIS) PORTLAND TIPO II TON $2,586.21 * 0.400000 $1034.48 80.23%
PUZOLANICO, TONELADA
358-AGU-0101 AGUA DE TOMA M3 $45.00 * 0.300000 $13.50 1.05%
ANALISIS DE BÁSICOS
Análisis: MABA001 ML
CIMBRA COMUN
MATERIALES
MALA0180 ALAMBRE RECOCIDO No. 18 KG $20.69 * 0.100000 $2.07 5.70%
MCLA0021 CLAVO KG $20.00 * 0.100000 $2.00 5.50%
MAMA0001 MADERA DE PINO PT $12.00 * 2.000000 $24.00 66.04%
DIESEL DIESEL LTO $16.54 * 0.500000 $8.27 22.76%
ANALISIS DE BÁSICOS
Análisis: MABA15 M3
CONCRETO F´C=100 KG/CM2 T.M.A 3/4"
MATERIALES
301-ARE-0101 ARENA M3 $201.15 * 0.550000 $110.63 7.26%
301-GRA-0401 GRAVA DE MINA T.M.A. 19 MM Ø (3/4), M3 M3 $531.61 * 0.650000 $345.55 22.67%
358-AGU-0101 AGUA DE TOMA M3 $45.00 * 0.250000 $11.25 0.74%
302-CEM-0102 CEMENTO (GRIS) PORTLAND TIPO II TON $2,586.21 * 0.260000 $672.41 44.12%
PUZOLANICO, TONELADA