POSIBLES SECTORIZACION

CONCRETO

SECTOR OPCION II
T-A 14.47 CONCRETO
T-B 15.81 * METRADO TOTAL 133.06
VERTICALES
T-C 11.44 * PROMEDIO DE SECTORES 33.27
T-D 11.19
T-A 8.98
T-B 8.57
VIGAS
T-C 8.87
T-D 8.04
T-A 12.66 SOBRAN 5.10 m³
PARA TENER EL
T-B 13.99 PROMEDIO
LOSAS REQUERIDO.
T-C 8.36
T-D 10.78

TOTAL T - A (m³) 36.11


TOTAL T - B (m³) 38.37
TOTAL T - C (m³) 28.67
TOTAL T - D (m³) 30.01
LE FALTA 4.60 m³ PARA
TENER EL PROMEDIO
REQUERIDO.
RIZACION

ENCOFRADO

SECTOR OPCION II
EMCOFRADO T-A 135.21
1274.45 T-B 142.43
VERTICALES
318.61 T-C 120.50
T-D 101.94
T-A 47.05
T-B 53.78
VIGAS
T-C 54.80
T-D 43.78 SOBRAN 30.13 m²
PARA TENER EL
T-A 166.48 PROMEDIO
REQUERIDO.
T-B 140.66
LOSAS
T-C 120.69
T-D 148.04

TOTAL T - A (m²) 348.74


TOTAL T - B (m²) 336.87
TOTAL T - C (m²) 295.99
TOTAL T - D (m²) 293.76
DE VERTICALES

11
9.6
Día de obra 1 2 3 4 5 6 7 8 9 10 11 12
hh 105.60 105.60 105.60 105.60 105.60 105.60 105.60 105.60 105.60 105.60 105.60 105.60
hhacum 105.60 211.20 316.80 422.40 528.00 633.60 739.20 844.80 950.40 1,056.00 1,161.60 1,267.20
met 135.21 142.43 120.50 101.94 135.21 142.43 120.50 101.94 135.21 142.43 120.50 101.94
met acum 135.21 277.64 398.14 500.08 635.29 777.72 898.22 1,000.16 1,135.37 1,277.80 1,398.30 1,500.24
Ren diario 0.78 0.74 0.88 1.04 0.78 0.74 0.88 1.04 0.78 0.74 0.88 1.04
Ren. Acum. 0.78 0.76 0.80 0.84 0.83 0.81 0.82 0.84 0.84 0.83 0.83 0.84
Rend. Pres 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

RADO DE VIGAS

6
9.6
Día de obra 1 2 3 4 5 6 7 8 9 10 11 12
hh 57.60 57.60 57.60 57.60 57.60 57.60 57.60 57.60 57.60 57.60 57.60
hhacum - 57.60 115.20 172.80 230.40 288.00 345.60 403.20 460.80 518.40 576.00 633.60
met 47.05 53.78 54.80 43.78 47.05 53.78 54.80 43.78 47.05 53.78 54.80
met acum - 47.05 100.83 155.63 199.41 246.46 300.24 355.04 398.82 445.87 499.65 554.45
Ren diario - 1.22 1.07 1.05 1.32 1.22 1.07 1.05 1.32 1.22 1.07 1.05
Ren. Acum. - 1.22 1.14 1.11 1.16 1.17 1.15 1.14 1.16 1.16 1.15 1.14
Rend. Pres 1.60 1.60 1.60 1.60 1.60 1.60 1.60 1.60 1.60 1.60 1.60 1.60