CONTRATISTA DIEGO ANTONIO ACOSTA R.GONZALEZ CARATULA HOJA NUM.

01

IMPORTE DEL CONTRATO 451,912.99 CASA-HABITACION PERIODO DE :Del 16 al 31 Mayo al de 2020

IMPORTE DEL ANTICIPO 135,573.90 30.00% RESUMEN POR PARTIDAS OBRA Construcción de casa habitacion.

FONDO DE RETENCION 0.00 0.00% ESTIMACION DE OBRA NORMAL NUM. 2 UBICACION Km 14 carretera a Barra Vieja.

NUMERO DE CLAVE DE PARTIDAS DEL PRESUPUESTO ORIGINAL APROBADO ESTIMACIONES ANTERIORES ESTIMACION ACTUAL ACUMULADO A LA FECHA MONTO POR ESTIMAR
CUENTA LA PARTIDA NOMBRE DE LA PARTIDA / CONCEPTO IMPORTE PORCIENTO IMPORTE PORCIENTO IMPORTE PORCIENTO IMPORTE PORCIENTO IMPORTE PORCIENTO

I Preliminares 3,764.00 1% $3,764.00 100% 0% 3,764.00 100% 0.00 0%


II Cimentación 70,858.34 16% $70,858.34 100% 0% 70,858.34 100% 0.00 0%
III Estructura 170,588.10 38% $110,380.05 65% 60,208.05 35% 170,588.10 100% 0.00 0%
IV Albañileria 52,934.20 12% 52,934.20 100% 52,934.20 100%
V Instalación Hidraulica 34,789.24 8% 34,789.24 100% 34,789.24 100%
VI Instalación Sanitaria 21,707.91 5% 21,707.91 100% 21,707.91 100%
VII Instalacion Electrica 26,109.50 6% 26,109.50 100% 26,109.50 100%
VIII Acabados 66,823.91 15% 0% 66,823.91 100%
IX Muebles 4,337.79 1% 0% 4,337.79 100%

ELABORO: REVISO: AUTORIZO:


VIKBRAK S.A. de C.V. CIDI, Empresa Supervisora CLUB TRES VIDAS

Arq. Diego Antonio Acosta R.Gonzalez Arq. Alberto Avila Contreras Arq. Jaime Garza V.
Residente de obra. Residente de obra.

TOTAL 451,912.99 100.00% $185,002.39 $0.41 195,748.90 43% 245,210.44 54% 206,702.55 $0.46

REGISTRO DE FIRMAS IMPORTE DE ESTIMACIONES AMORTIZACION DE ANTICIPO IMPORTE DE RETENCIONES IMPORTE NETO A PAGAR
ELABORO ESTIMACIONES ESTIMACION ACUMULADO ESTIMACIONES ESTIMACION ACUMULADO ESTIMACIONES ESTIMACION ACUMULADO ESTIMACIONES ESTIMACION ACUMULADO

Mendez & Gómez Arquitectos S.A de C.V ( Firma ) ANTERIORES ACTUAL A LA FECHA ANTERIORES ACTUAL A LA FECHA ANTERIORES ACTUAL A LA FECHA ANTERIORES ACTUAL A LA FECHA

REVISO 185,002.39 195,748.90 380,751.29 55,500.72 $58,724.67 $114,225.39 9,250.12 $9,787.45 19,037.57 $120,254.55 127,236.79 $247,491.34
A.A.C. ( Firma ) 27,750.36 29,362.34 57,112.70 8,325.11 $8,808.70 $17,133.81 0.00 $0.00 0.00 $18,037.73 19,085.52 $37,123.25
AUTORIZO. 212,752.75 225,111.24 437,863.99 63,825.83 $67,533.37 $131,359.20 0.00 $0.00 0.00 $138,289.29 146,322.30 $284,611.59
( Firma ) PORCENTAJE NETO 84.25% PORCENTAJE AMORTIZADO $0.84 PORCENTAJE RETENIDO 0.04 PORCENTAJE NETO 55%
RESIDENCIAL TRES VIDAS.

CONTRATISTA DIEGO ANTONIO ACOSTA R.GONZALEZ CARATULA HOJA NUM. 02


IMPORTE DEL CONTRATO 451,912.99 CASA HABITACION PERIODO DE : del 16 al 31 de mayo
AL del 2020

IMPORTE DEL ANTICIPO 135,573.90 0.00% DESGLOSE POR CONCEPTOS OBRA Remodelación de casa habitacion

FONDO DE RETENCION 0.00 0.00% ESTIMACION DE OBRA NORMAL NUM. 2 UBICACION Km 7 de la carretera a Barra Vieja, Acapulco, Gro.

NUMERO DE CLAVE DE PARTIDAS DEL PRESUPUESTO ORIGINAL APROBADO ESTIMACIONES ANTERIORES ESTIMACION ACTUAL ACUMULADO A LA FECHA %
CUENTA LA PARTIDA NOMBRE DE LA PARTIDA / CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE CANTIDAD IMPORTE CANTIDAD IMPORTE CANTIDAD IMPORTE AVANCE

I.- PARTIDA DE PRELIMINARES

1.2. Trazo y Nivelacion m2 200.00 $10.97 $2,194.00 200.00 $2,194.00 $0.00 200.00 $2,194.00 100%

1.3. Limpieza del terreno m2 200.00 $7.85 $1,570.00 200.00 $1,570.00 $0.00 200.00 $1,570.00 100%

Subtotal de preliminares $3,764.00 $3,764.00 $0.00 $3,764.00

II.CIMENTACION

2.1. Excavacion de cepas m3 45.00 $176.00 $7,920.00 45.00 $7,920.00 $0.00 45.00 $7,920.00 100%

2.2. Plantilla de 3cm m2 87.00 $68.97 $6,000.39 87.00 $6,000.39 $0.00 87.00 $6,000.39 100%

2.3. Anclaje de castillos kg 230.00 $20.44 $4,701.20 230.00 $4,701.20 $0.00 230.00 $4,701.20 100%

2.4. Zapata de 1.20 x 1.20 m pza 20.00 $1,346.19 $26,923.80 20.00 $26,923.80 $0.00 20.00 $26,923.80 100%

2.5. Trabe de liga de .15 x .30 cm ml 75.00 $302.85 $22,713.75 75.00 $22,713.75 $0.00 75.00 $22,713.75 100%

2.6. Relleno con material producto de la escavacion m3 30.00 $86.64 $2,599.20 30.00 $2,599.20 $0.00 30.00 $2,599.20 100%

Subtotal de cimentacion $70,858.34 $70,858.34 $0.00 $70,858.34


III.ESTRUCTURA

3.1. Trave de .15 x .45cm ml 85.00 $203.07 $17,260.95 85.00 $17,260.95 85.00 $17,260.95 100%

3.2. Muro de tabique rojo de 14 cm m2 160.00 $269.13 $43,060.80 140.00 $37,678.20 20.00 $5,382.60 160.00 $43,060.80 100%

3.3. Impermeabilizacion en areas de desplante ml 75.00 $41.39 $3,104.25 75.00 $3,104.25 $0.00 75.00 $3,104.25 100%

3.4. Cadena de cerramiento de .15 x 30cm ml 80.00 $523.45 $41,876.00 80.00 $41,876.00 $0.00 80.00 $41,876.00 100%

3.5. Cadena intermedia de .15 x .20cm ml 80.00 $346.52 $27,721.60 80.00 $27,721.60 $0.00 80.00 $27,721.60 100%

3.6. Losa maciza de 10 cm de espezor m2 75.00 $500.86 $37,564.50 75.00 $37,564.50 75.00 $37,564.50 100%

Subtotal de estructura $170,588.10 $110,380.05 $60,208.05 $170,588.10


IV.ALBAÑILERIA

4.1. Firme de concreto de 8 cm m2 90.00 $225.54 $20,298.60 90.00 $20,298.60 90.00 $20,298.60 100%

4.2. Aplanado de yeso m2 240.00 $117.99 $28,317.60 240.00 $28,317.60 240.00 $28,317.60 100%

4.3. Boquilla aplanado ml 50.00 $86.36 $4,318.00 50.00 $4,318.00 50.00 $4,318.00 100%

Subtotal de albañileria $52,934.20 $0.00 $52,934.20 $52,934.20


V.INSTALACION HIDRAULICA
5.1. Salida de lavadero sal 1.00 $720.22 $720.22 1.00 $720.22 1.00 $720.22 100%

5.2. Salida de wc sal 2.00 $785.59 $1,571.18 2.00 $1,571.18 2.00 $1,571.18 100%

5.3. Salida de lavabo sal 1.00 $873.12 $873.12 1.00 $873.12 1.00 $873.12 100%

5.4. Salida de fregadero sal 1.00 $1,179.87 $1,179.87 1.00 $1,179.87 1.00 $1,179.87 100%

5.5. Linea de llenado pza 1.00 $1,835.43 $1,835.43 1.00 $1,835.43 1.00 $1,835.43 100%

5.6. Linea de succion de llenado sal 1.00 $5,894.36 $5,894.36 1.00 $5,894.36 1.00 $5,894.36 100%

5.7. Linea descarga de tinaco sal 1.00 $9,867.82 $9,867.82 1.00 $9,867.82 1.00 $9,867.82 100%

5.8. salida de regadera sal 2.00 $6,423.62 $12,847.24 2.00 $12,847.24 2.00 $12,847.24 100%

Subtotal de inst.hidraulica $34,789.24 $0.00 $34,789.24 $34,789.24


VI.INSTALACION SANITARIA

6.1. Rgistro de .40 x .60 cm pza 7.00 $1,568.38 $10,978.66 7.00 $10,978.66 7.00 $10,978.66 100%

6.2. Tuberia de 15cm de concreto ml 40.00 $116.31 $4,652.40 40.00 $4,652.40 40.00 $4,652.40 100%

6.3. Coladera pza 5.00 $832.93 $4,164.65 5.00 $4,164.65 5.00 $4,164.65 100%

6.4. Coladera para piso pza $3.00 $637.40 $1,912.20 3.00 $1,912.20 3.00 $1,912.20 100%

Subtotal de inst.sanitaria $21,707.91 $0.00 $21,707.91 $21,707.91


VII.INSTALACION ELECTRICA

7.1. Salida TV sal 6.00 $762.19 $4,573.14 6.00 $4,573.14 6.00 $4,573.14 100%

7.2. Salida de telefono sal 6.00 $757.04 $4,542.24 6.00 $4,542.24 6.00 $4,542.24 100%

7.3. Salida de contactos pza 1.00 $768.90 $768.90 1.00 $768.90 1.00 $768.90 100%

7.4. Interruptor de seguridad pza 1.00 $2,849.09 $2,849.09 1.00 $2,849.09 1.00 $2,849.09 100%

7.5. Centro de carga pza 1.00 $433.54 $433.54 1.00 $433.54 1.00 $433.54 100%

7.6. Tablero de alumbrado pza 1.00 $11,087.08 $11,087.08 1.00 $11,087.08 1.00 $11,087.08 100%

7.7. Varilla de cobre tierra pza 1.00 $808.47 $808.47 1.00 $808.47 1.00 $808.47 100%

7.8. Registro electrico pza 1.00 $1,047.04 $1,047.04 1.00 $1,047.04 1.00 $1,047.04 100%

$26,109.50 0% $26,109.50 $26,109.50

$380,751.29 $185,002.39 195,748.90 $380,751.29


RESIDENCIAL TRES VIDAS.

ELABORO: REVISO: AUTORIZO:


VIKBRAK S.A. de C.V. CIDI, Empresa Supervisora CLUB TRES VIDAS
Arq. Diego Antonio Acosta R.Gonzalez Arq. Alberto Avila Contreras Arq. Jaime Garza V.