REPORTE DE AVANCES INCLINADO 370 NV 370 - NV 3

TERCERA SEMANA ENERO 2


NIVEL LABOR ACTIVIDADES PROGRAMA
SEMANAL LUN MAR MIER JUE

16 17 18 19
T 370 Inc. 370 Avance Profundizacion 10.00 1.00
A
L 370 Inc. 370 Avance Collera 10.00 5.04
L
A
370 Inc. 371 P / H + malla electrosoldada 10.00 0.00
N 370 Inc. 370 Escalera 10.00 0.00
E
S 370 Inc. 370 Entablado de Trocha 10.00 3.00
370 Inc. 370 Refugio 2.00 1.00
370 Inc. 370 Ventana 169 N 0.00 0.00
### 370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00

REALIZADOS
NIVEL LABOR ACTIVIDADES

Jul-16 Aug-16 Sep-16 Oct-16 Nov-16


370 Inc. 370 Avance Profundizacion 28.40 31.60 15.00 23.00 21.00
T
A 370 Inc. 370 Avance Collera 20.87 35.21 15.16 20.21 20.16
L
L 370 Inc. 371 Sostenimiento con P / H 22.57 33.61 11.60 24.80 22.05
A
N 370 Inc. 370 Escalera 19.35 24.90 16.00 31.45 15.00
E
S 370 Inc. 370 Entablado de Trocha 17.03 26.40 12.36 30.91 15.55
370 Inc. 370 Refugio + Poza de bombeo 2.00 2.00 0.00 9.00 0.00
370 Inc. 370 Ventana 169 N +Pocket 01 0.00 0.00 0.00 0.00 6.00
370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

Lunes, 16 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 18.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 1.0 m.
3 . Perforacion y voladura (sellado de 5 to refugio) = 1.0 m.
4 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 2.00 Unid.
5 . Instalacion de collera de 45 Lb / Yd = 5.04 m.
6 . Instalacion de trocha = 3 m.
CIA MINERA LONDRES SAC-POMACOCHA

DO 370 NV 370 - NV 320

ERCERA SEMANA ENERO 2017


MES DE ENERO - 2017
VIE SAB DOM ACUMULADO DE
TOTAL
LA SEMANA
20 21 22 PROGRAMA REALIZADO CUMPLIM FALTA

155.50 20.00 11.00 55.00% 9.00 1.00


151.89 20.00 10.08 50.40% 9.92 5.04
149.63 20.00 8.70 43.50% 11.30 0.00
142.70 20.00 6.00 30.00% 14.00 0.00
144.25 20.00 9.00 45.00% 11.00 3.00
16.00 2.00 1.00 50.00% 1.00 1.00
6.00 5.00 0.00 0.00% 5.00 0.00
0.00 15.00 0.00 0.00% 15.00 0.00

REALIZADOS TOTAL TOTAL

Dec-16 Jan-17 REALIZADOPROGRAMA FALTA CUMPLIMIENTO


25.50 11.00 155.50 200.00 44.50 77.75%
30.20 10.08 151.89 200.00 48.11 75.95%
26.30 8.70 149.63 200.00 50.37 74.82%
30.00 6.00 142.70 200.00 57.30 71.35%
33.00 9.00 144.25 200.00 55.75 72.13%
2.00 1.00 16.00 26.00 10.00 61.54%
0.00 0.00 6.00 5.00 -1.00 120.00%
0.00 0.00 0.00 21.00 21.00 0.00%

A - SUR
REPORTE DE AVANCES INCLINADO 370 NV 370 - NV 3

TERCERA SEMANA ENERO 2


NIVEL LABOR ACTIVIDADES PROGRAMA
SEMANAL LUN MAR MIER JUE

16 17 18 19
T 370 Inc. 370 Avance Profundizacion 10.00 1.00 0.00
A
L 370 Inc. 370 Avance Collera 10.00 5.04 0.00
L
A
370 Inc. 371 P / H + malla electrosoldada 10.00 0.00 2.90
N 370 Inc. 370 Escalera 10.00 0.00 6.00
E
S 370 Inc. 370 Entablado de Trocha 10.00 3.00 3.00
370 Inc. 370 Refugio 2.00 1.00 1.00
370 Inc. 370 Ventana 169 N 0.00 0.00 0.00
### 370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00

REALIZADOS
NIVEL LABOR ACTIVIDADES

Jul-16 Aug-16 Sep-16 Oct-16 Nov-16


370 Inc. 370 Avance Profundizacion 28.40 31.60 15.00 23.00 21.00
T
A 370 Inc. 370 Avance Collera 20.87 35.21 15.16 20.21 20.16
L
L 370 Inc. 371 Sostenimiento con P / H 22.57 33.61 11.60 24.80 22.05
A
N 370 Inc. 370 Escalera 19.35 24.90 16.00 31.45 15.00
E
S 370 Inc. 370 Entablado de Trocha 17.03 26.40 12.36 30.91 15.55
370 Inc. 370 Refugio + Poza de bombeo 2.00 2.00 0.00 9.00 0.00
370 Inc. 370 Ventana 169 N +Pocket 01 0.00 0.00 0.00 0.00 6.00
370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

Martes, 17 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 24.00 Carros U - 35.
2 . Perforacion y voladura (5to refugio) = 1.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 1.00 Unid.
4 . Instalacion de sostenimiento con P /H de 5´ = 18.00 Unid.
5 . Instalacion de gradas = 6.00 m.
6 . Instalacion de trocha = 3 m.
CIA MINERA LONDRES SAC-POMACOCHA

DO 370 NV 370 - NV 320

ERCERA SEMANA ENERO 2017


MES DE ENERO - 2017
VIE SAB DOM ACUMULADO DE
TOTAL
LA SEMANA
20 21 22 PROGRAMA REALIZADO CUMPLIM FALTA

155.50 20.00 11.00 55.00% 9.00 1.00


151.89 20.00 10.08 50.40% 9.92 5.04
152.53 20.00 11.60 58.00% 8.40 2.90
148.70 20.00 12.00 60.00% 8.00 6.00
147.25 20.00 12.00 60.00% 8.00 6.00
17.00 2.00 2.00 100.00% 0.00 2.00
6.00 5.00 0.00 0.00% 5.00 0.00
0.00 15.00 0.00 0.00% 15.00 0.00

REALIZADOS TOTAL TOTAL

Dec-16 Jan-17 REALIZADOPROGRAMA FALTA CUMPLIMIENTO


25.50 11.00 155.50 200.00 44.50 77.75%
30.20 10.08 151.89 200.00 48.11 75.95%
26.30 11.60 152.53 200.00 47.47 76.27%
30.00 12.00 148.70 200.00 51.30 74.35%
33.00 12.00 147.25 200.00 52.75 73.63%
2.00 2.00 17.00 26.00 9.00 65.38%
0.00 0.00 6.00 5.00 -1.00 120.00%
0.00 0.00 0.00 21.00 21.00 0.00%

A - SUR
REPORTE DE AVANCES INCLINADO 370 NV 370 - NV 3

TERCERA SEMANA ENERO 2


NIVEL LABOR ACTIVIDADES PROGRAMA
SEMANAL LUN MAR MIER JUE

16 17 18 19
T 370 Inc. 370 Avance Profundizacion 10.00 1.00 0.00 2.00
A
L 370 Inc. 370 Avance Collera 10.00 5.04 0.00 0.00
L
A
370 Inc. 371 P / H + malla electrosoldada 10.00 0.00 2.90 0.00
N 370 Inc. 370 Escalera 10.00 0.00 6.00 0.00
E
S 370 Inc. 370 Entablado de Trocha 10.00 3.00 3.00 0.00
370 Inc. 370 Refugio 2.00 1.00 1.00 0.00
370 Inc. 370 Ventana 169 N 0.00 0.00 0.00 0.00
### 370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00

REALIZADOS
NIVEL LABOR ACTIVIDADES

Jul-16 Aug-16 Sep-16 Oct-16 Nov-16


370 Inc. 370 Avance Profundizacion 28.40 31.60 15.00 23.00 21.00
T
A 370 Inc. 370 Avance Collera 20.87 35.21 15.16 20.21 20.16
L
L 370 Inc. 371 Sostenimiento con P / H 22.57 33.61 11.60 24.80 22.05
A
N 370 Inc. 370 Escalera 19.35 24.90 16.00 31.45 15.00
E
S 370 Inc. 370 Entablado de Trocha 17.03 26.40 12.36 30.91 15.55
370 Inc. 370 Refugio + Poza de bombeo 2.00 2.00 0.00 9.00 0.00
370 Inc. 370 Ventana 169 N +Pocket 01 0.00 0.00 0.00 0.00 6.00
370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

Miercoles, 18 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 15.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 2.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 2.00 Unid.
4 . Instalacion de sostenimiento con P /H de 5´ en refugio = 6.00 Unid.
5 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 24 carros U - 35.
2 . Apoyo a Mtto mecanico y electrico en Mtto de winche = 2.0 horas.
CIA MINERA LONDRES SAC-POMACOCHA

DO 370 NV 370 - NV 320

ERCERA SEMANA ENERO 2017


MES DE ENERO - 2017
VIE SAB DOM ACUMULADO DE
TOTAL
LA SEMANA
20 21 22 PROGRAMA REALIZADO CUMPLIM FALTA

157.50 20.00 13.00 65.00% 7.00 3.00


151.89 20.00 10.08 50.40% 9.92 5.04
152.53 20.00 11.60 58.00% 8.40 2.90
148.70 20.00 12.00 60.00% 8.00 6.00
147.25 20.00 12.00 60.00% 8.00 6.00
17.00 2.00 2.00 100.00% 0.00 2.00
6.00 5.00 0.00 0.00% 5.00 0.00
0.00 15.00 0.00 0.00% 15.00 0.00

REALIZADOS TOTAL TOTAL

Dec-16 Jan-17 REALIZADOPROGRAMA FALTA CUMPLIMIENTO


25.50 13.00 157.50 200.00 42.50 78.75%
30.20 10.08 151.89 200.00 48.11 75.95%
26.30 11.60 152.53 200.00 47.47 76.27%
30.00 12.00 148.70 200.00 51.30 74.35%
33.00 12.00 147.25 200.00 52.75 73.63%
2.00 2.00 17.00 26.00 9.00 65.38%
0.00 0.00 6.00 5.00 -1.00 120.00%
0.00 0.00 0.00 21.00 21.00 0.00%

A - SUR
REPORTE DE AVANCES INCLINADO 370 NV 370 - NV 3

TERCERA SEMANA ENERO 2


NIVEL LABOR ACTIVIDADES PROGRAMA
SEMANAL LUN MAR MIER JUE

16 17 18 19
T 370 Inc. 370 Avance Profundizacion 10.00 1.00 0.00 2.00 2.00
A
L 370 Inc. 370 Avance Collera 10.00 5.04 0.00 0.00 0.00
L
A
370 Inc. 371 P / H + malla electrosoldada 10.00 0.00 2.90 0.00 0.73
N 370 Inc. 370 Escalera 10.00 0.00 6.00 0.00 0.00
E
S 370 Inc. 370 Entablado de Trocha 10.00 3.00 3.00 0.00 0.00
370 Inc. 370 Refugio 2.00 1.00 1.00 0.00 0.00
370 Inc. 370 Ventana 169 N 0.00 0.00 0.00 0.00 0.00
### 370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

REALIZADOS
NIVEL LABOR ACTIVIDADES

Jul-16 Aug-16 Sep-16 Oct-16 Nov-16


370 Inc. 370 Avance Profundizacion 28.40 31.60 15.00 23.00 21.00
T
A 370 Inc. 370 Avance Collera 20.87 35.21 15.16 20.21 20.16
L
L 370 Inc. 371 Sostenimiento con P / H 22.57 33.61 11.60 24.80 22.05
A
N 370 Inc. 370 Escalera 19.35 24.90 16.00 31.45 15.00
E
S 370 Inc. 370 Entablado de Trocha 17.03 26.40 12.36 30.91 15.55
370 Inc. 370 Refugio + Poza de bombeo 2.00 2.00 0.00 9.00 0.00
370 Inc. 370 Ventana 169 N +Pocket 01 0.00 0.00 0.00 0.00 6.00
370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

Jueves, 19 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 22.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 2.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 2.00 Unid.
4 . Instalacion de sostenimiento con P /H de 5´ = 5.00 Unid.
5 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 36 carros U - 35.
CIA MINERA LONDRES SAC-POMACOCHA

DO 370 NV 370 - NV 320

ERCERA SEMANA ENERO 2017


MES DE ENERO - 2017
VIE SAB DOM ACUMULADO DE
TOTAL
LA SEMANA
20 21 22 PROGRAMA REALIZADO CUMPLIM FALTA

159.50 20.00 15.00 75.00% 5.00 5.00


151.89 20.00 10.08 50.40% 9.92 5.04
153.26 20.00 12.33 61.63% 7.68 3.63
148.70 20.00 12.00 60.00% 8.00 6.00
147.25 20.00 12.00 60.00% 8.00 6.00
17.00 2.00 2.00 100.00% 0.00 2.00
6.00 5.00 0.00 0.00% 5.00 0.00
0.00 15.00 0.00 0.00% 15.00 0.00

REALIZADOS TOTAL TOTAL

Dec-16 Jan-17 REALIZADOPROGRAMA FALTA CUMPLIMIENTO


25.50 15.00 159.50 200.00 40.50 79.75%
30.20 10.08 151.89 200.00 48.11 75.95%
26.30 12.33 153.26 200.00 46.75 76.63%
30.00 12.00 148.70 200.00 51.30 74.35%
33.00 12.00 147.25 200.00 52.75 73.63%
2.00 2.00 17.00 26.00 9.00 65.38%
0.00 0.00 6.00 5.00 -1.00 120.00%
0.00 0.00 0.00 21.00 21.00 0.00%

A - SUR
REPORTE DE AVANCES INCLINADO 370 NV 370 - NV 3

TERCERA SEMANA ENERO 2


NIVEL LABOR ACTIVIDADES PROGRAMA
SEMANAL LUN MAR MIER JUE

16 17 18 19
T 370 Inc. 370 Avance Profundizacion 10.00 1.00 0.00 2.00 2.00
A
L 370 Inc. 370 Avance Collera 10.00 5.04 0.00 0.00 0.00
L
A
370 Inc. 371 P / H + malla electrosoldada 10.00 0.00 2.90 0.00 0.73
N 370 Inc. 370 Escalera 10.00 0.00 6.00 0.00 0.00
E
S 370 Inc. 370 Entablado de Trocha 10.00 3.00 3.00 0.00 0.00
370 Inc. 370 Refugio 2.00 1.00 1.00 0.00 0.00
370 Inc. 370 Ventana 169 N 0.00 0.00 0.00 0.00 0.00
### 370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

REALIZADOS
NIVEL LABOR ACTIVIDADES

Jul-16 Aug-16 Sep-16 Oct-16 Nov-16


370 Inc. 370 Avance Profundizacion 28.40 31.60 15.00 23.00 21.00
T
A 370 Inc. 370 Avance Collera 20.87 35.21 15.16 20.21 20.16
L
L 370 Inc. 371 Sostenimiento con P / H 22.57 33.61 11.60 24.80 22.05
A
N 370 Inc. 370 Escalera 19.35 24.90 16.00 31.45 15.00
E
S 370 Inc. 370 Entablado de Trocha 17.03 26.40 12.36 30.91 15.55
370 Inc. 370 Refugio + Poza de bombeo 2.00 2.00 0.00 9.00 0.00
370 Inc. 370 Ventana 169 N +Pocket 01 0.00 0.00 0.00 0.00 6.00
370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

Viernes, 20 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 11.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 1.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 1.00 Unid.
4 . Instalacion de sostenimiento con P /H de 5´ = 14.00 Unid.
5 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 24 carros U - 35.
6 . Instalacion de collera 45 Lb / Yd = 5.04 m.
CIA MINERA LONDRES SAC-POMACOCHA

DO 370 NV 370 - NV 320

ERCERA SEMANA ENERO 2017


MES DE ENERO - 2017
VIE SAB DOM ACUMULADO DE
TOTAL
LA SEMANA
20 21 22 PROGRAMA REALIZADO CUMPLIM FALTA

1.00 160.50 20.00 16.00 80.00% 4.00 6.00


5.04 156.93 20.00 15.12 75.60% 4.88 10.08
2.18 155.43 20.00 14.50 72.50% 5.50 5.80
6.00 154.70 20.00 18.00 90.00% 2.00 12.00
3.00 150.25 20.00 15.00 75.00% 5.00 9.00
0.00 17.00 2.00 2.00 100.00% 0.00 2.00
0.00 6.00 5.00 0.00 0.00% 5.00 0.00
0.00 0.00 15.00 0.00 0.00% 15.00 0.00

REALIZADOS TOTAL TOTAL

Dec-16 Jan-17 REALIZADOPROGRAMA FALTA CUMPLIMIENTO


25.50 16.00 160.50 200.00 39.50 80.25%
30.20 15.12 156.93 200.00 43.07 78.47%
26.30 14.50 155.43 200.00 44.57 77.72%
30.00 18.00 154.70 200.00 45.30 77.35%
33.00 15.00 150.25 200.00 49.75 75.13%
2.00 2.00 17.00 26.00 9.00 65.38%
0.00 0.00 6.00 5.00 -1.00 120.00%
0.00 0.00 0.00 21.00 21.00 0.00%

A - SUR
REPORTE DE AVANCES INCLINADO 370 NV 370 - NV 3

TERCERA SEMANA ENERO 2


NIVEL LABOR ACTIVIDADES PROGRAMA
SEMANAL LUN MAR MIER JUE

16 17 18 19
T 370 Inc. 370 Avance Profundizacion 10.00 1.00 0.00 2.00 2.00
A
L 370 Inc. 370 Avance Collera 10.00 5.04 0.00 0.00 0.00
L
A
370 Inc. 371 P / H + malla electrosoldada 10.00 0.00 2.90 0.00 0.73
N 370 Inc. 370 Escalera 10.00 0.00 6.00 0.00 0.00
E
S 370 Inc. 370 Entablado de Trocha 10.00 3.00 3.00 0.00 0.00
370 Inc. 370 Refugio 2.00 1.00 1.00 0.00 0.00
370 Inc. 370 Ventana 169 N 0.00 0.00 0.00 0.00 0.00
### 370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

REALIZADOS
NIVEL LABOR ACTIVIDADES

Jul-16 Aug-16 Sep-16 Oct-16 Nov-16


370 Inc. 370 Avance Profundizacion 28.40 31.60 15.00 23.00 21.00
T
A 370 Inc. 370 Avance Collera 20.87 35.21 15.16 20.21 20.16
L
L 370 Inc. 371 Sostenimiento con P / H 22.57 33.61 11.60 24.80 22.05
A
N 370 Inc. 370 Escalera 19.35 24.90 16.00 31.45 15.00
E
S 370 Inc. 370 Entablado de Trocha 17.03 26.40 12.36 30.91 15.55
370 Inc. 370 Refugio + Poza de bombeo 2.00 2.00 0.00 9.00 0.00
370 Inc. 370 Ventana 169 N +Pocket 01 0.00 0.00 0.00 0.00 6.00
370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

Sabado, 21 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 11.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 1.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 1.00 Unid.
5 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 23 carros U - 35.

SUPERFICIE / OROYA - SUR


1 . Desinstalacion de collera P / nivelacion de 45 Lb / Yd = 6.0 Unid
2 . Instalacion de caballetes = 9.0 Unid
3 . Instalacion de collera nivelado de 45 Lb / Yd = 6.0 Unid
4 . Acarreo de desmonte del PQ - 160 Nv - 500 = 50 carros U - 35
CIA MINERA LONDRES SAC-POMACOCHA

DO 370 NV 370 - NV 320

ERCERA SEMANA ENERO 2017


MES DE ENERO - 2017
VIE SAB DOM ACUMULADO DE
TOTAL
LA SEMANA
20 21 22 PROGRAMA REALIZADO CUMPLIM FALTA

1.00 1.00 161.50 20.00 17.00 85.00% 3.00 7.00


5.04 0.00 156.93 20.00 15.12 75.60% 4.88 10.08
2.18 0.00 155.43 20.00 14.50 72.50% 5.50 5.80
6.00 0.00 154.70 20.00 18.00 90.00% 2.00 12.00
3.00 0.00 150.25 20.00 15.00 75.00% 5.00 9.00
0.00 0.00 17.00 2.00 2.00 100.00% 0.00 2.00
0.00 0.00 6.00 5.00 0.00 0.00% 5.00 0.00
0.00 0.00 0.00 15.00 0.00 0.00% 15.00 0.00

REALIZADOS TOTAL TOTAL

Dec-16 Jan-17 REALIZADOPROGRAMA FALTA CUMPLIMIENTO


25.50 17.00 161.50 200.00 38.50 80.75%
30.20 15.12 156.93 200.00 43.07 78.47%
26.30 14.50 155.43 200.00 44.57 77.72%
30.00 18.00 154.70 200.00 45.30 77.35%
33.00 15.00 150.25 200.00 49.75 75.13%
2.00 2.00 17.00 26.00 9.00 65.38%
0.00 0.00 6.00 5.00 -1.00 120.00%
0.00 0.00 0.00 21.00 21.00 0.00%

A - SUR

- SUR
CIA MINERA LONDRES SAC-POMACOCHA

REPORTE DE AVANCES INCLINADO 370 NV 370 - NV 320

TERCERA SEMANA ENERO 2017


PROGRAMA MES DE ENERO - 2017
NIVEL LABOR ACTIVIDADES LUN MAR MIER JUE VIE SAB DOM
SEMANAL ACUMULADO DE
TOTAL LA SEMANA
16 17 18 19 20 21 22 PROGRAMA REALIZADO CUMPLIM FALTA

T 370 Inc. 370 Avance Profundizacion 10.00 1.00 0.00 2.00 2.00 1.00 1.00 2.00 163.50 20.00 19.00 95.00% 1.00 9.00
A
L 370 Inc. 370 Avance Collera 10.00 5.04 0.00 0.00 0.00 5.04 0.00 0.00 156.93 20.00 15.12 75.60% 4.88 10.08
L
A
370 Inc. 371 P / H + malla electrosoldada 10.00 0.00 2.90 0.00 0.73 2.18 0.00 0.00 155.43 20.00 14.50 72.50% 5.50 5.80
N 370 Inc. 370 Escalera 10.00 0.00 6.00 0.00 0.00 6.00 0.00 0.00 154.70 20.00 18.00 90.00% 2.00 12.00
E
S 370 Inc. 370 Entablado de Trocha 10.00 3.00 3.00 0.00 0.00 3.00 0.00 3.00 153.25 20.00 18.00 90.00% 2.00 12.00
370 Inc. 370 Refugio 2.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 17.00 2.00 2.00 100.00% 0.00 2.00
370 Inc. 370 Ventana 169 N 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.00 5.00 0.00 0.00% 5.00 0.00
### 370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.00 0.00 0.00% 15.00 0.00

REALIZADOS TOTAL TOTAL


NIVEL LABOR ACTIVIDADES

Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 REALIZADOPROGRAMA FALTA CUMPLIMIENTO
370 Inc. 370 Avance Profundizacion 28.40 31.60 15.00 23.00 21.00 25.50 19.00 163.50 200.00 36.50 81.75%
T
A 370 Inc. 370 Avance Collera 20.87 35.21 15.16 20.21 20.16 30.20 15.12 156.93 200.00 43.07 78.47%
L
L 370 Inc. 371 Sostenimiento con P / H 22.57 33.61 11.60 24.80 22.05 26.30 14.50 155.43 200.00 44.57 77.72%
A
N 370 Inc. 370 Escalera 19.35 24.90 16.00 31.45 15.00 30.00 18.00 154.70 200.00 45.30 77.35%
E
S 370 Inc. 370 Entablado de Trocha 17.03 26.40 12.36 30.91 15.55 33.00 18.00 153.25 200.00 46.75 76.63%
370 Inc. 370 Refugio + Poza de bombeo 2.00 2.00 0.00 9.00 0.00 2.00 2.00 17.00 26.00 9.00 65.38%
370 Inc. 370 Ventana 169 N +Pocket 01 0.00 0.00 0.00 0.00 6.00 0.00 0.00 6.00 5.00 -1.00 120.00%
370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.00 21.00 |

Domingo, 22 Enero 2017


INCLINADO 370 / OROYA - SUR
1 . Limpieza a pulso de fondo del inclinado = 22.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 2.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 2.00 Unid.
4 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 40 carros U - 35.
5 . Instalacion trocha = 3.0 m.
REPORTE DE AVANCES INCLINADO 370 NV 370 - NV 3

TERCERA SEMANA ENERO 2


NIVEL LABOR ACTIVIDADES PROGRAMA
SEMANAL LUN MAR MIER JUE

16 17 18 19
T 370 Inc. 370 Avance Profundizacion 10.00 1.00 0.00 2.00 2.00
A
L 370 Inc. 370 Avance Collera 10.00 5.04 0.00 0.00 0.00
L
A
370 Inc. 371 P / H + malla electrosoldada 10.00 0.00 2.90 0.00 0.73
N 370 Inc. 370 Escalera 10.00 0.00 6.00 0.00 0.00
E
S 370 Inc. 370 Entablado de Trocha 10.00 3.00 3.00 0.00 0.00
370 Inc. 370 Refugio 2.00 1.00 1.00 0.00 0.00
370 Inc. 370 Ventana 169 N 0.00 0.00 0.00 0.00 0.00
### 370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00

REALIZADOS
NIVEL LABOR ACTIVIDADES

Jul-16 Aug-16 Sep-16 Oct-16 Nov-16


370 Inc. 370 Avance Profundizacion 28.40 31.60 15.00 23.00 21.00PROGRA
T
A 370 Inc. 370 Avance Collera 20.87 35.21 15.16 20.21 20.16200.00
L
L 370 Inc. 371 Sostenimiento con P / H 22.57 33.61 11.60 24.80 22.05160.00
A
N 370 Inc. 370 Escalera 19.35 24.90 16.00 31.45 15.00120.00
E 80.00
S 370 Inc. 370 Entablado de Trocha 17.03 26.40 12.36 30.91 15.55 40.00
370 Inc. 370 Refugio + Poza de bombeo 2.00 2.00 0.00 9.00 0.00 0.00
n
a cio
370 Inc. 370 Ventana 169 N +Pocket 01 0.00 0.00 0.00 0.00 6.00 z
di
un an
c
370 Inc. 370 Pocket - 01 / Nv 320 0.00 0.00 0.00 0.00 0.00 Prof Av
ec
an
Av
Domingo, 22 Enero 2017 S

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 22.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 2.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 2.00 Unid.
5 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 50 carros U - 35.

Sabado, 21 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 11.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 1.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 1.00 Unid.
5 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 23 carros U - 35.

SUPERFICIE / OROYA - SUR


1 . Desinstalacion de collera P / nivelacion de 45 Lb / Yd = 6.0 Unid
2 . Instalacion de caballetes = 9.0 Unid
3 . Instalacion de collera nivelado de 45 Lb / Yd = 6.0 Unid
4 . Acarreo de desmonte del PQ - 160 Nv - 500 = 50 carros U - 35

Viernes, 20 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 11.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 1.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 1.00 Unid.
4 . Instalacion de sostenimiento con P /H de 5´ = 14.00 Unid.
5 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 24 carros U - 35.
6 . Instalacion de collera 45 Lb / Yd = 5.04 m.

Jueves, 19 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 22.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 2.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 2.00 Unid.
4 . Instalacion de sostenimiento con P /H de 5´ = 5.00 Unid.
5 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 36 carros U - 35.

Miercoles, 18 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 15.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 2.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 2.00 Unid.
4 . Instalacion de sostenimiento con P /H de 5´ en refugio = 6.00 Unid.
5 . Acarreo de desmonte del INC. - 370 al echadero del PQ - 160 = 24 carros U - 35.
2 . Apoyo a Mtto mecanico y electrico en Mtto de winche = 2.0 horas.
Martes, 17 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 24.00 Carros U - 35.
2 . Perforacion y voladura (5to refugio) = 1.0 m.
3 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 1.00 Unid.
4 . Instalacion de sostenimiento con P /H de 5´ = 18.00 Unid.
5 . Instalacion de gradas = 6.00 m.
6 . Instalacion de trocha = 3 m.

Lunes, 16 Enero 2017

INCLINADO 370 / OROYA - SUR


1 . Limpieza a pulso de fondo del inclinado = 18.00 Carros U - 35.
2 . Perforacion y voladura (profundizacion) = 1.0 m.
3 . Perforacion y voladura (sellado de 5 to refugio) = 1.0 m.
4 . Instalacion y desinstalacion de plataforma de perforacion (2.4 m X 3.0 m) = 2.00 Unid.
5 . Instalacion de collera de 45 Lb / Yd = 5.04 m.
6 . Instalacion de trocha = 3 m.
CIA MINERA LONDRES SAC-POMACOCHA

DO 370 NV 370 - NV 320

ERCERA SEMANA ENERO 2017


MES DE ENERO - 2017
VIE SAB DOM ACUMULADO DE
TOTAL
LA SEMANA
20 21 22 PROGRAMA REALIZADO CUMPLIM FALTA

1.00 1.00 2.00 163.50 20.00 19.00 95.00% 1.00 9.00


PROGRAM
5.04 0.00 0.00 156.93 20.00 15.12 75.60% 4.88 10.08
12.00 10.00 10.00 10.08 10.0
9.00
2.18 0.00 0.00 155.43 20.00 14.50 72.50% 5.50 5.80 10.00
8.00 5
6.00 0.00 0.00 154.70 20.00 18.00 90.00% 2.00 12.00
6.00
3.00 0.00 0.00 150.25 20.00 15.00 75.00% 5.00 9.00 4.00
2.00
0.00 0.00 0.00 17.00 2.00 2.00 100.00% 0.00 2.00 0.00
n ra a
0.00 0.00 0.00 6.00 5.00 0.00 0.00% 5.00 0.00 cio ol
le ld
ad
i za C s o
0.00 0.00 0.00 0.00 15.00 0.00 0.00% 15.00 0.00 nd nc
e ro
ofu a ect
Pr Av el
nce a lla
a
Av +
m
/H
P
REALIZADOS TOTAL TOTAL
PR
Dec-16 Jan-17 REALIZADOPROGRAMA FALTA CUMPLIMIENTO
PROGRAMA
25.50 DEL PROYECTO PARA
19.00 163.50EL NV
200.00- 270 36.50 81.75%
200.00 30.20 15.12 156.93 200.00 43.07 78.47%
160.00 26.30 14.50 155.43 200.00 44.57 77.72%
120.00 30.00 18.00 154.70 200.00 45.30 77.35%
80.00
40.00 33.00 15.00 150.25 200.00 49.75 75.13%
0.00 2.00 2.00
n 17.00 126.00 20 9.00 65.38%
io ra er
a ha be
o
c l e H
al oc t0 3
i za
0.00 C ol 0.00 P / sc T r m
o 6.00 ock
e
5.00/ Nv -1.00 120.00%
d n E e b
un ce co d de +P 1
rof 0.00 van 0.00nto
ad
o
z a N -0
P A ie l 0.00
9 21.00
t 21.00 0.00%
ce ta
b Po 16 ke
a n ni m
En o
+
na Poc
Av e i a
st fu
g nt
So Re Ve

EJECUTADO PROGRAMADO
A - SUR

A - SUR
- SUR

A - SUR

A - SUR

A - SUR
A - SUR

A - SUR
PROGRAMA DE LA SEMANA
12.00
12.00 10.00 10.0010.08 10.00 10.00 10.00
9.00 9.00
10.00
8.00 5.80
6.00
4.00 2.002.00
2.00 0.000.00 0.00 0.00
0.00
n ra a a a o N 20
cio le ad er ch gi 9
i za Col old cal T ro e fu 16 N v3
s R
nd e ro
s E de na /
ofu a nc ct o nta 01
v e d -
Pr A el bl
a Ve et
nce a lla nta ock
a E P
Av +
m
/ H
P

PROGRAMA EJECUTADO

PROGRAMA DEL MES


20.00 20.00 20.00 20.00 20.00
19.00
20.00 18.00
18.00
15.12 14.50 15.00 15.00
16.00
14.00
12.00
10.00
8.00
5.00
6.00
4.00 2.00
2.00
2.00 0.00 0.00
0.00
1 2 3 4 5 6 7 8

PROGRAMADO EJECUTADO