Está en la página 1de 10

ANALISIS DE PRECIOS UNITARIOS

SIN IVA
PROYECTO:

1
PARTIDA : Hechura de concreto simple f'c=210 Kg/cm2. UNIDAD: m3

ITEM No.: 1

A- MATERIALES

DESCRIPCION UNIDAD CANTIDAD PRECIO SUB TOTAL


Cemento Portland Bolsas 11.00 $7.43 $ 81.73
Arena M3 0.66 $14.73 $ 9.72
Grava M3 0.66 $35.88 $ 23.68
Agua Barril 1.00 $3.00 $ 3.00

SUB T: $118.13
B-MANO DE OBRA

DESCRIPCION JORNAL PRESTACION JORN-TOTAL RENDIMIENTO SUB TOTAL


5 auxiliares $7.00 $2.00 $45.00 0.34 $15.30

SUB T: $15.30
C-EQUIPO Y HERRAMIENTAS

DESCRIPCION TIPO CAPACIDAD RENDIMIENTO COSTO/HORA SUB TOTAL


Herramientas menores x x 0.03 $4.00
Concretera 0.34 $29.00 $9.86

SUB T: $13.86
D-SUBCONTRATOS

DESCRIPCION UNIDAD CANTIDAD PRECIO SUB TOTAL

SUB T: $0.00

COSTO DIRECTO $147.29


COSTO INDIRECTO 25.0% $36.82
PRECIO UNITARIO $184.11

NOMBRE Y FIRMA REP. LEGAL FECHA:


ANALISIS DE PRECIOS UNITARIOS
SIN IVA

PROYECTO:

1
PARTIDA : Columna C-1 de 0.30x0.40m; ref 4 # 5 + 2 # 4 EST #3 @ 0. UNIDAD: ML

ITEM No.: 1

A- MATERIALES

DESCRIPCION UNIDAD CANTIDAD PRECIO SUB TOTAL


Concreto f ' 210 Kg/Cm2 M3 0.12 $ 189.23 $ 22.71
Acero No. 5 qq 0.15 $ 35.00 $ 5.25
Acero No. 4 qq 0.05 $ 37.39 $ 1.87
Acero No. 3 qq 0.12 $ 38.50 $ 4.62
Alambre Lb 2.00 $ 0.66 $ 1.32
Tabla de 16 '' Vrs 1.25 $ 5.00 $ 6.25
Tabla de 12 '' Vrs 1.25 $ 5.00 $ 6.25
Clavos de 2 1/2 " Lb 1.00 $ 0.70 $ 0.70
Costanera Vrs 10.00 $ 0.70 $ 7.00
Desmoldante Galón 0.20 $ 3.00 $ 0.60
SUB T: $56.57
B-MANO DE OBRA

DESCRIPCION JORNAL PRESTACION JORN-TOTAL RENDIMIENTO SUB TOTAL


Auxiliar $7.00 $2.00 $9.00 1.18 $10.58
Obrero $10.00 $5.00 $15.00 0.68 $10.13

SUB T: $20.71
C-EQUIPO Y HERRAMIENTAS

DESCRIPCION TIPO CAPACIDAD RENDIMIENTO COSTO/HORA SUB TOTAL


Herramientas menores x x 0.03 $2.32

SUB T: $2.32
D-SUBCONTRATOS

DESCRIPCION UNIDAD CANTIDAD PRECIO SUB TOTAL


SUB T: $0.00

COSTO DIRECTO $79.60


COSTO INDIRECTO 25.0% $19.90
PRECIO UNITARIO $99.50

NOMBRE Y FIRMA REP. LEGAL FECHA:


red 1.18 j/m3
ANALISIS DE PRECIOS UNITARIOS
SIN IVA

PROYECTO:

1
PARTIDA : Columna C-2 de 0.20x0.40m; ref 4 # 5 + 2 # 4 EST UNIDAD: ML

ITEM No.: 1

A- MATERIALES

DESCRIPCION UNIDAD CANTIDAD PRECIO SUB TOTAL


Concreto f ' 210 Kg/Cm2 M3 0.08 $ 189.23 $ 15.14
Acero No. 4 qq 0.05 $ 37.39 $ 1.87
Acero No. 3 qq 0.10 $ 35.68 $ 3.57
Alambre Lb 2.00 $ 0.66 $ 1.32
Tabla de 16 '' Vrs 1.25 $ 5.00 $ 6.25
Tabla de 10 '' Vrs 1.25 $ 5.00 $ 6.25
Clavos de 2 1/2 " Lb 1.00 $ 0.70 $ 0.70
Costanera Vrs 10.00 $ 0.70 $ 7.00
Desmoldante Galón 0.20 $ 3.00 $ 0.60
SUB T: $42.70
B-MANO DE OBRA

DESCRIPCION JORNAL PRESTACION JORN-TOTAL RENDIMIENTO SUB TOTAL


1 Auxiliar $7.00 $2.00 $9.00 1.18 $10.58
1 Obrero $10.00 $5.00 $15.00 0.68 $10.13

SUB T: $20.71
C-EQUIPO Y HERRAMIENTAS

DESCRIPCION TIPO CAPACIDAD RENDIMIENTO COSTO/HORA SUB TOTAL


Herramientas menores x x 0.03 $1.90

SUB T: $1.90
D-SUBCONTRATOS

DESCRIPCION UNIDAD CANTIDAD PRECIO SUB TOTAL


SUB T: $0.00

COSTO DIRECTO $65.31


COSTO INDIRECTO 25.0% $16.33
PRECIO UNITARIO $81.64

NOMBRE Y FIRMA REP. LEGAL FECHA:


red 0.34 j/m3
ANALISIS DE PRECIOS UNITARIOS
SIN IVA

PROYECTO:

1
PARTIDA : PISOS DE CERAMICA (33*33) UNIDAD: M2

ITEM No.: 1

A- MATERIALES

DESCRIPCION UNIDAD CANTIDAD PRECIO SUB TOTAL


Piso de Ceramica de Hispacensa de 33*33 UNIDAD 9.18 $ 0.95 $ 8.72
Pegamix Bls 0.40 $ 4.00 $ 1.60
Porcelana Bls 0.05 $ 6.00 $ 0.30
Separadores Bls 0.05 $ 3.00 $ 0.15
Concreto f ' 210 Kg/Cm2 M3 0.07 $ 189.23 $ 13.25
Suelo Cemento 1:20 M3 0.30 $ 55.51 $ 16.65

SUB T: $40.67
B-MANO DE OBRA

DESCRIPCION JORNAL PRESTACION JORN-TOTAL RENDIMIENTO SUB TOTAL


1 Auxiliar $7.00 $2.00 $9.00 0.07 $0.60
1 Obrero $10.00 $5.00 $15.00 0.07 $1.01

SUB T: $1.61
C-EQUIPO Y HERRAMIENTAS

DESCRIPCION TIPO CAPACIDAD RENDIMIENTO COSTO/HORA SUB TOTAL


Herramientas menores x x 0.03 $1.27

SUB T: $1.27
D-SUBCONTRATOS

DESCRIPCION UNIDAD CANTIDAD PRECIO SUB TOTAL


SUB T: $0.00

COSTO DIRECTO $43.55


COSTO INDIRECTO 25.0% $10.89
PRECIO UNITARIO $54.44

NOMBRE Y FIRMA REP. LEGAL FECHA: