Está en la página 1de 2

1 What is the nominated size of the lintel for brickwork if the opening is 1808mm?

100x100x8 EA, 150 EB


2 How many light points are in this project internally and externally?
21
3 What height is given on the temporary benchmark and where is it?
10m
4 What is the bearing of the front boundary of this project
288⁰18'0"
5 How many down pipes are on this project?
6 DP
6 What is the difference in height from the FFL of the inside of the dwelling to the FFL of garage?
0.172 m
7 What is the % of the total site coverage?
37.57%
8 Where are the finials situated on this project?
One Finial is located on the garage roof and another located on the main roof
9 What is the Lot number of the project site?
LOT 767
10 What is the nominated pitch of the roof?
25⁰
11 Are the rafters to be located over studs?
YES, Rafter to be located directly over stud
12 What is the scale of site plan?
0.180556
13 What is the height of FFL on this project?
11.1m
14 What is the set-out dimension to the center of the garage?
3.065 m
15 What is the nominated capacity of rainwater tank?
2000lt
16 All concrete works should comply with what Australian standard?
AS3600
17 Wha is the size and type of piping nominated for the strom water drain for this project?
90mm UPVC SWD pipe
18 Wha does the abbreviation (AJ) stand for? And how many are o be installed in his project?
AJ - ARTICULATION JOINTS 13 Articulation joints in this project
19 Termite protection is required on his project, which Australian standard should it be in
accordance with?
AS 3660.1
20 What is the member size of the ceiling joist for this project?
100x38 FB at 600 CRS
21 Wha is the ovderall size of bedroom 1, not includin the ensuite and WIR which are separate areas?
12.96 m^2
22 Bedroom 3, Laundry and bathroom face approximately which direction?
South direction
23 Where is the main sewer pit located related to the building?
Main Sewer pit is located at northeast corner of the building
24 Where is the 11.0m contour line located relative to the buildin?
11.0m contour line located at northeast corner of the building
25 Refer to section A-A on the Sections and Details drawing, what is the type of roof construction?
Concrete Tile roofing pitched and propped construction barap trusses
26 What kind of hinge is nominated to be installed on the sanitary compartment(WC, toilet) doors?
"Lift off Hinges" to be installed on the sanitary compartment
27 The price for one pair of lift- off hinges is $7.00 Assumeing 1 pair of lift -off hinges per
sanitory compartment(WC) door, What is the cost of lift-off hinges for this job?
$14.00
28 Determinet the difference in height of the FFL of the main residence above or below the
TBM(top of electric pit)
1.1m(above)
29 According to site plan, the difference in height between the northeast and southwest
corner is 1100mm(11.16-10.06) Given that the FFL is over 1000m higher than the
existing(pre-construction) ground level at the front of the block this would likely mean(cut
Net Cut
30 What is the member size and center to center dimension of the common studs?
90x35 F5 at 600 CRS

También podría gustarte