VALOR GANADO

VALORES PROGRAMADOS (PV)


Actividad sem 0 sem 1 sem 2 sem 3 sem 4 Total Chart Title
tarea 0 40,000.00 35,000.00 75,000.00 300,000.00
tarea 1 25,000.00 40,000.00 65,000.00
tarea 2 10,000.00 30,000.00 15,000.00 10,000.00 65,000.00
tarea 3 30,000.00 10,000.00 40,000.00
250,000.00
PV acumulado 40,000.00 110,000.00 180,000.00 225,000.00 245,000.00 245,000.00

200,000.00
PORCENTAJE DE AVANCE
Actividad sem 0 sem 1 sem 2 sem 3 sem 4 Total

Axis Title
tarea 0 53% 47% 100%
tarea 1 38% 62% 100% 150,000.00
tarea 2 15% 46% 23% 84%
tarea 3 75% 75%
100,000.00

COSTO REAL (AC)


Actividad sem 0 sem 1 sem 2 sem 3 sem 4 Total 50,000.00
tarea 0 30,000.00 15,000.00 45,000.00
tarea 1 5,000.00 20,000.00 15,000.00 40,000.00
tarea 2 15,000.00 20,000.00 10,000.00 45,000.00
tarea 3 5,000.00 10,000.00 15,000.00 0.00
sem 0 sem 1 sem 2 sem 3 sem 4
AC acumulado 35,000.00 85,000.00 125,000.00 145,000.00

VARIACION DE COSTO (CV)


SOLUCION: CV=EV-AC 79,600.00 Se ha gastado menos de lo presupestado

VALOR GANADO (EV) INDICE DEL DESEMPEÑO DE COSTO (CPI)


Actividad sem 0 sem 1 sem 2 sem 3 sem 4 Total CPI=EV/AC 1.55 La tendencia del costo esta por debajo de lo programado
tarea 0 39,750.00 35,250.00 0.00 0.00 0.00 75,000
tarea 1 0.00 24,700.00 40,300.00 0.00 0.00 65,000 VARIACION DEL CRONOGRAMA (SV)
tarea 2 0.00 9,750.00 29,900.00 14,950.00 0.00 54,600 SV=EV-PV -400.00 El proyecto esta atrazado respecto al cronograma
tarea 3 0.00 0.00 0.00 30,000.00 0.00 30,000

EV acumulado 39,750.00 109,450.00 179,650.00 224,600.00


INDICE DEL DESEMPEÑO DEL CRONOGRAMA (SPI)
SPI=EV/PV 1.00

ACUMULADO INDICE DEL DESEMPEÑO DEL TRABAJO POR COMPLETAR (TCPI)


Actividad sem 0 sem 1 sem 2 sem 3 sem 4 Total TCPI=(BAC-EV)/(BAC-AC) 0.20
PV acumulado 40,000.00 110,000.00 180,000.00 225,000.00 245,000.00 245,000.00
PROGRAMADO
AC acumulado 35,000.00 85,000.00 125,000.00 145,000.00 0.00
REAL ESTIMACION A LA CONCLUCION.- CUANTO COSTARA AL FINALIZAR EL PROYECTO.(EAC)

EV acumulado 39,750.00 109,450.00 179,650.00 224,600.00 0.00


VALOR GANADO EAC=AC+(BAC-EV) 165,400.00

ESTIMACION A LA CONCLUCION(ETC)
ETC=EAC-AC 20,400.00

ESTIMACION A LA CONCLUCION.- CUANTO COSTARA AL FINALIZAR EL PROYECTO.(EAC)


EAC=AC+(BAC-EV)/(CPI*SPI) 158,161.29

VARIACION A LA CONCLUCION(VAC)
VAC=BAC-EAC 79,600.00