Está en la página 1de 60

Obras

Contrato : A Precios Unitarios


Obra : REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208 KM)
Contratista : xxxxxxxxxxxxxxxxxx

Datos :
Fecha base : Nov-18
Inicio : 11-Feb-19
Termino: 11-May-19
VALOR REFERENCIAL S/. 2,222,136.77 (CON IGV)
VALOR REFERENCIAL (SIN IGV) S/. 1,883,166.75 (SIN IGV)
PRESUPUESTO CONTRATADO S/. 1,999,923.11 (CON IGV)
PRESUPUESTO CONTRATADO (SIN IGV) S/. 1,694,850.09 (SIN IGV)

Adelantos Otorgados:
Adelanto Directo ( 10% M.C.) S/. 169,485.00 (SIN IGV)
Fecha Pago Adelanto Directo : Feb-19
Adelanto de Materiales
Acero de Refuerzo S/. 11,799.00 (SIN IGV)
Cemento Portland S/. 76,688.00 (SIN IGV)
Madera S/. 15,324.00 (SIN IGV)
Fecha Pagos de Adelantos de Materiales : Feb-19
METRADOS EJE
OBRA REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.20
ENTIDAD xxxxxxxxxxxxxxxx
CONTRAT. xxxxxxxxxxxxxxxx

ITEM DESCRIPCION

Presupuesto Contratado
01 OBRAS PRELIMINARES

01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS

01.02 TOPOGRAFIA Y GEOREFERENCIACION

01.03 DESBROCE Y LIMPIEZA

02 MOVIMIENTO DE TIERRAS

02.01 CORTE EN MATERIAL SUELTO

02.02 CORTE EN ROCA SUELTA

02.03 CORTE EN ROCA FIJA

02.04 RELLENO CON MATERIAL DE PRESTAMO

02.05 PERFILADO Y COMPACTACION SUB-RASANTE EN ZONAS DE CORTE


03 PAVIMENTOS

03.01 AFIRMADO

03.02 ESCARIFICADO DE AFIRMADO EXISTENTE

03.03 PERFILADO Y COMPACTACION DE AFIRMADO EXISTENTE

04 TRANSPORTE

04.01 TRANSPORTE DE MATERIAL AFIRMADO D<1 KM

04.02 TRANSPORTE DE MATERIAL AFIRMADO D>1 KM

04.03 TRANSPORTE DE MATERIAL DE PRESTAMO D<1 KM

04.04 TRANSPORTE DE MATERIAL DE PRESTAMO D>1 KM

04.05 TRANSPORTE DE MATERIAL EXCEDENTE D<1 KM

05 OBRAS DE ARTE Y DRENAJE

05.01 ALCANTARILLAS TIPO MARCO DE 1.00 x 1.00 M

05.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO

05.01.02 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO

05.01.03 EMBOQUILADO DE PIEDRA

05.01.04 CONCRETO F'C=100 KG/CM2

05.01.05 CONCRETO F'C=175 KG/CM2

05.01.06 CONCRETO F'C=210 KG/CM2

05.01.07 ACERO DE REFUERZO FY= 4200 KG/CM2


05.01.08 ENCOFRADO Y DESENCOFRADO

05.02 REPOSICION DE CABEZALES DE ALCANTARILLA

05.02.01 DEMOLICION DE ESTRUCTURAS

05.02.02 CONCRETO F'C=175 KG/CM2

05.02.03 ENCOFRADO Y DESENCOFRADO

05.03 LIMPIEZA DE ALCANTARILLAS

05.03.01 LIMPIEZA DE ALCANTARILLAS

05.04 BADENES

05.04.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO

05.04.02 CONCRETO CICLOPEO F'C=175 KG/CM2 + 30% P.M.

05.04.03 AFIRMADO PARA BADEN

05.04.04 ENCOFRADO Y DESENCOFRADO

05.04.05 JUNTAS ASFALTICAS

06 SEÑALIZACION

06.01 SEÑAL PREVENTIVA

06.02 SEÑAL INFORMATIVA

06.03 SEÑAL REGLAMENTARIA

06.04 HITOS KILOMETRICOS

06.05 PINTADO DE BARANDAS METALICAS EN PUENTES


07 PROTECCION AMBIENTAL

07.01 SEÑALIZACION AMBIENTAL

07.02 RESTAURACION DE AREA DE CAMPAMENTOS Y PATIO DE MAQUINAS

07.03 RESTAURACION DE CANTERAS

07.04 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN EL DME

07.05 REVEGETACION

COSTO DIRECTO
GASTOS GENERALES FIJOS
GASTOS GENERALES VARIABLES
UTILIDADES
SUB TOTAL
IGV 18%
TOTAL GENERAL
ADOS EJECUTADOS MENSUALES
xxxxxxxx (L= 19.208 KM)

P.U. PARCIAL MAY 12


METRADO DE
UND
EXPEDIENTE
S/. S/. METRADO EJEC.

1,424,243.77

78,442.91

GLB 1.00 49,821.93 49,821.93 0.50

GLB 1.00 19,260.92 19,260.92 0.75

ha 5.76 1,625.01 9,360.06 5.76

549,568.25

m3 43,810.78 5.16 226,063.62 7,047.71

m3 6,930.43 11.60 80,392.99 2,289.31

m3 6,143.97 19.80 121,650.61 2,179.66

m3 3,307.61 16.80 55,567.85 312.30

m2 70,099.13 0.94 65,893.18 3,765.08


401,783.58

m3 16,563.46 22.77 377,149.98 -

m2 27,905.22 0.58 16,185.03 -

m2 8,987.84 0.94 8,448.57 -

204,854.47

m3-km 14,947.19 5.56 83,106.38 -

m3-km 44,273.10 1.25 55,341.38 -

m3-km 2,829.07 5.56 15,729.63 109.79

m3-km 4,655.12 1.25 5,818.90 449.86

m3-km 17,943.27 2.50 44,858.18 4,374.78

69,435.98

42,244.65

m3 186.60 38.83 7,245.68 56.21

m3 50.60 26.77 1,354.56 -

m3 5.96 180.28 1,074.47 -

m3 1.73 186.11 321.97 0.49

m3 27.54 339.81 9,358.37 -

m3 19.21 379.35 7,287.31 -

kg 1,138.33 4.85 5,520.90 335.69


m2 222.40 45.33 10,081.39 67.52

6,482.49

m3 11.78 50.66 596.77 -

m3 11.89 339.81 4,040.34 -

m2 40.71 45.33 1,845.38 -

1,279.50

und 30.00 42.65 1,279.50 -

19,429.34

m3 79.04 38.83 3,069.12 -

m3 72.75 195.83 14,246.63 -

m3 5.86 34.81 203.99 -

m2 28.60 45.33 1,296.44 -

m 31.77 19.30 613.16 -

31,366.85

und 28.00 390.29 10,928.12 -

und 10.00 1,400.44 14,004.40 -

und 5.00 458.50 2,292.50 -

und 20.00 104.86 2,097.20 -

m 137.50 14.87 2,044.63 -


88,791.73

und 26.00 471.71 12,264.46 10.00

ha 0.25 8,595.43 2,148.86 -

ha 1.78 7,522.04 13,389.23 -

m3 56,885.18 1.00 56,885.18 -

ha 3.42 1,200.00 4,104.00 -

1,424,243.77
5.00% 71,212.19
8.00% 113,939.50
6.00% 85,454.63
1,694,850.09
18.00% 305,073.02
1,999,923.11
JUN 12 JUL 12 AGO 12

METRADO EJEC. METRADO EJEC. METRADO EJEC.

0.25 0.10 0.15 0.00

0.15 0.10 - 0.00

- - - 0.00

33,854.02 2,909.05 - 0.00

3,887.08 754.04 - 0.00

3,175.03 789.28 - 0.00

2,316.86 678.45 - 0.00

59,448.04 6,886.01 - 0.00


- 11,881.86 4,681.60 0.00

- 22,443.45 5,461.77 0.00

- 8,865.76 122.08 0.00

2,004.50 11,987.58 955.11 0.00

6,598.45 35,240.18 2,434.47 0.00

2,241.66 477.62 - 0.00

3,896.79 308.47 - 0.00

11,438.10 2,130.39 - 0.00

49.71 80.68 - 0.00

31.92 18.68 - 0.00

- 5.96 - 0.00

0.52 0.72 - 0.00

18.36 9.18 - 0.00

11.47 7.74 - 0.00

352.38 450.26 - 0.00


69.08 85.80 - 0.00

- 11.78 - 0.00

- 11.89 - 0.00

- 40.71 - 0.00

11.00 19.00 - 0.00

54.58 24.46 - 0.00

49.21 23.54 - 0.00

3.80 2.06 - 0.00

18.82 9.78 - 0.00

- - 31.77 0.00

- - 28.00 0.00

- - 10.00 0.00

- - 5.00 0.00

- - 20.00 0.00

- 137.50 - 0.00
- 16.00 - 0.00

- - 0.25 0.00

- - 1.78 0.00

- - 56,885.18 0.00

- 3.42 - 0.00
OBRA REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208
ENTIDAD xxxxxxxxxxxxxxxx
CONTRAT. xxxxxxxxxxxxxxxx

ITEM DESCRIPCION

01 OBRAS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS
01.02 TOPOGRAFIA Y GEOREFERENCIACION
01.03 DESBROCE Y LIMPIEZA

02 MOVIMIENTO DE TIERRAS
02.01 CORTE EN MATERIAL SUELTO
02.02 CORTE EN ROCA SUELTA
02.03 CORTE EN ROCA FIJA
02.04 RELLENO CON MATERIAL DE PRESTAMO
02.05 PERFILADO Y COMPACTACION SUB-RASANTE EN ZONAS DE CORTE

03 PAVIMENTOS
03.01 AFIRMADO
03.02 ESCARIFICADO DE AFIRMADO EXISTENTE
03.03 PERFILADO Y COMPACTACION DE AFIRMADO EXISTENTE

04 TRANSPORTE
04.01 TRANSPORTE DE MATERIAL AFIRMADO D<1 KM
04.02 TRANSPORTE DE MATERIAL AFIRMADO D>1 KM
04.03 TRANSPORTE DE MATERIAL DE PRESTAMO D<1 KM
04.04 TRANSPORTE DE MATERIAL DE PRESTAMO D>1 KM
04.05 TRANSPORTE DE MATERIAL EXCEDENTE D<1 KM

05 OBRAS DE ARTE Y DRENAJE


05.01 ALCANTARILLAS TIPO MARCO DE 1.00 x 1.00 M
05.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO
05.01.02 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO
05.01.03 EMBOQUILADO DE PIEDRA
05.01.04 CONCRETO F'C=100 KG/CM2
05.01.05 CONCRETO F'C=175 KG/CM2
05.01.06 CONCRETO F'C=210 KG/CM2
05.01.07 ACERO DE REFUERZO FY= 4200 KG/CM2
05.01.08 ENCOFRADO Y DESENCOFRADO
05.02 REPOSICION DE CABEZALES DE ALCANTARILLA
05.02.01 DEMOLICION DE ESTRUCTURAS
05.02.02 CONCRETO F'C=175 KG/CM2
05.02.03 ENCOFRADO Y DESENCOFRADO
05.03 LIMPIEZA DE ALCANTARILLAS
05.03.01 LIMPIEZA DE ALCANTARILLAS
05.04 BADENES
05.04.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO
05.04.02 CONCRETO CICLOPEO F'C=175 KG/CM2 + 30% P.M.
05.04.03 AFIRMADO PARA BADEN
05.04.04 ENCOFRADO Y DESENCOFRADO
05.04.05 JUNTAS ASFALTICAS

06 SEÑALIZACION
06.01 SEÑAL PREVENTIVA
06.02 SEÑAL INFORMATIVA
06.03 SEÑAL REGLAMENTARIA
06.04 HITOS KILOMETRICOS
06.05 PINTADO DE BARANDAS METALICAS EN PUENTES

07 PROTECCION AMBIENTAL
07.01 SEÑALIZACION AMBIENTAL
07.02 RESTAURACION DE AREA DE CAMPAMENTOS Y PATIO DE MAQUINAS
07.03 RESTAURACION DE CANTERAS
07.04 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN EL DME
07.05 REVEGETACION
COSTO DIRECTO
GASTOS GENERALES FIJOS
GASTOS GENERALES VARIABLES
UTILIDADES
VALORIZACION

% DE AVANCE

OBRA REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208


ENTIDAD xxxxxxxxxxxxxxxx
CONTRAT. xxxxxxxxxxxxxxxx

ITEM DESCRIPCION

01 OBRAS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS
01.02 TOPOGRAFIA Y GEOREFERENCIACION
01.03 DESBROCE Y LIMPIEZA

02 MOVIMIENTO DE TIERRAS
02.01 CORTE EN MATERIAL SUELTO
02.02 CORTE EN ROCA SUELTA
02.03 CORTE EN ROCA FIJA
02.04 RELLENO CON MATERIAL DE PRESTAMO
02.05 PERFILADO Y COMPACTACION SUB-RASANTE EN ZONAS DE CORTE

03 PAVIMENTOS
03.01 AFIRMADO
03.02 ESCARIFICADO DE AFIRMADO EXISTENTE
03.03 PERFILADO Y COMPACTACION DE AFIRMADO EXISTENTE

04 TRANSPORTE
04.01 TRANSPORTE DE MATERIAL AFIRMADO D<1 KM
04.02 TRANSPORTE DE MATERIAL AFIRMADO D>1 KM
04.03 TRANSPORTE DE MATERIAL DE PRESTAMO D<1 KM
04.04 TRANSPORTE DE MATERIAL DE PRESTAMO D>1 KM
04.05 TRANSPORTE DE MATERIAL EXCEDENTE D<1 KM

05 OBRAS DE ARTE Y DRENAJE


05.01 ALCANTARILLAS TIPO MARCO DE 1.00 x 1.00 M
05.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO
05.01.02 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO
05.01.03 EMBOQUILADO DE PIEDRA
05.01.04 CONCRETO F'C=100 KG/CM2
05.01.05 CONCRETO F'C=175 KG/CM2
05.01.06 CONCRETO F'C=210 KG/CM2
05.01.07 ACERO DE REFUERZO FY= 4200 KG/CM2
05.01.08 ENCOFRADO Y DESENCOFRADO
05.02 REPOSICION DE CABEZALES DE ALCANTARILLA
05.02.01 DEMOLICION DE ESTRUCTURAS
05.02.02 CONCRETO F'C=175 KG/CM2
05.02.03 ENCOFRADO Y DESENCOFRADO
05.03 LIMPIEZA DE ALCANTARILLAS
05.03.01 LIMPIEZA DE ALCANTARILLAS
05.04 BADENES
05.04.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO
05.04.02 CONCRETO CICLOPEO F'C=175 KG/CM2 + 30% P.M.
05.04.03 AFIRMADO PARA BADEN
05.04.04 ENCOFRADO Y DESENCOFRADO
05.04.05 JUNTAS ASFALTICAS

06 SEÑALIZACION
06.01 SEÑAL PREVENTIVA
06.02 SEÑAL INFORMATIVA
06.03 SEÑAL REGLAMENTARIA
06.04 HITOS KILOMETRICOS
06.05 PINTADO DE BARANDAS METALICAS EN PUENTES

07 PROTECCION AMBIENTAL
07.01 SEÑALIZACION AMBIENTAL
07.02 RESTAURACION DE AREA DE CAMPAMENTOS Y PATIO DE MAQUINAS

07.03 RESTAURACION DE CANTERAS


07.04 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN EL DME
07.05 REVEGETACION

COSTO DIRECTO
GASTOS GENERALES FIJOS
GASTOS GENERALES VARIABLES
UTILIDADES
VALORIZACION

% DE AVANCE

OBRA REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208


ENTIDAD xxxxxxxxxxxxxxxx
CONTRAT. xxxxxxxxxxxxxxxx

ITEM DESCRIPCION

01 OBRAS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS
01.02 TOPOGRAFIA Y GEOREFERENCIACION
01.03 DESBROCE Y LIMPIEZA

02 MOVIMIENTO DE TIERRAS
02.01 CORTE EN MATERIAL SUELTO
02.02 CORTE EN ROCA SUELTA
02.03 CORTE EN ROCA FIJA
02.04 RELLENO CON MATERIAL DE PRESTAMO
02.05 PERFILADO Y COMPACTACION SUB-RASANTE EN ZONAS DE CORTE

03 PAVIMENTOS
03.01 AFIRMADO
03.02 ESCARIFICADO DE AFIRMADO EXISTENTE
03.03 PERFILADO Y COMPACTACION DE AFIRMADO EXISTENTE

04 TRANSPORTE
04.01 TRANSPORTE DE MATERIAL AFIRMADO D<1 KM
04.02 TRANSPORTE DE MATERIAL AFIRMADO D>1 KM
04.03 TRANSPORTE DE MATERIAL DE PRESTAMO D<1 KM
04.04 TRANSPORTE DE MATERIAL DE PRESTAMO D>1 KM
04.05 TRANSPORTE DE MATERIAL EXCEDENTE D<1 KM

05 OBRAS DE ARTE Y DRENAJE


05.01 ALCANTARILLAS TIPO MARCO DE 1.00 x 1.00 M
05.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO
05.01.02 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO
05.01.03 EMBOQUILADO DE PIEDRA
05.01.04 CONCRETO F'C=100 KG/CM2
05.01.05 CONCRETO F'C=175 KG/CM2
05.01.06 CONCRETO F'C=210 KG/CM2
05.01.07 ACERO DE REFUERZO FY= 4200 KG/CM2
05.01.08 ENCOFRADO Y DESENCOFRADO
05.02 REPOSICION DE CABEZALES DE ALCANTARILLA
05.02.01 DEMOLICION DE ESTRUCTURAS
05.02.02 CONCRETO F'C=175 KG/CM2
05.02.03 ENCOFRADO Y DESENCOFRADO
05.03 LIMPIEZA DE ALCANTARILLAS
05.03.01 LIMPIEZA DE ALCANTARILLAS
05.04 BADENES
05.04.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO
05.04.02 CONCRETO CICLOPEO F'C=175 KG/CM2 + 30% P.M.
05.04.03 AFIRMADO PARA BADEN
05.04.04 ENCOFRADO Y DESENCOFRADO
05.04.05 JUNTAS ASFALTICAS

06 SEÑALIZACION
06.01 SEÑAL PREVENTIVA
06.02 SEÑAL INFORMATIVA
06.03 SEÑAL REGLAMENTARIA
06.04 HITOS KILOMETRICOS
06.05 PINTADO DE BARANDAS METALICAS EN PUENTES

07 PROTECCION AMBIENTAL
07.01 SEÑALIZACION AMBIENTAL
07.02 RESTAURACION DE AREA DE CAMPAMENTOS Y PATIO DE MAQUINAS

07.03 RESTAURACION DE CANTERAS


07.04 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN EL DME
07.05 REVEGETACION

COSTO DIRECTO
GASTOS GENERALES FIJOS
GASTOS GENERALES VARIABLES
UTILIDADES
VALORIZACION
% DE AVANCE

OBRA REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208


ENTIDAD xxxxxxxxxxxxxxxx
CONTRAT. xxxxxxxxxxxxxxxx

ITEM DESCRIPCION

01 OBRAS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS
01.02 TOPOGRAFIA Y GEOREFERENCIACION
01.03 DESBROCE Y LIMPIEZA

02 MOVIMIENTO DE TIERRAS
02.01 CORTE EN MATERIAL SUELTO
02.02 CORTE EN ROCA SUELTA
02.03 CORTE EN ROCA FIJA
02.04 RELLENO CON MATERIAL DE PRESTAMO
02.05 PERFILADO Y COMPACTACION SUB-RASANTE EN ZONAS DE CORTE

03 PAVIMENTOS
03.01 AFIRMADO
03.02 ESCARIFICADO DE AFIRMADO EXISTENTE
03.03 PERFILADO Y COMPACTACION DE AFIRMADO EXISTENTE

04 TRANSPORTE
04.01 TRANSPORTE DE MATERIAL AFIRMADO D<1 KM
04.02 TRANSPORTE DE MATERIAL AFIRMADO D>1 KM
04.03 TRANSPORTE DE MATERIAL DE PRESTAMO D<1 KM
04.04 TRANSPORTE DE MATERIAL DE PRESTAMO D>1 KM
04.05 TRANSPORTE DE MATERIAL EXCEDENTE D<1 KM

05 OBRAS DE ARTE Y DRENAJE


05.01 ALCANTARILLAS TIPO MARCO DE 1.00 x 1.00 M
05.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO
05.01.02 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO
05.01.03 EMBOQUILADO DE PIEDRA
05.01.04 CONCRETO F'C=100 KG/CM2
05.01.05 CONCRETO F'C=175 KG/CM2
05.01.06 CONCRETO F'C=210 KG/CM2
05.01.07 ACERO DE REFUERZO FY= 4200 KG/CM2
05.01.08 ENCOFRADO Y DESENCOFRADO
05.02 REPOSICION DE CABEZALES DE ALCANTARILLA
05.02.01 DEMOLICION DE ESTRUCTURAS
05.02.02 CONCRETO F'C=175 KG/CM2
05.02.03 ENCOFRADO Y DESENCOFRADO
05.03 LIMPIEZA DE ALCANTARILLAS
05.03.01 LIMPIEZA DE ALCANTARILLAS
05.04 BADENES
05.04.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO
05.04.02 CONCRETO CICLOPEO F'C=175 KG/CM2 + 30% P.M.
05.04.03 AFIRMADO PARA BADEN
05.04.04 ENCOFRADO Y DESENCOFRADO
05.04.05 JUNTAS ASFALTICAS

06 SEÑALIZACION
06.01 SEÑAL PREVENTIVA
06.02 SEÑAL INFORMATIVA
06.03 SEÑAL REGLAMENTARIA
06.04 HITOS KILOMETRICOS
06.05 PINTADO DE BARANDAS METALICAS EN PUENTES

07 PROTECCION AMBIENTAL
07.01 SEÑALIZACION AMBIENTAL
07.02 RESTAURACION DE AREA DE CAMPAMENTOS Y PATIO DE MAQUINAS

07.03 RESTAURACION DE CANTERAS


07.04 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN EL DME
07.05 REVEGETACION

COSTO DIRECTO
GASTOS GENERALES FIJOS
GASTOS GENERALES VARIABLES
UTILIDADES
VALORIZACION

% DE AVANCE
VALORIZACION Nº 01

xxxxxxxx (L= 19.208 KM)

P.U. PARCIAL ACUMULADO ANTERIOR


UND METRADO
S/. S/. % CANT. P. TOTAL

78,442.91
GLB 1.00 49,821.93 49,821.93 0.00% 0.00 0.00
GLB 1.00 19,260.92 19,260.92 0.00% 0.00 0.00
ha 5.76 1,625.01 9,360.06 0.00% 0.00 0.00

549,568.25
m3 43,810.78 5.16 226,063.62 0.00% 0.00 0.00
m3 6,930.43 11.60 80,392.99 0.00% 0.00 0.00
m3 6,143.97 19.80 121,650.61 0.00% 0.00 0.00
m3 3,307.61 16.80 55,567.85 0.00% 0.00 0.00
m2 70,099.13 0.94 65,893.18 0.00% 0.00 0.00

401,783.58
m3 16,563.46 22.77 377,149.98 0.00% 0.00 0.00
m2 27,905.22 0.58 16,185.03 0.00% 0.00 0.00
m2 8,987.84 0.94 8,448.57 0.00% 0.00 0.00

204,854.47
m3-km 14,947.19 5.56 83,106.38 0.00% 0.00 0.00
m3-km 44,273.10 1.25 55,341.38 0.00% 0.00 0.00
m3-km 2,829.07 5.56 15,729.63 0.00% 0.00 0.00
m3-km 4,655.12 1.25 5,818.90 0.00% 0.00 0.00
m3-km 17,943.27 2.50 44,858.18 0.00% 0.00 0.00

69,435.98
42,244.65
m3 186.60 38.83 7,245.68 0.00% 0.00 0.00
m3 50.60 26.77 1,354.56 0.00% 0.00 0.00
m3 5.96 180.28 1,074.47 0.00% 0.00 0.00
m3 1.73 186.11 321.97 0.00% 0.00 0.00
m3 27.54 339.81 9,358.37 0.00% 0.00 0.00
m3 19.21 379.35 7,287.31 0.00% 0.00 0.00
kg 1,138.33 4.85 5,520.90 0.00% 0.00 0.00
m2 222.40 45.33 10,081.39 0.00% 0.00 0.00
6,482.49
m3 11.78 50.66 596.77 0.00% 0.00 0.00
m3 11.89 339.81 4,040.34 0.00% 0.00 0.00
m2 40.71 45.33 1,845.38 0.00% 0.00 0.00
1,279.50
und 30.00 42.65 1,279.50 0.00% 0.00 0.00
19,429.34
m3 79.04 38.83 3,069.12 0.00% 0.00 0.00
m3 72.75 195.83 14,246.63 0.00% 0.00 0.00
m3 5.86 34.81 203.99 0.00% 0.00 0.00
m2 28.60 45.33 1,296.44 0.00% 0.00 0.00
m 31.77 19.30 613.16 0.00% 0.00 0.00

31,366.85
und 28.00 390.29 10,928.12 0.00% 0.00 0.00
und 10.00 1,400.44 14,004.40 0.00% 0.00 0.00
und 5.00 458.50 2,292.50 0.00% 0.00 0.00
und 20.00 104.86 2,097.20 0.00% 0.00 0.00
m 137.50 14.87 2,044.63 0.00% 0.00 0.00

88,791.73
und 26.00 471.71 12,264.46 0.00% 0.00 0.00
ha 0.25 8,595.43 2,148.86 0.00% 0.00 0.00
ha 1.78 7,522.04 13,389.23 0.00% 0.00 0.00
m3 56,885.18 1.00 56,885.18 0.00% 0.00 0.00
ha 3.42 1,200.00 4,104.00 0.00% 0.00 0.00

S/. 1,424,243.77 S/. 0.00


5.00% S/. 71,212.19 S/. 0.00
8.00% S/. 113,939.50 S/. 0.00
6.00% S/. 85,454.63 S/. 0.00
S/. 1,694,850.09 S/. 0.00

0.0%

VALORIZACION Nº 02

xxxxxxxx (L= 19.208 KM)

P.U. PARCIAL ACUMULADO ANTERIOR


UND METRADO
S/. S/. % CANT. P. TOTAL

78,442.91
GLB 1.00 49,821.93 49,821.93 50.00% 0.50 24910.97
GLB 1.00 19,260.92 19,260.92 75.00% 0.75 14445.69
ha 5.76 1,625.01 9,360.06 100.00% 5.76 9360.06

549,568.25
m3 43,810.78 5.16 226,063.62 16.09% 7,047.71 36366.18
m3 6,930.43 11.60 80,392.99 33.03% 2,289.31 26556.00
m3 6,143.97 19.80 121,650.61 35.48% 2,179.66 43157.27
m3 3,307.61 16.80 55,567.85 9.44% 312.30 5246.64
m2 70,099.13 0.94 65,893.18
5.37% 3,765.08 3539.18

401,783.58
m3 16,563.46 22.77 377,149.98 0.00% 0.00 0.00
m2 27,905.22 0.58 16,185.03 0.00% 0.00 0.00
m2 8,987.84 0.94 8,448.57 0.00% 0.00 0.00

204,854.47
m3-km 14,947.19 5.56 83,106.38 0.00% 0.00 0.00
m3-km 44,273.10 1.25 55,341.38 0.00% 0.00 0.00
m3-km 2,829.07 5.56 15,729.63 3.88% 109.79 610.43
m3-km 4,655.12 1.25 5,818.90 9.66% 449.86 562.33
m3-km 17,943.27 2.50 44,858.18 24.38% 4,374.78 10936.95

69,435.98
42,244.65
m3 186.60 38.83 7,245.68 30.12% 56.21 2182.63
m3 50.60 26.77 1,354.56 0.00% 0.00 0.00
m3 5.96 180.28 1,074.47 0.00% 0.00 0.00
m3 1.73 186.11 321.97 28.32% 0.49 91.19
m3 27.54 339.81 9,358.37 0.00% 0.00 0.00
m3 19.21 379.35 7,287.31 0.00% 0.00 0.00
kg 1,138.33 4.85 5,520.90 29.49% 335.69 1628.10
m2 222.40 45.33 10,081.39 30.36% 67.52 3060.68
6,482.49
m3 11.78 50.66 596.77 0.00% 0.00 0.00
m3 11.89 339.81 4,040.34 0.00% 0.00 0.00
m2 40.71 45.33 1,845.38 0.00% 0.00 0.00
1,279.50
und 30.00 42.65 1,279.50 0.00% 0.00 0.00
19,429.34
m3 79.04 38.83 3,069.12 0.00% 0.00 0.00
m3 72.75 195.83 14,246.63 0.00% 0.00 0.00
m3 5.86 34.81 203.99 0.00% 0.00 0.00
m2 28.60 45.33 1,296.44 0.00% 0.00 0.00
m 31.77 19.30 613.16 0.00% 0.00 0.00

31,366.85
und 28.00 390.29 10,928.12 0.00% 0.00 0.00
und 10.00 1,400.44 14,004.40 0.00% 0.00 0.00
und 5.00 458.50 2,292.50 0.00% 0.00 0.00
und 20.00 104.86 2,097.20 0.00% 0.00 0.00
m 137.50 14.87 2,044.63 0.00% 0.00 0.00

88,791.73
und 26.00 471.71 12,264.46 38.46% 10.00 4717.10
ha 0.25 8,595.43 2,148.86
0.00% 0.00 0.00
ha 1.78 7,522.04 13,389.23 0.00% 0.00 0.00
m3 56,885.18 1.00 56,885.18 0.00% 0.00 0.00
ha 3.42 1,200.00 4,104.00 0.00% 0.00 0.00

S/. 1,424,243.77 S/. 187,371.40


5.00% S/. 71,212.19 S/. 9,368.57
8.00% S/. 113,939.50 S/. 14,989.71
6.00% S/. 85,454.63 S/. 11,242.28
S/. 1,694,850.09 S/. 222,971.96

13.2%

VALORIZACION Nº 03

xxxxxxxx (L= 19.208 KM)

P.U. PARCIAL ACUMULADO ANTERIOR


UND METRADO
S/. S/. % CANT. P. TOTAL

78,442.91
GLB 1.00 49,821.93 49,821.93 75.00% 0.75 37366.45
GLB 1.00 19,260.92 19,260.92 90.00% 0.90 17334.83
ha 5.76 1,625.01 9,360.06 100.00% 5.76 9360.06

549,568.25
m3 43,810.78 5.16 226,063.62 93.36% 40,901.73 ###
m3 6,930.43 11.60 80,392.99 89.12% 6,176.39 71646.12
m3 6,143.97 19.80 121,650.61 87.15% 5,354.69 ###
m3 3,307.61 16.80 55,567.85 79.49% 2,629.16 44169.89
m2 70,099.13 0.94 65,893.18
90.18% 63,213.12 59420.33

401,783.58
m3 16,563.46 22.77 377,149.98 0.00% 0.00 0.00
m2 27,905.22 0.58 16,185.03 0.00% 0.00 0.00
m2 8,987.84 0.94 8,448.57 0.00% 0.00 0.00

204,854.47
m3-km 14,947.19 5.56 83,106.38 13.41% 2,004.50 11145.02
m3-km 44,273.10 1.25 55,341.38 14.90% 6,598.45 8248.06
m3-km 2,829.07 5.56 15,729.63 83.12% 2,351.45 13074.06
m3-km 4,655.12 1.25 5,818.90 93.37% 4,346.65 5433.31
m3-km 17,943.27 2.50 44,858.18 88.13% 15,812.88 39532.20

69,435.98
42,244.65
m3 186.60 38.83 7,245.68 56.76% 105.92 4112.87
m3 50.60 26.77 1,354.56 63.08% 31.92 854.50
m3 5.96 180.28 1,074.47 0.00% 0.00 0.00
m3 1.73 186.11 321.97 58.38% 1.01 187.97
m3 27.54 339.81 9,358.37 66.67% 18.36 6238.91
m3 19.21 379.35 7,287.31 59.71% 11.47 4351.14
kg 1,138.33 4.85 5,520.90 60.45% 688.07 3337.14
m2 222.40 45.33 10,081.39 61.42% 136.60 6192.08
6,482.49
m3 11.78 50.66 596.77 0.00% 0.00 0.00
m3 11.89 339.81 4,040.34 0.00% 0.00 0.00
m2 40.71 45.33 1,845.38 0.00% 0.00 0.00
1,279.50
und 30.00 42.65 1,279.50 36.67% 11.00 469.15
19,429.34
m3 79.04 38.83 3,069.12 69.05% 54.58 2119.34
m3 72.75 195.83 14,246.63 67.64% 49.21 9636.79
m3 5.86 34.81 203.99 64.85% 3.80 132.28
m2 28.60 45.33 1,296.44 65.80% 18.82 853.11
m 31.77 19.30 613.16 0.00% 0.00 0.00

31,366.85
und 28.00 390.29 10,928.12 0.00% 0.00 0.00
und 10.00 1,400.44 14,004.40 0.00% 0.00 0.00
und 5.00 458.50 2,292.50 0.00% 0.00 0.00
und 20.00 104.86 2,097.20 0.00% 0.00 0.00
m 137.50 14.87 2,044.63 0.00% 0.00 0.00

88,791.73
und 26.00 471.71 12,264.46 38.46% 10.00 4717.10
ha 0.25 8,595.43 2,148.86
0.00% 0.00 0.00
ha 1.78 7,522.04 13,389.23 0.00% 0.00 0.00
m3 56,885.18 1.00 56,885.18 0.00% 0.00 0.00
ha 3.42 1,200.00 4,104.00 0.00% 0.00 0.00

S/. 1,424,243.77 S/. 677,008.50


5.00% S/. 71,212.19 S/. 33,850.43
8.00% S/. 113,939.50 S/. 54,160.68
6.00% S/. 85,454.63 S/. 40,620.51
S/. 1,694,850.09 S/. 805,640.12
47.5%

VALORIZACION Nº 04

xxxxxxxx (L= 19.208 KM)

P.U. PARCIAL ACUMULADO ANTERIOR


UND METRADO
S/. S/. % CANT. P. TOTAL

78,442.91
GLB 1.00 49,821.93 49,821.93 85.00% 0.85 42348.64
GLB 1.00 19,260.92 19,260.92 100.00% 1.00 19260.92
ha 5.76 1,625.01 9,360.06 100.00% 5.76 9360.06

549,568.25
m3 43,810.78 5.16 226,063.62 100.00% 43,810.78 ###
m3 6,930.43 11.60 80,392.99 100.00% 6,930.43 80392.99
m3 6,143.97 19.80 121,650.61 100.00% 6,143.97 ###
m3 3,307.61 16.80 55,567.85 100.00% 3,307.61 55567.85
m2 70,099.13 0.94 65,893.18
100.00% 70,099.13 65893.18

401,783.58
m3 16,563.46 22.77 377,149.98 71.74% 11,881.86 ###
m2 27,905.22 0.58 16,185.03 80.43% 22,443.45 13017.20
m2 8,987.84 0.94 8,448.57 98.64% 8,865.76 8333.81

204,854.47
m3-km 14,947.19 5.56 83,106.38 93.61% 13,992.08 77795.96
m3-km 44,273.10 1.25 55,341.38 94.50% 41,838.63 52298.29
m3-km 2,829.07 5.56 15,729.63 100.00% 2,829.07 15729.63
m3-km 4,655.12 1.25 5,818.90 100.00% 4,655.12 5818.90
m3-km 17,943.27 2.50 44,858.18 100.00% 17,943.27 44858.18

69,435.98
42,244.65
m3 186.60 38.83 7,245.68 100.00% 186.60 7245.68
m3 50.60 26.77 1,354.56 100.00% 50.60 1354.56
m3 5.96 180.28 1,074.47 100.00% 5.96 1074.47
m3 1.73 186.11 321.97 100.00% 1.73 321.97
m3 27.54 339.81 9,358.37 100.00% 27.54 9358.37
m3 19.21 379.35 7,287.31 100.00% 19.21 7287.31
kg 1,138.33 4.85 5,520.90 100.00% 1,138.33 5520.90
m2 222.40 45.33 10,081.39 100.00% 222.40 10081.39
6,482.49
m3 11.78 50.66 596.77 100.00% 11.78 596.77
m3 11.89 339.81 4,040.34 100.00% 11.89 4040.34
m2 40.71 45.33 1,845.38 100.00% 40.71 1845.38
1,279.50
und 30.00 42.65 1,279.50 100.00% 30.00 1279.50
19,429.34
m3 79.04 38.83 3,069.12 100.00% 79.04 3069.12
m3 72.75 195.83 14,246.63 100.00% 72.75 14246.63
m3 5.86 34.81 203.99 100.00% 5.86 203.99
m2 28.60 45.33 1,296.44 100.00% 28.60 1296.44
m 31.77 19.30 613.16 0.00% 0.00 0.00

31,366.85
und 28.00 390.29 10,928.12 0.00% 0.00 0.00
und 10.00 1,400.44 14,004.40 0.00% 0.00 0.00
und 5.00 458.50 2,292.50 0.00% 0.00 0.00
und 20.00 104.86 2,097.20 0.00% 0.00 0.00
m 137.50 14.87 2,044.63 100.00% 137.50 2044.63

88,791.73
und 26.00 471.71 12,264.46 100.00% 26.00 12264.46
ha 0.25 8,595.43 2,148.86
0.00% 0.00 0.00
ha 1.78 7,522.04 13,389.23 0.00% 0.00 0.00
m3 56,885.18 1.00 56,885.18 0.00% 0.00 0.00
ha 3.42 1,200.00 4,104.00 100.00% 3.42 4104.00

S/. 1,424,243.77 S/. 1,196,175.70


5.00% S/. 71,212.19 S/. 59,808.79
8.00% S/. 113,939.50 S/. 95,694.06
6.00% S/. 85,454.63 S/. 71,770.54
S/. 1,694,850.09 S/. 1,423,449.09

84.0%

Resumen
Val 1 222,971.96
Val 2 582,668.18
Val 3 617,808.94
Val 4 271,401.00
S/1,694,850.08
PRESUPUESTO BASE :

PRESUPUESTO CONTRATADO :

PLAZO EJECUCION : 90 DIAS

AVANCE ACTUAL ACUMULADO TOTAL SALDO


% CANT. P. TOTAL % CANT. P. TOTAL % CANT.

50.00% 0.50 24,910.97 50.00% 0.50 24910.97 50.00% 0.50


75.00% 0.75 14,445.69 75.00% 0.75 14445.69 25.00% 0.25
100.00% 5.76 9,360.06 100.00% 5.76 9360.06 0.00% -

16.09% 7,047.71 36,366.18 16.09% 7,047.71 36366.18 83.91% 36,763.07


33.03% 2,289.31 26,556.00 33.03% 2,289.31 26556.00 66.97% 4,641.12
35.48% 2,179.66 43,157.27 35.48% 2,179.66 43157.27 64.52% 3,964.31
9.44% 312.30 5,246.64 9.44% 312.30 5246.64 90.56% 2,995.31
5.37% 3,765.08 3,539.18 5.37% 3,765.08 3539.18 94.63% 66,334.05

0.00% - - 0.00% 0.00 0.00 100.00% 16,563.46


0.00% - - 0.00% 0.00 0.00 100.00% 27,905.22
0.00% - - 0.00% 0.00 0.00 100.00% 8,987.84

0.00% - - 0.00% 0.00 0.00 100.00% 14,947.19


0.00% - - 0.00% 0.00 0.00 100.00% 44,273.10
3.88% 109.79 610.43 3.88% 109.79 610.43 96.12% 2,719.28
9.66% 449.86 562.33 9.66% 449.86 562.33 90.34% 4,205.26
24.38% 4,374.78 10,936.95 24.38% 4,374.78 10936.95 75.62% 13,568.49

30.12% 56.21 2,182.63 30.12% 56.21 2182.63 69.88% 130.39


0.00% - - 0.00% 0.00 0.00 100.00% 50.60
0.00% - - 0.00% 0.00 0.00 100.00% 5.96
28.32% 0.49 91.19 28.32% 0.49 91.19 71.68% 1.24
0.00% - - 0.00% 0.00 0.00 100.00% 27.54
0.00% - - 0.00% 0.00 0.00 100.00% 19.21
29.49% 335.69 1,628.10 29.49% 335.69 1628.10 70.51% 802.64
30.36% 67.52 3,060.68 30.36% 67.52 3060.68 69.64% 154.88

0.00% - - 0.00% 0.00 0.00 100.00% 11.78


0.00% - - 0.00% 0.00 0.00 100.00% 11.89
0.00% - - 0.00% 0.00 0.00 100.00% 40.71

0.00% - - 0.00% 0.00 0.00 100.00% 30.00


0.00% - - 0.00% 0.00 0.00 100.00% 79.04
0.00% - - 0.00% 0.00 0.00 100.00% 72.75
0.00% - - 0.00% 0.00 0.00 100.00% 5.86
0.00% - - 0.00% 0.00 0.00 100.00% 28.60
0.00% - - 0.00% 0.00 0.00 100.00% 31.77

0.00% - - 0.00% 0.00 0.00 100.00% 28.00


0.00% - - 0.00% 0.00 0.00 100.00% 10.00
0.00% - - 0.00% 0.00 0.00 100.00% 5.00
0.00% - - 0.00% 0.00 0.00 100.00% 20.00
0.00% - - 0.00% 0.00 0.00 100.00% 137.50

38.46% 10.00 4,717.10 38.46% 10.00 4717.10 61.54% 16.00


0.00% - - 0.00% 0.00 0.00 100.00% 0.25
0.00% - - 0.00% 0.00 0.00 100.00% 1.78
0.00% - - 0.00% 0.00 0.00 100.00% 56,885.18
0.00% - - 0.00% 0.00 0.00 100.00% 3.42

S/. 187,371.40 S/. 187,371.40 S/. 1,236,872.37


S/. 9,368.57 S/. 9,368.57 S/. 61,843.62
S/. 14,989.71 S/. 14,989.71 S/. 98,949.79
S/. 11,242.28 S/. 11,242.28 S/. 74,212.34
S/. 222,971.96 S/. 222,971.96 S/. 1,471,878.12

13.2% 13.2% 86.8%

PRESUPUESTO BASE :
PRESUPUESTO CONTRATADO :

PLAZO EJECUCION : 90 DIAS

AVANCE ACTUAL ACUMULADO TOTAL SALDO


% CANT. P. TOTAL % CANT. P. TOTAL % CANT.

25.00% 0.25 12,455.48 75.00% 0.75 37366.45 25.00% 0.25


15.00% 0.15 2,889.14 90.00% 0.90 17334.83 10.00% 0.10
0.00% - - 100.00% 5.76 9360.06 0.00% -

77.27% ### ### 93.36% 40,901.73 211052.92 6.64% 2,909.05


56.09% 3,887.08 45,090.13 89.12% 6,176.39 71646.13 10.88% 754.04
51.68% 3,175.03 62,865.59 87.15% 5,354.69 106022.86 12.85% 789.28
70.05% 2,316.86 38,923.25 79.49% 2,629.16 44169.89 20.51% 678.45
84.81% ### 55,881.16 90.18% 63,213.12 59420.34 9.82% 6,886.01

0.00% - - 0.00% 0.00 0.00 100.00% 16,563.46


0.00% - - 0.00% 0.00 0.00 100.00% 27,905.22
0.00% - - 0.00% 0.00 0.00 100.00% 8,987.84

13.41% 2,004.50 11,145.02 13.41% 2,004.50 11145.02 86.59% 12,942.69


14.90% 6,598.45 8,248.06 14.90% 6,598.45 8248.06 85.10% 37,674.65
79.24% 2,241.66 12,463.63 83.12% 2,351.45 13074.06 16.88% 477.62
83.71% 3,896.79 4,870.99 93.37% 4,346.65 5433.32 6.63% 308.47
63.75% ### 28,595.25 88.13% 15,812.88 39532.20 11.87% 2,130.39

26.64% 49.71 1,930.24 56.76% 105.92 4112.87 43.24% 80.68


63.08% 31.92 854.50 63.08% 31.92 854.50 36.92% 18.68
0.00% - - 0.00% 0.00 0.00 100.00% 5.96
30.06% 0.52 96.78 58.38% 1.01 187.97 41.62% 0.72
66.67% 18.36 6,238.91 66.67% 18.36 6238.91 33.33% 9.18
59.71% 11.47 4,351.14 59.71% 11.47 4351.14 40.29% 7.74
30.96% 352.38 1,709.04 60.45% 688.07 3337.14 39.55% 450.26
31.06% 69.08 3,131.40 61.42% 136.60 6192.08 38.58% 85.80

0.00% - - 0.00% 0.00 0.00 100.00% 11.78


0.00% - - 0.00% 0.00 0.00 100.00% 11.89
0.00% - - 0.00% 0.00 0.00 100.00% 40.71

36.67% 11.00 469.15 36.67% 11.00 469.15 63.33% 19.00

69.05% 54.58 2,119.34 69.05% 54.58 2119.34 30.95% 24.46


67.64% 49.21 9,636.79 67.64% 49.21 9636.79 32.36% 23.54
64.85% 3.80 132.28 64.85% 3.80 132.28 35.15% 2.06
65.80% 18.82 853.11 65.80% 18.82 853.11 34.20% 9.78
0.00% - - 0.00% 0.00 0.00 100.00% 31.77

0.00% - - 0.00% 0.00 0.00 100.00% 28.00


0.00% - - 0.00% 0.00 0.00 100.00% 10.00
0.00% - - 0.00% 0.00 0.00 100.00% 5.00
0.00% - - 0.00% 0.00 0.00 100.00% 20.00
0.00% - - 0.00% 0.00 0.00 100.00% 137.50

0.00% - - 38.46% 10.00 4717.10 61.54% 16.00


0.00% - - 0.00% 0.00 0.00 100.00% 0.25
0.00% - - 0.00% 0.00 0.00 100.00% 1.78
0.00% - - 0.00% 0.00 0.00 100.00% 56,885.18
0.00% - - 0.00% 0.00 0.00 100.00% 3.42

S/. 489,637.12 S/. 677,008.52 S/. 747,235.25


S/. 24,481.86 S/. 33,850.43 S/. 37,361.76
S/. 39,170.97 S/. 54,160.68 S/. 59,778.82
S/. 29,378.23 S/. 40,620.51 S/. 44,834.12
S/. 582,668.18 S/. 805,640.14 S/. 889,209.95

34.4% 47.5% 52.5%

PRESUPUESTO BASE :
PRESUPUESTO CONTRATADO :

PLAZO EJECUCION : 90 DIAS

AVANCE ACTUAL ACUMULADO TOTAL SALDO


% CANT. P. TOTAL % CANT. P. TOTAL % CANT.

10.00% 0.10 4,982.19 85.00% 0.85 42348.64 15.00% 0.15


10.00% 0.10 1,926.09 100.00% 1.00 19260.92 0.00% -
0.00% - - 100.00% 5.76 9360.06 0.00% -

6.64% 2,909.05 15,010.70 100.00% 43,810.78 226063.63 0.00% -


10.88% 754.04 8,746.86 100.00% 6,930.43 80392.98 0.00% -
12.85% 789.28 15,627.74 100.00% 6,143.97 121650.60 0.00% -
20.51% 678.45 11,397.96 100.00% 3,307.61 55567.85 0.00% -

9.82% 6,886.01 6,472.85 100.00% 70,099.13 65893.18 0.00% -

71.74% ### ### 71.74% 11,881.86 270549.95 28.26% 4,681.60


80.43% ### 13,017.20 80.43% 22,443.45 13017.20 19.57% 5,461.77
98.64% 8,865.76 8,333.81 98.64% 8,865.76 8333.81 1.36% 122.08

80.20% ### 66,650.94 93.61% 13,992.08 77795.96 6.39% 955.11


79.60% ### 44,050.23 94.50% 41,838.63 52298.29 5.50% 2,434.47
16.88% 477.62 2,655.57 100.00% 2,829.07 15729.63 0.00% -
6.63% 308.47 385.59 100.00% 4,655.12 5818.90 0.00% -
11.87% 2,130.39 5,325.98 100.00% 17,943.27 44858.18 0.00% -

43.24% 80.68 3,132.80 100.00% 186.60 7245.67 0.00% -


36.92% 18.68 500.06 100.00% 50.60 1354.56 0.00% -
100.00% 5.96 1,074.47 100.00% 5.96 1074.47 0.00% -
41.62% 0.72 134.00 100.00% 1.73 321.97 0.00% -
33.33% 9.18 3,119.46 100.00% 27.54 9358.37 0.00% -
40.29% 7.74 2,936.17 100.00% 19.21 7287.31 0.00% -
39.55% 450.26 2,183.76 100.00% 1,138.33 5520.90 0.00% -
38.58% 85.80 3,889.31 100.00% 222.40 10081.39 0.00% -

100.00% 11.78 596.77 100.00% 11.78 596.77 0.00% -


100.00% 11.89 4,040.34 100.00% 11.89 4040.34 0.00% -
100.00% 40.71 1,845.38 100.00% 40.71 1845.38 0.00% -

63.33% 19.00 810.35 100.00% 30.00 1279.50 0.00% -

30.95% 24.46 949.78 100.00% 79.04 3069.12 0.00% -


32.36% 23.54 4,609.84 100.00% 72.75 14246.63 0.00% -
35.15% 2.06 71.71 100.00% 5.86 203.99 0.00% -
34.20% 9.78 443.33 100.00% 28.60 1296.44 0.00% -
0.00% - - 0.00% 0.00 0.00 100.00% 31.77

0.00% - - 0.00% 0.00 0.00 100.00% 28.00


0.00% - - 0.00% 0.00 0.00 100.00% 10.00
0.00% - - 0.00% 0.00 0.00 100.00% 5.00
0.00% - - 0.00% 0.00 0.00 100.00% 20.00
100.00% 137.50 2,044.63 100.00% 137.50 2044.63 0.00% -

61.54% 16.00 7,547.36 100.00% 26.00 12264.46 0.00% -

0.00% - - 0.00% 0.00 0.00 100.00% 0.25


0.00% - - 0.00% 0.00 0.00 100.00% 1.78
0.00% - - 0.00% 0.00 0.00 100.00% 56,885.18
100.00% 3.42 4,104.00 100.00% 3.42 4104.00 0.00% -

S/. 519,167.18 S/. 1,196,175.68 S/. 228,068.09


S/. 25,958.36 S/. 59,808.78 S/. 11,403.40
S/. 41,533.37 S/. 95,694.05 S/. 18,245.45
S/. 31,150.03 S/. 71,770.54 S/. 13,684.09
S/. 617,808.94 S/. 1,423,449.05 S/. 271,401.03
36.5% 84.0% 16.0%

PRESUPUESTO BASE :
PRESUPUESTO CONTRATADO :

PLAZO EJECUCION : 90 DIAS

AVANCE ACTUAL ACUMULADO TOTAL SALDO


% CANT. P. TOTAL % CANT. P. TOTAL % CANT.

15.00% 0.15 7,473.29 100.00% 1.00 49821.93 0.00% -


0.00% - - 100.00% 1.00 19260.92 0.00% -
0.00% - - 100.00% 5.76 9360.06 0.00% -

0.00% - - 100.00% 43,810.78 226063.62 0.00% -


0.00% - - 100.00% 6,930.43 80392.99 0.00% -
0.00% - - 100.00% 6,143.97 121650.61 0.00% -
0.00% - - 100.00% 3,307.61 55567.85 0.00% -

0.00% - - 100.00% 70,099.13 65893.18 0.00% -

28.26% 4,681.60 ### 100.00% 16,563.46 377149.98 0.00% -


19.57% 5,461.77 3,167.83 100.00% 27,905.22 16185.03 0.00% -
1.36% 122.08 114.76 100.00% 8,987.84 8448.57 0.00% -

6.39% 955.11 5,310.42 100.00% 14,947.19 83106.38 0.00% -


5.50% 2,434.47 3,043.09 100.00% 44,273.10 55341.38 0.00% -
0.00% - - 100.00% 2,829.07 15729.63 0.00% -
0.00% - - 100.00% 4,655.12 5818.90 0.00% -
0.00% - - 100.00% 17,943.27 44858.18 0.00% -

0.00% - - 100.00% 186.60 7245.68 0.00% -


0.00% - - 100.00% 50.60 1354.56 0.00% -
0.00% - - 100.00% 5.96 1074.47 0.00% -
0.00% - - 100.00% 1.73 321.97 0.00% -
0.00% - - 100.00% 27.54 9358.37 0.00% -
0.00% - - 100.00% 19.21 7287.31 0.00% -
0.00% - - 100.00% 1,138.33 5520.90 0.00% -
0.00% - - 100.00% 222.40 10081.39 0.00% -

0.00% - - 100.00% 11.78 596.77 0.00% -


0.00% - - 100.00% 11.89 4040.34 0.00% -
0.00% - - 100.00% 40.71 1845.38 0.00% -

0.00% - - 100.00% 30.00 1279.50 0.00% -

0.00% - - 100.00% 79.04 3069.12 0.00% -


0.00% - - 100.00% 72.75 14246.63 0.00% -
0.00% - - 100.00% 5.86 203.99 0.00% -
0.00% - - 100.00% 28.60 1296.44 0.00% -
100.00% 31.77 613.16 100.00% 31.77 613.16 0.00% -

100.00% 28.00 10,928.12 100.00% 28.00 10928.12 0.00% -


100.00% 10.00 14,004.40 100.00% 10.00 14004.40 0.00% -
100.00% 5.00 2,292.50 100.00% 5.00 2292.50 0.00% -
100.00% 20.00 2,097.20 100.00% 20.00 2097.20 0.00% -
0.00% - - 100.00% 137.50 2044.63 0.00% -

0.00% - - 100.00% 26.00 12264.46 0.00% -

100.00% 0.25 2,148.86 100.00% 0.25 2148.86 0.00% -


100.00% 1.78 13,389.23 100.00% 1.78 13389.23 0.00% -
100.00% ### 56,885.18 100.00% 56,885.18 56885.18 0.00% -
0.00% - - 100.00% 3.42 4104.00 0.00% -

S/. 228,068.07 S/. 1,424,243.77 S/. 0.00


S/. 11,403.40 S/. 71,212.19 S/. 0.00
S/. 18,245.45 S/. 113,939.50 S/. 0.00
S/. 13,684.08 S/. 85,454.63 S/. 0.00
S/. 271,401.00 S/. 1,694,850.09 S/. 0.00

16.0% 100.0% 0.0%


90 DIAS

SALDO
P. TOTAL

24,910.96
4,815.23
-

189,697.44
53,836.99
78,493.34
50,321.21
62,354.00

377,149.98
16,185.03
8,448.57

83,106.38
55,341.38
15,119.20
5,256.57
33,921.23

5,063.05
1,354.56
1,074.47
230.78
9,358.37 0.00 #DIV/0!
7,287.31
3,892.80
7,020.71

596.77
4,040.34
1,845.38

1,279.50
3,069.12
14,246.63
203.99
1,296.44
613.16

10,928.12
14,004.40
2,292.50
2,097.20
2,044.63

7,547.36
2,148.86
13,389.23
56,885.18
4,104.00

S/. 1,236,872.37
S/. 61,843.62
S/. 98,949.79
S/. 74,212.34
S/. 1,471,878.12

86.8%

90 DIAS

SALDO
P. TOTAL

12,455.48
1,926.09
-

15,010.70
8,746.86
15,627.75
11,397.96
6,472.84

377,149.98
16,185.03
8,448.57

71,961.36
47,093.32
2,655.57
385.58
5,325.98

3,132.81
500.06
1,074.47
134.00
3,119.46
2,936.17
2,183.76
3,889.31

596.77
4,040.34
1,845.38

810.35

949.78
4,609.84
71.71
443.33
613.16

10,928.12
14,004.40
2,292.50
2,097.20
2,044.63

7,547.36
2,148.86
13,389.23
56,885.18
4,104.00

S/. 747,235.25
S/. 37,361.76
S/. 59,778.82
S/. 44,834.12
S/. 889,209.95

52.5%

90 DIAS

SALDO
P. TOTAL

7,473.29
-
-

-0.01
0.01
0.01
-

106,600.03
3,167.83
114.76

5,310.42
3,043.09
-
-
-

0.01
-
-
-
-
-
-
-

-
-
-

-
-
-
-
613.16

10,928.12
14,004.40
2,292.50
2,097.20
-

2,148.86
13,389.23
56,885.18
-

S/. 228,068.09
S/. 11,403.40
S/. 18,245.45
S/. 13,684.09
S/. 271,401.03
16.0%

90 DIAS

SALDO
P. TOTAL

-
-
-

-
-
-
-

-
-
-

-
-
-
-
-

-
-
-
-
-
-
-
-

-
-
-

-
-
-
-
-

-
-
-
-
-

-
-
-
-

S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00

0.0%
0.00%
CALCULO DEL COEFICIENTE DE REAJUSTE "K1"

OBRA : REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208 KM)


FECHA DEL PRESUPUESTO : Nov-18
AREA GEOGRAFICA N° 06

COEF. Io (Nov.
%
2018)
Ir (Mar. 2019)
SIMB. IU INC.
1 2 3 4 5=1x2x4/3
M 47 0.126 100.00% 602.11 600.40 0.126
CMA 3 0.061 11.48% 539.69 530.00 0.007
21 73.77% 416.28 418.57 0.045
43 14.75% 889.68 893.85 0.009
MM 48 0.609 7.06% 371.13 368.51 0.043
49 92.94% 311.07 308.64 0.562
I 39 0.204 100.00% 451.18 456.16 0.206

0.998

K = 0.126 (Mr/Mo) + 0.061 (CMAr/CMAo) + 0.609 (MMr/MMo) + 0.204 (Ir/Io)

CALCULO DEL COEFICIENTE DE REAJUSTE "K2"

OBRA : 0
FECHA DEL PRESUPUESTO : Nov-18
AREA GEOGRAFICA N° 06

COEF. Io (Nov.
%
2018)
Ir (Abr. 2019)
SIMB. IU INC.
1 2 3 4 5=1x2x4/3
M 47 0.126 100.00% 602.11 600.40 0.126
CMA 3 0.061 11.48% 539.69 529.91 0.007
21 73.77% 416.28 420.47 0.045
43 14.75% 889.68 897.58 0.009
MM 48 0.609 7.06% 371.13 369.76 0.043
49 92.94% 311.07 309.08 0.562
I 39 0.204 100.00% 451.18 457.08 0.207

0.999

K = 0.126 (Mr/Mo) + 0.061 (CMAr/CMAo) + 0.609 (MMr/MMo) + 0.204 (Ir/Io)

CALCULO DEL COEFICIENTE DE REAJUSTE "K3"

OBRA : 0
FECHA DEL PRESUPUESTO : Nov-18
AREA GEOGRAFICA N° 06

COEF. Io (Nov.
%
2018)
Ir (May. 2019)
SIMB. IU INC.
1 2 3 4 5=1x2x4/3
M 47 0.126 100.00% 602.11 600.40 0.126
CMA 3 0.061 11.48% 539.69 534.40 0.007
21 73.77% 416.28 418.76 0.045
43 14.75% 889.68 902.26 0.009
MM 48 0.609 7.06% 371.13 371.16 0.043
49 92.94% 311.07 312.35 0.568
I 39 0.204 100.00% 451.18 457.75 0.207

1.005

K = 0.126 (Mr/Mo) + 0.061 (CMAr/CMAo) + 0.609 (MMr/MMo) + 0.204 (Ir/Io)

CALCULO DEL COEFICIENTE DE REAJUSTE "K4"

OBRA : 0
FECHA DEL PRESUPUESTO : Nov-18
AREA GEOGRAFICA N° 06

COEF. Io (Nov.
%
2018)
Ir (Jun. 2019)
SIMB. IU INC.
1 2 3 4 5=1x2x4/3
M 47 0.126 100.00% 602.11 600.40 0.126
CMA 3 0.061 11.48% 539.69 533.28 0.007
21 73.77% 416.28 418.57 0.045
43 14.75% 889.68 903.33 0.009
MM 48 0.609 7.06% 371.13 370.90 0.043
49 92.94% 311.07 311.91 0.568
I 39 0.204 100.00% 451.18 457.36 0.207

1.005

K = 0.126 (Mr/Mo) + 0.061 (CMAr/CMAo) + 0.609 (MMr/MMo) + 0.204 (Ir/Io)

CALCULO DEL COEFICIENTE DE REAJUSTE "Ka"

OBRA : 0
FECHA DEL PRESUPUESTO : Nov-18
AREA GEOGRAFICA N° 06

COEF. Io (Nov.
%
2018)
Ir (Feb. 2019)
SIMB. IU INC.
SIMB. IU
1 2 3 4 5=1x2x4/3
M 47 0.126 100.00% 602.11 600.40 0.126
CMA 3 0.061 11.48% 539.69 536.72 0.007
21 73.77% 416.28 418.57 0.045
43 14.75% 889.68 893.78 0.009
MM 48 0.609 7.06% 371.13 370.25 0.043
49 92.94% 311.07 309.14 0.562
I 39 0.204 100.00% 451.18 452.87 0.205

0.997

K = 0.126 (Mr/Mo) + 0.061 (CMAr/CMAo) + 0.609 (MMr/MMo) + 0.204 (Ir/Io)

Resumen
K1 0.998
K2 0.999
K3 1.005
K4 1.005
Ka 0.997
CRONOGRAMA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
Obra REHABILITACION DEL CAMINO VECINAL: XXXXXXXXXXXXXXXXXXXX L= 19.208KM
Cliente
Lugar Costo al 11/30/2018

Feb-19 Mar-19 Apr-19 May-19


Nº PARTIDA NOMBRE DE PARTIDAS UND. METRADO PRECIO PARCIAL 11 - 28 01 - 31 01 - 30 01 - 11
18 días 31 días 30 días 11 días

01 OBRAS PRELIMINARES 78,442.91 31,798.68 15,717.78 3,482.00 27,444.45


01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 49,821.93 49,821.93 18,390.96 6,520.00 - 24,910.97
01.02 TOPOGRAFIA Y GEOREFERENCIACION GLB 1.00 19,260.92 19,260.92 7,667.16 5,578.28 3,482.00 2,533.48
01.03 DESBROCE Y LIMPIEZA ha 5.76 1,625.01 9,360.06 5,740.56 3,619.50 - -
02 MOVIMIENTO DE TIERRAS 549,568.25 70,388.12 479,180.13 - -
02.01 CORTE EN MATERIAL SUELTO m3 43,810.78 5.16 226,063.62 31,663.09 194,400.53 - -
02.02 CORTE EN ROCA SUELTA m3 6,930.43 11.60 80,392.99 15,408.66 64,984.33 - -
02.03 CORTE EN ROCA FIJA m3 6,143.97 19.80 121,650.61 23,316.37 98,334.24 - -
02.04 RELLENO CON MATERIAL DE PRESTAMO m3 3,307.61 16.80 55,567.85 55,567.85 - -
02.05 PERFILADO Y COMPACTACION SUB-RASANTE EN ZONAS DE CORTE m2 70,099.13 0.94 65,893.18 65,893.18 - -
03 PAVIMENTOS 401,783.58 - 94,406.35 307,377.23 -
03.01 AFIRMADO m3 16,563.46 22.77 377,149.98 - 69,772.75 307,377.23 -
03.02 ESCARIFICADO DE AFIRMADO EXISTENTE m2 27,905.22 0.58 16,185.03 - 16,185.03 - -
03.03 PERFILADO Y COMPACTACION DE AFIRMADO EXISTENTE m2 8,987.84 0.94 8,448.57 - 8,448.57 - -
04 TRANSPORTE 204,854.47 - 93,433.27 111,421.20 -
04.01 TRANSPORTE DE MATERIAL AFIRMADO D<1 KM m3-km 14,947.19 5.56 83,106.38 - 19,378.15 63,728.23 -
04.02 TRANSPORTE DE MATERIAL AFIRMADO D>1 KM m3-km 44,273.10 1.25 55,341.38 - 13,237.06 42,104.32 -
04.03 TRANSPORTE DE MATERIAL DE PRESTAMO D<1 KM m3-km 2,829.07 5.56 15,729.63 - 15,729.63 - -
04.04 TRANSPORTE DE MATERIAL DE PRESTAMO D>1 KM m3-km 4,655.12 1.25 5,818.90 - 5,818.90 - -
04.05 TRANSPORTE DE MATERIAL EXCEDENTE D<1 KM m3-km 17,943.27 2.50 44,858.18 - 39,269.53 5,588.65 -
05 OBRAS DE ARTE Y DRENAJE 69,435.98 48,275.62 3,577.10 17,583.26 -
05.01 ALCANTARILLAS TIPO MARCO DE 1.00 x 1.00 M 42,244.65 41,793.13 451.52 - -
05.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO m3 186.60 38.83 7,245.68 7,245.68 - - -
05.01.02 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO m3 50.60 26.77 1,354.56 903.04 451.52 - -
05.01.03 EMBOQUILADO DE PIEDRA m3 5.96 180.28 1,074.47 1,074.47 - - -
05.01.04 CONCRETO F'C=100 KG/CM2 m3 1.73 186.11 321.97 321.97 - - -
05.01.05 CONCRETO F'C=175 KG/CM2 m3 27.54 339.81 9,358.37 9,358.37 - - -
05.01.06 CONCRETO F'C=210 KG/CM2 m3 19.21 379.35 7,287.31 7,287.31 - - -
05.01.07 ACERO DE REFUERZO FY= 4200 KG/CM2 kg 1,138.33 4.85 5,520.90 5,520.90 - - -
05.01.08 ENCOFRADO Y DESENCOFRADO m2 222.40 45.33 10,081.39 10,081.39 - - -
05.02 REPOSICION DE CABEZALES DE ALCANTARILLA 6,482.49 6,482.49 - - -
05.02.01 DEMOLICION DE ESTRUCTURAS m3 11.78 50.66 596.77 596.77 - - -
05.02.02 CONCRETO F'C=175 KG/CM2 m3 11.89 339.81 4,040.34 4,040.34 - - -
05.02.03 ENCOFRADO Y DESENCOFRADO m2 40.71 45.33 1,845.38 1,845.38 - - -
05.03 LIMPIEZA DE ALCANTARILLAS 1,279.50 - 1,279.50 - -
CRONOGRAMA VALORIZADO ACTUALIZADO A LA FECHA DE INICIO DE OBRA
Obra REHABILITACION DEL CAMINO VECINAL: XXXXXXXXXXXXXXXXXXXX L= 19.208KM
Cliente
Lugar Costo al 11/30/2018

Feb-19 Mar-19 Apr-19 May-19


Nº PARTIDA NOMBRE DE PARTIDAS UND. METRADO PRECIO PARCIAL 11 - 28 01 - 31 01 - 30 01 - 11
18 días 31 días 30 días 11 días

05.03.01 LIMPIEZA DE ALCANTARILLAS und 30.00 42.65 1,279.50 - 1,279.50 - -


05.04 BADENES 19,429.34 - 1,846.08 17,583.26 -
05.04.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL SUELTO m3 79.04 38.83 3,069.12 - 1,846.08 1,223.04 -
05.04.02 CONCRETO CICLOPEO F'C=175 KG/CM2 + 30% P.M. m3 72.75 195.83 14,246.63 - - 14,246.63 -
05.04.03 AFIRMADO PARA BADEN m3 5.86 34.81 203.99 - - 203.99 -
05.04.04 ENCOFRADO Y DESENCOFRADO m2 28.60 45.33 1,296.44 - - 1,296.44 -
05.04.05 JUNTAS ASFALTICAS m 31.77 19.30 613.16 - - 613.16 -
06 SEÑALIZACION 31,366.85 - - 17,911.23 13,455.62
06.01 SEÑAL PREVENTIVA und 28.00 390.29 10,928.12 - - 6,285.41 4,642.71
06.02 SEÑAL INFORMATIVA und 10.00 1,400.44 14,004.40 - - 7,336.27 6,668.13
06.03 SEÑAL REGLAMENTARIA und 5.00 458.50 2,292.50 - - 1,528.33 764.17
06.04 HITOS KILOMETRICOS und 20.00 104.86 2,097.20 - - 1,398.13 699.07
06.05 PINTADO DE BARANDAS METALICAS EN PUENTES m 137.50 14.87 2,044.63 - - 1,363.09 681.54
07 PROTECCION AMBIENTAL 88,791.73 - - 29,396.44 59,395.29
07.01 SEÑALIZACION AMBIENTAL und 26.00 471.71 12,264.46 - - 12,264.46 -
07.02 RESTAURACION DE AREA DE CAMPAMENTOS Y PATIO DE MAQUINAS ha 0.25 8,595.43 2,148.86 - - 537.22 1,611.64

07.03 RESTAURACION DE CANTERAS ha 1.78 7,522.04 13,389.23 - - 3,347.31 10,041.92


07.04 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN EL DME m3 56,885.18 1.00 56,885.18 - - 12,221.30 44,663.88
07.05 REVEGETACION ha 3.42 1,200.00 4,104.00 - - 1,026.15 3,077.85

COSTO DIRECTO 1,424,243.77 150,462.42 686,314.63 487,171.36 100,295.36


GASTOS GENERALES FIJOS 5.00% 71,212.19 7,523.12 34,315.73 24,358.57 5,014.77
GASTOS GENERALES VARIABLES 8.00% 113,939.50 12,036.99 54,905.17 38,973.71 8,023.63
UTILIDADES 6.00% 85,454.63 9,027.75 41,178.88 29,230.28 6,017.72
SUB TOTAL 1,694,850.09 179,050.28 816,714.41 579,733.92 119,351.48
I.G.V. 18.00% 305,073.02 32,229.05 147,008.59 104,352.11 21,483.27
TOTAL 1,999,923.11 211,279.33 963,723.00 684,086.03 140,834.75

PORCENTAJE DE AVANCE PARCIAL 10.56% 48.19% 34.21% 7.04%

PORCENTAJE DE AVANCE ACUMULADO 10.56% 58.75% 92.96% 100.00%


RECALCULO DE REINTEGROS DEL MES
( Con los K del mes posterior a la Valorización)

OBRA: REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208 KM)


FECHA DEL PRESUPUESTO BASE Nov-18
AREA GEOGRAFICA 06
INSPECTOR
CONTRATISTA
UBICACIÓN XXXX
VALOR REFERENCIAL S/. 2,222,136.77 (CON IGV) S/. 1,883,166.75 (SIN IGV)
PRESUPUESTO CONTRATADO S/. 1,999,923.11 (CON IGV) S/. 1,694,850.09 (SIN IGV)

FORMULA UNICA

Val. Programada Val. Ejecutada Reint. Programada Reint. Ejecutada Reint. Autorizado
Val. Nº Fecha K-1

Mes Acumulado Mes Acumulado Mes Acumulado Mes Acumulado Mes Acumulado

1 Feb-19 179,050.28 179,050.28 222,971.96 222,971.96 -0.002 -358.10 -358.10 -445.94 -445.94 -445.94 -445.94

2 Mar-19 816,714.41 995,764.69 582,668.18 805,640.14 -0.001 -816.71 -1,174.81 -582.67 -1,028.61 -728.87 -1,174.81

3 Apr-19 579,733.92 1,575,498.61 617,808.94 1,423,449.08 0.005 2,898.67 1,723.86 3,089.04 2,060.43 2,898.67 1,723.86

4 May-19 119,351.48 1,694,850.09 271,401.00 1,694,850.08 0.005 596.76 2,320.62 1,357.00 3,417.43 596.76 2,320.62
SOLICITUD POR ADELANTO DE MATERIALES

OBRA: REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxx


FECHA DEL PRESUPUESTO BASE Nov-18
AREA GEOGRAFICA 06
INSPECTOR
CONTRATISTA
UBICACIÓN XXXX
VALOR REFERENCIAL S/. 2,222,136.77 (CON IGV)
PRESUPUESTO CONTRATADO S/. 1,999,923.11 (CON IGV)

PLAZO EJECUCIÓN 90 DIAS CALENDARIOS


FECHA DE INICIO 11-feb-19
FECHA DE TÉRMINO 11-may-19
ADELANTOS SOLICITADOS:
- ACERO
- CEMENTO
- MADERA
FECHA DE ADELANTOS 27-feb-19

D.S. No. 017-79-VC Mmax = Monto Maximo de Adelanto d


ci = coeficiente de incidencia del mat
Mmax = c.i. x SBV x (Ima/Imo) SBV = Saldo Bruto por Valorizar
Ima = Indice del material al mes del a
Imo = Indice del material al mes del P

Se solicita Adelanto SBV c.i. Ima Imo


S/. material Ene.2019 Nov.2018
Material I.U.
a b c d

Acero de Refuerzo 03 S/. 1,694,850.09 0.007 537.43 539.69


Cemento Portland 21 S/. 1,694,850.09 0.045 418.38 416.28
Madera 43 S/. 1,694,850.09 0.009 892.60 889.68
RIALES

INO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208 KM)

S/. 1,883,166.75 (SIN IGV)


S/. 1,694,850.09 (SIN IGV)

max = Monto Maximo de Adelanto de Materiales


= coeficiente de incidencia del material
V = Saldo Bruto por Valorizar
a = Indice del material al mes del adelanto
o = Indice del material al mes del P.B.

Monto
Mmax Monto Otorgado
Solicitado

e = a x b x c/d

11,814.00 15,000.00 11,814.00


76,653.00 80,000.00 76,653.00
15,304.00 20,000.00 15,304.00
SUMATORIA: S/. 103,771.00
CALCULO DE LA DEDUCCION DEL REAJUSTE QUE NO CORRESPONDEN POR EL
ADELANTO DIRECTO

OBRA: REHABILITACION DEL CAMINO VECINAL: XXXXXXXXXXXXXXXXXXXX


L= 19.208KM
FECHA DEL PRESUPUESTO BASE Nov-18
AREA GEOGRAFICA 06
INSPECTOR
CONTRATISTA

UBICACIÓN
VALOR REFERENCIAL S/. 2,222,136.77 (CON IGV)
VALOR REFERENCIAL (SIN IGV) S/. 1,883,166.75 (SIN IGV)
PRESUPUESTO CONTRATADO S/. 1,999,923.11 (CON IGV)
PRESUPUESTO CONTRATADO (SIN IGV) S/. 1,694,850.09 (SIN IGV)

Adelanto en Efectivo (A) S/. 169,485.00 Sin IGV


Monto del Contrato (C) S/. 1,694,850.09 Sin IGV

K Formula Unica K = 0.126 (Mr/Mo) + 0.061 (CMAr/CMAo) + 0.609 (MMr/MMo) + 0.204 (Ir/Io)

Coeficientes del mes del

Pago del Adelanto en Deducción (De)


Mes Monto Reajuste
Efectivo (FEB. 2019)

V (formulas) K Ka De =V*(A/C)*( K / Ka - 1)

Valorización 01
Formula Unica 222,971.96 0.998 0.997 22.36
Valorización 02
Formula Unica 582,668.18 0.999 0.997 116.88
Valorización 03
Formula Unica 617,808.94 1.005 0.997 495.73
Valorización 04
Formula Unica 271,401.00 1.005 0.997 217.77

TOTALES 852.74
AMORTIZACIÓN DEL ADELANTO DIRECTO

OBRA REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208 KM)


PROPIETARIO
DEPARTAMENTO

PRESUP. CONTRATO.: S/1,999,923.11

VAL.MES Sin ADELANTO OTORGADO


DESCRIPCION
Reaj.
SIN I.G.V. CON I.G.V.

ADELANTO 169,485.00 199,992.30


10.00% 10.00%

VALORIZACIÓN N° 01 febrero-19 222,971.96


VALORIZACIÓN N° 02 marzo-19 582,668.18
VALORIZACIÓN N° 03 abril-19 617,808.94
VALORIZACIÓN N° 04 mayo-19 271,401.00

TOTAL A LA FECHA

Consumo de Materiales
Febrero Marzo
Acero de Refuerzo S/. 8,000.00 S/. 3,500.00
Cemento Portland S/. 55,000.00 S/. 10,000.00
Madera S/. 9,500.00 S/. 4,000.00

AMORTIZACIÓN DEL ADELANTO DE MATERIALES

OBRA REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208 KM)


PROPIETARIO
DEPARTAMENTO

PRESUP. CONTRATO.: S/1,999,923.11

FORMULA UNICA
Material : ACERO DE CONSTRUCCION CORRUGADO IU = 03
Material
Valorización Ima Imo
Utilizado
S/. Feb.2019 Nov.2018
No. Mes
a b c

1 febrero-19 S/. 8,000.00 536.72 539.69


2 marzo-19 S/. 3,500.00 536.72 539.69
3 abril-19 S/. 500.00 536.72 539.69
4 mayo-19 536.72 539.69

FORMULA UNICA
Material : CEMENTO PORTLAND TIPO I IU = 21
Material
Valorización Ima Imo
Utilizado
S/. Feb.2019 Nov.2018
No. Mes
a b c

1 febrero-19 S/. 55,000.00 418.57 416.28


2 marzo-19 S/. 10,000.00 418.57 416.28
3 abril-19 S/. 8,000.00 418.57 416.28
4 mayo-19 S/. 5,000.00 418.57 416.28

FORMULA UNICA
Material : MADERA NACIONAL PARA ENCOF. Y CARPINT. IU = 43
Material
Valorización Ima Imo
Utilizado
S/. Feb.2019 Nov.2018
No. Mes
a b c

1 febrero-19 S/. 9,500.00 893.78 889.68


2 marzo-19 S/. 4,000.00 893.78 889.68
3 abril-19 S/. 1,500.00 893.78 889.68
4 mayo-19 S/. 500.00 893.78 889.68
IRECTO

xx (L= 19.208 KM)

AMORTIZACION
AMORTIZACION SALDO POR AMORTIZ.
Amort=VB * 10.00% (SIN I.G.V)

22,297.19 147,187.81
58,266.81 88,921.00
61,780.89 27,140.11
27,140.11 -

169,485.00 0.00

Abril Mayo
S/. 500.00 S/. -
S/. 8,000.00 S/. 5,000.00
S/. 1,500.00 S/. 500.00

ATERIALES

xx (L= 19.208 KM)


Mat Util *Ima/Imo Saldo x Amortizar Amortizacion

d=axb/c

7956 11,814.00 7956


3481 3,858.00 3481
497 377.00 377.00
0 0.00

SUMATORIA: S/. 11814.00

Mat Util *Ima/Imo Saldo x Amortizar Amortizacion

d=axb/c

55,303.00 76,653.00 55,303.00


10,055.00 21,350.00 10,055.00
8,044.00 11,295.00 8,044.00
5,028.00 3,251.00 3,251.00
0.00
SUMATORIA: S/. 76653.00

Mat Util *Ima/Imo Saldo x Amortizar Amortizacion

d=axb/c

9,544.00 15,304.00 9,544.00


4,018.00 5,760.00 4,018.00
1,507.00 1,742.00 1,507.00
502.00 235.00 235.00
0.00
SUMATORIA: S/. 15,304.00
CALCULO DE LA DEDUCCION DEL REAJUSTE QUE NO CORRESPONDEN POR EL ADELANTO DE MATERIALES
OBRA: REHABILITACION DEL CAMINO VECINAL: XXXXXXXXXXXXXXXXXXXX L= 19.208KM
FECHA DEL PRESUPUESTO BASE Nov-18
AREA GEOGRAFICA 06
INSPECTOR
CONTRATISTA

UBICACIÓN
VALOR REFERENCIAL S/. 2,222,136.77 (CON IGV) S/. 1,883,166.75 (SIN IGV)
PRESUPUESTO CONTRATADO S/. 1,999,923.11 (CON IGV) S/. 1,694,850.09 (SIN IGV)

D.S. No. 017-79-VC


D =Mu x [(Imr - Ima)/Imo] , donde: D = Deducción de reintegro que no corresponde
Mu = ci x V ci = coeficiente de incidencia del material del adelanto
V = valorización recalculada del mes
Imr = Indice del material al mes de reajuste (Julio - Septiembre 2012)
Ima = Indice del material al mes del adelanto (Junio 2012)
Imo = Indice del material al mes del P.B. (Agosto 2011)
FORMULA UNICA
Material : ACERO DE CONSTRUCCION CORRUGADO IU = 03
Valorización Monto Valoriz. c.i. Monto Otorg. Ima Imo Adelanto Deflactado Monto utilizado
Imr Mu = c.i. x V para la Deducción
S/. material (SIN IGV) Feb.2019 Nov.2018 Adel. Otorg. x Imo / Ima deducción
No. Mes
a b c d e f g=cxf/e h=axb j k = j x (d - e)/f

1 febrero-19 222,971.96 0.007 11,814.00 530.000 536.72 539.69 11,879.37 1,560.80 1,560.80 -19.43
2 marzo-19 582,668.18 0.007 11,814.00 529.910 536.72 539.69 11,879.37 4,078.68 4,078.68 -51.47
3 abril-19 617,808.94 0.007 11,814.00 534.400 536.72 539.69 11,879.37 4,324.66 4,324.66 -18.59
4 mayo-19 271,401.00 0.007 11,814.00 533.280 536.72 539.69 11,879.37 1,899.81 1,915.23 -12.21

SUMATORIA: S/. 11,863.95 11,879.37 -101.70

Material : CEMENTO PORTLAND TIPO I IU = 21


Valorización Monto Valoriz. c.i. Monto Otorg. Ima Imo Adelanto Deflactado Monto utilizado
Imr Mu = c.i. x V para la Deducción
S/. material (SIN IGV) Feb.2019 Nov.2018 Adel. Otorg. x Imo / Ima deducción
No. Mes
a b c d e f g=cxf/e h=axb j k = j x (d - e)/f

1 febrero-19 222,971.96 0.045 76,653.00 418.570 418.57 416.28 76,233.63 10,033.74 10,033.74 0.00
2 marzo-19 582,668.18 0.045 76,653.00 420.470 418.57 416.28 76,233.63 26,220.07 26,220.07 119.67
3 abril-19 617,808.94 0.045 76,653.00 418.760 418.57 416.28 76,233.63 27,801.40 27,801.40 12.69
4 mayo-19 271,401.00 0.045 76,653.00 418.570 418.57 416.28 76,233.63 12,213.05 12,178.42 0.00

SUMATORIA: S/. 76,268.26 76,233.63 132.36

Material : MADERA NACIONAL PARA ENCOF. Y CARPINT. IU = 43


Valorización Monto Valoriz. c.i. Monto Otorg. Ima Imo Adelanto Deflactado Monto utilizado
Imr Mu = c.i. x V para la Deducción
S/. material (SIN IGV) Feb.2019 Nov.2018 Adel. Otorg. x Imo / Ima deducción
No. Mes
a b c d e f g=cxf/e h=axb j k = j x (d - e)/f

1 febrero-19 222,971.96 0.009 15,304.00 893.78 889.68 15,233.80 2,006.75 2,006.75 -2016.00
2 marzo-19 0.009 15,304.00 893.78 889.68 15,233.80 0.00 0.00 0.00
3 abril-19 0.009 15,304.00 893.78 889.68 15,233.80 0.00 0.00 0.00
CALCULO DE LA DEDUCCION DEL REAJUSTE QUE NO CORRESPONDEN POR EL ADELANTO DE MATERIALES
OBRA: REHABILITACION DEL CAMINO VECINAL: XXXXXXXXXXXXXXXXXXXX L= 19.208KM
FECHA DEL PRESUPUESTO BASE Nov-18
AREA GEOGRAFICA 06
INSPECTOR
CONTRATISTA

UBICACIÓN
VALOR REFERENCIAL S/. 2,222,136.77 (CON IGV) S/. 1,883,166.75 (SIN IGV)
PRESUPUESTO CONTRATADO S/. 1,999,923.11 (CON IGV) S/. 1,694,850.09 (SIN IGV)

D.S. No. 017-79-VC


D =Mu x [(Imr - Ima)/Imo] , donde: D = Deducción de reintegro que no corresponde
Mu = ci x V ci = coeficiente de incidencia del material del adelanto
V = valorización recalculada del mes
Imr = Indice del material al mes de reajuste (Julio - Septiembre 2012)
Ima = Indice del material al mes del adelanto (Junio 2012)
Imo = Indice del material al mes del P.B. (Agosto 2011)
4 mayo-19 0.009 15,304.00 893.78 889.68 15,233.80 0.00 0.00 0.00

SUMATORIA: S/. 2,006.75 2,006.75 -2016.00

CONTROL DE DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR ADELANTO No. 01 DE MATERIALES

Monto deducido en Valorización No. 02 Mes de Junio 2012 -2,035.43


Monto deducido en Valorización No. 03 Mes de Julio 2012 -5.90
Monto deducido en Valorización No. 04 Mes de Agosto 2012 -12.21

TOTAL DEDUCCION (S/.) -2,053.54


RESUMEN DE VALORIZACIONES RECA

OBRA: REHABILITACION DEL CAMINO VECINAL: xxxxxxxxxxxxxxxxxxxxxxxxxx (L=


FECHA DEL PRESUPUESTO BASE Nov-18
AREA GEOGRAFICA
INSPECTOR
CONTRATISTA
UBICACIÓN XXXX
VALOR REFERENCIAL S/. 2,222,136.77 (CON IGV) S/. 1,883,166.75
PRESUPUESTO CONTRATADO S/. 1,999,923.11 (CON IGV) S/. 1,694,850.09

PLAZO EJECUCIÓN 90 DIAS CALENDARIOS


FECHA DE INICIO 11-feb-19
FECHA DE TÉRMINO 11-may-19

Valorización Reajuste TOTAL Amortizaciones de VALORIZAC.


Monto S/. Concedido REAJUSTADO Adelantos ( D ) NETA
En Efectivo Para Mater. ( VN )
A B C=A+B D1 D2 VN = C - D

1 - -
2 - -
3 - -
4 - -

TOTAL - - - - - -

Adelantos

1
2
ALORIZACIONES RECALCULADAS

xxxxxxxxxxxxxxxxxxxxxxxx (L= 19.208 KM)

/. 1,883,166.75 (SIN IGV)


/. 1,694,850.09 (SIN IGV)

Otras Deducciones ( NETO PAGADO S/. Comprob. de Pago


Fondo de Multa Fecha de
Garantía Efectivo IGV N° Cobranza
FG VN - FG - E

- - -
- - -
- - -
- - -

- - - -

Adelantos NETO PAGADO S/. Comprob. Pago


En Efectivo Materiales Efectivo IGV N° Fecha Cob
-
-
- - - -

Total = S/. - -

También podría gustarte