Asignatura:
PROGRAMACIÓN DE OBRAS
Integrantes:
Pavel Jossue Useda Garcia
Hanssel Jonathan Acosta Icabalceta
Docente:
Ing. Lázaro González Herrera
Fecha De Entrega:
Tiempo de Espera.
Formula a utilizar
𝑎 + 4𝑚 + 𝑏
𝑡𝑒 =
6
1 + 4(5) + 9 2 + 4(3) + 8
𝑡𝑒(𝐴) = =5 𝑡𝑒(𝐵) = =4
6 6
12 + 4(15) + 22 11 + 4(15) + 18
𝑡𝑒(𝐶) = = 16 𝑡𝑒(𝐷) = = 15
6 6
13 + 4(25) + 31 12 + 4(19) + 45
𝑡𝑒(𝐸) = = 24 𝑡𝑒(𝐹) = = 22
6 6
5 + 4(12) + 20 24 + 4(38) + 45
𝑡𝑒(𝐺) = = 12 𝑡𝑒(𝐻) = = 37
6 6
9 + 4(12) + 20 40 + 4(45) + 50
𝑡𝑒(𝐼) = = 13 𝑡𝑒(𝐽) = = 45
6 6
30 + 4(50) + 70 10 + 4(12) + 13
𝑡𝑒(𝐾) = = 50 𝑡𝑒(𝐿) = = 12
6 6
Diagrama de Pert:
Ruta Crítica:
C, H, I, K
Varianza
𝑏−𝑎 2
𝜎2 = ( )
6
2 (𝐴)
9−1 2 8−2 2
𝜎 = ( ) = (1.3)2 𝜎 2 (𝐵)
= ( ) = (1)2
6 6
22 − 12 2 18 − 11 2
𝜎 2 (𝑐) = ( ) = (1.7)2 𝜎 2 (𝐷) = ( ) = (1.2)2
6 6
31 − 13 2 45 − 12 2
𝜎 2 (𝐸) = ( ) = (3)2 𝜎 2 (𝐹) = ( ) = (5.5)2
6 6
2 (𝐺)
20 − 5 2 45 − 24 2
𝜎 = ( ) = (2.5)2 𝜎 2 (𝐻)
= ( ) = (3.5)2
6 6
2 (𝐼)
20 − 9 2 50 − 40 2
𝜎 = ( ) = (1.8)2 𝜎 2 (𝐽)
= ( ) = (1.7)2
6 6
2 (𝐾)
70 − 30 2 13 − 10 2
𝜎 = ( ) = (6.7)2 𝜎 2 (𝐿)
= ( ) = (0.5)2
6 6
Calculo de probabilidad
Actividad A B C D E F G H I J K
to 1 2 12 11 13 12 5 24 9 40 30
tm 5 3 15 15 25 19 12 38 12 45 50
tp 9 8 22 18 31 45 20 45 20 50 70
Tiempo de Espera.
Formula a utilizar
𝑎 + 4𝑚 + 𝑏
𝑡𝑒 =
6
1 + 4(5) + 9 2 + 4(3) + 8
𝑡𝑒(𝐴) = =5 𝑡𝑒(𝐵) = =4
6 6
12 + 4(15) + 22 11 + 4(15) + 18
𝑡𝑒(𝐶) = = 16 𝑡𝑒(𝐷) = = 15
6 6
13 + 4(25) + 31 12 + 4(19) + 45
𝑡𝑒(𝐸) = = 24 𝑡𝑒(𝐹) = = 22
6 6
5 + 4(12) + 20 24 + 4(38) + 45
𝑡𝑒(𝐺) = = 12 𝑡𝑒(𝐻) = = 37
6 6
9 + 4(12) + 20 40 + 4(45) + 50
𝑡𝑒(𝐼) = = 13 𝑡𝑒(𝐽) = = 45
6 6
30 + 4(50) + 70
𝑡𝑒(𝐾) = = 50
6
Diagrama de Pert:
Varianza
2
𝑏−𝑎 2
𝜎 = ( )
6
9−1 2 8−2 2
𝜎 2 (𝐴) = ( ) = (1.3)2 𝜎 2 (𝐵) = ( ) = (1)2
6 6
22 − 12 2 18 − 11 2
𝜎 2 (𝑐) = ( ) = (1.7)2 𝜎 2 (𝐷) = ( ) = (1.2)2
6 6
2 (𝐸)
31 − 13 2 45 − 12 2
𝜎 = ( ) = (3)2 𝜎 2 (𝐹)
= ( ) = (5.5)2
6 6
2 (𝐺)
20 − 5 2 45 − 24 2
𝜎 = ( ) = (2.5)2 𝜎 2 (𝐻)
= ( ) = (3.5)2
6 6
2 (𝐼)
20 − 9 2 50 − 40 2
𝜎 = ( ) = (1.8)2 𝜎 2 (𝐽)
= ( ) = (1.7)2
6 6
2 (𝐾)
70 − 30 2
𝜎 = ( ) = (6.7)2
6
Calculo de probabilidad
Actividad A B C D E F G H I J K L
to 1 2 12 11 13 12 5 24 9 40 30 10
tm 5 3 15 15 25 19 12 38 12 45 50 12
tp 9 8 22 18 31 45 20 45 20 50 70 13
Tiempo de Espera.
Formula a utilizar
𝑎 + 4𝑚 + 𝑏
𝑡𝑒 =
6
1 + 4(5) + 9 2 + 4(3) + 8
𝑡𝑒(𝐴) = =5 𝑡𝑒(𝐵) = =4
6 6
12 + 4(15) + 22 11 + 4(15) + 18
𝑡𝑒(𝐶) = = 16 𝑡𝑒(𝐷) = = 15
6 6
13 + 4(25) + 31 12 + 4(19) + 45
𝑡𝑒(𝐸) = = 24 𝑡𝑒(𝐹) = = 22
6 6
5 + 4(12) + 20 24 + 4(38) + 45
𝑡𝑒(𝐺) = = 12 𝑡𝑒(𝐻) = = 37
6 6
9 + 4(12) + 20 40 + 4(45) + 50
𝑡𝑒(𝐼) = = 13 𝑡𝑒(𝐽) = = 45
6 6
30 + 4(50) + 70 10 + 4(12) + 13
𝑡𝑒(𝐾) = = 50 𝑡𝑒(𝐿) = = 12
6 6
Diagrama de Pert:
Varianza
2
𝑏−𝑎 2
𝜎 = ( )
6
9−1 2 8−2 2
𝜎 2 (𝐴) = ( ) = (1.3)2 𝜎 2 (𝐵) = ( ) = (1)2
6 6
22 − 12 2 18 − 11 2
𝜎 2 (𝑐) = ( ) = (1.7)2 𝜎 2 (𝐷) = ( ) = (1.2)2
6 6
2 (𝐸)
31 − 13 2 45 − 12 2
𝜎 = ( ) = (3)2 𝜎 2 (𝐹)
= ( ) = (5.5)2
6 6
2 (𝐺)
20 − 5 2 45 − 24 2
𝜎 = ( ) = (2.5)2 𝜎 2 (𝐻)
= ( ) = (3.5)2
6 6
2 (𝐼)
20 − 9 2 50 − 40 2
𝜎 = ( ) = (1.8)2 𝜎 2 (𝐽)
= ( ) = (1.7)2
6 6
70 − 30 2 13 − 10 2
𝜎 2 (𝐾) = ( ) = (6.7)2 𝜎 2 (𝐿) = ( ) = (0.5)2
6 6
Calculo de probabilidad
Actividad A B C D E F G H I J K L M N
to 1 2 12 11 13 12 5 24 9 40 30 10 5 6
tm 5 3 15 15 25 19 12 38 12 45 50 12 7 8
tp 9 8 22 18 31 45 20 45 20 50 70 13 9 10
Tiempo de Espera.
Formula a utilizar
𝑎 + 4𝑚 + 𝑏
𝑡𝑒 =
6
1 + 4(5) + 9 2 + 4(3) + 8
𝑡𝑒(𝐴) = =5 𝑡𝑒(𝐵) = =4
6 6
12 + 4(15) + 22 11 + 4(15) + 18
𝑡𝑒(𝐶) = = 16 𝑡𝑒(𝐷) = = 15
6 6
13 + 4(25) + 31 12 + 4(19) + 45
𝑡𝑒(𝐸) = = 24 𝑡𝑒(𝐹) = = 22
6 6
5 + 4(12) + 20 24 + 4(38) + 45
𝑡𝑒(𝐺) = = 12 𝑡𝑒(𝐻) = = 37
6 6
9 + 4(12) + 20 40 + 4(45) + 50
𝑡𝑒(𝐼) = = 13 𝑡𝑒(𝐽) = = 45
6 6
30 + 4(50) + 70 10 + 4(12) + 13
𝑡𝑒(𝐾) = = 50 𝑡𝑒(𝐿) = = 12
6 6
5 + 4(7) + 9 10 + 4(12) + 13
𝑡𝑒(𝑀) = =7 𝑡𝑒(𝑁) = = 12
6 6
Diagrama de Pert:
Varianza
2
𝑏−𝑎 2
𝜎 = ( )
6
2 (𝐴)
9−1 2 8−2 2
𝜎 = ( ) = (1)2 𝜎 2 (𝐵)
= ( ) = (1)2
6 6
2 (𝑐)
22 − 12 2 18 − 11 2
𝜎 = ( ) = (2)2 𝜎 2 (𝐷)
= ( ) = (1)2
6 6
2 (𝐸)
31 − 13 2 45 − 12 2
𝜎 = ( ) = (3)2 𝜎 2 (𝐹)
= ( ) = (6)2
6 6
2 (𝐺)
20 − 5 2 45 − 24 2
𝜎 = ( ) = (3)2 𝜎 2 (𝐻)
= ( ) = (4)2
6 6
20 − 9 2 50 − 40 2
𝜎 2 (𝐼) = ( ) = (2)2 𝜎 2 (𝐽) = ( ) = (2)2
6 6
2 (𝐾)
70 − 30 2 13 − 10 2
𝜎 = ( ) = (7)2 𝜎 2 (𝐿)
= ( ) = (1)2
6 6
9−5 2 10 − 30 2
𝜎 2 (𝑀) = ( ) = (1)2 𝜎 2 (𝑁) = ( ) = (1)2
6 6
Calculo de probabilidad
Actividad A B C D E F G H I J K L M N
to 1 2 12 11 13 12 5 24 9 40 30 10 5 6
tm 5 3 15 15 25 19 12 38 12 45 50 12 7 8
tp 9 8 22 18 31 45 20 45 20 50 70 13 9 10
A PRECEDEN A F–G–H
B >> G–H
C >> G–H–I–J–K
D–E >> K
F–G >> L
H–I >> M
J-K >> N
Tiempo de Espera.
Formula a utilizar
𝑎 + 4𝑚 + 𝑏
𝑡𝑒 =
6
1 + 4(5) + 9 2 + 4(3) + 8
𝑡𝑒(𝐴) = =5 𝑡𝑒(𝐵) = =4
6 6
12 + 4(15) + 22 11 + 4(15) + 18
𝑡𝑒(𝐶) = = 16 𝑡𝑒(𝐷) = = 15
6 6
13 + 4(25) + 31 12 + 4(19) + 45
𝑡𝑒(𝐸) = = 24 𝑡𝑒(𝐹) = = 22
6 6
5 + 4(12) + 20 24 + 4(38) + 45
𝑡𝑒(𝐺) = = 12 𝑡𝑒(𝐻) = = 37
6 6
9 + 4(12) + 20 40 + 4(45) + 50
𝑡𝑒(𝐼) = = 13 𝑡𝑒(𝐽) = = 45
6 6
30 + 4(50) + 70 10 + 4(12) + 13
𝑡𝑒(𝐾) = = 50 𝑡𝑒(𝐿) = = 12
6 6
5 + 4(7) + 9 10 + 4(12) + 13
𝑡𝑒(𝑀) = =7 𝑡𝑒(𝑁) = = 12
6 6
Diagrama de Pert:
Varianza
2
𝑏−𝑎 2
𝜎 = ( )
6
2 (𝐴)
9−1 2 8−2 2
𝜎 = ( ) = (1)2 𝜎 2 (𝐵)
= ( ) = (1)2
6 6
2 (𝑐)
22 − 12 2 18 − 11 2
𝜎 = ( ) = (2)2 𝜎 2 (𝐷)
= ( ) = (1)2
6 6
2 (𝐸)
31 − 13 2 45 − 12 2
𝜎 = ( ) = (3)2 𝜎 2 (𝐹)
= ( ) = (6)2
6 6
2 (𝐺)
20 − 5 2 45 − 24 2
𝜎 = ( ) = (3)2 𝜎 2 (𝐻)
= ( ) = (4)2
6 6
2 (𝐼)
20 − 9 2 50 − 40 2
𝜎 = ( ) = (2)2 𝜎 2 (𝐽)
= ( ) = (2)2
6 6
70 − 30 2 13 − 10 2
𝜎 2 (𝐾) = ( ) = (7)2 𝜎 2 (𝐿) = ( ) = (1)2
6 6
2 (𝑀)
9−5 2 10 − 30 2
𝜎 = ( ) = (1)2 𝜎 2 (𝑁)
= ( ) = (1)2
6 6
Calculo de probabilidad