PLANILLA DE METRADOS

MEJORAMIENTO DEL SERVICIO DE EDUCACION INICIAL EN LA I.E.I N° 070 SAN MIGUEL EN EL CENTRO POBLADO SAN MIGUEL DE
OBRA:
PALLAQUES - DISTRITO DE SAN MIGUEL - PROVINCIA DE SAN MIGUEL- REGION CAJAMARCA
FECHA: Abril -19
08.00.00 MÓDULO "PSICOMOTRICIDAD Y SALA DE USOS MULTIPLES"
08.01.00 TRABAJOS PRELIMINARES
08.01.01 LIMPIEZA DE TERRENO A MANO
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m2)
Psicomotricidad 1.00 10.00 6.30 63.00
Veredas Frontal 1.00 10.00 2.10 21.00
Posterior 1.00 10.00 0.90 9.00
Canaleta de evacuacion pluvial 1.00 10.00 0.33 3.25
Total (m2) 96.25
08.01.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m2)
Psicomotricidad 1.00 10.00 6.30 63.00
Veredas Frontal 1.00 10.00 2.10 21.00
Posterior 1.00 10.00 0.90 9.00
Canaleta de evacuacion pluvial 1.00 10.00 0.33 3.25
Total (m2) 96.25
08.01.03 TRAZO, NIVELES Y REPLANTEO EN PROCESO DE OBRA
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m2)
Psicomotricidad 1.00 10.00 6.30 63.00
Pasadizo Frontal 1.00 10.00 1.70 17.00
Total (m2) 80.00
08.02.00 MOVIMIENTO DE TIERRAS
08.02.01 EXCAVACION MANUAL PARA CIMIENTOS Y ZAPATAS
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m3)
Zapatas : A-1, A-3 2.00 1.60 1.60 1.45 7.42
Zapatas : A-2 1.00 1.90 1.60 1.45 4.41
Zapatas : B1, B3 2.00 1.20 1.30 1.45 4.52
Zapatas : C-1, C-3 2.00 1.45 1.45 1.45 6.10
Zapatas : C-2 1.00 1.80 1.70 1.45 4.44
Cimiento Corrido : Sección 1-1 2.00 3.19 0.60 1.30 4.98
Cimiento Corrido : Sección 3-3 2.00 5.09 0.50 1.30 6.62
Excavación para redes aguas de lluvia 1.00 10.00 0.33 0.40 1.30
Total (m3) 39.78
08.02.02 RELLENO COMPACTADO MANUAL, MATERIAL PROPIO A MANO
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m3)
Zapatas : A-1, A-3 2.00 1.60 1.60 0.65 3.33
Zapatas : A-2 1.00 1.90 1.60 0.65 1.98
Zapatas : B1, B3 2.00 1.20 1.30 0.65 2.03
Zapatas : C-1, C-3 2.00 1.45 1.45 0.65 2.73
Zapatas : C-2 1.00 1.80 1.70 0.65 1.99
Cimiento Corrido : Sección 1-1 2.00 3.19 0.60 0.65 2.49
Cimiento Corrido : Sección 3-3 2.00 5.09 0.50 0.65 3.31
Total (m3) 17.85
08.02.03 AFIRMADO COMPACTADO E=6" PARA ZAPATAS
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Área (m2)
Zapatas : A-1, A-3 2.00 1.60 1.60 5.12
Zapatas : A-2 1.00 1.90 1.60 3.04
Zapatas : B1, B3 2.00 1.20 1.30 3.12
Zapatas : C-1, C-3 2.00 1.45 1.45 4.21
Zapatas : C-2 1.00 1.80 1.70 3.06
Total (m2) 18.55
08.02.4 AFIRMADO COMPACTADO E=4" PARA CIMIENTOS
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Área (m2)
Cimiento Corrido : Sección 1-1 1.00 3.19 0.60 1.91
Cimiento Corrido : Sección 3-3 1.00 5.09 0.50 2.55
Total (m2) 4.46
08.02.05 NIVELACION INT. PARA FALSO PISO Y VEREDAS
Descripción Cantidad Largo (m) Área (m) Parcial (m2)
Psicomotricidad 1.00 Area = 56.88 56.88
Vereda Frontal 1.00 Area = 21.00 21.00
Vereda Posterior 1.00 Area = 9.00 9.00
Total (m2) 86.88
08.02.06 AFIRMADO COMPACTADO E=4", PARA PISOS Y VEREDAS
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m2)
Igual a 08.02. 06 86.88
Total (m2) 86.88
08.02.07 ACARREO INTERNO DE MATERIAL EXCEDENTE
Descripción Cantidad Largo (m) Ancho (m) Coeficiente Parcial (m3)
Psicomotricidad
Acarreo interno de material excedente 21.93 1.25 27.42
Total (m3) 27.42
08.02.08 ELIMINACION DE MATERIAL EXCEDENTE
Descripción Cantidad Largo (m) Ancho (m) Coeficiente Parcial (m3)
Psicomotricidad
ELIMINACION DE MATERIAL EXCEDENTE 21.93 1.25 27.42
Total (m3) 27.42
PLANILLA DE METRADOS

MEJORAMIENTO DEL SERVICIO DE EDUCACION INICIAL EN LA I.E.I N° 070 SAN MIGUEL EN EL CENTRO POBLADO SAN MIGUEL DE
OBRA:
PALLAQUES - DISTRITO DE SAN MIGUEL - PROVINCIA DE SAN MIGUEL- REGION CAJAMARCA
FECHA: Abril -19
08.00.00 MÓDULO "PSICOMOTRICIDAD Y SALA DE USOS MULTIPLES"
08.03.00 OBRAS DE CONCRETO SIMPLE
08.03.01 SOLADOS
08.03.01.01 SOLADO PARA ZAPATAS DE 4" MEZCLA 1:12 CEMENTO-HORMIGON
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m2)
Igual a 08.02.04 18.55
Total (m2) 19.47
08.03.02 CIMIENTOS CORRIDOS
08.03.02.01 CIMIENTOS CORRIDOS MEZCLA C:H 1:10 + 30% PG MAX 8"
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m3)
Cimiento Corrido : Sección 1-1 2.00 3.19 0.60 0.55 2.11
Cimiento Corrido : Sección 3-3 2.00 5.09 0.50 0.55 2.80
Total (m3) 5.15
08.03.03 SOBRECIMIENTOS
08.03.03.01 SOBRECIMIENTOS, CONCRETO C:H 1:8 + 25% PM
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m3)
Sobrecimiento : Secciones 1-1 4.00 2.55 0.25 0.45 1.15
Sobrecimiento : Secciones 3-3 1.00 15.85 0.15 0.45 1.07
Sobrecimiento : Secciones 3-3 (Puertas) 1.00 1.05 0.15 0.35 0.06
Total (m3) 2.39
08.03.03.02 SOBRECIMIENTOS, ENCOFRADO Y DESENCOFRADO
Descripción Cantidad Largo (m) #caras Alto (m) Parcial (m2)
Sobrecimiento : Secciones 1-1 4.00 2.55 2.00 0.45 9.18
Sobrecimiento : Secciones 3-3 1.00 15.85 2.00 0.45 14.27
Sobrecimiento : Secciones 3-3 (Puertas) 1.00 1.05 2.00 0.35 0.74
Total (m2) 24.18
08.03.04 FALSO PISO
08.03.08.01 FALSO PISO DE 4" DE CONCRETO C:H 1:8
Descripción Cantidad Area (m2) Parcial (m2)
Psicomotricidad 1.00 Area = 56.88 56.88
Total (m2) 59.72
08.08.00 OBRAS DE CONCRETO ARMADO
08.08.01 ZAPATAS
08.08.01.01 ZAPATAS, CONCRETO F'C=210 KG/CM2
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m3)
Psicomotricidad + COMEDOR
Zapatas : A-1, A-3 2.00 1.60 1.60 0.55 2.82
Zapatas : A-2 1.00 1.90 1.60 0.55 1.67
Zapatas : B1, B3 2.00 1.20 1.30 0.55 1.72
Zapatas : C-1, C-3 2.00 1.45 1.45 0.55 2.31
Zapatas : C-2 1.00 1.80 1.70 0.55 1.68
Total (m3) 10.71
08.08.01.02 ZAPATAS, ACERO CORRUGADO Fy=4200 KG/CM2
Descripción Ø (pulg) # Elem. # Piezas/Elem Long (m) Peso (kg/m) Parcial (Kg)
Acero longitudinal :
Zapatas : A-1, A-3 1/2 2.00 9.00 1.52 1.02 27.91
Zapatas : A-2 1/2 1.00 10.00 1.82 1.02 18.56
Zapatas : B1, B3 1/2 2.00 6.00 1.12 1.02 13.71
Zapatas : C-1, C-3 1/2 2.00 8.00 1.37 1.02 22.36
Zapatas : C-2 1/2 1.00 9.00 1.72 1.02 15.79
Acero transversal :
Zapatas : A-1, A-3 1/2 2.00 8.00 1.52 1.02 24.81
Zapatas : A-2 1/3 1.00 8.00 1.52 1.02 12.40
Zapatas : B1, B3 1/2 2.00 7.00 1.22 1.02 17.42
Zapatas : C-1, C-3 1/2 2.00 8.00 1.37 1.02 22.36
Zapatas : C-2 1/2 1.00 9.00 1.62 1.02 14.87
Total (kg) 190.19
08.08.02 VIGAS DE CIMENTACION
08.08.02.01 VIGAS DE CIMENTACION, CONCRETO F'C= 210 KG/CM2
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m3)
Secciones 1-1 4.00 2.55 0.25 0.45 1.15
Secciones 3-3 1.00 16.90 0.25 0.45 1.90
Total (M3) 3.20
08.08.02.02 VIGAS DE CIMENTACION, ENCOFRADO Y DESENCOFRADO
Descripción Cantidad Largo (m) #caras Alto (m) Parcial (m2)
Secciones 1-1 4.00 2.55 2.00 0.45 9.18
Secciones 3-3 1.00 16.90 2.00 0.45 15.21
Total (m2) 24.39
08.08.02.03 VIGAS DE CIMENTACION, ACERO FY=4200 KG/CM2
Descripción Ø (pulg) # Elem. # Piezas/Elem Long (m) Peso (kg/m) Parcial (Kg)
Acero longitudinal :
Secciones 1-1 5/8 2 6 6.70 1.56 125.42
Secciones 3-3 5/8 2 6 10.40 1.56 194.69
Estribos :
Secciones 1-1 1/4 4 18 1.59 0.25 28.62
Secciones 3-3 1/4 4 25 1.59 0.25 39.75
Total (kg) 388.48
08.08.03 COLUMNAS Y COLUMNETAS
08.08.03.01 COLUMNAS Y COLUMNETAS, CONCRETO F'C=210 KG/CM2
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m3)
Psicomotricidad + USOS MULTIPLES
Tipo C1 2.00 0.30 0.25 7.15 1.07
Tipo C3 4.00 0.65 0.25 6.55 4.26
Tipo C4 2.00 0.85 0.25 6.55 2.78
Columneta (Ventanas frontales-1.20m) 8.00 0.15 0.20 1.20 0.29
Columneta (Ventanas posteriores-1.50m) 8.00 0.15 0.20 1.50 0.36
Total (M3) 8.76
08.08.03.02 COLUMNAS Y COLUMNETAS, ENCOFRADO Y DESENCOFRADO
Descripción Cantidad Perímetro (m) #caras Alto (m) Parcial (m2)
Psicomotricidad + USOS MULTIPLES
Tipo C1 2.00 1.10 6.50 14.30
Tipo C3 4.00 1.80 6.10 43.92
Tipo C4 2.00 2.20 6.10 26.84
Columneta (Ventanas frontales-1.20m) 8.00 0.50 1.20 4.80
Columneta (Ventanas posteriores-1.50m) 8.00 0.50 1.50 6.00
Total (M2) 95.86
08.08.03.03 COLUMNAS Y COLUMNETAS, ACERO CORRUGADO FY=4200 KG/CM2
Descripción Ø (pulg) # Elem. # Piezas/Elem Long (m) Peso (kg/m) Parcial (Kg)
Psicomotricidad + USOS MULTIPLES
Acero longitudinal :
TIPO C1 1/2 2 4 8.95 1.00 71.60
  5/8 4 8 8.35 1.55 414.16
TIPO C4 5/8 2 6 8.35 1.55 155.31
TIPO C4 3/4 2 4 8.35 2.24 149.63
Columneta (Ventanas frontales-1.20m) 3/8 8 4 1.75 0.56 31.36
Columneta (Ventanas posteriores-1.50m) 3/8 8 4 1.95 0.56 34.94
Estribos :
TIPO C1 3/8 2 41 1.38 0.56 63.37
  3/8 4 43 3.36 0.56 323.64
  3/8 2 45 3.76 0.56 189.50
Columneta (Ventanas frontales-1.20m) 3/8 8 8.00 0.89 0.56 31.90
Columneta (Ventanas posteriores-1.50m) 3/8 8 9.00 0.89 0.56 35.88
Total (kg) 1501.30
08.08.04 VIGAS, VIGUETAS Y DINTELES
08.08.08.01 VIGAS, VIGUETAS Y DINTELES, CONCRETO F'C=210 KG/CM2
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m3)
Psicomotricidad + USOS MULTIPLES
V: 10A Y 10C 2.00 10.00 0.25 0.40 2.00
V: 20A Y 20C 2.00 10.00 0.25 0.35 1.75
V: 10 B (30X30), 1.00 10.00 0.30 0.30 0.90
V 20B 1.00 10.00 0.25 0.35 0.88
VS: 103, VS 105 (25X40) 2.00 6.30 0.25 0.40 1.26
VS: 104 (25X50) 1.00 6.30 0.25 0.50 0.79
V103, V104, 105 VOLADOS PRIMER PISO 3.00 0.75 2.38 1.79
vb1 2.00 4.63 0.25 0.25 0.29
VS-203 (25X20) INFERIOR 2.00 5.40 0.25 0.20 0.27
VS-203 (25X25) SUPERIOR 1.00 9.57 0.25 0.25 0.60
VS-205 (25X20) INFERIOR 1.00 5.40 0.25 0.20 0.27
VS-205 (25X25) SUPERIOR 1.00 9.57 0.25 0.25 0.60
vb2 1.00 27.45 0.17 0.15 0.70
V: a (Ventanas de V1) 2.00 3.18 0.15 0.15 0.07
V: a (Ventana V2) 2.00 4.23 0.15 0.15 0.10
V: a (Ventana V3) 4.00 4.23 0.15 0.15 0.10
Total (M3) 12.96
08.08.08.02 VIGAS, VIGUETAS Y DINTELES, ENCOFRADO Y DESENCOFRADO
Descripción Cantidad Largo (m) Ancho (m) Perim (m) Parcial (m2)
Psicomotricidad + USOS MULTIPLES
V: 10A Y 10C 2.00 10.00 0.65 13.00
V: 20A Y 20C 2.00 10.00 0.56 11.20
V: 10 B (30X30) 1.00 10.00 0.30 3.00
V: 20 B 1.00 10.00 0.25 2.50
VS: 103, VS 105 (25X40) 2.00 6.30 0.65 8.19
VS: 104 (25X50) 1.00 6.30 0.85 5.36
V103, V104,105 VOLADOS PRIMER PISO 3.00 0.75 3.45 7.76
vb1 2.00 4.63 0.50 4.63
VS-203 (25X20) INFERIOR 1.00 6.30 0.45 2.84
VS-203 (25X25) SUPERIOR 1.00 5.40 0.50 2.70
VS-205 (25X20) INFERIOR 1.00 5.40 0.45 2.43
VS-205 (25X25) SUPERIOR 1.00 5.40 0.50 2.70
vb2 1.00 27.45 0.37 10.02
V: a (Ventanas de V1) 2.00 3.18 0.30 1.91
V: a (Ventana V2) 2.00 4.23 0.30 2.54
V: a (Ventana V3) 4.00 4.23 0.30 5.07
Total (M2) 85.83
08.08.08.03 VIGAS, VIGUETAS Y DINTELES, ACERO CORRUGADO FY=4200 KG/CM2
Descripción Ø (pulg) # Elem. # Piezas/Elem Long (m) Peso (kg/m) Parcial (Kg)
Psicomotricidad + USOS MULTIPLES
V: 10A Y 10C 5/8 2.00 4.00 10.34 1.56 129.04
1/2 2.00 2.00 10.32 1.00 41.28
Estribos 3/8 2.00 52.00 1.32 0.56 76.88
V: 10 B (30X30) 5/8 1.00 4.00 10.36 1.56 64.65
3/8 1.00 2.00 10.36 0.56 11.60
Estribos 3/8 1.00 52.00 1.22 0.56 35.53
V: 20 B 5/8 1.00 4.00 6.66 1.56 41.56
3/8 1.00 2.00 6.66 0.56 7.46
Estribos 3/8 1.00 52.00 1.22 0.56 35.53
V103, V104,105 VOLADOS PRIMER PISO 5/8 3.00 2.00 2.40 1.56 22.46
3/4 3.00 2.00 3.18 2.728 52.05
Estribos 3/8 2.00 16.00 1.22 0.56 21.86
VS: 103, VS 105 (25X40) 5/8 2.00 4.00 8.34 1.56 104.08
Estribos 1/4 2.00 36.00 1.32 0.25 23.76
VS:104 5/8 1.00 2.00 8.34 1.56 26.02
3/4 1.00 2.00 8.34 2.728 45.50
1/2 1.00 2.00 7.84 1.00 15.68
5/8 1.00 2.00 4.20 1.56 13.10
Refuerzo
3/4 1.00 2.00 3.20 2.728 17.46
Estribos 3/8 1.00 33.00 1.56 0.56 28.83
VB 1 1/2 1.00 4.00 10.44 1.00 41.76
Estribos 1/4 1.00 58.00 0.82 0.25 11.89
VS-203 (25X20) INFERIOR 3/8 1.00 4.00 6.44 0.56 14.43
Estribos 1/4 1.00 34.00 0.98 0.25 8.33
VS-203 (25X25) SUPERIOR 3/8 1.00 4.00 9.67 0.56 21.66
Estribos 1/4 1.00 34.00 0.98 0.25 8.33
Estribos (Volado) 1/4 1.00 32.00 0.98 0.25 7.84
VS-205 (25X20) INFERIOR 3/8 1.00 4.00 6.44 0.56 14.43
Estribos 1/4 1.00 34.00 0.98 0.25 8.33
VS-205 (25X25) SUPERIOR 3/8 1.00 4.00 9.67 0.56 21.66
Estribos 1/4 1.00 34.00 0.98 0.25 8.33
Estribos (Volado) 1/4 1.00 32.00 0.98 0.25 7.84
vb2 3/8 1.00 2.00 27.45 0.56 30.74
Estribos 1/4 1.00 184.00 0.76 0.25 34.96
V: a (Ventanas de V1) 3/8 2.00 4.00 2.50 0.56 11.20
Estribos 1/4 2.00 16.00 0.58 0.25 4.64
V: a (Ventana V2) 3/8 2.00 4.00 4.37 0.56 19.58
Estribos 1/4 2.00 25.00 0.58 0.25 7.25
V: a (Ventana V3) 3/8 4.00 4.00 4.25 0.56 38.08
Estribos 1/4 4.00 25.00 0.58 0.25 14.50
Total (kg) 1150.11
08.08.05 LOSAS ALIGERADAS
08.08.08.01 LOSAS ALIGERADAS, CONCRETO F'C=210 KG/CM2
Descripción Cantidad Largo (m) Ancho (m) Factor Parcial (m3)
Psicomotricidad + USOS MULTIPLES
Aligerado (Paños interiores) 8 4.63 2.80 0.08 8.29
Aligerado (Volado Frontal) 4 4.63 0.85 0.08 1.26
Aligerado (Volado Posterior) 4 4.63 0.35 0.08 0.52
1 0.35 0.35 0.08 0.01
Aligerado (Volado derecho) 2 0.35 2.78 0.08 0.16
1 0.35 0.85 0.08 0.02
Total (m3) 10.77
08.08.08.02 LOSAS ALIGERADAS, ENCOFRADO Y DESENCOFRADO
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial
Psicomotricidad + USOS MULTIPLES
Aligerado e=20cm 1 5.56 9.26 51.49
Aligerado primer piso (Volado Frontal) 1 1.50 9.26 13.89
Aligerado e=17cm 1 9.58 9.26 88.71
Aligerado segundo piso(Volado derecho) 1 9.58 0.35 3.35
Total (m2) 157.44
08.08.08.03 LOSAS ALIGERADAS, ACERO Fy=4200 KG/CM2
Descripción Ø (pulg) # Viguetas # Long (m) Peso (kg/m) Parcial (Kg)
Psicomotricidad
Positivo 1/2 15 1 9.95 1.02 152.24
Negativo 1/2 15 2 1.14 1.02 34.88
Negativo 3/8 15 2 3.35 0.57 57.29
Temperatura Longitudinal 1/4 1 38 9.57 0.25 90.92
Transversal 1/4 1 41 10.49 0.25 107.52
USOS MULTIPLES SEGUNDO PISO
Positivo 1/2 18 1 10.41 1.02 191.13
Negativo 1/2 18 2 1.14 1.02 41.86
Negativo 3/8 18 2 3.35 0.57 68.74
Temperatura Longitudinal 1/4 1 37 9.94 0.25 91.95
Transversal 1/4 1 41 7.94 0.25 81.39

  917.90

08.08.08.04 LADRILLO HUECO DE ARCILLA DE 0.15 x 0.30 x 0.25 m PARA TECHO ALIGERADO
Descripción Area (m2) Largo (m) Ancho (m) Factor Parcial
PSICOMOTRICIDAD 65.38 10 653.76
Total (und) 653.76
08.08.08.05 BLOQUE DE POLIESTIRENO DE 0.12 x 0.30 x 0.25 m. PARA TECHO ALIGERADO
Descripción Area (m2) Largo (m) Ancho (m) Factor Parcial
USOS MULTIPLES 92.06 10 920.64
Total (und) 920.64
08.08.00 MUROS Y TABIQUES DE ALBAÑILERIA
08.08.01 MURO DE SOGA LADRILLO DE ARCILLA 9X13X24 CM, MEZ 1:5
Descripción Cantidad Largo (m) # Veces Alto (m) Parcial
Aula de Psicomotricidad y Sala de usos Mult.
Eje A (primer y segundo nivel ) 4 3.775 1 1.25 18.875
EJE C (Primer y segundo nivel) 4 3.775 1 0.95 14.345
(-) Descontamos: Puerta 1 2 1.050 1 0.95 -1.995
Total (m2) 31.23
08.08.01 MURO DE CABEZA LADRILLO ARCILLA 9X13X24 CM, MEZ 1:5
Descripción Cantidad Long (m) # Veces Alto (m) Parcial
Psicomotricidad y Sala de usos Mult.
Ejes 1, 3 (primer nivel) 2 5.1 1 2.85 29.07
Ejes 1, 3 (segundo nivel) 2 5.1 1 2.95 30.09
Ejes 1, 3 (entre viga superior y techo-segundo nivel) 2 3.934 1 0.49 1.93
Total (m2) 61.09
08.06.00 COBERTURA
08.06.01 COBERTURA DE TEJA ANDINA SOBRE LOSA DE CONCRETO
Descripción Cantidad Largo (m) Ancho (m) 25° Parcial (m2)
Psicomotricidad y Sala de usos Mult. 1 10.50 9.63 101.12
Total (m2) 101.12
08.06.02 CUMBRERA DE TEJA ANDINA
descripción cantidad largo (m) ancho (m) alto (m) parcial (m)
Psicomotricidad y Sala de usos Mult. 1 10.50 10.5
Total (m2) 10.5
08.07.00 REVOQUES, ENLUCIDOS Y MOLDURAS
08.07.01 TARRAJEO EN INTERIORES Y EXTERIORES ESPESOR 1.5 CM, MEZ 1:5
Cantidad
Descripción Long (m) # Veces Alto (m) Parcial (m2)
(m2)
Muros de cabeza total 61.09 2 122.18
Muros de soga total 31.23 2 62.45
Total (m2) 203.09
08.07.02 TARRAJEO DE COLUMNAS, E=1.5 CM, MEZ. 1:5
Cantidad
Descripción Largo (m) # Veces Alto (m) Parcial (m2)
(m2)
Tarrajeo de columnas 60.08 1 60.08
Total (m2) 66.09
08.07.03 TARRAJEO DE VIGAS, E=1.5 CM, MEZ. 1:5
Cantidad
Descripción Largo (m) # Veces Alto (m) Parcial (m2)
(m2)
Tarrajeo de vigas 85.83 1 85.83
Total (m2) 94.41
08.07.04 VESTIDURA DE DERRAMES E=1.5, MEZ. 1:5
Descripción Cantidad Ancho Largo Alto (m) Parcial (ml)
P1 2.00 1.05 2.80 13.30
V1 2.00 3.175 1.60 19.10
V2 2.00 4.225 1.60 23.30
V3 4.00 4.225 1.30 44.20
Total (ml) 109.89
08.07.05 BRUÑAS 1 cm EN INTERIORES Y VEREDAS
Descripción Cantidad LONG (M) Parcial (ml)
Paredes interiores (25 cm) 2.00 21.52 43.04
Vereda frontal (2.10m) 2.00 19.60 39.20
Vereda posterior (0.90m) 2.00 8.75 17.50
Total (ml) 99.74
08.08.00 CIELORRASOS
08.08.01 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA
Descripción Cantidad Area (m2) Parcial (m2)
Psicomotricidad y Sala de usos Mult. 2 Area = 56.88 56.88
Volados 1 Area = 51.65 51.65
Total (m2) 119.38
08.09.00 PISOS Y PAVIMENTOS
08.09.01 CONTRAPISO DE CEMENTO DE 48 MM
Descripción Cantidad Area (m2) Parcial (m2)
Psicomotricidad y Sala de usos Mult. 2 Area = 56.88 56.88
Pasadizo 1 Area = 15.50 15.50
Total (m2) 56.88
08.09.02 PISO DE CERAMICO NACIONAL 30 X 30 CM
Descripción Cantidad Area (m2) Parcial (m2)
Psicomotricidad y Sala de usos Mult. 2 Area = 56.88 56.88
Pasadizo 1 Area = 15.50 15.50
Total (m2) 56.88
08.09.03 VEREDAS, CONCRETO F'C=140 KG/CM2, E=10 CM
Descripción Cantidad Largo (m) Ancho (m) Area
Vereda Frontal 1 10.00 2.10 21.00
Vereda posterior (0.90m) 1 10.00 0.90 9.00
Total (m2) 30.00
08.09.04 SARDINEL, CONCRETO F'C=175 KG/CM2
Descripción Cantidad Long (m) Alto (m) Ancho (m) Parcial (m3)
Vereda Frontal 1 10.00 0.3 0.1 0.30
Vereda posterior (0.90m) 1 10.00 0.3 0.1 0.30
Total (m3) 0.60
08.09.05 SARDINEL, ENCOFRADO Y DESENCOFRADO
Descripción Cantidad Long (m) Alto (m) Parcial (m2)
Vereda Frontal 1 10.00 0.35 3.50
Vereda posterior (0.90m) 1 10.00 0.35 3.50
Total (m2) 7.00
08.09.06 JUNTAS ASFALTICAS DE DILATACION 1:5, E=1 (VEREDAS)
Descripción Cantidad Long (m) Ancho (m) Alto (m) Parcial (ml)
Veredas Frontal 2 2.1 4.2
Posterior 3 0.9 2.7
Canaleta de evacuacion pluvial 3 0.9 2.7
Total (ml) 9.60
08.10.00 ZOCALOS Y CONTRAZOCALOS
08.10.01 CONTRAZOCALO DE CERAMICO H=10 CM, A=20 CM
Descripción Cantidad Long (m) Ancho (m) Alto (m) Parcial (ml)
Psicomotricidad y Sala de usos Mult. 2 9.5 6 0.1 62
Pasadizo en volado 2 8.95 0.1 35.8
Total (ml) 62
08.10.02 CONTRAZOCALO DE CEMENTO PULIDO H=20 CM EN EXTERIORES
Descripción Cantidad Long (m) Ancho (m) Alto (m) Parcial (ml)
Frente al módulo 1 8.95 0.20 8.95
Pared Posterior del Módulo 1 10.00 0.20 10.00
Total (ml) 18.95
08.11.00 CARPINTERIA DE MADERA
08.11.01 PUERTA DE MADERA DE CEDRO P-1 TABLERADA S/MODELO DE 1.05X2.80 m
Descripción Cantidad Long (m) Ancho (m) Alto (m) Parcial (m2)
Psicomotricidad y Sala de usos Mult. 2 1.05 2.8 5.88
Total (m2) 5.88
08.11.04 VENTANA DE MADERA DE CEDRO V-1 DE 3.175 X 1.60 m.
Descripción Cantidad Long (m) Ancho (m) Alto (m) Parcial (m2)
Psicomotricidad y Sala de usos Mult. 2 3.175 1.6 10.16
Total (m2) 10.16
08.11.05 VENTANA DE MADERA DE CEDRO V-2 DE 4.225 X 1.60 m.
Descripción Cantidad Long (m) Ancho (m) Alto (m) Parcial (m2)
Psicomotricidad y Sala de usos Mult. 2 4.225 1.6 13.52
Total (m2) 13.52
08.11.06 VENTANA DE MADERA DE CEDRO V-3 DE 4.225 X 1.30 m.
Descripción Cantidad Long (m) Ancho (m) Alto (m) Parcial (m2)
Cocina 4 4.225 1.3 21.97
Total (m2) 21.97
08.12.00 CARPINTERIA METALICA
08.12.01 BARRAS DE SEGURIDAD FIERRO LISO DE 1/2" EN VENTANAS
Descripción Cantidad Largo (m) # Veces Alto (m) Parcial (ml)
Sobreluz P1 2 1.05 2 4.20
V-1 2 3.175 6 38.10
V-2 2 4.225 6 50.70
V-3 4 4.225 6 101.40
Total (ml) 194.40
08.13.00 CERRAJERIA
08.13.01 BISAGRA CAPUCHINA DE 4" X 4"
Descripción Cantidad Largo (m) # Veces Alto (m) Parcial (und)
Puertas (1 simple y 1 doble - 4 por hoja) 2 4 8
Total (und) 8
08.13.02 BISAGRA CAPUCHINA DE 2 1/2" X 2 1/2"
Descripción Cantidad Largo (m) # Veces Alto (m) Parcial (und)
Bisagras en ventanas 56 56
Total (und) 56
08.13.03 CERRADURA FORTE 3 GOLPES EN PUERTA
Descripción Cantidad Largo (m) # Veces Alto (m) Parcial (und)
Puertas 2 1 2
Total (und) 2
08.13.04 CERRADURA SAPITO PARA VENTANAS
Descripción Cantidad Largo (m) # Veces Alto (m) Parcial (und)
Ventanas 28 1 28
Total (und) 28
08.13.05 MANIJA DE BRONCE DE 4" PARA PUERTAS
Descripción Cantidad Largo (m) # Veces Alto (m) Parcial (und)
Puertas P1 2 1 2
Total (und) 2
08.14.00 VIDRIOS, CRISTALES Y SIMILARES
08.14.01 VIDRIO SEMIDOBLE NACIONAL TRASLUCIDO
Descripción Cantidad Largo (m) Alto (m) Factor Parcial (p2)
Sobreluz P1 2 1.05 0.55 10.77 12.44
V-1 2 3.175 1.6 10.77 109.42
V-2 1 4.225 1.6 10.77 72.81
V-3 1 4.225 1.3 10.77 59.15
Total (p2) 253.82
08.15.00 PINTURA
08.15.01 PINTURA LATEX EN VIGAS Y CIELORRASOS (DOS MANOS)
Descripción Cantidad Largo (m) # Veces Alto (m) Parcial (m2)
cielorrasos 119.38 1 119.38
vigas 94.41 1 94.41
Total (m2) 213.79
08.15.02 PINTURA LATEX EN MUROS Y COLUMNAS (DOS MANOS)
Descripción Cantidad Largo (m) # Veces Alto (m) Parcial (m2)
muros 203.09 1 203.09
columnas 66.09 1 66.09
Total (m2) 269.18
08.15.03 PINTURA EN PUERTAS DE MADERA CON BARNIZ
Descripción Cantidad Largo (m) # Caras Factor 1.15 Parcial (m2)
puertas 5.88 2 1.15 13.52
Total (m2) 13.52
08.15.04 PINTURA EN VENTANAS DE MADERA CON BARNIZ
Descripción Cantidad Largo (m) # Caras Factor 1.15 Parcial (m2)
ventanas 45.65 2 1.15 105.00
Total (m2) 105.00
08.15.05 PINTURA DE CONTRAZOCALOS CON ESMALTE
Descripción Cantidad Largo (m) # Caras Alto (m) Parcial (m2)
Contrazocalos de 20 cm de alto 1 18.95 1 0.2 3.79
Contrazocalos de 10 cm de alto 1 62 1 0.1 6.20
Total (m2) 9.99
08.16.00 SISTEMA DE AGUAS DE LLUVIA
08.16.01 DADO CONCRETO PROTECCION MONTANTE BAJADA DE AGUA DE LLUVIA
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m3)
Dado de concreto aulas 2 0.2 0.1 1.5 0.06
Total (m3) 0.06
08.16.02 CANALETA DE ZINC DE 6" PARA EVACUACION PLUVIAL INC. EMBUDO
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (ml)
aleros de Psicom. y Sala de usos Mult. 2 10.5 21
Total (ml) 21.00
08.16.03 MONTANTE PARA BAJADA DE AGUA DE LLUVIA PVC SAL D=3"
Descripción Cantidad Largo (m) Ancho (m) Alto (m) Parcial (ml)
aleros de Psicom. Frontal 1 9 9
aleros de Psicom. Posterior 1 7.8 7.8
Total (ml) 16.80