OBRA : CONSTRUCCION DE CANAL DE IRRIGACION SAN JOSE DE SUCRE
LUGAR : COLCA - FAJARDO - AYACUCHO COSTO DIRECTO : 904,184.66 PLAZO DE EJECUCION DE OBRA PRESUPUESTO DE ITEM ACTIVIDADES MES 01 MES 02 MES 03 MES 04 MES 05 PARCIALES S/. OBRA 30 DIAS 60 DIAS 90 DIAS 120.00 143 DIAS
1.0 OBRAS PROVISIONALES
01 OBRAS PROVISIONALES 10,231.89 10,231.89 10,231.89 2.0 BOCATOMA 01 TRABAJOS PRELIMINARES 3,449.05 3,449.05 3,449.05 02 MOVIMIENTO DE TIERRAS 31,064.42 31,064.42 31,064.42 03 OBRAS DE CONCRETO SIMPLE 32,781.84 11,473.64 21,308.20 32,781.84 04 OBRAS DE CONCRETO ARMADO 40,598.60 18,269.37 22,329.23 40,598.60 05 ENCOFRADO Y DESENCOFRADO 12,151.92 12,151.92 12,151.92 06 ACERO DE REFUERZO 19,738.66 19,738.66 19,738.66 07 ESTRUCTURAS METALICAS 13,584.96 5,433.98 8,150.98 13,584.96 3.0 ANTECANAL 01 TRABAJOS PRELIMINARES 97.09 97.09 97.09 02 MOVIMIENTO DE TIERRAS 3,850.69 3,850.69 3,850.69 03 REVESTIMIENTO DE CANAL 27,594.53 9,658.09 17,936.44 27,594.53 04 JUNTAS 544.43 163.33 381.10 544.43 05 CANAL DESRIPEADOR 10,393.72 10,393.72 10,393.72 4.0 CANAL PRINCIPAL 01 OBRAS PRELIMINARES 7,124.63 7,124.63 7,124.63 02 MOVIMIENTO DE TIERRAS 116,774.76 116,774.76 116,774.76 03 INSTALACION DE TUBERIAS 460,608.87 92,121.77 276,365.32 92,121.77 460,608.87 04 CAJAS DE INSPECCIÓN Y VOLTEO 15,562.83 6,225.13 9,337.70 15,562.83 05 TOMAS LATERALES 1,600.49 80.02 1,520.47 1,600.49 5.0 OBRAS DE ARTE 0.00 0.00 01 DESARENADOR 6,314.04 6,314.04 6,314.04 02 POZA DE CAPTACIÓN 766.29 766.29 766.29 CRONOGRAMA VALORIZADO DE OBRA
OBRA : CONSTRUCCION DE CANAL DE IRRIGACION SAN JOSE DE SUCRE
LUGAR : COLCA - FAJARDO - AYACUCHO COSTO DIRECTO : 904,184.66 PLAZO DE EJECUCION DE OBRA PRESUPUESTO DE ITEM ACTIVIDADES MES 01 MES 02 MES 03 MES 04 MES 05 PARCIALES S/. OBRA 30 DIAS 60 DIAS 90 DIAS 120.00 143 DIAS
03 CANOAS 3,418.48 3,418.48 3,418.48
04 RAPIDAS 2,136.29 1,709.03 427.26 2,136.29 05 TOMAS TIPICAS DE INGRESO Y SALIDA 6,665.04 5,332.03 1,333.01 6,665.04 06 VERTEDERO DE EXDENCIAS 3,833.92 3,833.92 3,833.92 07 DADOS DE CONCRETO 7,314.43 7,314.43 7,314.43 08 ALCANTARRILLAS DE CONCRETO ARMADO 35,544.17 21,326.50 14,217.67 35,544.17 09 CANAL DE PURGA 353.50 353.50 353.50 6.0 FLETE 22,377.30 11,188.65 11,188.65 22,377.30 7.0 IMPACTO AMBIENTAL 7,707.82 1,926.96 1,926.96 1,926.96 1,926.96 7,707.82