CAPITULO:5. PISOS
ACTIVIDAD ANALIZADA: 5.16. ANDENES EN CONCRETO 2500 PSI E= 10 CMS
UNIDAD : M2
1. EQUIPO
DESCRIPCION TIPO TAR/HORA RENDIMIENTO
2. MATERIALES EN OBRA
DECRIPCION UNIDAD P/UNITARIO CANTIDAD
CONCRETO DE 2500 PSI M3 273500.00 0.10
PUNTILLAS LB 5000.00 0.80
FORMALETA ML 8000.00 1.58
DESPERDICIO % 43990.00 5.00
SUBTOTAL
3. TRANSPORTES
DESCRIPCION CANT. VR/DIA RENDIMIENTO
SUBTOTAL
4. MANO DE OBRA
TRABAJADOR JORNAL/DIA PRESTACIONES CANTIDAD RENDIMIENTO
OFICIAL 68500.00 75% 1.00 8.00
AYUDANTE 42065.00 75% 3.00 8.00
SUBTOTAL
TOTAL COSTO DIRECTO
5. COSTOS INDIRECTOS
DESCRIPCION PORCENTAJE
A.I.U. 35%
SUBTOTAL
10 CMS
FECHA: Mar-14
V/UNITARIO
284.00
SUBTOTAL $ 284.00
V/UNITARIO
27,350.00
4,000.00
12,640.00
2,199.50
SUBTOTAL $ 46,189.50
V/TOTAL
$ -
SUBTOTAL $ -
V/UNITARIO
8,562.50
15,774.38
SUBTOTAL $ 24,336.88
TOTAL COSTO DIRECTO 70,810.38
V/TOTAL
24,783.63
SUBTOTAL $ 24,784
PRESUPUESTO DE OBRA
ITEM DESCRIPCION
1. PRELIMINARES
1.1 CAMPAMENTO
1.2 VALLA INFORMATIVA
1.3 LOCALIZACION Y REPLANTEO
1.4 DESCAPOTE MANUAL
1.5 DEMOLICION DE PISOS EN CONCRETO
1.6 RETIRO DE JUEGOS INFANTILES EXISTENTES
1.7 DEMOLICION BORDILLO
1.8 DESMONTE DE APARATOS ELECTRICOS(LAMPARAS ,REFLECTORES, APAGADORES)
1.9 DESMONTE DE APARATOS ELECTRICOS(, TUBERIAS, CABLEADO)
1.10 CERRAMIENTO EN POLISOMBRA
1.11 TALA DE ARBOLES
1.12 RETIRO DE ESCOMBROS Y MATERIAL SOBRANTE
SUBTOTAL
2. MOVIMIENTO DE TIERRA
2.1 EXCAVACION MANUAL DE O.Om A 2.0m
2.2 EXCAVACION A MAQUINA
2.3 RELLENO COMPACTADO CON MATERIAL SELECCIONADO
2.4 RELLENO CON MATERIAL DE LA MISMA EXCAVACION
2.5 RELLENO CON MATERIAL GRANULAR (ARENA)
SUBTOTAL
3. CONCRETO
3.1 CONCRETO CICLOPEDO
3.2 RAMPAS EN CONCRETO DE 2500 PSI
3.3 CONCRETO PARA MURO PANTALLA CASETAS COMERCIALES
3.4 VADOS PARA DISCAPACITADOS
SUBTOTAL
4 CARPINTERIA METALICA Y ACERO
4.1 ACERO POR 60 KG
4.2 CUBIERTA METALICA ALUZINC
4.3 ESTRUCTURA METALICA CASETAS
PUERTAS PARA CASETAS EN LAMINA COLD ROLD CALIBRE 18 INCLUYE ANTICOROSIVO Y
4.4 PINTURA
4.5 CANAL EN LAMINA CALIBRE 18 INCLUYE ANTICORROSIVO Y PINTURA
4.6 ENTREPAÑOS EN LAMINA CALIBRE 10 PARA CASETAS
SUBTOTAL
5. PISOS
5.1 MORTERO DE PISO
5.2 SUMINISTRO E INSTALACION DE BORDILLO(REMATES) EN CONCRETO DE 20 CM
5.3 SUMINISTRO E INSTALACION PISO EN CONCRETO ROJO TIPO DECK
5.4 SUMINISTRO E INSTALACION PISO EN CONCRETO GRIS TIPO DECK
5.5 SUMINISTRO E INSTALACION DE PISO EN LOCETAS DE CONCRETO (1X1X.68)
5.6 SUMINISTRO EINSTALACION DE LOCETAS EN CONCRETO TIPO DECK
5.7 SUMINISTRO E INSTALACION DE PISO PARA TERRAZA EN DECK
5.8 SUMINISTRO E INSTALACION DE PISO EN DECK PVC
5.9 SUMINISTRO E INSTALACION DE GRAMOQUIN
5.10 SUMINISTRO E INSTALACIÓN DE PISO PARA CICLORUTA
5.11 SUMINISTRO E INSTALACION DE LOCETA GUIA PARA CONCRETO
5.12 SUMINISTRO E INSTALACION DE SARDINELES EN CONCRETO
5.13 CONSTRUCCIÓN DE ANDEN EN CONCRETO
5.14 PISO EN CAUCHO RECICLADO EN COLORES
SUBTOTAL
8 OBRAS DE ELECTRICIDAD
8.1 DUCTO SUBTERRANEO EN PVC 1"
8.2 DUCTO SUBTERRANEO EN PVC 1 1 /4"
8.3 DUCTO SUBTERRANEO EN PVC 2"
8.4 SISTEMA DE PUESTA A TIERRA
8.5 SUMINISTRO E INSTALACION DE LUMINARIAS
8.6 CAJA PREFABRICADA 40X40 CONCRETO CON TAPA
8.7 CAJA PREFABRICADA 30X30 CONCRETO CON TAPA
9 LIMPIEZA Y VARIOS
9.1 LIMPIEZA Y RETIRO DE SOBRANTES
9.2 ENSAYO DE PROCTOR MODIFICADO (Cada 50m3)
9.3 TOMA Y ROTURA DE CILINDROS
9.4 PLANOS RECORD DE CONSTRUCCION
9.5 CERTIFICACION RETIE EN ALUMBRADO PUBLICO Y PRUEBAS DE ALUMBRADO
SUBTOTAL
COSTO DITRECTO
A.I.U.
VALOR TOTAL
NOMBRE PROYECTO
DE OBRA
UN 1 3,130,000.00 3,130,000.00
UN 1 2,300,000.00 2,300,000.00
M2 5600 4,700.00 26,320,000.00
M2 1200 7,000.00 8,400,000.00
M2 3200 36,000.00 115,200,000.00
UN 15 260,000.00 3,900,000.00
ML 100 22,500.00 2,250,000.00
UN 20 12,900.00 258,000.00
ML 500 6,000.00 3,000,000.00
ML 160 20,000.00 3,200,000.00
UN 12 320,000.00 3,840,000.00
M3 920 18,200.00 16,744,000.00
188,542,000.00
-
M3 350 25,000.00 -
M3 2590 32,600.00 84,434,000.00
M3 2200 49,100.00 108,020,000.00
M3 300 24,000.00 7,200,000.00
M3 280 70,000.00 19,600,000.00
219,254,000.00
-
M3 15 430,000.00 6,450,000.00
M2 430 92,100.00 39,603,000.00
M3 16 670,000.00 10,720,000.00
UN 2 890,200.00 1,780,400.00
58,553,400.00
-
KLG 2500 8,700.00 21,750,000.00
M2 64 138,200.00 8,844,800.00
ML 194 93,000.00 18,042,000.00
UN 8 680,000.00 5,440,000.00
ML 8.4 85,000.00 714,000.00
ML 64 78,000.00 4,992,000.00
59,782,800.00
-
M2 2583 58,000.00 149,814,000.00
ML 973 75,000.00 72,975,000.00
M2 592 105,000.00 62,160,000.00
M2 433 105,000.00 45,465,000.00
M2 585 92,000.00 53,820,000.00
ML 100 55,000.00 5,500,000.00
M2 276 270,000.00 74,520,000.00
M2 202 270,000.00 54,540,000.00
M2 242 92,400.00 22,360,800.00
M2 351 650,000.00 228,150,000.00
ML 195 62,000.00 12,090,000.00
ML 153 86,000.00 13,158,000.00
M2 195 80,000.00 15,600,000.00
M2 216 225,000.00 48,600,000.00
858,752,800.00
UN 25 2,500,000.00 62,500,000.00
un 23 2,100,000.00 48,300,000.00
UN 11 910,000.00 10,010,000.00
M2 335 35,000.00 11,725,000.00
UN 70 25,000.00 1,750,000.00
UN 44 175,000.00 7,700,000.00
UN 6 282,000.00 1,692,000.00
UN 1 5,100,000.00 5,100,000.00
UN 2 1,500,000.00 3,000,000.00
UN 1 9,100,000.00 9,100,000.00
UN 1 3,800,000.00 3,800,000.00
UN 1 9,500,000.00 9,500,000.00
UN 1 3,800,000.00 3,800,000.00
UN 12 3,500,000.00 42,000,000.00
219,977,000.00
UN 7 1,700,200.00 11,901,400.00
ML 205 89,300.00 18,306,500.00
ML 120 65,100.00 7,812,000.00
UN 20 315,000.00 6,300,000.00
ML 230 16,000.00 3,680,000.00
ML 120 18,000.00 2,160,000.00
50,159,900.00
-
ML 350 13,200.00 4,620,000.00
ML 80 15,000.00 1,200,000.00
ML 90 26,800.00 2,412,000.00
UN 1 1,300,000.00 1,300,000.00
UN 33 323,000.00 10,659,000.00
UN 20 120,000.00 2,400,000.00
UN 20 110,000.00 2,200,000.00
UN 1 200,000,000.00 220,000,000.00
244,791,000.00
-
M2 1200 16,000.00 19,200,000.00
UN 5 34,000.00 170,000.00
UN 10 21,000.00 210,000.00
GLB 1 690,000.00 690,000.00
GLB 1 2,500,000.00 2,500,000.00
22,770,000.00
1,922,582,900.00
35% 672,904,015.00
2,595,486,915.00
Aréa de muroN. muro Largo Alto M cuadrado Total aréa
1 2.85 3 8.55
2 1.2 3 3.6
Dormitorio 3 2.85 3 8.55
1 4 1.95 3 5.85 26.55
2 1.35 3 4.05
3 1.95 3 5.85
Baño 4 0.6 3 1.8 11.7
2 3.15 3 9.45
3 1.2 3 3.6
Dormitorio 2 4 3.15 3 9.45 22.5
3 0.6 3 1.8
Cocina y 4 5.85 3 17.55
sala 5 0.6 3 1.8 21.15
Total muro 81.9