%Incidencia

ITEM DESCRIPCION UND Metrado HH/unit HH Totales


LB 01

1 CONSTRUCCION DE AMPLIACION PAD FASE I 23,416.38 100.00%


1.1 HITOS DE PROYECTO 0.00 0.00%
1.1.1 Hito de Inicio de la Construcción
1.1.2 Hito de Fin de la Construcción
1.2 MOVILIZACION Y OBRAS PRELIMINARES 40.00 0.17%
1.2.1 MOVILIZACION GLB 1.00 10.0000 10.00
1.2.2 CONSTRUCCION DE OFICINAS, ALMACENES Y COMEDORES GLB 1.00 20.0000 20.00
1.2.3 DESMOVILIZACION GLB 1.00 10.0000 10.00
1.3 CONSTRUCCION DE AMPLIACION DE PAD 23,376.38 99.83%
1.3.1 MOVIMIENTO DE TIERRAS 10,219.79 43.72%
1.3.1.1 TRABAJOS EN MATERIAL ORGANICO (TOP S0IL) 157.62 1.54%
1.3.1.1.1 DESBROCE DE MATERIAL ORGANICO (TOP SOIL) m3 4,635.95 0.0100 46.36 29.41%
1.3.1.1.2 CARGUIO DE MATERIAL INORGANICO (TOP SOIL) m3 5,563.14 0.0200 111.26 70.59%
1.3.1.2 TRABAJOS EN MATERIAL INORGANICO (PEAT) 7,069.21 69.17%
1.3.1.2.1 CORTE DE MATERIAL INORGÁNICO m3 252,471.87 0.0100 2,524.72 35.71%
1.3.1.2.2 CARGUÍO DE MATERIAL INORGÁNICO m3 302,966.24 0.0150 4,544.49 64.29%
1.3.1.3 TRABAJOS EN MATERIAL ROCA FIJA 2,992.96 29.29%
1.3.1.3.1 CARGUIO DE ROCA VOLADA m3 83,137.70 0.0100 831.38 27.78%
1.3.1.3.2 EXTENDIDO DE MATERIAL EN BOTADERO (ROCA VOLADA) m3 108,079.01 0.0200 2,161.58 72.22%
1.3.2 SISTEMA DE SUB DRENAJE 4,621.89 19.77%
1.3.2.1 INSTALACION DE TUBERIA DE SUB DRENAJE 1,751.33 37.89%
1.3.2.1.1 EXCAVACION PARA SUB-DRENAJE (ROCA SUELTA) m3 5,449.00 0.0100 54.49 3.11%
1.3.2.1.2 TUBERIA PERFORADA CPT-HDPE DE SUB-DRENAJE PARED DOBLE 200 m 4,233.30 0.0200 84.67 4.83%
1.3.2.1.3 TUBERIA PERFORADA CPT-HDPE DE SUB-DRENAJE PARED DOBLE 300 m 1,215.70 0.0300 36.47 2.08%
1.3.2.1.4 GEOTEXTIL NO TEJIDO DE 270 gr/cm2 EN SUB DRENAJE m2 32,694.00 0.0400 1,307.76 74.67%
1.3.2.1.5 COLOCACION DE GRAVA (3/4"- 3") EN SUB DRENES m3 5,358.91 0.0500 267.95 15.30%
1.3.2.2 RELLENO ESTRUCTURAL 2,870.56 62.11%
1.3.2.2.1 PRODUCCION DE RELLENO ESTRUCTURAL m3 95,685.20 0.0100 956.85 33.33%
1.3.2.2.2 COLOCACION DE MATERIAL CALSIFICADO PARA RELLENO ESTRUCTURAL
m3 (in 95,685.20 0.0200 1,913.70 66.67%
1.3.3 SISTEMA DE REVESTIMIENTO 6,932.63 29.66%
1.3.3.1 CAPA IMPERMEABLE (CLAY) 4,741.87 68.40%
1.3.3.1.1 EXTRACCION DE CLAY m3 26,840.76 0.0100 268.41 5.66%
1.3.3.1.2 CONFORMACION DE CAPA IMPERMEABLE (CLAY) E=0.30m m2 89,469.20 0.0200 1,789.38 37.74%
1.3.3.1.3 REFINE DE MATERIAL CLASIFICADO m2 89,469.20 0.0300 2,684.08 56.60%
1.3.3.2 BERMAS PERIMETRICAS 268.88 3.88%
1.3.3.2.1 PRODUCCION DE CLAY m3 3,563.06 0.0100 35.63 13.25%
1.3.3.2.2 CONFORMACION DE BERMAS m 1,476.11 0.0200 29.52 10.98%
1.3.3.2.3 REFINE DE MATERIAL CLASIFICADO m2 6,790.84 0.0300 203.73 75.77%
1.3.3.3 GEOMEMBRANA 1,921.89 27.72%
1.3.3.3.1 EXCAVACION DE ZANJA DE ANCLAJE P/GEOMEMBRANA m3 523.71 0.0100 5.24 0.27%
1.3.3.3.2 INSTALACION DE GEOMEMBRANA HDPE e= 2mm EN PAD Y BERMAS m2 95,046.90 0.0200 1,900.94 98.91%
1.3.3.3.3 RELLENO DE ZANJA DE ANCLAJE m3 523.71 0.0300 15.71 0.82%
1.3.4 SISTEMA DE COLECCIÓN DE SOLUCION LIXIVIADA 487.31 2.08%
1.3.4.1 INSTALACION DE TUBERIA DE SUB DRENAJE 487.31 100.00%
1.3.4.1.1 TUBERIA PERFORADA CPT-HDPE PARED DOBLE 100 MM m 6,464.80 0.0100 64.65 13.27%
1.3.4.1.2 TUBERIA PERFORADA CPT-HDPE PARED DOBLE 300mm m 1,499.50 0.0200 29.99 6.15%
1.3.4.1.3 GEOTEXTIL NO TEJIDO DE 270 gr/cm2 EN DRENAJE m2 8,997.00 0.0300 269.91 55.39%
1.3.4.1.4 COLOCACION DE GRAVA (3/4"- 3") EN SUB- DRENES m3 3,069.02 0.0400 122.76 25.19%
1.3.5 CAPA PROTECTORA (OVER LINER) 1,114.76 4.77%
1.3.5.1 EXTENDIDO DE OVERLINER SOBRE REVESTIMIENTO DE GEOMEMBRANA m3 111,475.80 0.0100 1,114.76 100.00%

DESCRIPCION
Schedule % Complete

Valores de Schedule calculados en la Sesión N° 08 del taller N°02:


"COMPRENDIENDO LAS CURVAS S & LOS HISTOGRAMAS DE OBRA EN LOS PROYECTOS"