Está en la página 1de 150

Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Telkom Mobile 2G3G4G Hardware


Installation Guide

Project Name: Telkom Mobile LTE Project


Department: Telkom Quality Department

Product-Process: Installation Guide V1.65

Prepared By: Shawn Jordaan / Samuel Reddy

Project Quality Plan Version Control

Version Date Author Change Description


Ver 0.1 16/11/2012 Edward Grobler Draft
Ver 0.2 8/01/2013 Shawn Jordaan Ver 0.2 Update
Ver 0.3 18/02/2013 Shawn Jordaan Update
Ver 0.4 3/03/2013 Shawn Jordaan Corrections and Added new ARP 4B 1½
CABINET Plinth
Ver 0.5 15/05/2013 Samuel Reddy Final ammendment of draft
Ver 0.6 03/04/2017 M. Stone \ J. Ver 0.6 Update
Koekemoer

FORWARD

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 1,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

TABLE OF CONTENTS
1 CHAPTER 1: INTRODUCTION
OBJECTIVE
1.1 SCOPE OF APPLICATION
1.2 INTERPRETATION AND EFFECTIVENESS OF THE GUIDE
1.3 PRECEDENCE
1.4 WIRING CODE
1.5 CODE OF PRACTICE AND REGULATIONS
1.6 STANDARD OF TELKOM SA LTD PROJECT INSTALLATION
2 CHAPTER 2:INSTALLATION OVERVIEW
2.1 SCENARIO 1- NEW SINGLE BAND ANTENNA FOR LTE
2.2 FIGURE 1
2.3 FIGURE 2
2.4 SCENARIO 2- NEW TRI-BAND ANTENNA TO SUPPORT 2G/3G/LTE
2.5 FIGURE 3
2.6 FIGURE 4
2.7 SCENARIO 3-NEW SITE BUILD SOLUTION (TRI-BAND, DUAL + SINGLE BAND)
2.8 FIGURE 5
2.9 FIGURE 6
2.10 FIGURE 7
2.11 FIGURE 8
2.12 SCENARIO 4-NEW & BILLBOARD SITE BUILD SOLUTION (2G/3G/LTE USING RRU)
2.13 FIGURE 9
2.14 FIGURE 10
3 CHAPTER 3:RFI, CIVIL WORK, AC
3.1 RFI (SITE READY FOR INSTALLATION)
3.2 CONTRACTOR RESPONSIBILITIES & INSTRUCTIONS
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 2,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

3.3 CIVIL WORK A


3.4 FIGURE 11 A, B - LAYOUT OF CONCRETE PLINTH-ARP CABINET
FIGURE 12 A, B, C - ARP 4B 1½ CABINET PLINTH
FIGURE 13- LAYOUT OF CONCRETE PLINTH-CK CABINET
FIGURE 14-CONCRETE PLINTH PROFILE-CK CABINET
3.5 CIVIL WORK B
3.6 ELECTRICAL CONNECTION / INSTALLATION
4 CHAPTER 4: SITE ESTABLISHMENT
4.1 SITE ESTABLISHMENT
5 CHAPTER 5: MATERIAL CHECKLIST
5.1 COLLECT MATERIAL FROM HUAWEI WAREHOUSE
THE MATERIAL OF ONE SITE INCLUDES THREE PARTS:-
5.2 UNPACK AND CHECK THE MATERIAL AFTER RECEIVED
5.3 LOCAL MATERIAL WHICH HUAWEI PURCHASES WITHIN REPUBLIC OF SOUTH AFRICA
3932
TABLE 1 LOCAL MATERIAL LIST (HUAWEI)
5.1 TABLE 1 LOCAL MATERIAL LIST (HUAWEI)
393732
5.2 LOCAL MATERIAL LIST, ADDITIONAL MATERIAL WHICH NEEDS TO BE PROVIDED BY THE
SUB-CONTRACTOR

5.3 TABLE 2 A, B, C, D LOCAL MATERIAL LIST (SUB CONTRACTOR)


6 CHAPTER 6: INSTALLATION OF LTE EQUIPMENT
6.1 APPROVED MINI SHELTERS (CK/ARP/HW & INDOOR) AND POSITION FOR LTE UPGRADE
454337
6.2 FIGURE 15 CK DIMENSIONS
6.3 FIGURE 16 CK CABINET CURRENT LAYOUT AND REQUIRED LAYOUT
6.4 FIGURE 17 CK CABINET 19” U RACK
6.5 FIGURE 18 OLD ARP 4T CABINET CURRENT LAYOUT AND REQUIRED LAYOUT
6.6 FIGURE 19 ARP CABINET 19” U RACK
6.7 FIGURE 20 NEW ARP 4T CABINET REQUIRED LAYOUT
6.8 FIGURE 21 CABINET & HALF DIMENTIONS
6.9 FIGURE 22CABINET & HALF REQUIRED LAYOUT
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 3,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

6.10 FIGURE 23INDOOR CABINET


6.11 FIGURE 24RPG DIMENTIONS
6.12 FIGURE 25HUAWEI CABINET REQUIRED LAYOUT
6.13 RECTIFIER TYPES AND LTE SOLUTIONS
Figure 26 Old ARP Rectifier (Battery technology J7) ............................................. 545245

Figure 27 Old ARP Rectifier (Battery technology J5) ............................................. 555346

6.13.1 Figure 28 ARP Rectifier (Grintek) .......................................................... 565447

6.13.2 Figure 29 CK Rectifier (Enertel) ............................................................ 575548

6.14 TDD ANTENNA, RRU SPECIFICATIONS WITH RCU CONFIGURATION SOLUTIONS.


6.14.1 2G3G4G Antennas ............................................................................... 585649

6.14.2 2G3G Antennas Dual Band................................................................... 595750

6.14.3 4G Antennas Single Band ..................................................................... 605750

6.14.4 4G Antennas Tri Band .......................................................................... 615851

6.15 2G RRU 3928


6.15.1 3G RRU 3804 ....................................................................................... 625952

6.15.2 4G RRU 3251 ....................................................................................... 626052

6.16 RCU CONNECTION SOLUTION


7 INSTALLATION PROCEDURE
7.1 PREPARATION OF EXISTING 2G/3G RAN EQUIPMENT
7.1.1 Installing 6U Rack .................................................................................... 646153

7.1.2 Figure 30 Position of 6U Rack .................................................................. 656255

7.1.3 Install LTE Equipment in 6U Rack............................................................. 666356

7.1.4 Reconnect Existing 2G/3G RAN Equipment .............................................. 666356

7.1.5 Connecting DC to the LTE Equipment ...................................................... 676457

Figure 32 .............................................................................................................. 676457

7.1.6 LTE Equipment in 6U Rack....................................................................... 676457

7.1.7 Connection to Rectifier DC Bars ............................................................... 686558

7.1.8 Connection DC Cables to DCDU-03 ......................................................... 686658

7.1.9 Connection DC Cables to BBU from DCDU-03 ......................................... 696659

7.2 CABLING REQUIREMENTS FOR POWER CABLES AND PGND CABLES


7.2.1 Power Supply Requirements of the DBS3900 ........................................... 706760

Input power requirement of the DBS3900 ............................................................. 706760

7.2.2 Installing the PDU (if applicable) ............................................................... 706760


2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 4,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

7.2.3 PDU Connection....................................................................................... 726962

7.2.4 Earthing BBU & DCDU-03 ........................................................................ 737063

7.2.5 Grounding Requirements of the BBU3900 ................................................ 747164

7.3 INSTALLING THE FE TRANSMISSION CABLE


7.3.1 Cabling Requirements for E1/T1 Cables (Required When E1/T1 Transmission Is Used)
747164

7.3.2 Transmission Requirements for the eNodeB ............................................. 757265

7.3.3 Requirements for ODF.............................................................................. 757265

7.3.4 Requirements for the Transmission Mode ................................................. 757265

7.4 INSTALLING THE INDOOR GPS COAXIAL CABLE AND GPS EMP DEVICE ON ENTRY PLATE
757365
7.4.1 Cabling Requirements for the eNodeB........................................................ 797669

7.4.2 Feeder Bending Radius ............................................................................ 797669

7.4.3 Installing the connectors on the external GPS cable ................................. 807770

7.4.4 Gland Plate layout ................................................................................... 817871

7.4.5 CK Gland Plate......................................................................................... 817871

7.4.6 ARP Gland Plate ...................................................................................... 827972

7.4.7 Roof Top Installations ............................................................................... 838073

7.4.8 Rooftop Installation and Waterproof .......................................................... 848174

7.5 INSTALLING THE RRU POWER CABLES TO DCDU-03


7.5.1 Install Fiber and power cable .................................................................... 888578

Fiber Cable Label ................................................................................................. 898678

7.5.2 Table 5 Fiber Cable Spec ......................................................................... 898678

7.6 ASSEMBLE ANTENNA AND RRU ON THE GROUND


7.6.1 Antennas and RRU Assembly .................................................................. 908779

7.6.2 Use of Heatshrink in Waterproofing .......................................................... 918880

7.6.3 Connector Waterproofing .......................................................................... 918880

7.6.4 Antenna Jumping Waterproofing ............................................................... 949183

7.6.5 Figure 46 a, b, c, Antenna Port Configuration............................................ 959284

7.6.6 RCU Connection ...................................................................................... 969385

7.6.7 Single Band Set Up .................................................................................. 989687

7.6.8 Dual Band RCU Set up ............................................................................. 999788

7.6.9 Tri Band RCU Set up .............................................................................. 1009889

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 5,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

7.6.10 Assembly RRU on Ground .................................................................. 1019990

7.6.11 Install new pole and Bracket (Optional) ............................................. 10310192

8 CHAPTER 8: INSTALL ANTENNA AND RRU ON TOWER


8.1.1 Figure 52 a, b notes the Lifting of RRU and Antennas onto Tower ........ 10410293

8.2 MOUNT RRU ON POLE


8.2.1 Mounting the RRU on the Pole ............................................................. 10510394

8.2.2 Safety Sling for the RRU ....................................................................... 10610495

8.2.3 Mounting the RRU on Pole ................................................................... 10710596

8.2.4 Mounting Antenna on Pole.................................................................... 10810696

8.3 CONNECTING THE LTE JUMPERS FROM ANTENNA TO RRU


8.4 CONNECTING THE RCU CABLE FROM RCU TO RRU
FIGURE 58
8.5 ADJUST AZIMUTH AND TILT OF ANTENNA
8.5.1 Azimuth and Tilts .................................................................................. 11110899

9 CHAPTER 9: INSTALL CLAMPS (FEEDER / FIBER / POWER CABLES


9.1 MOUNTING FEEDER CLAMPS
9.1.1 Comfy Clamp Installation .................................................................... 112110100

10 CHAPTER 10: VSWR TESTING


10.1 VSWR TESTING OVERVIEW
11 CHAPTER 11: INSTALL RRU POWER / FIBER CABLE
11.1.1 Install RRU Power Cable ................................................................ 118116106

11.2 CUT POWER AND GROUNDING CABLE AND INSTALLATION FOR RRU
11.3 INSTALL FIBRE CABLE
12 CHAPTER 12: LABELLING
12.1 INDOOR/OUTDOOR PART (TO BE DONE WITH REFERENCE TO PR-WR0099 FOR 2G/3G
LABELLING)
12.1.1 Labeling Indoor ............................................................................... 125122112

12.2 RRU POWER CABLE LABEL


12.3 AC/DC POWER SUPPLY LABEL
12.4 DC PANEL LABELS
12.5 POWER CABLE LABELS
12.6 FIBRE CABLE LABELS

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 6,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

12.7 LTE LABELING


13 CHAPTER 13: HARDWARE QA
ERROR! BOOKMARK NOT DEFINED.ERROR! BOOKMARK NOT DEFINED.122
13.1 HARDWARE QA
ERROR! BOOKMARK NOT DEFINED.ERROR! BOOKMARK NOT DEFINED.122
14 APPENDIX
ERROR! BOOKMARK NOT DEFINED.ERROR! BOOKMARK NOT DEFINED.122
15 INSTALLATION MANUAL APPROVALS
ERROR! BOOKMARK NOT DEFINED.ERROR! BOOKMARK NOT DEFINED.123
1 CHAPTER 1: INTRODUCTION .......................................................................................8
OBJECTIVE ...........................................................................................................................8
1.1 SCOPE OF APPLICATION ..........................................................................................8
1.2 INTERPRETATION AND EFFECTIVENESS OF THE GUIDE .............................................8
1.3 PRECEDENCE ..........................................................................................................8
1.4 WIRING CODE .........................................................................................................8
1.5 CODE OF PRACTICE AND REGULATIONS...................................................................9
1.6 STANDARD OF TELKOM SA LTD PROJECT INSTALLATION ....................................9
2 CHAPTER 2:INSTALLATION OVERVIEW ....................................................................10
2.1 SCENARIO 1- NEW SINGLE BAND ANTENNA FOR LTE ..............................................10
2.2 FIGURE 1 ................................................................................................................10
2.3 FIGURE 2 ................................................................................................................11
2.4 SCENARIO 2- NEW TRI-BAND ANTENNA TO SUPPORT 2G/3G/LTE ..........................12
2.5 FIGURE 3 ................................................................................................................12
2.6 FIGURE 4 ................................................................................................................13
2.7 SCENARIO 3-NEW SITE BUILD SOLUTION (TRI-BAND, DUAL + SINGLE BAND) .........14
2.8 FIGURE 5 ................................................................................................................14
2.9 FIGURE 6 ................................................................................................................15
2.10 FIGURE 7 ................................................................................................................16
2.11 FIGURE 8 ................................................................................................................17
2.12 SCENARIO 4-NEW & BILLBOARD SITE BUILD SOLUTION (2G/3G/LTE USING RRU) 18
2.13 FIGURE 9 ................................................................................................................18

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 7,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.14 FIGURE 10 ..............................................................................................................19


3 CHAPTER 3:RFI, CIVIL WORK, AC...........................................................................20
3.1 RFI (SITE READY FOR INSTALLATION) .....................................................................20
3.2 CONTRACTOR RESPONSIBILITIES & INSTRUCTIONS .................................................20
3.3 CIVIL WORK A .........................................................................................................21
3.4 FIGURE 11 A, B - LAYOUT OF CONCRETE PLINTH-ARP CABINET .............................22
FIGURE 12 A, B, C - ARP 4B 1½ CABINET PLINTH ..........................................................24
FIGURE 13- LAYOUT OF CONCRETE PLINTH-CK CABINET ..................................................27
FIGURE 14-CONCRETE PLINTH PROFILE-CK CABINET .......................................................27
3.5 CIVIL WORK B .........................................................................................................28
3.6 ELECTRICAL CONNECTION / INSTALLATION .............................................................28
4 CHAPTER 4: SITE ESTABLISHMENT ......................................................................31
4.1 SITE ESTABLISHMENT ............................................................................................31
5 CHAPTER 5: MATERIAL CHECKLIST ...........................................................................32
5.1 COLLECT MATERIAL FROM HUAWEI WAREHOUSE ...................................................32
THE MATERIAL OF ONE SITE INCLUDES THREE PARTS:- ......................................................32
5.2 UNPACK AND CHECK THE MATERIAL AFTER RECEIVED.............................................32
5.3 LOCAL MATERIAL WHICH HUAWEI PURCHASES WITHIN REPUBLIC OF SOUTH AFRICA
33
5.1 TABLE 1 LOCAL MATERIAL LIST (HUAWEI) .............................................................33
5.2 LOCAL MATERIAL LIST, ADDITIONAL MATERIAL WHICH NEEDS TO BE PROVIDED BY THE
SUB-CONTRACTOR .............................................................................................................34

5.3 TABLE 2 A, B, C, D LOCAL MATERIAL LIST (SUB CONTRACTOR)..............................34


6 CHAPTER 6: INSTALLATION OF LTE EQUIPMENT......................................................38
6.1 APPROVED MINI SHELTERS (CK/ARP/HW & INDOOR) AND POSITION FOR LTE UPGRADE
38
6.2 FIGURE 15 CK DIMENSIONS ....................................................................................38
6.3 FIGURE 16 CK CABINET CURRENT LAYOUT AND REQUIRED LAYOUT ......................39
6.4 FIGURE 17 CK CABINET 19” U RACK .....................................................................40
6.5 FIGURE 18 OLD ARP 4T CABINET CURRENT LAYOUT AND REQUIRED LAYOUT.......41
6.6 FIGURE 19 ARP CABINET 19” U RACK ...................................................................42
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 8,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

6.7 FIGURE 20 NEW ARP 4T CABINET REQUIRED LAYOUT ...........................................43


6.8 FIGURE 21 CABINET & HALF DIMENTIONS...............................................................43
6.9 FIGURE 22CABINET & HALF REQUIRED LAYOUT .....................................................44
6.10 FIGURE 23INDOOR CABINET ...................................................................................44
6.11 FIGURE 24RPG DIMENTIONS ..................................................................................45
6.12 FIGURE 25HUAWEI CABINET REQUIRED LAYOUT ....................................................45
6.13 RECTIFIER TYPES AND LTE SOLUTIONS ..................................................................46
Figure 26 Old ARP Rectifier (Battery technology J7) ..................................................... 46

Figure 27 Old ARP Rectifier (Battery technology J5) ..................................................... 47

6.13.1 Figure 28 ARP Rectifier (Grintek) .................................................................. 48

6.13.2 Figure 29 CK Rectifier (Enertel) .................................................................... 49

6.14 TDD ANTENNA, RRU SPECIFICATIONS WITH RCU CONFIGURATION SOLUTIONS. ..50
6.14.1 2G3G4G Antennas ....................................................................................... 50

6.14.2 2G3G Antennas Dual Band........................................................................... 51

6.14.3 4G Antennas Single Band ............................................................................. 51

6.14.4 4G Antennas Tri Band .................................................................................. 52

6.15 2G RRU 3928 ........................................................................................................52


6.15.1 3G RRU 3804 ............................................................................................... 53

6.15.2 4G RRU 3251 ............................................................................................... 53

6.16 RCU CONNECTION SOLUTION .................................................................................54


7 INSTALLATION PROCEDURE .....................................................................................54
7.1 PREPARATION OF EXISTING 2G/3G RAN EQUIPMENT..............................................54
7.1.1 Installing 6U Rack ............................................................................................ 54

7.1.2 Figure 30 Position of 6U Rack .......................................................................... 56

7.1.3 Install LTE Equipment in 6U Rack..................................................................... 57

7.1.4 Reconnect Existing 2G/3G RAN Equipment ...................................................... 57

7.1.5 Connecting DC to the LTE Equipment .............................................................. 58

Figure 32 ...................................................................................................................... 58

7.1.6 LTE Equipment in 6U Rack............................................................................... 58

7.1.7 Connection to Rectifier DC Bars ....................................................................... 59

7.1.8 Connection DC Cables to DCDU-03 ................................................................. 59

7.1.9 Connection DC Cables to BBU from DCDU-03 ................................................. 60


2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 9,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

7.2 CABLING REQUIREMENTS FOR POWER CABLES AND PGND CABLES .....................60
7.2.1 Power Supply Requirements of the DBS3900 ................................................... 61

Input power requirement of the DBS3900 ..................................................................... 61

7.2.2 Installing the PDU (if applicable) ....................................................................... 61

7.2.3 PDU Connection............................................................................................... 63

7.2.4 Earthing BBU & DCDU-03 ................................................................................ 64

7.2.5 Grounding Requirements of the BBU3900 ........................................................ 65

7.3 INSTALLING THE FE TRANSMISSION CABLE .............................................................65


7.3.1 Cabling Requirements for E1/T1 Cables (Required When E1/T1 Transmission Is Used)
65

7.3.2 Transmission Requirements for the eNodeB ..................................................... 66

7.3.3 Requirements for ODF...................................................................................... 66

7.3.4 Requirements for the Transmission Mode ......................................................... 66

7.4 INSTALLING THE INDOOR GPS COAXIAL CABLE AND GPS EMP DEVICE ON ENTRY PLATE
66
7.4.1 Cabling Requirements for the eNodeB................................................................ 70

7.4.2 Feeder Bending Radius .................................................................................... 70

7.4.3 Installing the connectors on the external GPS cable ......................................... 71

7.4.4 Gland Plate layout ........................................................................................... 72

7.4.5 CK Gland Plate................................................................................................. 72

7.4.6 ARP Gland Plate .............................................................................................. 73

7.4.7 Roof Top Installations ....................................................................................... 74

7.4.8 Rooftop Installation and Waterproof .................................................................. 75

7.5 INSTALLING THE RRU POWER CABLES TO DCDU-03 .............................................77


7.5.1 Install Fiber and power cable ............................................................................ 78

Fiber Cable Label ......................................................................................................... 79

7.5.2 Table 5 Fiber Cable Spec ................................................................................. 79

7.6 ASSEMBLE ANTENNA AND RRU ON THE GROUND ...................................................80


7.6.1 Antennas and RRU Assembly .......................................................................... 80

7.6.2 Use of Heatshrink in Waterproofing .................................................................. 81

7.6.3 Connector Waterproofing .................................................................................. 81

7.6.4 Antenna Jumping Waterproofing ....................................................................... 84

7.6.5 Figure 46 a, b, c, Antenna Port Configuration.................................................... 85

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 10,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

7.6.6 RCU Connection .............................................................................................. 86

7.6.7 Single Band Set Up .......................................................................................... 88

7.6.8 Dual Band RCU Set up ..................................................................................... 89

7.6.9 Tri Band RCU Set up ........................................................................................ 90

7.6.10 Assembly RRU on Ground ............................................................................ 91

7.6.11 Install new pole and Bracket (Optional) ......................................................... 93

8 CHAPTER 8: INSTALL ANTENNA AND RRU ON TOWER ............................................94


8.1.1 Figure 52 a, b notes the Lifting of RRU and Antennas onto Tower .................... 94

8.2 MOUNT RRU ON POLE ............................................................................................95


8.2.1 Mounting the RRU on the Pole ......................................................................... 95

8.2.2 Safety Sling for the RRU ................................................................................... 96

8.2.3 Mounting the RRU on Pole ............................................................................... 97

8.2.4 Mounting Antenna on Pole................................................................................ 97

8.3 CONNECTING THE LTE JUMPERS FROM ANTENNA TO RRU .....................................98


8.4 CONNECTING THE RCU CABLE FROM RCU TO RRU ...............................................99
FIGURE 58 .........................................................................................................................99
8.5 ADJUST AZIMUTH AND TILT OF ANTENNA.................................................................100
8.5.1 Azimuth and Tilts ............................................................................................ 100

9 CHAPTER 9: INSTALL CLAMPS (FEEDER / FIBER / POWER CABLES ..................101


9.1 MOUNTING FEEDER CLAMPS...................................................................................101
9.1.1 Comfy Clamp Installation ................................................................................ 101

10 CHAPTER 10: VSWR TESTING .....................................................................................104


10.1 VSWR TESTING OVERVIEW ....................................................................................104
11 CHAPTER 11: INSTALL RRU POWER / FIBER CABLE.................................................107
11.1.1 Install RRU Power Cable ............................................................................ 107

11.2 CUT POWER AND GROUNDING CABLE AND INSTALLATION FOR RRU .......................108
11.3 INSTALL FIBRE CABLE ............................................................................................111
12 CHAPTER 12: LABELLING ............................................................................................113
12.1 INDOOR/OUTDOOR PART ........................................................................................113
12.1.1 Labeling Indoor ........................................................................................... 113

12.2 RRU POWER CABLE LABEL ...................................................................................114


12.3 AC/DC POWER SUPPLY LABEL ..............................................................................114

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 11,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

12.4 DC PANEL LABELS .................................................................................................115


12.5 POWER CABLE LABELS ..........................................................................................116
12.6 FIBRE CABLE LABELS.............................................................................................118
12.7 LTE LABELING .......................................................................................................119
13 CHAPTER 13: HARDWARE QA ......................................................................................123
13.1 HARDWARE QA ......................................................................................................123
14 APPENDIX .......................................................................................................................123
15 INSTALLATION MANUAL APPROVALS .....................................................................124

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 12,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

1 CHAPTER 1: INTRODUCTION

Objective

The purpose of this guide is to define the hardware installation requirements for Huawei 2G3G4G
system. It also serves as a guide for partners to carry out engineering work. In case
of any conflict between this guide and other related processes or systems of Huawei
Technologies Co., Ltd the latter shall prevail.

1.1 Scope of application

This guide applies to TELKOM SA LTD LTE Project, for hardware installation guidance and as a
reference for quality check.

1.2 Interpretation and Effectiveness of the guide

Huawei Technologies Co., Ltd. has the power for the final interpretation of this guide. This guide shall
come into force from the date of issuance and shall prevail in the event of any discrepancy between
this guide and any old guide. For any questions, please consult Huawei Technologies Co., Ltd.

1.3 Precedence

Should there be any contradictory requirements between the specification, the drawings referenced and
other specifications that have been quoted, the order of precedence, from highest to lowest is:
a) Statutory and mandatory requirements
b) Actual specification - Telkom/Telkom Mobile
c) Referenced specifications - Telkom/Telkom Mobile
d) Workmanship standards, work instructions and guidelines of Telkom/Telkom Mobile
e) All contradictions or uncertainties shall be communicated with Huawei site
Management, who in turn will obtain clarity from Telkom/Telkom Mobile in writing before
installation commences.

1.4 Wiring Code

a) All electrical installations shall comply with the regulations stipulated in SANS
10142-1. Should a conflict exist between a requirement in this specification and
a requirement in the Wiring Code, then the more stringent of the specifications
shall be applicable.
b) An electrical Certificate of Compliance (CoC) shall be provided for the electrical
connection from the point of control to the cabinet input electrical terminals.
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 13,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

c) The Certificate of Compliance (CoC) shall be in the format of “Annexure 1” as


published in Government Gazette No. 31975 dated 6 March 2009.The certificate of
complianceof compliance is not valid unless all the sections have been completed correctly
and the test report in the format approved by the Chief Inspector is attached. (Refer to SANS
10142-1: 2009, edition 1.7, section 8.8 for the approved test report.)
d) The electrical installation inside the cabinet, inclusive of the AC and DC wiring,
shall be inspected and tested by a registered person who shall issue a
certificate of compliance in accordance with the requirements of SANS 10142-1.
e) The cabinet supplier shall accept full responsibility for the safety of the cabinet
in accordance with the requirements of section 10 of the Occupational Health
and Safety Act, no 85 of 1993.

1.5 Code of practice and regulations

a) All designs are to comply with the SABS codes of practice or National Building
Regulations.
b) SANS 10160: The general procedures and loading to be adopted in the design
of buildings.
c) SANS 10162: The Structural use of steel.
d) In the absence of coverage on any item in the SANS codes of practice the
Professional engineer shall base their assumptions on conclusive testing and
results based on experiments and research done in that field of design

1.6 Standard of TELKOM SA LTD Project installation

This guide serves as the standard for all regions and therefore there should be no deviation between
the regions.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 14,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2 CHAPTER 2:INSTALLATION OVERVIEW

Typical Installation Scenarios for Telkom Mobile project outdoor site upgrading

2.1 Scenario 1- New single band antenna for LTE

a) Existing hardware configuration: 1 BTS3900 cabinet, DCDU_01, DCDU_03, 1 BBU, 3 RFU, 3


3G RRU (RRU3804), 3 Dual-band Antenna
b) New 19'' 6U rack will be installed
c) BBU, DCDU_03B will be installed in the new 6U rack
d) 63A CB to be connected to 4G DCDU (DCDU_03B)
e) An(Extra ) rectifier module will be added
f) LBBP, UMPT and RRU 3251 will be installed

Output: Telkom Mobile/Huawei quality standard agreement or specs.


 1 Single-band antenna will be used on different sites according to Telkom Mobile requirement.
 Figure 1 & 2 Scenario 1 Single Band with Existing Dual band

2.2 Figure 1

2G/ 3G BBU

4G BBU

Figure 1

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 15,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.3 Figure 2

2G/ 3G BBU

4G BBU

Optical
fiber

Figure 2

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 16,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.4 Scenario 2- New Tri-Band antenna to support 2G/3G/LTE

a) Existing hardware configuration: 1 BTS3900 cabinet, DCDU_01/11A, DCDU_03/11B, 1 BBU,


3 RFU, 3 3G RRU (RRU3804), 3 Dual-band Antenna
b) New 19'' 6U rack will be installed
c) BBU, DCDU_03B/11B will be installed in the new 6U rack
d) 63A CB to be connected to 4G DCDU (DCDU_03B/11B)
e) An(extra) rectifier module will be added to existing rectifier
f) LBBP, UMPT and RRU 3251 will be installed
g) Existing Dual-band antenna will be recovered and delivered back to Huawei warehouse
h) Tri-band antenna will be installed for 2G, 3G and LTE

2.5 Figure 3
Figure 3 & 4 Scenario 2: Swop Existing Dual band with New Tri-band Antenna

2G/ 3G BBU

4G BBU

Figure 3

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 17,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.6 Figure 4

2G/ 3G BBU

4G BBU

Optical
fiber

Figure 4

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 18,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.7 Scenario 3-New site Build Solution (Tri-Band, Dual + Single Band)

a) Tri-band antenna or Dual-band + Single-band


b) LTE antenna will be used on different sites according to Telkom Mobile BBU, DCDU_03B/11B
will be installed in the new 6U rack, and 2G/3G will be installed as per normal standard
c) 63A CB to be connected to 4G DCDU(DCDU_03B/11B)
d) An(Extra ) rectifier module will be added to existing rectifier
e) LBBP, UMPT and RRU 3251 will be installed. UMPT and WBBP will be used to provide 4G
service.

Figure 5 & 6 Single+Dual band on 2G/3G/4GNew Build


Figure 7 & 8 Tri-band on 2G/3G/LTE New build

2.8 Figure 5

2G/ 3G BBU

4G BBU

Optical
fiber

Figure 5

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 19,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.9 Figure 6

2G/ 3G BBU

4G BBU

Figure 6

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 20,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.10 Figure 7

2G/ 3G BBU

4G BBU

Optical
fiber

Figure 7

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 21,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.11 Figure 8

2G/ 3G BBU

4G BBU

Figure 8

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 22,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.12 Scenario 4-New & Billboard Site Build Solution (2G/3G/LTE using RRU)

a) Tri-band or Dual-band Pipe Antenna with concealment solution will be used on different sites
according to Telkom Mobile
b) BBU, DCDU_03B will be installed in the new 6U rack, 2G/3G will be installed as per normal
standard
c) 63A CB to be connected to 4G DCDU (DCDU_03B)
d) An(Extra ) rectifier module will be added to the rectifier system
e) LBBP, UMPT and RRU 3251 will be installed
f) UMPT and WBBP will be used to provide 4G service.

Figure 9 & 10 Tri-band Omni on 2G/3G/LTE Swop and New Build

2.13 Figure 9

2G/ 3G BBU

4G BBU

Optical
fiber

Figure 9

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 23,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2.14 Figure 10

2G/ 3G BBU

4G BBU

Figure 10

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 24,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

3 CHAPTER 3:RFI, CIVIL WORK, AC

3.1 RFI (Site ready for installation)

a) Before the site establishment is held, the following actions shall be determined.
b) The site file shall be generated by the appointed Huawei Technologies Co., LTD. Contractor.
The site file should include the information as noted in the Annexure A TSSR Requirement and
Template
c) Site access must be arranged via Telkom Mobile PM for Telkom managed sites and via the site
acquisition manager (Huawei or Telkom Mobile Property management) for all non-Telkom
managed sites.
d) Obtain confirmation that the equipment has been delivered to site or contractor warehouse, via
email or any written format.

3.2 Contractor Responsibilities & Instructions

a) Contractors must be in possession of technical documents for all equipment, materials and
other operators requirements (MCO Specs etc)
b) Contractors must have all necessary tools and test equipment. It is the contractor’s
responsibility to collect site materials and all missing materials and/or damaged materials
shall be reported to the Huawei Site Engineer within 24hrs of you receiving the materials.
c) Test equipment must be calibrated as required and valid certificates must be available as proof
on request on Site and on test result documentation.
d) Contractors must have in their possession all the necessary tools and test equipment required
for the full installation.
e) Complete Health & Safety files and documents as per construction regulations must always
be with contractors and Site Engineer on sites.
f) Contractors must perform full site risk assessment and have this documented in the site file.
g) The contractors must perform complete site establishment and comply with all legal
requirements, this includes all methods and procedures supplied by Huawei Technologies Co.,
LTD.
h) Contractors must have completed Fall Arrest (climbing), Medical fitness and First Aid courses
and have copies of all certificates of training completed. This is required to be present on site
indicating date and validity of courses for all personnel climbing or working on the tower or at
height. Failure to produce such certification on request by either Telkom Mobile representative
or Huawei representative will result in either individual or entire build team been barred from
working further on the site until such compliance is met, this in non-negotiable.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 25,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

i) If any uncertainty arises regarding RF design and installation, the contractor needs to contact
the Huawei site engineer immediately and obtain clarification as well as procedure going
forward.
j) Contractors will be held liable for any damages on site and sites will only be accepted once all
snags have been cleared and certified as such by FSA.
k) Each contractor team will have a team leader per site and this person’s contact details shall be
updated in the site file.
l) The site file must be left in the container at all times during construction phase; this document
shall remain in the container after site handover.
m) The team leader will be responsible for the quality and progress of work to be carried out.
n) The team leader will inspect site and complete the quality checklist (Internal Quality) on
completion of all work.

3.3 Civil work A

a) All civil work shall comply with the document called Specification for Civil
Engineering Works associated with the Installation of Underground Telecommunications
Plant SPEC-0325. Note installation of street distribution cabinet (SDC) for similar reference to
the Telkom Mobile RAN Cabinet. All materials required and specified in SPEC-0325 shall be
provided by the service provider as part of the end –to-end solution.
b) In using this installation guide, the service provider and its sub-contractors shall comply with the
requirements stipulated for all parts of the civil project undertaken at the site. Huawei shall
through the relevant Telkom Mobile Property Management arrange and comply with all
statutory requirements of site work such as, but not limited to: way leaves, servitudes, work plans
etc.
c) The Huawei appointed sub-contractor shall prepare the additional materials required for the
installation of the RAN site according to the Technical Site Survey Report.
d) A plinth of the dimension stated in the TSSR for the relevant cabinet as per the site summary,
shall be prepared and installed in an industry approved manner and according to the
SPEC-0325.
e) All duct and pipe work shall be installed and fixed firmly in position (when required) according to
requirements of the plinth prior to the area been boxed and made ready for casting. NB.
Overhead installations where the feeder cables does not go underground do not require
underground installation of conduit for such purposes (this is determined by the technical site
survey)
f) The area to be used for the plinth shall be leveled, excavated (if required) and compacted, to
the correct compaction level. As required according to the DCP levels in the Telkom Spec and
according to the requirements of the plinth dimension, prior to the installation of the boxing.
g) The plinth dimension shall then be firmly boxed and the re-enforcing mesh installed as per
dimensional requirements of the plinth.
h) The preferred method to install the mounting bolts is as follows:

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 26,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

i. Galvanized threaded mounting down bolts (M16) shall be inserted at exactly the correct
positions as per defined cabinet on six positions and held in place with a removable position jig
(a jig shall be used to ensure that the correct mounting positions are maintained at all times
during plinth construction).
ii. An alternative and less preferred method is to install the fixed mounting bolts using chemical
anchor installation method once the cabinet plinth is cast and in has cured to minimum
requirements.
i) Maximum use must be made of ready-mixed concrete, with strength of 25 Mpa after 28 days,
supplied by a reputable concrete supplier and delivered in agitator trucks. Whichever method of
mixing is used, the total delivered period must not exceed 3 hours.(See SANS 878 /SABS 878).
The Local Mixing Machine method can be adopted, with the RAN installation manager’s
approval, if ready mixed concrete is not available or the terrain is inaccessible for agitator
trucks.
j) Whilst pouring / placing the concrete, ensure even spread and proper flow of the concrete by
using vibrators or suitable rods/sticks to facilitate proper flow and filling to ensure no air-pockets
or holes are caused or appears in the walls or other parts of the plinth.
k) Where project timelines do not permit the required curing time of the concrete plinth, alternative
curing practices may be sought and implemented using civil engineered practices. These
practices may not be implemented if not approved and signed off by a registered civil engineer.
All practices must be guaranteed to provide the correct strength and grade of installation.
Alternative practice would be to deploy a precast plinth.
l) Once the concrete has set then the installation jig may be removed and the plinth neatened
and made ready for the installation of the cabinet (removal of excess cement and runoff)
m) The approved layout for the plinth is noted in Figures 11 and 12 for ARP cabinets and Figures
13 and 14 for CK cabinets.

3.4 Figure 11 a, b - Layout of Concrete Plinth-ARP Cabinet

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 27,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 11 a

Figure 11 b

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 28,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 12 a, b, c - ARP 4B 1½ CABINET Plinth

Figure 12 a,

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 29,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 12 b

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 30,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 12 c

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 31,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 13- Layout of Concrete Plinth-CK Cabinet

Figure 13

Figure 14-Concrete Plinth Profile-CK Cabinet

Figure 14

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 32,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

3.5 Civil work B

a) In certain circumstances, and only at Telkom owned sites, the armored


electrical connection cable between the cabinet and the boundary box shall be
installed in the appropriate trench as described in the SPEC-0325.
b) In all installations and unless otherwise arranged with Telkom Mobile RAN Installation all
armored AC cable shall be buried an effective 600mm deep in the earth, a slow
bend cable duct of 75mm diameter shall be used on the points where the cable
exits the earth on either side.
c) The installation of the concrete sleeve around the armored cable shall only take place with the
written approval of TMRAN Installation and Property department at sites that are indicated in
the technical site survey, as high risk for cable theft.
d) The AC cable in this trench will be covered in its entirety by a 200mm x 200mm
concrete surrounding from the boundary box to the plinth. Only the AC power
cable and the associated copper earth continuity cable are to be installed with
concrete protection.
e) The AC power cable and earth continuity cable shall be physically separated in
the concrete cable trench by 50mm horizontally and/or 75mm vertically. The AC
cable shall be covered by a galvanized metal duct of appropriate size from the
point the cable exits the concrete to the point it enters the electrical boundary box
or Telkom Mobile cabinet.
f) Installation of the approved Telkom Mobile RAN Outdoor Shelter on a roof top will require the
use of weight bearing and distribution beams. The material and length of the beams requires
approval from a structural engineer and is determined on a per site basis. The complete site
design and clearance certificates by a structural engineer for such installation are required prior
to installation of the beams.
g) The minimum allowable I-Beam size to be used is IPE140; larger I-Beams are
permitted to be used.
h) The I-Beam size is subject to the length of the beam, therefore the length of the
beam is to be calculated by spreading the load in such a manner that the
maximum allowable weight per square meter of the rooftop is not exceeded, this is determined
by a qualified civil engineer on a per site basis.
i) All areas disturbed by the installation of the Telkom Mobile RAN site, such as
ducts, cabling, trenching etc. shall be re-instated to the an appropriate level of original neatness
as determined appropriate by the Telkom ILO. This shall form part of the final quality
acceptance of the site and be determined during static acceptance.
j) All civil work shall be signed off as acceptable and require approval from a registered structural
engineer.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 33,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

3.6 Electrical Connection / Installation

a) The AC electrical connection of the Telkom Mobile RAN site is part of the end-to-end
solution completed by the service provider: Huawei.
b) The service provider is responsible (directly or through their appointed sub-contractors) to
supply and install the AC electrical cable and associated connection requirements
between the mains point of supply and the Telkom Mobile RAN cabinet. A single point of
disconnect for the supply is required and shall be installed by the service provider, the single
point of disconnect shall be external to the RAN cabinet.
c) The specification of the cable and associated protective circuit breakers is noted in the
Telkom Mobile RAN cabinet specification. The values stated in this document may change
only under correction by a Telkom Mobile RAN Installation team member or by a suitably
qualified and responsible person as is governed by SANS 10142-1 (this will have to first be
communicated to Telkom Mobile management, in writing, before acceptance).
I. Changes to the components of the electrical connection may be implemented due to cable
lengths and associated voltage drops.
II. Larger electrical loads in the cabinet etc.
III. All changes shall be signed off as correct and compliant as per SANS 10142-1 by a competent
individual.
d) Total Facilities Management Company (TFMC) is responsible for the connection (to the
main distribution board) and approval of all electrical installations on Telkom owned sites.
The service provider shall remain responsible for the electrical installation of the AC supply
cable (under the control and management of an ECB appointed competent person) and the
associated protection devices and distribution board, but shall make use of TFMC to
perform the connection
e) The service provider through their sub-contractor is responsible for the connection and the
approval of the entire electrical installation associated with the Telkom Mobile RAN
installation at all other non-Telkom sites.
f) All electrical connections and or changes are to be approved and an electrical certificate of
compliance with test report in the approved format is to be delivered to the ILO and Telkom
acceptance officer. A copy of the certificate is to remain in the site file.
g) Installation of the RAN equipment inside Telkom equipment rooms may be required. If the
equipment is installed inside the Telkom equipment room then power to the equipment
shall be obtained from the Telkom DC power system on site. All planning of the DC power
shall be performed by Telkom SA NIP department; all installations shall be according to
plan and as per Telkom DC standard (ST-AP0015). The Telkom ILO shall apply for the
planned work ref and the planned break ref prior to any work and or connection to the DC
power reticulation on site. Note. The service provider through their sub-contractor is
responsible for the connection and the approval of the entire DC electrical installation
associated with the Telkom Mobile RAN installation.
h) On outside installations on Telkom owned sites, once the electrical reticulation is installed
(under the guidance and control of ECB approved competent person) according to
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 34,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

standard and approved by a competent person, a break ref will be applied for by TFMC
according to Telkom procedures, in order to perform the physical connection of the AC
power to the Telkom Mobile RAN equipment.
i) At sites that are not controlled by Telkom, the Huawei site manager shall arrange via the
Telkom Mobile PM that the relevant authority is notified of the intent to connect the
electrical power, all required arrangements shall be made prior to connection.
j) A SANS 1507 approved fully sheathed armored electrical cable of size and amount of cores is
to be installed by direct burial method in the earth at a effective depth of 600mm from the
site electrical boundary box to the Telkom Mobile RAN cabinet AC distribution board(at sites
that permit such installation method). The trench excavation, cable burial and
re-instatement of trench shall be completed as per SPEC-0325.
k) At certain sites the electrical cable may be required to be installed in concrete protective
sleeve, this would be defined at the TSS. At such sites the electrical cable shall be installed in
a galvanized conduit at points where it exits the concrete and enters either the boundary box
or the cabinet.
l) The electrical cable armor should be connected with cable glands on either side of the
installation, the armor shall be bonded to the site earth on one side of the cable using a
correctly sized earth tag installed on the gland and then electrically bonded to the site earth
in the boundary box by min. 6mm² sheathed green and yellow stranded copper cables with
correctly sized ring lugs.
m) A 6mm² stranded sheathed (green/yellow) earth continuity conductor shall be installed
between the cabinet electrical AC distribution board and the boundary box earth to
ensure that the same earth continuity is maintained. The earth tag shall have correctly
sized ring lugs installed on either side and these shall be connected to the site earth on
the boundary box side and the cabinet AC DB on the other side.
n) On rooftop sites where the installation of the generator cannot be located in close
proximity to the cabinet, then the generator plug shall be extended to an appropriate
position near to the generator installation. All cabling and cable routes shall be designated
in the technical site survey; this shall be installed by the service provider. The use of the
Telkom Mobile approved generator change over switch shall be required, (supplied by
Huawei). The switch shall be installed in a maintenance friendly, easily accessible position
that has been approved by the building owner.
o) The earth cable shall remain physically separate to the electrical supply at all points and
shall not be installed in a metal pipe at any point in the installation. All conduit piping for
electrical cabling is to be sealed with resin once the cables are installed.
Roof tops sites or sites that require cable to be installed above ground shall incorporate fully
protected (enclosed) gantry for the entire route of installation. This gantry shall be bonded to the site
earth.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 35,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

4 CHAPTER 4: SITE ESTABLISHMENT

4.1 Site establishment

a) Although not chronologically in order this is an essential process before civil and electrical work
can be performed.
b) Every Telkom owned site must have a work authorization procedure (WAP) and Co-location
approval created by Huawei PMO
c) It is the service providers (Huawei) Site Engineer’s responsibility to arrange the WAP and
Co-location approval
d) A WAP needs to be arranged and signed prior to the start of site construction by contractor. (At
least 2 days before work is to commence).
e) A work ref for the installation of the Huawei single, dual, tri-band site will be arranged for
Telkom owned sites A break ref for the cutover of the Huawei single, dual, tri-band site will
be arranged for the Telkom owned sites by Huawei.
i. The following points need to be clearly understood by the contractor before any work
commences, a site file with a copy of the technical site survey report, copy of the executable file
and must allow the contractor to understand the following details:
i. Antenna height, directions and tilts.
ii. Cable routing from tower to building or outdoor unit.
iii. Cable routing for the AC power cables from the AC boundary box to the Telkom
Mobile RAN cabinet
iv. Placing of cabinet - outside or inside exchange (includes MCO, billboards and
non-Telkom sites)
v. Cable routing inside building of both feeder cable and AC cables.
vi. Power connection, primary and back-up (generator) power
vii. Time constraints for building of the site.
f) For rooftop sites and shared sites, special requirements from property owners and share
parties should be acknowledged and access should be arranged well in advance via Huawei site
management (Telkom Mobile Property) and the relevant owners. No work is to be started without
the relevant authorization and documentation in place.
g) Ensure that you have the approval certificate from the Telkom/Telkom Mobile PMO noting the
approval to go ahead and begin the installation of the equipment.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 36,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

5 CHAPTER 5: MATERIAL CHECKLIST

5.1 Collect material from Huawei Warehouse

The material of one site includes three parts:-

a) Equipment and material coming directly via the service provider from China,
b) Local Material which Huawei purchases within Republic of South Africa,
c) Additional Material which needs to be provided by the sub-contractor,

5.2 Unpack and check the material after received

a) Unpack all the boxes on site and confirm if correct equipment has been delivered.
b) Unpacking must be stopped immediately once inconsistent box no. is found or if any material is
damaged. Contact Huawei Material Manager in such cases.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 37,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

5.3 Local Material which Huawei purchases within Republic of South Africa

5.1 Table 1 Local Material List (Huawei)

Table 1

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 38,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

5.2 Local Material list, Additional Material which needs to be provided by the
sub-contractor

5.3 Table 2 a, b, c, d Local Material List (Sub Contractor)

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 39,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Table 2 a

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 40,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 41,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Table 2 b

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 42,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Table 2 c

Table 2 d

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 43,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

96 CHAPTER 6: INSTALLATION OF LTE EQUIPMENT

9.16.1 Approved Mini Shelters (CK/ARP/HW & Indoor) and position for LTE Upgrade

Shelter Types and specifications

9.26.2 Figure 15 CK Dimensions

Figure15

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 44,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.36.3 Figure 16 CK Cabinet Current Layout and Required Layout

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 45,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 16

9.76.4 Figure 17 CK Cabinet 19” U Rack

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 46,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 17

9.86.5 Figure 18 Old ARP 4T Cabinet Current Layout and Required Layout

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 47,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 18

9.96.6 Figure 19 ARP Cabinet 19” U Rack

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 48,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 19
Formatted: Centered

9.106.7 Figure 20 New ARP 4T Cabinet Required Layout

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 49,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 20

9.116.8 Figure 21 Cabinet & Half Dimentions

Figure 21

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 50,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.126.9 Figure 22Cabinet & Half Required Layout

Figure 22

9.136.10 Figure 23Indoor Cabinet

Figure 23
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 51,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.156.11 Figure 24RPG Dimentions

Figure 24

9.166.12 Figure 25Huawei Cabinet Required Layout

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 52,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 25

9.176.13 Rectifier Types and LTE solutions

Note. When the New Rectifier Module is installed ensure and verify that it is not installed on the same
phase as the Shelter Aircon supply phase. E.g. ARP uses the Blue/3rd phase to provide the Aircon unit
with power. CK uses the Red/1st phase to provide the Aircon unit with power. The phases not used may
be used to for the additional module. When the site is supplied by a single phase AC power supply, the
Rectifier module position may be installed in any unused position.

Figure 26 Old ARP Rectifier (Battery technology J7)

Figure 26

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 53,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 27 Old ARP Rectifier (Battery technology J5)

Figure 27

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 54,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.17.16.13.1 Figure 28 ARP Rectifier (Grintek)

Figure 28

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 55,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.17.26.13.2 Figure 29 CK Rectifier (Enertel)

Figure 29

NOTE: ABOVE ILLUSTRATION FOR RECTIFIER MODULE IS ONLY VALID WHERE


THE AIRCON UNIT SUPPLY PHASE IS WHITE/YELLOW OR BLUE PHASE, OR
SINGLE PHASE AC SUPPLY. VERIFY AIRCON PHASE SUPPLY AND INSTALL MODULE IN
RECTIFIER ON OTHER PHASE THAN AIRCON SUPPLY PHASE.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 56,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.186.14 TDD Antenna, RRU specifications with RCU configuration solutions.

The following specifications are related to the LTE Rollout and are for referencing purposes.

9.18.16.14.1 2G3G4G Antennas

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 57,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.18.26.14.2 2G3G Antennas Dual Band

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 58,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.18.36.14.3 4G Antennas Single Band

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 59,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.18.76.14.4 4G Antennas Tri Band

9.196.15 2G RRU 3928

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 60,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.19.16.15.1 3G RRU 3804

9.19.26.15.2 4G RRU 3251

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 61,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

9.206.16 RCU Connection Solution

107 INSTALLATION PROCEDURE

The following describes the installation procedure of 4G Equipment inside the cabinet:

10.17.1 Preparation of existing 2G/3G RAN equipment

Ensure that a CR ref is available prior to going to site. After obtaining an Entry ref from Front Office you
are allowed to enter shelter.
a) Start with loosening the existing fly leads so that pre sweeps can be done (refer to 7.1.1 a),
thereafter loosen Optical Fibres, RRU DC cable, BTS/DBS DC cable, TX cables routed on,
behind and above BTS. Secure all cables temporarily out of the way when BTS is lifted.
b) Loosen BTS base plate secured on the shelter shelf.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 62,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.1.17.1.1 Installing 6U Rack


Ensure that when lifting Existing RAN; prevent damage and loss on the equipment. Note. CR ref
must be activated, switch off RAN, disconnect cables and secure all cables temporarily out of the
way when BTS is lifted.

a) Use Site Master to perform Pre-sweeps, VSWR and DTF. Save and add to
As build document. Report sweeps above limit (1.35) to the Huawei Site Engineer that
the info can be sent to Maintenance Department for Rectification. Notify Huawei SE of
sweeps above 1.5 as this needs to be corrected immediately by Huawei MS prior to
upgrade
b) Lift the BTS and base plate high enough for the 6U rack to fit underneath.
c) Install new 6U Rack below BTS. Note. Ensure anti-static plate is between the 6U rack and
shelter shelf and holes correctly align. Ensure that there is bonding between the 6U Rack
and the cabinet earth
d) When installing the bolts ensure the washers is reinstalled.
e) Secure the BTS Base plate on the 6U Rack.
f) Re-secure BTS to BTS base plate.
g) Install DBS LTE BBU in 6U rack on top. (2nd hole from top)
h) Install DCDU-03 below LTE BBU; leave 1 whole separation between DCDU and BBU.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 63,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.1.27.1.2 Figure 30 Position of 6U Rack

Figure 30

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 64,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.1.37.1.3 Install LTE Equipment in 6U Rack


Handle equipment with care as not to bump and damage.
a) Use supplied cage nuts at applicable securing points on the 6U rack.
b) Install DBS LTE BBU in 6U rack on top. (2nd hole from top)
c) Install DCDU-03 below LTE BBU, leave 2 holes separation between DCDU and BBU.

Figure 31

10.1.47.1.4 Reconnect Existing 2G/3G RAN Equipment


a) Use caution when re-routing and reconnecting jumpers and optics to BTS3900.
b) Use Site Master to perform Post-sweeps, VSWR and DTF. Save and add to As build
document. If Post-sweeps FAIL (Limit 1.35) after Pre-sweeps passed, the installations
contractor will be held responsible for rectifications to be within the Limit 1.35.
c) Re-route BTS and DBS DC cables, between Rectifier and BTS so that the DC cables enters
the BTS from below of BTS, thru 6U rack and re-connect if DC cables aren’t long enough.
Alternatively DC cables may be routed as per original route.
d) Reconnect TX cables to UFLP, UELP, routing may remain the same, above the BTS cabinet.
e) 3G Optical Fibre cable routing remains as per original installation.(Note additional
slack must be re-secured with Velcro straps behind BTS cabinet). 3G DC cable routing remains

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 65,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

as per original installation. (Note additional slack must be rerouted as not to have coils,
excessive bends/kinks. Preferably a neat loop over the 2G/3G BBU leading into the DCDU-03.
f) Re-route ½’fly leads between the GRFU/MRFU (2G) Radios and the Entry plate as not to
exceed bending radius (20 times the cable core) and secure neatly.

10.1.57.1.5 Connecting DC to the LTE Equipment

Ensure qualified personnel perform reticulation and use caution when connecting on the Rectifier. Note
Power related connections must be accompanied with an electrical/ DC COC.

a) Route 25mm^2 DC cable between DCDU-03 and Rectifier. Switch off all power then connect
onto the positive and negative bar behind rectifier using applicable lugs (pin lugs).

Figure 32

10.1.6 LTE Equipment in 6U Rack

Formatted: Heading 3,Heading 3 Char

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 66,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Upgraded Reticulation Original Reticulation


Figure 32

a) Once DC routing and connection to the Rectifier DC bars has been connected. The Rectifier
front & top cover needs to be removed for installation of the 63ACB (on the approved TSSR
position) and upgrading the 6mm^2 cable between the CB and DC power bar at the back of
the Rectifier.

10.1.77.1.6 Connection to Rectifier DC Bars

Figure 33

a) Connect DC cables on the DCDU-03 side, using correct OT lugs, Single-/double


whole lugs are accepted. Note, all securing bolts must be properly tightened, even if unused.
(As prevent surges/ induction between points)

10.1.87.1.7 Connection DC Cables to DCDU-03

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 67,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 34

a) Supply to BBU from DCDU. Using provided power cable in the Huawei kit, screw in the
Positive and Negative cables to the DCDU-03 on position “LOAD 7” or “LOAD 8”. (Far right
when facing the equipment)

10.1.97.1.8 Connection DC Cables to BBU from DCDU-03

Figure 35

10.27.2 Cabling Requirements for Power Cables and PGND Cables

a) The power cables and PGND cables must be routed in compliance with the engineering
design and general cabling specifications. If the cable is not long enough, replace the cable.
Do not add connectors or solder joints to lengthen the cable.
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 68,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

b) The cables must be insulated if they are bound and routed on the metal cable tray.
c) Fuses or switches are not allowed on the cables.
d) The -48 V power cable and the GND cable must be bound together. Both ends of the ground
cables must be anti-corrosive and anti-rust.
e) Connections of the ground cables must be secure.
f) The low-voltage AC power cable for the base station must be led through a metallic conduit
and buried in the ground for at least 50 m before it is led into the equipment room. If the AC
power cable is shorter than 50 m, it must be routed under the ground. If such cables are routed
overhead and led into the room, surge protection for the connectors of the AC power cables
are seriously affected.
g) The PGND cable must be buried in the ground or routed indoors.

10.2.17.2.1 Power Supply Requirements of the DBS3900

To ensure the proper operation of the power system of the DBS3900, the power supply of all the
functional modules must comply with the related specifications. The table below lists the power supply
requirements of the DBS3900.

Input power requirement of the DBS3900

Table 3

10.2.27.2.2 Installing the PDU (if applicable)

A PDU is only required if no space is available on the Rectifier DC side for the required CB
upgrade to a 63A CB for the4G DBS. The existing equipment must be relocated to an alternative
source (which will be the PDU), e.g. SAR-F, T5C, CSR, DC light, CK25 etc. Note, if PDU is required the
PDU supply CB must be 63A. 2 x 63A CB’s will be installed in the rectifier. Note Power related
connections must be accompanied with an electrical/DC COC.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 69,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

a) Confirm PDU kit is complete. Contents in the package, and check the quantities (PDU, 4M
red/black cables, 1*63A breaker, lugs and heat shrink)

Figure 36a Figure 36b

Figure 36c Figure 36d

b) Remove the front cover of the PDU. Install the PDU on the top on the left side front
19” U rack frame. Install the 25mm^2 blue and red DC cables on the 1st 63A CB on
the Rectifier

Figure 36e Figure 36f

d) Remove the front and top cover of the Rectifier system. Use 1*63A to replace the marked red
breaker for PDU (the breaker is in the PDU kit). Use 1*63A to replace the marked orange
breaker for LTE (subcontractor offer the breaker). Connect the blue and red cable from the
PDU to the back of the rectifier system. Connect the blue and red cable from the back of the
rectifier system to the breaker on the front panel of the rectifier system.
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 70,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.2.37.2.3 PDU Connection

Figure 37 a Figure 37 b

Figure 37 c Figure 37 d

a) Disconnect the equipment from the breakers on the Rectifier System and connect the
equipments on the PDU breakers according to the label on the PDU and the appropriate
breakers. Switch on the breakers in the rectifier system and the PDU breakers. Measure the
voltage on the Rectifier breakers and the PDU breakers to make sure we are receiving the
right voltage for the equipments. Install the PDU cover and Label the PDU front panel and the
Rectifier front panel as shown on the picture.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 71,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 37 e Figure 37 f

Figure 37 g Figure 37 h

b) Unforeseen complications might be possible and treat as follow; If the power cable of existing
equipment which is connected to the Rectifier, is too short to be re-routed to the PDU, leave in
installed position. If the power cable of the equipment installed in the left panel of the shelter
is long enough to reach the PDU; then install the equipment to the PDU. In some ARP shelters,
you will find 2 x 63A breakers and usually 1x 63A breaker is not used. Use the spare 63A
breaker to install the LTE DBS, do not install PDU.

10.2.47.2.4 Earthing BBU & DCDU-03

Ensure after connecting the earthing, continuity testing is performed between equipment
and main earth. Minimum earth cable size 6mm^2 green/yellow insulation. Ensure appropriate lug
sizes are used.
a) For the DCDU, multiple earth points are available, 1st option is in front next to The DC
connection point (Most right bottom corner in front). 2nd option is to use the back earth point
(Most left corner on the back of the DCDU). Note on both options, 2 securing earth points are
available.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 72,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

b) For the BBU, as the 6U rack is painted, an earth on the securing screws are not allowed. There
for the only valid earth point is on the right side of the BBU, again 2 securing earth points is
available.
c) After connecting on the BBU & DCDU side the earth, choose the Primary equipment earth
point, there after install earth between Primary and Main earth bar allocated at the
entry plate. E.G. Primary is DCDU, Secondary is BBU, connected at the BBU, route neatly to
the back of the DCDU at the earth point.
d) Connect the BBU earth on the 1st earth point; on the 2nd earth point connect Earth cable, route
neatly to the earth bar and secure properly.

10.2.57.2.5 Grounding Requirements of the BBU3900

The PGND (earth) cable of the BBU3900 must be copper-based and insulated with the green and
yellow plastic jacket, and the cross-sectional area of the cable must be at least 6 mm 2. The grounding
resistance of the BBU3900 must be less than 10. When the BBU3900 is installed in the equipment
room, the PGND cable must be connected to the protection ground bar of the equipment room. When
the BBU3900 is installed in outdoor cabinets such as the APM30H, the PGND cable of the BBU3900
must be connected to the ground bar in the cabinet. When the BBU3900 is connected to the RRU, do
not use optical cables that have strengthening ribs.

10.37.3 Installing the FE transmission cable

Note. Standard indoor length CAT5e cable is supplied with RJ45 connectors on both sides.
a) Connect 1 point to the position FE/GE0 on the LMPT/UMPT board in the BBU, route neatly to the
Cisco Router (CSR).
b) Connect remaining point to approved position on the CSR as per TSSR,
positions may vary on each site.
c) Additional slack must be neatly coiled and properly secured on the indoor wire way grid.

10.3.17.3.1 Cabling Requirements for E1/T1 Cables (Required When E1/T1

Transmission Is Used)

a) E1/T1 cables must be routed according to the associated engineering design drawing and
general cabling specifications.
b) E1/T1 cables must not be routed overhead outside an equipment room.
c) E1/T1 cables can be routed underground through PVC tubes outside an equipment room.
d) An E1/T1 cable must be grounded by using a surge protection box if its length exceeds 5 m
outside an equipment room.
e) Sufficient slack is provided for E1/T1 cables at turns.
f) The reserved wires in an E1/T1 cable can be used for grounding in an equipment room.
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 73,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.3.27.3.2 Transmission Requirements for the eNodeB

a) Before the site construction, the transmission devices and auxiliary devices must be prepared
based on the practical application. Transmission requirements of the eNodeB site involve the
optical distribution frame (ODF), and transmission mode.

10.3.37.3.3 Requirements for ODF

If optical transmission is applied, and the optical cables on the eNodeB side are connected to the
transmission device through the ODF. The requirements for the ODF are listed as follows:
a) The delivered transmission cables and connectors match the connectors on the ODF on the
transmission device side.
b) Before you install the eNodeB, the ODF is installed and external optical cables are connected
to the ODF.
c) It is recommended that the copper wires be used to connect the ODF and the ground bar of
the equipment room.

10.3.47.3.4 Requirements for the Transmission Mode

a) When the BBU3900 uses GE electric transmission, a 10 m long Ethernet cable is configured
for each site by default. When the required GE Ethernet cable for BBU3900 is longer than 10
m, provide the required length.
b) Transmission resources must meet the upcoming requirements of the eNodeB site and extra
resources are reserved for capacity expansion.
c) If the eNodeB is within the LOS of microwave transmission, and the microwave transmission
are used. The indoor units of the microwave transmission devices must be installed in the
space for the transmission devices in the cabinet.
d) If the eNodeB is not within the LOS of microwave transmission, and the x digital subscriber
line (xDSL) transmission is used. It is recommended that the devices for xDSL transmission be
installed in the space reserved in the cabinet.

10.47.4 Installing the indoor GPS coaxial cable and GPS EMP device on entry
plate

a) Note. Although indoor GPS coaxial cable is highly flexible, use caution as not to kink or
damage cable with installation. GPS EMP device must also be installed with caution as
unnecessary bumps etc will cause internal damage.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 74,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 38

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 75,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

GPS should be installed in the 45 degree under lightening spike, if GPS is on top of the building

Figure 39a

a) Connect the internal GPS coaxial cable on the LMPT/UMPT board position indicating GPS,
above the reset button. Ensure the female connector on the board is tight and tighten the cable
without straining the cable at the connector.

Figure 39 b

b) Route the coaxial cable between the BBU and DCDU to behind the 6Uupwards to the entry
plate. Secure cable along the way without kinking the cable with cable ties.

c) Connect the EMP device on the entry plate with the Surge female pointing to the outside of the
shelter in existing hole. Secure the EMP device with the nut provided and adding a M12
“Chassis Washer” on the outside of the entry plate.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 76,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 39c

d) Ensure the EMP device is secured on the entry plate, connect an earth cable between the
EMP device and the main earth bar.

Figure 39 d

e) Connect GPS indoor Coaxial cable to EMP. Ensure connections are properly tightened on the
Protect side

Figure 39 e

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 77,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 39 f

10.4.17.4.1 Cabling Requirements for the eNodeB

a. The power cables and signal cables must be routed in compliance with the cabling specifications
to avoid electromagnetic interference to the signals.

10.4.27.4.2 Feeder Bending Radius

Table 4
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 78,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.4.37.4.3 Installing the connectors on the external GPS

cable

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 79,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.4.47.4.4 Gland Plate layout

Please note below requirements. If not possible notify applicable Huawei and Telkom Mobile ILO’s to
advise alternative positions. Note on shelters with side entry, you are required to move the 2 G feeders
to top centre holes, as the BTS above the 6U rack will cause damage to feeders/fly leads.

10.4.57.4.5 CK Gland Plate

Figure 40a

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 80,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.4.67.4.6 ARP Gland Plate

Figure 40b

Figure 40c Figure 40d

Figure 40e Figure 40f

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 81,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 40 g

10.4.77.4.7 Roof Top Installations

a) Set out equipment orientation (shelter I-beams/legs, antenna pole base) and mark roof surface
for removal of waterproofing to accommodate I-beams or base plate size.
b) Cut waterproofing and break back screed (if evident) neatly to expose reinforced concrete
(RC) roof slab.
c) Mark the bolt / anchor positions, drill and install anchors as detailed in the Engineering
drawings, or shutter the required plinth after the slab has been scabbed (roughening).
d) After cleaning away dust and any loose pieces, grout the area between the RC slab, I-beam or
pole base plate to the correct level as detailed in the drawings.
e) Bolt together the steel sections by using turn-of-the-nut method, then screed to a minimum of
25 mm above the previous level with 10 Mpa screed mix.
f) Allow to dry for at least 30 hours, and then clean the entire area, specifically the existing
waterproofing, to at least 150 mm from the cutting edge.
g) Waterproof the damaged areas. Note Waterproofing must comply with standards.
h) Flame-on/Torch-on waterproofing method is recommended as its lifetime is higher than
membrane with waterproofing paint. Certification of Waterproofing must be
provided.
i) Photographs of the installation before and after work needs to be provided.
j) Ensure paths are clear of obstruction and water flow and diversion addressed.
k) The service provider needs to supply a certificate guarantee of the work completed and the
waterproofing provided.
l) Ensure that all steel, bolt, nuts and washers confirm to Structural Requirements. High Tensile
steel, hot dipped galvanizing etc. Note, double nuts with flat washers must be used to secure
equipment and a minimum of 3 threads of bolts used must protrude from the top nut.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 82,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.4.87.4.8 Rooftop Installation and Waterproof

Figure 41a Figure 41b

Figure 41c Figure 41d

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 83,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 41e Figure 41f

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 84,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 41 g

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 85,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.277.5 Installing the RRU Power Cables to DCDU-03

Making of OT Connector on RRU Power Cable for DCDU-03, Skin power cables between 100mm

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 86,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 42

10.27.17.5.1 Install Fiber and power cable

Fiber label should be installed nearest to termination point, after spiral wrap has been installed.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 87,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Fiber Cable Label

Figure 43

10.27.27.5.2 Table 5 Fiber Cable Spec

Table 5 a

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 88,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Table 5 b

10.287.6 Assemble Antenna and RRU on the Ground

10.28.17.6.1 Antennas and RRU Assembly

Figure 44a.Antenna Bracket Assembly

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 89,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 44b.Installing Antenna Brackets

10.28.27.6.2 Use of Heatshrink in Waterproofing

Waterproofing of cables on the RRU and Antenna


a) Connect Jumper cables on antenna using torque wrench.
b) Connect two Jumpers for GSM, two for 3G two for LTE. Manually adjust the
mechanical tilt of the Antenna to the specified value and the Antenna Electrical tilt to the
specified value.
c) Do the waterproofing for all connectors.
d) When installing the waterproofing put two layers of insulation tape, with the glue side on the
outside before the waterproofing tape.

10.28.37.6.3 Connector Waterproofing

Installation specification
1. Clean the feeder / Fly Leads and connectors.
2. Place the Heatshrink over the Fly lead before connecting the connector to the Antenna / RRU’s

Figure 45a
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 90,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

3. Wrap 3 layers of PVC tape before wrapping the waterproof tape for the convenience of
removing the tapes.
4. When wrapping to the point over the connector, reverse the direction to let the wrapping goes
back towards starting point, reverse the direction to let the wrapping goes back towards the
connector. In this way, the feeder / Fly Lead is wrapped up with3 layers of PVC tape

Figure 45b
5. Uncoil the waterproof-insulating tape. Stick the end of the tape to the feeder / Fly lead at the
point 150mmbelow the connector.
6. Stretch the tape until it is as 3/4 to 1/2 wide as its original shape. Make sure that the stretched
width is at least 1/2 of the original width; otherwise over-stretching may damage the molecular
structure of the tape and lower its reliability.
7. Wrap up the feeder / Fly Lead spirally upward while maintaining this stretching strength. Make
sure that the overlapping area of adjacent tape layers is 1/2 of the stretched width.
8. When wrapping to the point over the connector, reverse the direction to let the wrapping goes
back towards starting point, reverse the direction to let the wrapping goes back towards the
connector. In this way, the feeder / Fly lead is wrapped up with 3 layers of waterproof tape.

Figure 45c
9. After wrapping, squeeze the tape stuck to the feeder to make sure no air remains between the
tape layers.
10. After wrapping the waterproof-insulating tape, it is necessary to wrap it up with PVC tape to
prevent the wearing and aging of the waterproof-insulating tape.
11. The wrapping of PVC tape is similar to that of waterproof-insulating tape. Start wrapping spirally
upward with 1/2 width of overlapping between adjacent layers.
12. When wrapping to the point over the connector, reverse the direction to let the wrapping goes
back towards starting point, reverse the direction to let the wrapping goes back towards the
connector. In this way, the feeder / Fly lead is wrapped up with 3 layers PVC tape cover.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 91,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 45 d
13. Make sure to maintain the stretching strength.
14. Push the Heatshrink over the connector.
15. Use a heat gun and shrink the Heatshrink securely over the waterproofing.
16. After the shrinking is completed secure the ends (bottom and top) with cable ties while the
shrink is still hot and flexible for titer sealing.

Figure 45 e Figure 45 f Figure 45 g

250mm

Figure 45h

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 92,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.28.47.6.4 Antenna Jumping Waterproofing

a) Place the 50mm x 250mm or 33mm x 250mm (dia x length) shroud of heat shrink over the
taped area. Using the heat gun, gently heat the shrink. Excessive or prolonged use of heat
WILL damage the connector and cable. Heat the shroud sufficiently enough for the glue to
seal all around the cable.
This method of waterproofing must be done at the:-
I. Entry plate behind the cabinet;
II. The change over between fly lead and feeder cable
III. Antenna.
IV. RRU
V. GPS

b) Antenna Port connection orientation.


c) Note. +45 degree SLANT on Antennas is the A-feed TXRX connection.
-45 degree SLANT on Antennas is the B feed RX connection.
d) Technology configuration on Antenna from LEFT to RIGHT. (facing back of antenna) GSM/2G
two ports, UMTS/3G two ports, and LTE two ports.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 93,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

10.28.177.6.5 Figure 46 a, b, c, Antenna Port Configuration

Figure 46 a

Figure 46 b

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 94,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 46 c

10.28.197.6.6 RCU Connection

Connect RCU to Antenna. Please take note of the step by step process tosuccessfully install the RCU
to the Antenna.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 95,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 96,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Step by step process of RCU installation to Antenna

Figure 47

10.28.207.6.7 Single Band Set Up

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 97,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 48

10.28.237.6.8 Dual Band RCU Set up

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 98,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 49

10.28.247.6.9 Tri Band RCU Set up

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 99,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 50

10.28.257.6.10 Assembly RRU on Ground

Note the following when installing the RRU DC Power two earth kits to be installed:
a) A set of earth kit must be installed from the bottom of tower close to container.
b) A second set of earth kit must be installed from the RRU’s side to the closest earth bar running
down.
c) Earth tails to be connected to earth bar and greased. Earth tails should point downwards and
not looped, coiled etc.
d) Earth the RRU on Ground

Figure 51a

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 100,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 51b

Figure 51c

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 101,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 51d

10.28.267.6.11 Install new pole and Bracket (Optional)

a) The brackets must be mounted with the tails pointing inwards i.e. facing each other.
b) All horizontal bolts of the brackets shall have a flat washer on both side with nut and the lock
nuts mounted on the back when viewed from behind.
c) All vertical bolts must have the nuts and the lock nuts facing down such that if the nuts become
loose the bolt will prevent the antenna from falling.
d) All bolts used for the antenna mounting brackets and accessories must be secured with the
bolts and lock nuts.
e) All bolts must have a minimum of three (3) threads protruding from the lock nuts.
f) All bolts and nuts must be Cold Galvanizing sprayed on to prevent rust due to tools that
damage the galvanizing of the bolts and nuts.
g) For Stainless Steel bolts and nuts, Cold Galvanizing spray need not to be used.
h) NB! Do not mix Stainless Steel and Galvanized Bolts, Nuts and Washers.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 102,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

118 CHAPTER 8: INSTALL ANTENNA AND RRU ON TOWER

11.1.18.1.1 Figure 52 a, b notes the Lifting of RRU and Antennas onto Tower

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 103,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 52a

Figure 52b

11.28.2 Mount RRU on Pole

a) The mounting of the RRU’s must be according to the RRU Mounting Instruction, which
requires the RRU to be mounted 90 deg to the pole and NOT at an angle.
b) Take special precaution at Billboard and Rooftop sites. When performing a Tri-band swop,
move the existing 3G RRU down to make enough space on the pole for the LTE RRU to be
mounted above the 3G RRU.
c) Note RRU’s to be mounted back to back on antenna, unless otherwise approved by Huawei
and Telkom Mobile Representative in writing.
Also refer to the IIS Report provided for the applicable sites regarding the Mounting Plate Option where
needed.

11.2.18.2.1 Mounting the RRU on the Pole

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 104,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 53

11.2.28.2.2 Safety Sling for the RRU

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 105,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 54

11.2.38.2.3 Mounting the RRU on Pole

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 106,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 55

11.2.48.2.4 Mounting Antenna on Pole

Figure 56

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 107,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

11.38.3 Connecting the LTE jumpers from Antenna to RRU

a) Follow the standard waterproofing specification as required.


Formatted: Numbered + Level: 1 + Numbering Style:
a, b, c, … + Start at: 1 + Alignment: Left + Aligned at:
0.63 cm + Indent at: 1.27 cm

Figure 57

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 108,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

11.48.4 Connecting the RCU Cable from RCU to RRU

Figure 58

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 109,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

11.58.5 Adjust azimuth and tilt of Antenna

11.5.18.5.1 Azimuth and Tilts

a) A SANS approved compass that is in good working order is to be used at all times.
b) Mechanical down-tilts are to be set by using a tilt meter.

Figure 59a

Figure59b
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 110,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

129 CHAPTER 9: INSTALL CLAMPS (FEEDER / FIBER /


POWER CABLES

12.19.1 Mounting Feeder Clamps

a) Please note that fiber comfy clamps must be used in the installation of the fiber Cables wherever
the cable is fastened to a fixed point. This is necessary for the protection of the fiber cables.
Loosen the nut on the clip and change to U-shaped

12.1.19.1.1 Comfy Clamp Installation

Figure 60a

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 111,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 60b Loosen the nut on the clip and change to U-shaped

Figure 60c

Figure 60d

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 112,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 60e

Figure 60f Mounting Feeder Clamps

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 113,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 60g Install Clip on the tower, 1 PCS/M

1310 CHAPTER 10: VSWR TESTING

13.110.1 VSWR Testing Overview

a) Before testing the antenna system equipped with no TMA, Calibrate the Site Master before
connecting the jumper of RF output port of the Site Master.
b) Two way receive diversity (two feeder for each sector) is applied throughout the project;
therefore two VSWR tests are required for each sector. Record and
c) The accepted VSWR Value is 1.35.For VSWR value above 1.35 perform Distance to Fault
measurements and rectify the problem.

Performing VSWR Measurements

Take all the VSWR Measurements according to the table below:

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 114,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

VSWR Measurements

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 115,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

DTF & VSWR with Limit Line Accept Format

Note the following when performing the VSWR Test.


a) Set the marker as Marker to Peak to establish proper sweep limit acceptance.
b) Set the Site Master to have the Calibration on - “CAL ON”
c) STAC Codes are accepted where the Site Master cannot contain the SiteName. Pre Sweep Test
Results MUST be saved as “STAC code-PRE-Sector& feed A/B”. E.g. VHTH PRE 1A.
d) Indicate the time and date on your sweep results.
2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 116,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

e) Sweep Tests must not exceed the 1.35 Limit Line.


f) Sweep Results to be submitted in above FORMAT per sector. (Note. This counts for Pre-
and Post Sweep Test Results.

1411 CHAPTER 11: INSTALL RRU POWER / FIBER CABLE

a) Measure the length of the power cable and cut the appropriate length

14.1.111.1.1 Install RRU Power Cable

Figure 61a Installing RRU Power and PGND Cable

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 117,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

14.211.2 Cut Power and Grounding cable and Installation for RRU

a) Cut the power cable according to the length identifiers on the RRU power cable.
b) Ensure that you unroll the cable so as to prevent coiling and twisting of
the power cable. All power cables to be made off neatly and correctly on either end.

Figure 61 b Length Identifier

c) To prevent swapping sectors, put coloring immediately after cutting the power
cable. Install the power cables on the tower and fix the Power cables clamp.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 118,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 61 c Apply coloring immediately after cutting the power cable

d) Lift power cable to tower, make OT Connectors and connect RRU Power Cable.
e) Please refer to the figure 102 below indicating step by step process to make of
the OT Connector.
f) All power cables must be made off neatly and correctly on either end.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 119,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 61 d

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 120,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 61 e Connecting RRU Power Cable

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 121,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

14.311.3 Install Fibre Cable

a) Layout the fiber cable and stick color ring on the ground, color rings Red, Yellow, Blue are for
Sector 1-3.
b) The fibre cable must be installed within comfy clamps.

Figure 62a Protecting Fiber Tails


c) Install CPRI fiber cable on CPRI 0 port RRU

Figure 62b CPRI Fiber Cable to RRU

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 122,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 62c LTE CPRI Fiber Cable to LTE RRU

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 123,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

1512 CHAPTER 12: LABELLING

15.112.1 Indoor/Outdoor Part (to be done with reference to PR-WR0099 for


2G/3G labelling)

15.1.112.1.1 Labeling Indoor

a) Telkom Network Element Identifier labeling (to be done with reference to PR-WR0099)

Figure 63a Network Identifier Labeling

b) Cat5e/FE Cable Labeling (to be done with reference to PR-WR0099)


c) The BBU LTE accommodates one control card. LMPT/UMPT card.
d) In the top position on the single label the information of termination position at the nearby end
and the bottom position must indicate the termination position of the remote end of the patch
cord. The label must be placed that all the information is visible. Part of the information
must not be placed around the bend of the cord. The same information must also be
accommodated on the back side of the label on the roll-over side of the label. The Brother
label is wrapped around the cable/cord close to the connector plugged into
the interface card.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 124,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 63b Cat5e Labeling

15.212.2 RRU Power Cable Label

Figure 63c RRU Power

15.312.3 AC/DC Power Supply Label

Figure 63d Row and Rack Position Label


2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 125,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

15.412.4 DC Panel Labels

a) The DC Power Distribution panel accommodates all the circuit breakers for the different
equipment in the outdoor cabinet. The panel accommodates labeling provider by the supplier
of the distribution panel. This labeling identifies the DC power termination of the Node-B as
“DBS” and the BTS as “BTS”. The circuit breakers on the power distribution panel must also be
labeled in accordance with the Telkom power labeling specification. The circuit breakers must
be labeled from left to right starting with the first circuit breaker as “A1”.

b) The circuit breaker labeling must be done with 9mm Yellow Brother tape with Black font. All
characters must be capital letters. The largest font setting as available on the specific Brother
machine must be used on the label. The Brother Tape label must be placed underneath each
specific circuit breaker on the front cover.

Figure 63 e ARP Rectifier BOX Power Label

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 126,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 63 f CK Rectifier BOX Power Label

15.512.5 Power Cable Labels

a) The BTS and Node-B are powered by means of a -48V DC feed. The physical power feed at
the BTS and Node-B equipment must be labeled with Brother Tape. The Brother tape label
may be placed on the DC power cable in any of the following two ways:
b) Wrapped around the cable in the same way as with the other cable labeling. The label is
wrapped around the cable in the “flag” method. The same information must be indicated on the
front as well as the back of the Brother Tape label.
c) Be placed on the DC power cable and covered with transparent heat shrink.
d) The Brother Tape label must indicate the specific circuit breaker on the power
distribution panel feeding the specific equipment. The top row of the label must indicate the
power distribution panel manufacturer specific circuit breaker labeling. “BTS” for the BTS 2G
equipment and “DBS” for the Node-B equipment. The bottom row of the label must indicate
“CB” for circuit breaker and then the specific Telkom standard identifier for the specific circuit
breaker, example CB A7. The label must be placed on the blue copper power cable close
to the termination of the power cable on the BTS equipment. The Following Figure indicates
the label on the blue cable and the position of the label.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 127,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Figure 63g BTS Power Labels

The same labeling method must also be followed for the Node-B power feed. The Node-B is identified
as “DBS” on the power distribution panel.

Figure 63h Node B Power Label


2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page
Distribution 128,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

15.612.6 Fibre Cable Labels

Label at RRU, Building entry and BBU - Please do not tighten the cable tie to an extent that it will
cause damage to the cable. The label for fiber should be put in protected area.

Figure 63 i Fibre Cable Labels

Fly lead cable label for DBS -LTE - Please do not tighten the cable tie to an extent that it will cause
damage to the cable.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 129,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

15.712.7 LTE Labeling

Table 6 a

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 130,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Table 6 b

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 131,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

TML4PWRRRU0
TML4PWRRRU1
TML4PWRRRU2

Table 6 c

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 132,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Formatted: Centered

Formatted: Centered

Table 6 c

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 133,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 134,
Total150
Quad Band Installation
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 135,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 136,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 137,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 138,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 139,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 140,
Total150
Formatted: Font: 20 pt
Lamp Post Installation Formatted: Font: 20 pt

Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Site need to be
barricaded

Before and after DCP tests


needs to be done on all sites

Dig 450mm and install G5


ground and compact
100mm before installing
plinth

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 141,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 142,
Total150
Formatted: Font: 20 pt, Font color: Black
DCP TEMPLATE Formatted: Centered

Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 143,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 144,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

When fence installed


stonechip and curbstones
need to be installed

When RFO is done


mark it clearly and
install draw wire

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 145,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Check all antenna tilts and


azimuthsAZM are
correct. Safetey slings to
All1/2inch feeders be installed on all
needs to be swept antennas

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 146,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

Make sure all RRU’s is securely


installed and
spraypaintedspray-painted

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 147,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 148,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

2crosby clams to be
installed each side of
safety slings on RRU
with a farrelferrule at the
end.

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 149,
Total150
Telkom Mobile 2G3G4G Hardware Installation Guide Security Level

All earth cablesing to go


downwards and denso
paste to be applied at
connections.added

2017-04-212017-04-032017-04-032017-03-112013-05-242013-05-22 Huawei Proprietary - Restricted Page


Distribution 150,
Total150

También podría gustarte