16.2.

CRONOGRAMA VALORIZADO DE OBRA


PROYECTO :
MEJORAMIENTO DEL SERVICIO DE RECREACION DEL PARQUE INFANTIL DEL CERCADO DE LA BANDA DE SHILCAYO, UBICADA EN LAS INTERSECCIONES
DEL JR. SANTA MARIA, JR. RECREO, DISTRITO DE LA BANDA DE SHILCAYO - PROVINCIA DE SAN MARTIN - DEPARTAMENTO DE SAN MARTIN

FECHA : SETIEMBRE 2019


PRESUPUESTO S/. / MESES
ITEM PARTIDAS Und
S/. MES 1 MES 3
01 MEJORAMIENTO DEL SERVICIO DE RECREACION
01.02 ESTRUCTURAS ### S/. 24,744.02 (100.00%)
01.02.04 ESTRUCTURAS METÁLICAS ### S/. 24,488.12 (100%)
01.02.04.01 COLUMNA METALICA und ### S/. 10,720.92 (100%)
01.02.04.02 VIGAS METALICAS 50x100x1.8mm m 1,976.02 S/. 1,976.02 (100%)
01.02.04.03 CORREAS METALICAS 50x100x1.8mm m ### S/. 11,446.51 (100%)
01.02.04.04 ESTRUCTURA METÁLICA PARA BANCAS und 236.04 S/. 236.04 (100%)
01.02.04.05 REJILLA METALICA PARA CAMARA DE CASCADA INC. LLAVES Y CANDADO und 108.63 S/. 108.63 (100%)
01.02.05 ESTRUCTURA DE MADERA 255.90 S/. 255.90 (100%)
01.02.05.01 MADERA PARA BANCAS glb 255.90 S/. 255.90 (100%)
01.03 ARQUITECTURA ### S/. 19,595.10 (26.91%) S/. 53,227.30 (73.09%)
01.03.02 PISOS Y PAVIMENTOS ### S/. 19,595.10 (100.00%)
01.03.02.03 PISO DE PORCELANATO 0.60x0.60 m. m2 ### S/. 19,595.10 (100.00%)
01.03.03 COLOCACION E INSTALACION DE GRASS SINTETICO ### 0.00 S/. 36,064.40 (100.00%)
01.03.03.01 INSTALACION DE GRASS SINTETICO COLOR ROJO m2 ### 0.00 S/. 11,474.87 (100.00%)
01.03.03.02 INSTALACION DE GRASS SINTETICO COLOR AZUL m2 ### 0.00 S/. 11,474.87 (100.00%)
01.03.03.03 INSTALACION DE GRASS SINTETICO COLOR VERDE m2 ### 0.00 S/. 13,114.66 (100.00%)
01.03.04 PINTURA 5,496.54 0.00 S/. 5,496.54 (100%)
01.03.04.01 PINTURA ESMALTE EN SARDINEL m2 1,118.25 0.00 S/. 1,118.25 (100%)
01.03.04.02 PINTURA LÁTEX 2 MANOS EN DADOS DE CONCRETO m2 447.60 0.00 S/. 447.60 (100%)
01.03.04.03 PINTURA LÁTEX 2 MANOS EN COLUMNAS m2 247.14 0.00 S/. 1247.14 (100%)
01.03.04.04 PINTURA ESMALTE EN ESTRUCTURA METÁLICA m2 1,572.07 0.00 S/. 1,572.07 (100%)
01.03.04.05 PINTURA EN ESTRUCTURA DE MADERA und 2,111.48 0.00 S/. 2,111.48 (100%)
01.03.05 VARIOS, LIMPIEZA Y JARDINERÍA 519.96 0.00 S/. 519.96 (100%)
01.03.05.02 BASURERO METALICO und 519.96 0.00 S/. 519.96 (100%)
01.03.06 COBERTURAS 9,646.40 0.00 S/. 9,646.40 (100%)
01.03.06.01 COBERTURA CON POLICARBONATO m2 9,646.40 0.00 S/. 9,646.40 (100%)
01.03.07 LETRAS DE CONCRETO ARMADO (PARQUE INFANTIL) 1,500.00 0.00 S/. 1,500.00 (100%)
01.03.07.01 LETRAS DE CONCRETO ARMADO "PARQUE INFANTIL" glb 1,500.00 0.00 S/. 1,500.00 (100%)
01.04 MOBILIARIO URBANO ### S/. 15,635.62 (100%)
01.04.01 JUEGOS INFANTILES ### S/. 15,635.62 (100%)
01.04.01.01 MOVIMIENTO DE TIERRAS 35.62 S/. 35.62 (100%) 0.00
01.04.01.01.01 EXCAVACIÓN DE TERRENO MANUAL m3 35.62 S/. 35.62 (100%) 0.00
01.04.01.02 JUEGOS INFANTILES ### S/. 15,600.00 (100%)
PRESUPUESTO S/. / MESES
ITEM PARTIDAS Und
S/. MES 1 MES 3
01.04.01.02.04 JUEGOS INFANTILES - SET DE JUEGOS(MODELO 01) und ### S/. 12,800.00 (100%)
01.04.01.02.05 JUEGOS INFANTILES - SET DE JUEGOS(MODELO 02) und 2,800.00 S/. 2,800.00 (100%)
01.05 INSTALACIONES SANITARIAS 2,133.06 S/. 4,777.10 (100%) 0.00
01.05.01 SISTEMA DE AGUA FRÍA 2,133.06 S/. 3,916.06 (100%) 0.00
01.05.01.16 REFLECTOR PLANO 75W Aquant und 2,133.06 S/. 2,133.06 (100%) 0.00
01.06 INSTALACIONES ELÉCTRICAS ### 0.00 S/. 13,775.00 (100%)

01.06.01 SALIDAS PARA ALUMBRADO, TOMACORRIENTES, FUERZA Y SEÑALES DÉBILES ### 0.00 S/. 13,735.00 (100%)
01.06.01.03 ACOMETIDA TG AL TD m 451.20 0.00 S/. 451.20 (100%)
01.06.01.05 CONDUCTORES Y CABLES DE ENERGÍA EN TUBERÍAS m 1,515.00 0.00 S/. 1,515.00 (100%)
01.06.01.06 TABLERO GENERAL TG INC. LLAVES und 455.74 0.00 S/. 455.74 (100%)
01.06.01.07 TABLERO DE DISTRIBUCIÓN TD INC. LLAVES und 594.52 0.00 S/. 594.52 (100%)
01.06.01.08 LUMINARIAS TIPO STREET LIGHT T1FS SERIES HERMÉTICO und 5,139.54 0.00 S/. 5,139.54 (100%)
01.06.01.09 LUMINARIAS TIPO FAROLA und 4,152.90 0.00 S/. 4,152.90 (100%)
01.06.01.10 SUMINISTRO E INSTALACIÓN DE POSTES DE F°G° D=4" H=3.60m. CON CONCRETO SIMPLE und 1,426.10 0.00 S/. 1,426.10 (100%)
01.07 LIMPIEZA FINAL DE OBRA 477.65 0.00 S/. 477.65 (100%)
01.07.01 LIMPIEZA FINAL DE OBRA m2 477.65 0.00 S/. 477.65 (100%)
0 0 0 0.00 0.00 0.00
COSTO DIRECTO 129,547.74 62,107.80 67,439.95
GASTOS GENERALES (5 %CD) 6,477.39 3,105.39 3,372.00
PRESUPUESTO TOTAL 136,025.12 65,213.20 70,811.96
AVANCE MENSUAL (%) 100.00% 47.94% 52.06%
AVANCE ACUMULADO (%) 100.00% 47.94% 100.00%