PROGRAMA DE MANTENIMIENTO MOLINOS - MES DE AGOSTO

HR TOTAL
LUNES MARTES MIERCOLES JUEVES VIERNES SABADO DOMINGO SEMANA
28-Jul 29-Jul 30-Jul 31-Jul 1-Aug 2-Aug 3-Aug
Molino 2E Molino 2E
PM-12M Cambio
PM-12M CMB Shell de Shell Liners
liners, Instalar heads lifter
integrados- PM-12M
Giro de manguera
Ciclones, CMB Cajon
Underflow
24 8 32
4-Aug 5-Aug 6-Aug 7-Aug 8-Aug 9-Aug 10-Aug
Molino 2D Molino 2B Molino 1A Bomba 2S Molino 1D
PM-5M CMB de labios PM-35D Cambio de PM-5M Cambio de CMB de Niple en
del Scoop PM-2M Giro Plato de Succion, plato de Succion la Linea de
de Plato de Succion CMB de planchas en Alimentacion a
PM-2M Giro de Bomba de Ciclones los cajones descarga Ciclones
Plato de succion
Bomba de Ciclones
1.5 4 4 4 13.5
11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug
Grua Puente
Molinos Norte
CMB de ruedas
Lado Oeste
12 12
18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug

0
25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug
Molino 1C
PM-10M CMB de
Scoop
6 6
Rev. 2003-06-30 TOTAL MES 63.5