Está en la página 1de 1

PLANILLA DE METRADO ESTRUCTURAS I

OBRA: COMERCIO FECHA:


EMPRESA: ICIP
SECTOR:
DEPARTAMENLIMA PROVINCIA: LIMA DISTRITO: LIMA
HECHO POR: REVISADO POR:

Ítem Descripción Und. # de veces Largo Ancho Alto Área Perímetro Parcial 1 Parcial 2 Total
OE.2 ESTRUCTURAS

O.E.2.1.2 OBRAS DE CONCRETO SIMPLE


O.E.2.1.2.1
O.E.2.1.2.1.1 SOBRECIMIENTO 3.79
CONCRETO
EJES HORIZONTALES 0.48

EJE 6
ENTRE EJE A Y C M3 2 2.125 0.15 0.75 0.48

EJES VERTICALES 3.31


EJE A
ENTRE EJE 1 Y 2 M3 1 1.95 0.15 0.75 0.22
ENTRE EJE 2 Y 3 M3 1 3.1 0.15 0.75 0.35
ENTRE EJE 3 Y 4 M3 1 2.15 0.15 0.75 0.24
ENTRE EJE 4 Y 5 M3 1 3.1 0.15 0.75 0.35
ENTRE EJE 5 Y 6 M3 1 1.57 0.15 0.75 0.18

EJE B´
ENTRE EJE 1 Y 2 M3 1 1.3 0.15 0.75 0.15
ENTRE EJE 2 Y3 M3 1 3.4 0.15 0.75 0.38
horizontal M3 1 0.9 0.15 0.75 0.10
EJE C
ENTRE EJE 1 Y 2 M3 1 1.9 0.15 0.75 0.21
ENTRE EJE 2 Y 3 M3 1 3.25 0.15 0.75 0.37
ENTRE EJE 3 Y 4 M3 1 2.15 0.15 0.75 0.24
ENTRE EJE 4 Y 5 M3 1 3.1 0.15 0.75 0.35
ENTRE EJE 5 Y 6 M3 1 1.57 0.15 0.75 0.18

ENCOFRADO SOBRECIMIENTO 53.69


EJES HORIZONTALES 6.83

EJE 6
ENTRE EJE A Y C M2 4 2.125 0.75 6.38
TAPITAS M2 4 0.15 0.75 0.45
EJES VERTICALES 46.86
EJE A
ENTRE EJE 1 Y 2 M2 2 1.95 0.75 2.93
TAPITAS M2 2 0.15 0.75 0.23
ENTRE EJE 2 Y 3 M2 2 3.1 0.75 4.65
TAPITAS M2 2 0.15 0.75 0.23
ENTRE EJE 3 Y 4 M2 2 2.15 0.75 3.23
TAPITAS M2 2 0.15 0.75 0.23
ENTRE EJE 4 Y 5 M2 2 3.1 0.75 4.65
TAPITAS M2 2 0.15 0.75 0.23
ENTRE EJE 5 Y 6 M2 2 1.57 0.75 2.36
TAPITAS M2 2 0.15 0.75 0.23
EJE B´
ENTRE EJE 1 Y 2 M2 2 1.3 0.75 1.95
TAPITAS M2 2 0.15 0.75 0.23
ENTRE EJE 2 Y3 M2 2 3.4 0.75 5.10
TAPITAS M2 2 0.15 0.75 0.23
horizontal M2 2 0.9 0.75 1.35

EJE C
ENTRE EJE 1 Y 2 M2 2 1.9 0.75 2.85
TAPITAS M2 2 0.15 0.75 0.23
ENTRE EJE 2 Y 3 M2 2 3.25 0.75 4.88
TAPITAS M2 2 0.15 0.75 0.23
ENTRE EJE 3 Y 4 M2 2 2.15 0.75 3.23
TAPITAS M2 2 0.15 0.75 0.23
ENTRE EJE 4 Y 5 M2 2 3.1 0.75 4.65
TAPITAS M2 2 0.15 0.75 0.23
ENTRE EJE 5 Y 6 M2 2 1.57 0.75 2.36
TAPITAS M2 2 0.15 0.75 0.23