PROGRAMACION DE OBRA - METODO DE GANTT

PROYECTO NO.1
Actividad Imicio Durac. Fin Preced Costo directo Cos./dia
A 06/01/2020 4 $ 2,000,000.00 $ 500,000.00
B 4 A $ 2,000,000.00 $ 500,000.00
C 2 B $ 2,000,000.00 $ 1,000,000.00
D 4 B $ 8,000,000.00 $ 2,000,000.00
E 6 D $ 5,400,000.00 $ 900,000.00
F 4 D,E $ 8,000,000.00 $ 2,000,000.00
G 4 E $ 8,000,000.00 $ 2,000,000.00
H 6 G $ 6,000,000.00 $ 1,000,000.00
I 6 HG $ 12,000,000.00 $ 2,000,000.00
J 4 I $ 8,000,000.00 $ 2,000,000.00
$ 61,400,000.00
PROGRAMACION DE OBRA - METODO DE GANTT
PROYECTO NO.2
Actividad Imicio Durac. Fin Preced Costo directo Cos./dia
A 14/02/2019 4 $ 400,000.00 $ 100,000.00
B 5 A $ 2,500,000.00 $ 500,000.00
C 3 A $ 1,200,000.00 $ 400,000.00
D 3 B $ 900,000.00 $ 300,000.00
E 4 C $ 2,000,000.00 $ 500,000.00
F 5 E $ 1,800,000.00 $ 360,000.00
G 2 E,F $ 2,000,000.00 $ 1,000,000.00
H 5 G $ 2,500,000.00 $ 500,000.00
I 4 H $ 1,600,000.00 $ 400,000.00
J 3 H,I $ 1,200,000.00 $ 400,000.00
$ 16,100,000.00
PROGRAMACION DE OBRA - METODO DE GANTT
PROYECTO NO.3
Actividad Imicio Durac. Fin Preced Costo directo Cos./dia
Localización 07/01/2019 4 $ 8,000,000.00 $ 2,000,000.00
Excavacón 4 Localización $ 4,000,000.00 $ 1,000,000.00
Concreto Zapatas 10 Excavación $ 40,000,000.00 $ 4,000,000.00
Columnas 15 Concre.Zapat $ 30,000,000.00 $ 2,000,000.00
Rellenos estruct 4 Columnas $ 20,000,000.00 $ 5,000,000.00
Manholes 20 Localización $ 80,000,000.00 $ 4,000,000.00

Tub. de alcantarillado 10"


15 Manholes $ 120,000,000.00 $ 8,000,000.00
Domiciliarias de 6" 10 Tub. Alcantarillado
$ 10".
40,000,000.00 $ 4,000,000.00
Rellenos zanjas 4 Domiciliarias $ 6,000,000.00 $ 1,500,000.00
Andenes 5 Localización $ 10,000,000.00 $ 2,000,000.00
Bordillos 4 Andenes $ 8,000,000.00 $ 2,000,000.00
Sobrecimiento 6 Bordillo $ 1,800,000.00 $ 300,000.00
Tierra de abono 4 Sobrecimiento $ 2,000,000.00 $ 500,000.00
Empradización 6 Tierra de abono $ 3,000,000.00 $ 500,000.00
$ 372,800,000.00