CANTIDADES DE OBRA CASA 1 PISO BARRIO VILLA VICTORIA

ACEROS # 4 CANT. ML CANT. VARILLAS


VIGA DE AMARRE 565.44 94
COLUMNAS 252 42
TOTAL 136
AMARRES 204.36 1202

CONCRETOS LARGO ANCHO ALTO


VIGA DE AMARRE 141.36 0.3 0.3
COLUMNAS 63 0.3 0.3
PISO 14 6 0.1
TOTAL M3

BLOQUE CASA CANT. M2 CANT. BLOQUES


BLOQUE EXTERIOR CASA 140 1820
BLOQUE INTERIOR CASA 105 1365
TOTAL 3185

CEMENTO PEGUE BLOQUE 65*BULTO 49


CEMENTO PARA CONCRETOS 189

DESCRIPCION UND. CANT VALOR UND. VALOR TOTAL.


VARILLA DE 1/2" * 6M UND 136 12000 $ 1,632,000
FLEJE 0,25*0,25 UND 1202 1000 $ 1,202,000
CEMENTO BULTO BULTO 238 22000 $ 5,236,000
ARENA M3 24 18000 $ 432,000
TRITURADO M3 24 45000 $ 1,080,000
BLOQUE UND 3185 900 $ 2,866,500
TEJA * 3M UND 24 48000 $ 1,152,000
TEJA * 1,8 M UND 12 36000 $ 432,000
CABALLETES UND 6 45000 $ 270,000
AMARRES TEJA UND 324 200 $ 64,800
PERFIL CERCHA * 6 M UND 10 42000 $ 420,000
VALOR TOTAL MATERIALES $ 14,787,300
M3 FLEJES
12.72 832
5.67 371
8.4 1202 TOTAL FLEJES
27

COTIZADO EN
YOPAL

YOPAL
YOPAL
YOPAL
YOPAL
TRINIDAD
TRINIDAD
TRINIDAD
TRINIDAD
TRINIDAD