MATERIAL CONSUPTION FOR UNNATI INORGANICS PVT LTD. DAHEJ.

NOS OF
SAND IN
SR.NO DESCRIPTION QTY. CEMENT KAPCHI IN CMT
CMT
BAG.
1 FOR RCC QTY. 29.66
CEMENT RATIO = 8.3/CMT 246.17
SAND RATIO = 0.5/CMT 14.83
COARS AGGRICATE RATIO= 0.9/CMT 26.69

2 FOR PCC QTY 1.95


CEMENT RATIO =4.5/CMT 8.7845625
SAND RATIO= 0.54/CMT 1.05
COARS AGGRICATE RATIO = 8.0/CMT 1.56

3 FOR PLASTER 1398.60


CEMENT RATIO = 0.2/SQ.MT 279.72
SAND RATIO 22.38

4 FOR TILES FLOORING 0.00


CEMENT RATIO = 0.3/SQ.MT 0
SAND RATIO = 0.012/SQ.MT 0.00

5 FOR METAL SOLING 0.00


METAL RATIO WITH 10% VOIDS = 0.80/CMT 0.00
SAND RATIO = 0.3/CMT 0.00

6 FOR RCC TRIMIX 0.00


CEMENT RATIO = 8.3/CMT. 0
SAND RATIO = 0.5/CMT 0.00
COARS AGGRICATE RATIO = 0.9/CMT 0.00

7 FOR BRICK MASONARY 312.16


CEMENT RATIO = 1.4/CMT 437.0184
SAND RATIO= 0.167/CMT 52.13
BRICK RATIO = 550NOS/CMT

8 FOR WATER PROOFING 0.00


CEMENT RATIO = 1.4/CMT 0
SAND RATIO =0.167/CMT 0
BRICK RATIO = 550NOS /CMT

9 REINFORCEMENT STEEL

10 MURRUM FILLING

NOS. BAG CMT. CMT.


TOTAL. 971.70 90.39 28.26

MATERIAL CONSUPTION FOR compound wall.


SR.NO DESCRIPTION. QTY. UNIT. RATE. TOTAL.
1 CEMENT. 971.70 BAG. 280 272074.817
2 STEEL. 0.5 TON. 65000 32500
3 SAND. 90.39 CMT. 550 49715.31785
4 COARS AGGRICATE. 28.26 CMT. 700 19778.59625
5 BRICK. 171685.80 NOS. 4 686743.2
6 MURRUM 379.63 CMT. 250 94907.6446875
7 TUBULAR SECTION GATE APPOX. AMOUNT OF GATE 75000
TOTAL. 1230719.57579
DAHEJ.

BRICK IN
STEEL. MURUUM
NOS.
171685.8

0.5

379.63

NOS. TON. CMT.


171685.8 0.5 379.63058
COMPOUND WALL. VISHVAKARMA CONSULTANTS.
VADODARA.

BILL OF QUANTITY FOR THE PROPOSED COMPOUND WALL FOR UNNATI ORGANICS PVT.
LTD. AT DAHEJ.
For 740.0 mtr.
Sr. No Description Quantity Unit Rate Amount (Rs.)

1 Excavation work for pile foundation


(boring deep hole into ground) of diameter
250mm in all sorts of soil with required
interval etc as per drg complete as directed
by Engineer IN charge.

247.00 Rmt 150 37050.00

2 Earth work in excavation below final ground


level ( Raised ground level) in foundations,
trenches, in all class of soil / murrrum
except rock up to a depth of 1.50 mtrs.
Including shoring, strutting, dewatering, if
required, refilling the trenches with selected
excavated soil, watering and compaction to
95% of proctor density and disposing off the
un useful soil within plot boundary etc.
complete as directed by Engineer IN
charge.

Do--- as above in depth 1.50 mtrs. To 3.00


mtrs. 24.81 cmt 275 6823.91

3 Providing and laying cement concrete M –


10, equavelent to 1:3:6 (1 cement:3 coarse
sand : 6 graded stone aggregate 40 mm.
nominal size) and curing complete excluding
the cost of form work in foundations and
plinth complete as directed by Engineer In
charge. (for ground beams).

1.95 cmt 4200 8198.93

Page No:8 UNNATI ORGANICS PVT.LTD.


COMPOUND WALL. VISHVAKARMA CONSULTANTS.
VADODARA.

Sr. No Description Quantity Unit Rate Amount (Rs.)

4 Providing & Supplying & fixing in position


High yield deformed bar reinforcement
confirming to IS – 1139 or cold Twisted
bars, TOR steel / TMT / or Equivalent
Reinforcement bars confirming to IS – 1786
for RCC construction including transporting
(i.e. loading & unloading) the steel from
store/issue points to site of works including
unloading from Trucks/Trailers, cleaning, de
coiling, cutting, bending to required shape
and lengths as per detailed drawing, binding
with 16 SWG black soft annealed binding
wire, placing with proper cover block,
support chairs, overlap, spacers, etc.
complete in all respect as directed by
Engineer IN charge in foundation and up to
Plinth level and terrace level including all
floors

3000 KG 62 186000.00

5 Providing and laying controlled cement


concrete M-200 for rcc work and curing
complete including the cost of from work
and reinforcement for reinforced concrete
complete as directed by Engineer IN charge
for work in :

(A) For Pile foundations…… 25.01 cmt 6000 150052.50


(B.) Footing… 4.32 cmt 6500 28080.00
(D) Pedastal 0.33 cmt 8500 2810.31

ABOVE PLINTH
6 Providing and constructing Conventional
Brick masonry in CM 1:6 (1 Cement and 6
Coarse sand) for superstructure with
conventional size bricks having minimum
crushing strength of 35 Kg / Sq. Cm.
(in115mm/230mm) including scaffolding,
racking out joints, curing, watering etc.,
complete as directed by Engineer IN
charge.
56.86 cmt 4200 238795.20

Page No:9 UNNATI ORGANICS PVT.LTD.


COMPOUND WALL. VISHVAKARMA CONSULTANTS.
VADODARA.

Sr. No Description Quantity Unit Rate Amount (Rs.)

8 Providing and applying 12mm


Smooth/20MM sandfaced cement
plaster(form inside & outside as per design
of drg..) in CM 1:4 (1 Cement and 4 Coarse
sand) to walls, beams, column, drain,
bends, moulds, making grooves, pattas on
all brick and RCC surfaces including raking
joints, scaffolding, curing finishing smooth.
The plaster shall be rubbed with "Iron Plate'
till the surface shows cement paste in line
level complete as directed by Engineer IN
charge.

1398.6 Smt 275 384615.00

9 Finishing outer walls with water proofing


cement paint in 2 coats with approved brand
& manufacture to give an even and smooth
shade of color of approved shade after
thoroughly cleaning the walls by water and
brushing to remove all dirt and remains of
loose materials complete as directed by
Engineer In Charge.

1398.6 smt 80 111888.00

10 Providing, supplying and fixing Tubuler


section gate complete as directed by
Engineer In Charge. 1 nos. 75000 75000.00

11 Providing, supplying and pre cast partitions


and Precast pole (2.2 mtr heigth 100 x 100
mm) . complete as directed by Engineer In
Charge. 740 rmt. 550 407000.00

TOTAL AMOUNT 1636313.84