DATOS:

Pb= 43789.98
Fpb= 41091
Fr= 0.97785 Fr= Po/Pb

INICIO: OCTUBRE
DURACIÓN: 3 MESES
VALORIZACIÓN N° 01
DEL 01 AL 31 OCTUBRE 2012

OBRA: AMPLIACIÓN DE ALMACÉN


CONTRATISTA: MARCO CASAS CONTRATISTAS GRLS
PROPIETARIO: SENCICO
ANTERIOR ACTUAL ACUMULADO SALDO
ITEM DESCRIPCIÓN UND. CANT. P.UNIT PARCIAL CANT. IMP. CANT. IMP. CANT. IMP. CANT.
1.00 CONCRETO ARMADO
1.01 COLUMNA
1.01.01 CONCRETO F'C=175 KG/CM2 M3. 12.00 333.94 4,007.28 12.00
1.01.02 ENCOF.-DESENCOF. M2. 60.00 42.00 2,520.00 24.00 1,008.00 24.00 1,008.00 36.00
1.01.03 ACERO KG. 800.00 4.94 3,952.00 560.00 2,766.40 560.00 2,766.40 240.00
1.02 VIGA
1.02.01 CONCRETO F'C=175 KG/CM2 M3. 8.00 305.15 2,441.20 8.00
1.02.02 ENCOF.-DESENCOF. M2. 40.00 46.53 1,861.20 40.00
1.02.03 ACERO KG. 500.00 4.94 2,470.00 500.00
1.03 LOSA ALIGERADA
1.03.01 CONCRETO F'C=175 KG/CM2 M3. 9.00 279.22 2,512.98 9.00
1.03.02 ENCOF.-DESENCOF. M2. 120.00 33.07 3,968.40 120.00
1.03.03 ACERO KG. 700.00 4.94 3,458.00 700.00
1.03.04 LADRILLOS 0.15X0.30X0.30 UND. 1020.00 2.67 2,723.40 1020.00
2.00 MURO
2.01 LAD. KK. 18 HCO. SOGA M2. 30.00 48.84 1,465.20 4.50 219.78 4.50 219.78 25.50
2.02 LAD. KK. 18 HCO. CABEZA M2. 48.00 76.09 3,652.32 28.80 2,191.39 28.80 2,191.39 19.20
COSTO DIRECTO 35,031.98 6,185.57 6,185.57
GG (15%) 5,254.80 927.84 927.84
U ( 10%) 3,503.20 618.56 618.56
SUBTOTAL 43,789.98 7,731.97 7,731.97
% AVANCE 100.00 18% 18%
ACUMULADO= ANTERIOR + ACTUAL
SALDO= PRESUPUESTO - ACUMULADO
SALDO %
IMP. AVANCE

4,007.28
1,512.00 40.00
1,185.60 70.00

2,441.20
1,861.20
2,470.00

2,512.98
3,968.40
3,458.00
2,723.40

1,245.42 15.00
1,460.93 60.00
28,846.41
4326.9612
2884.6408
36,058.01
82%
FÓRMULA POLINÓMICA

OBRA: AMPLIACIÓN DE ALMACÉN P.B= ###


CONTRATISTA: MARCO CASAS CONTRATISTAS GRLS FECHA= Jul-12
ESPECIALIDAD: ESTRUCTURAS AREA GEOGRAFICA: 02

JUL SET.
MONOMIO DESCRIPCION SIMBOLO I.U C.I % Io Ir K
CEMENTO P.T 1 21 72.93 339.42 339.42
1 PIEDRA CHANCADA CPM 5 0.133 17.29 214.9 216.21 0.133
MAQUINARIA NACIONAL 48 9.78 327.55 325.11
LADRILLO ARCILLA 17 11.93 668.74 665.33 0.109
2 LA 0.109
ARENA GRUESA 4 88.07 724.59 724.59
MADERA NACIONAL P/ENCOFRADO 43 0.103 89.32 559.82 569.35 0.105
3 DH
HERRA. 37 10.68 292.14 291.59
4 ACERO CORRUGADO F 3 0.170 100.00 471.48 429.12 0.155
5 MANO DE OBRA INC. BS J 47 0.285 100.00 448.25 470.79 0.299
6 G.G.U G.G.U 39 0.200 100.00 377.5 381.48 0.202
1.003
REINTEGROS

Vo = V x Fr

V = 7,731.97
Fr = 0.97785

R = Vo x (K-1)

N° FECHA Vo K-1 R
1 OCT. 7,560.70 0.003 22.68
A PAGAR

N° FECHA Vo R Vb IGV TOTAL


1 OCT. 7,560.70 22.68 7,583.38 1,365.01 8,948.39

Vb = Vo + R
IGV = 0.18 x Vb
TOTAL = Vb + IGV