Está en la página 1de 63

ANALISIS DE PRECIOS UNITARIOS

RUBRO:

DETALLE: RENDIMIENTO H/U

EQUIPOS
DESCRIPCION CANTIDAD TARIFA/hora COSTO/HORA
Herramientas manuales (5% M.O.) 5% DE MANO DE OBRA
concretera 1.00 5.00 30.00
retroexcavadora 1.00 20.00 20.00
seguridad industrial (2% de M.O,)

MANO DE OBRA

DESCRIPCION CANTIDAD JORNAL/HORA COSTO-HORA


peon 6.00 5.00 30.00
albanil 0.50 3.62 1.81

MATERIALES
DESCRIPCION UNIDAD CANTIDAD
cemento kg 350
grava m3 0.9
arena m3 0.60
agua lt 200

TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD

Estos precios no incluyen IVA


TOTAL COSTOS DIRECTOS (M+N+O+P)
INDIRECTOS Y UTILIDADES
OTROS INDIRECTOS

XXXXXXXXXXXX COSTO TOTAL DEL RUBRO


OFERENTE
UNITARIOS
HOJA 1 DE 1

UNIDAD:

RENDIMIENTO COSTO = C.hora*rend


0.80
0.33 9.90
0.33 6.60
0.32

SUBTOTAL (M) 16.82

RENDIMIENTO COSTO = RENDIM*C.HORA*CANTIDAD


0.50 15.00
0.50 0.91

SUBTOTAL (N) 15.91

P. UNITARIO COSTO=CANT.*P.UNITARIO
0.15 52.5
18 16.2
15 9.00
0.01 2.00

SUBTOTAL (O) 79.7

TARIFA COSTO=CANT.*TARIFA

SUBTOTAL (P)

112.42
ANALISIS DE PRECIOS UNITARIOS
RUBRO: Hormigon simple fc'=210kg/cm2 en bordillos

DETALLE: RENDIMIENTO H/U 0.15

EQUIPOS
DESCRIPCION CANTIDAD TARIFA/hora COSTO/HORA
Herramientas manuales (5% M.O.) 5% DE MANO DE OBRA
seguridad industrial (2% M.O)
Concretera 1.00 5.00 5.00
vibrador 1.00 5.00 5.00

MANO DE OBRA

DESCRIPCION CANTIDAD JORNAL/HORA COSTO-HORA


peon 6.00 3.60 21.60
albanil 1.00 3.65 3.65
maestro 0.50 4.04 2.02

MATERIALES
DESCRIPCION UNIDAD CANTIDAD
cemento kg 47.25
grava m3 0.1215
arena m3 0.08
agua lt 27

TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD

Estos precios no incluyen IVA


TOTAL COSTOS DIRECTOS (M+N+O+P)
INDIRECTOS Y UTILIDADES
OTROS INDIRECTOS

XXXXXXXXXXXX COSTO TOTAL DEL RUBRO


OFERENTE
UNITARIOS
HOJA 1 DE 1

UNIDAD:

RENDIMIENTO COSTO = C.hora*rend


0.20
0.08
0.15 0.75
0.15 0.75

SUBTOTAL (M) 1.79

RENDIMIENTO COSTO = RENDIM*C.HORA*CANTIDAD


0.15 3.24
0.15 0.55
0.15 0.30

SUBTOTAL (N) 4.09

P. UNITARIO COSTO=CANT.*P.UNITARIO
0.15 7.09
18 2.19
15 1.22
0.01 0.27

SUBTOTAL (O) 10.76

TARIFA COSTO=CANT.*TARIFA

SUBTOTAL (P) 16.64

16.64
20% 3.33

19.96
ANALISIS DE PRECIOS UNITARIOS
RUBRO: Hormigon simple fc'=210kg/cm2 espesor 15 cmm

DETALLE: RENDIMIENTO H/U 0.17

EQUIPOS
DESCRIPCION CANTIDAD TARIFA/hora COSTO/HORA
Herramientas manuales (5% M.O.) 5% DE MANO DE OBRA
seguridad industrial (2% M.O)
Concretera 1.00 5.00 5.00
vibrador 1.00 5.00 5.00

MANO DE OBRA

DESCRIPCION CANTIDAD JORNAL/HORA COSTO-HORA


peon 6.00 3.60 21.60
albanil 1.00 3.65 3.65
maestro 0.50 4.04 2.02

MATERIALES
DESCRIPCION UNIDAD CANTIDAD
cemento kg 52.5
grava m3 0.135
arena m3 0.09
agua lt 30

TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD

Estos precios no incluyen IVA


TOTAL COSTOS DIRECTOS (M+N+O+P)
INDIRECTOS Y UTILIDADES
OTROS INDIRECTOS

XXXXXXXXXXXX COSTO TOTAL DEL RUBRO


OFERENTE
UNITARIOS
HOJA 1 DE 1

UNIDAD: m2

RENDIMIENTO COSTO = C.hora*rend


0.23
0.09
0.17 0.85
0.17 0.85

SUBTOTAL (M) 2.02

RENDIMIENTO COSTO = RENDIM*C.HORA*CANTIDAD


0.17 3.67
0.17 0.62
0.17 0.34

SUBTOTAL (N) 4.64

P. UNITARIO COSTO=CANT.*P.UNITARIO
0.15 7.88
18 2.43
15 1.35
0.01 0.30

SUBTOTAL (O) 11.96

TARIFA COSTO=CANT.*TARIFA

SUBTOTAL (P) 18.62

18.62
20% 3.72

22.34
ANALISIS DE PRECIOS UNITARIOS
RUBRO: Hormigon simple fc'=210kg/cm2

DETALLE: RENDIMIENTO H/U 0.15

EQUIPOS
DESCRIPCION CANTIDAD TARIFA/hora \
Herramientas manuales (5% M.O.) 5% DE MANO DE OBRA
seguridad industrial (2% M.O)
Concretera 1.00 5.00 5.00
vibrador 1.00 5.00 5.00

MANO DE OBRA

DESCRIPCION CANTIDAD JORNAL/HORA COSTO-HORA


peon 6.00 3.60 21.60
albanil 1.00 3.65 3.65
maestro 0.50 4.04 2.02

MATERIALES
DESCRIPCION UNIDAD CANTIDAD
cemento kg 59.5
grava m3 0.153
arena m3 0.09
agua lt 34

TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD

Estos precios no incluyen IVA


TOTAL COSTOS DIRECTOS (M+N+O+P)
INDIRECTOS Y UTILIDADES
OTROS INDIRECTOS

XXXXXXXXXXXX COSTO TOTAL DEL RUBRO


OFERENTE
UNITARIOS
HOJA 1 DE 1

UNIDAD:

RENDIMIENTO COSTO = C.hora*rend


0.20
0.08
0.15 0.75
0.15 0.75

SUBTOTAL (M) 1.79

RENDIMIENTO COSTO = RENDIM*C.HORA*CANTIDAD


0.15 3.24
0.15 0.55
0.15 0.30

SUBTOTAL (N) 4.09

P. UNITARIO COSTO=CANT.*P.UNITARIO
0.15 8.93
18 2.75
15 1.35
0.01 0.34

SUBTOTAL (O) 13.37

TARIFA COSTO=CANT.*TARIFA

SUBTOTAL (P) 19.25

19.25
20% 3.85

23.10
PRESUPUESTO DE OBRA
PRECIO
Nro.
DESCRIPCIÓN DE CONCEPTOS UNIDADCANTIDAD UNITARIO
RUBRO
US$
PRELIMINARES
3237 Caseta para Gaurdianía glb 1.00 446.86
1 Limpieza y desbroce manual m2 114.88 2.76
1505 Replanteo y nivelación m2 114.88

Cerramiento provisional con planchas de


107 zinc h=2.4 ml 7.10

Cerramiento provisional perimetral con


2946 yute ml 37.39
0 CIMENTACION
Excavación con maquina para
2162 cimentación m3 40.68

Replantillo hormigon simple fc=180


1976 kg/cm2 E=5 cm m2 27.12

Hormigon simple de fc=210 kg/cm2 en


2986 zapata m3 11.20
384 Acero de refuerzo fy=4200 kg/cm2 kg 2,464.00
3047 Relleno compactado m3 28.08
0 INSTALACIONES SANITARIAS
387 punto de agua potable 1/2 pulgada pto 12.00
439 punto de AA.SS 2pulg. pto 12.00
73 punto de AA.SS 3pulg. pto. 3.00
638 cajas de registro UNIDAD. 8.00
234 Tuberia PVC desague 6 pulgadas ml 30.00
386 Inodoro Tanque bajo u 3.00
89 lavamanos incluye mueble u 3.00
92 Ducha de acero inoxidable u 3.00

Fregadero para conina doble pozo


968 incluye grifería u 1.00
0 FASE ESTRUCTURAL
Hormigon simple de fc=210 kg/cm2 en
3113 COLUMNAS y vigas M3 7.84
1822 Losa alivianada de e=15 cm m2 70.65
148 Escalera de hormigon fc=210 kg/cm2 m3 1.50
0 MAMPOSTERIA Y REVESTIMIENTOS
2715 mamposteria de bloque E=15 cm m2 182.64
1588 Enlucido de paredes interior m2 365.28
2334 Enlucido de paredes exterior m2 96.00
1195 Enlucido horizontal en losa m2 70.65
118 enlucido de filos ml 88.40
3116 pilaretes ml 32.00
530 Empaste Interior m2 365.28
531 Empaste exterior m2 96.00
80 Pintura de latex interior m2 365.28
2535 Pintura de latex exterior m2 96.00
Contrapiso hormigon fc=180 kg/cm2 E=7
cm incluye malla electrosoldada d=0.05
2708 10X10 cm m2 52.56
Nivelado de piso con hormigon fc=180
1428 kg/cm2 E=5 cm m2 70.65
0 ACABADOS
534 Piso de porcelanato Nacional rectificado m2 70.65
2709 Piso de ceramica nacional tipo A m2 70.65
484 Granito en meson de cocina m2 3.50
2722 ceramica en paredes de baño m2 42.28
3128 Techo falso de gypsum m2 70.84
0 INSTALACIONES ELECTRICAS
Acometida Electrica incluye caja de
81 medidor u 1.00
1348 Punto de luz incluye foco ahorrador pto 31.00
2751 puntos tv cable pto 6.00
84 Tomacorriente
Toma especial doble
de 220polarizado
v. para cocina de pto 20.00

642 inducción pto 1.00


0 CUBIERTA
Techo con plancha galvanizada de
591 0.40mm m2 73.44
378 Acero estructural kg 730.59
185 canalones metalicos ml 14.50
0 CERRAJERIA
Provisión Y CARPINTERIA
e instalacion de Ventanas de
1578 Aluminio
Provisión e instalacion de puertas de m2 19.95

1124 madera
muebles altos y bajos en cocina u 7.00

579 terminados en malamina ml 4.95


1130 Closets de malamina m2 7.00
450 puerta corrediza de aluminio m2 8.58
2721 pasamano de acero inoxidable ml 3.50
483 piso de tablon en gradas u 17.00
565 Rastreras de madera ml 76.00
COSTO
TOTAL US$

446.86
317.06

15
CALCULO DE INDIRECTOS PARA UNA OBRA
MONTO DE LA OBRA 52,056.24
PLAZO DE EJECUCION 4 MESES

COMPONENTE
FUERA DE LA OBRA UNIDAD CANTIDAD GASTO P.TOTAL
ARRENDAMIENTO OFICINA MES 4.00 250.00 1000.00
PERSONAL ADMINISTRATIVO MES 4.00 368.00 1472.00

GASTOS SERVICIOS VARIOS AGUA LUZ TELEFONO MES 4.00 60.00 240.00
GASTOS DE MATERIALES PARA OFICINA PAPEL,
TINTA, ETC MES 4.00 80.00 320.00
GASTOS DE GARANTIAS PARA CONTRATO MES 4.00 250.00 1000.00

GASTOS DE FINANCIAMINETO CONSIDERO


PRESTAMO DE 20000 DOLARES POR TRES MESES GLB 1.00 600.00 600.00
DENTRO DE LA OBRA
GASTOS DE MOVILIZACION MES 4.00 220.00 880.00
IMPREVISTOS, PERDIDA DE MATERIAL, MES 4.00 100.00 400.00
PERMISOS Y AUTORIZACIONES MES 4.00 50.00 200.00
0.00
0.00
TOTAL
UTILIDAD
TOTAL
INDIRECTOS
ADOPTADO
A OBRA

INCIDENCIA EN LA OBRA 3600


EN % 1200
1.92%
2.83%

0.46%

0.61%
1.92%

1.15%

1.69%
0.77%
0.38%
0.00%
0.00%
11.74%
10%

21.74%
25%
ANALISIS DE PRECIOS UNITARIOS
RUBRO:
Caseta para Gaurdianía
DETALLE: RENDIMIENTO H/U 7.0
INCLUYE ENCOFRADO
EQUIPOS
DESCRIPCION CANTIDAD TARIFA/DIA COSTO/HORA
Herramientas manuales (5% M.O.) 1.00 5% DE MANO DE OBRA

MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO-HORA
Peón 3.00 3.51 10.53
CARPINTERO 1.00 3.55 3.55

MATERIALES
DESCRIPCION UNIDAD CANTIDAD
TABLAS u. 44
CUARTONES u. 18
CLAVOS KG 6.00
ZINC 3,6 e=0.25 u. 5
Candado u. 1
picaporte u. 1.00

TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD
0 0 0
0 0 0

Estos precios no incluyen IVA


TOTAL COSTOS DIRECTOS (M+N+O+P)
INDIRECTOS Y UTILIDADES
OTROS INDIRECTOS
XXXXXXXXXXXX COSTO TOTAL DEL RUBRO
OFERENTE VALOR OFERTADO
RIOS
HOJA 1 DE 3
CAS001
UNIDAD: glb

RENDIMIENTO COSTO CANTIDAD DEL RUBRO CANTIDAD DE MATERIALES


4.93 1.00 4.928
1.00 -
1.00 -
1.00 -
1.00 -
1.00 -
1.00 -
1.00 -
SUBTOTAL (M) 4.93 varios 1.00 4.93
1.00 -
RENDIMIENTO COSTO 1.00 MANO DE OBRA
7.00 73.710 1.00 73.71
7.00 24.850 1.00 24.85
0.000 1.00 -
1.00 -
SUBTOTAL (N) 98.560 1.00 98.56
1.00 -
P. UNITARIO COSTO 1.00 MATERIALES
3.25 143.00 1.00 143.00
2.50 45.00 1.00 45.00
1.50 9.00 1.00 9.00
9.00 45.00 1.00 45.00
10.00 10.00 varios 1.00 10.00
2.00 2.00 1.00 2.00
SUBTOTAL (O) 254.00 1.00 254.00
1.00 -
TARIFA COSTO 1.00 TRANSPORTE
0 0 1.00 -
0 0 1.00 -

SUBTOTAL (P) 0 1.00 -


1.00 -
357.49 1.00 357.49
25% 89.37 1.00 89.37
1.00 -
1.00 -
1.00 -
446.86 1.00 446.86
446.86 1.00 446.86
14.928 a VARIOS
197.00 a MADERA ASERRADA
47.00 a ACERO EN BARRAS

73.71
24.85
ANALISIS DE PRECIOS UNITARIOS
RUBRO:
Limpieza y desbroce manual
DETALLE: RENDIMIENTO H/U 0.2

EQUIPOS
DESCRIPCION CANTIDAD TARIFA/DIA COSTO/HORA
Herramientas manuales (5% M.O.) 1.00 5% DE MANO DE OBRA

MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO-HORA
Peón 3.00 3.51 10.53

MATERIALES
DESCRIPCION UNIDAD CANTIDAD

TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD
0 0 0
0 0 0

Estos precios no incluyen IVA


TOTAL COSTOS DIRECTOS (M+N+O+P)
INDIRECTOS Y UTILIDADES
OTROS INDIRECTOS

XXXXXXXXXXXX COSTO TOTAL DEL RUBRO


OFERENTE VALOR OFERTADO
RIOS
HOJA 2 DE 3
CAS002
UNIDAD: m2

EQUIPOS 0
RENDIMIENTO COSTO
0.11 varios 2,250.00 236.925 0.1053
2,250.00 -
2,250.00 -
2,250.00 -
2,250.00 -
2,250.00 -
2,250.00 -
2,250.00 -
SUBTOTAL (M) 0.1050 2,250.00 236.25
2,250.00 -
RENDIMIENTO COSTO 2,250.00 MANO DE OBRA
0.20 2.106 2,250.00 4,738.50
0.000 2,250.00 -
0.000 2,250.00 -
2,250.00 -
SUBTOTAL (N) 2.106 2,250.00 4,738.50
2,250.00 -
P. UNITARIO COSTO 2,250.00 MATERIALES
0.00 2,250.00 -
0.00 2,250.00 -
0.00 2,250.00 -
0.00 2,250.00 -
0.00 2,250.00 -
0.00 2,250.00 -
SUBTOTAL (O) 0.00 2,250.00 -
2,250.00 -
TARIFA COSTO 2,250.00 TRANSPORTE
0 0 2,250.00 -
0 0 2,250.00 -
SUBTOTAL (P) 0 2,250.00 -
2,250.00 -
2.21 2,250.00 4,972.50
25% 0.55 2,250.00 1,237.50
2,250.00 -
2,250.00 -
2,250.00 -
2.76 2,250.00 6,210.00
2.76 2,250.00 6,210.00
a VARIOS

2.106
ANALISIS DE PRECIOS UNITARIOS
RUBRO:
Replanteo y nivelación
DETALLE: RENDIMIENTO H/U 0.1
manual
EQUIPOS
DESCRIPCION CANTIDAD TARIFA/DIA COSTO/HORA
Herramientas manuales (5% M.O.) 1.00 5% DE MANO DE OBRA

MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HORA COSTO-HORA
Peón 0.50 3.51 1.76
ALBAÑIL 0.50 3.55 1.78
maestro mayor 1.00 3.93 3.93

MATERIALES
DESCRIPCION UNIDAD CANTIDAD
estacas u 1.00
piola rollo 0.01
cal SACO 0.01

TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD
0 0 0
0 0 0

Estos precios no incluyen IVA


TOTAL COSTOS DIRECTOS (M+N+O+P)
INDIRECTOS Y UTILIDADES
OTROS INDIRECTOS

XXXXXXXXXXXX COSTO TOTAL DEL RUBRO


OFERENTE VALOR OFERTADO
RIOS
HOJA 3 DE 3
CAS003
UNIDAD: m2

EQUIPOS
RENDIMIENTO COSTO 2,250.00 #VALUE!
0.04 varios 2,250.00 83.93 2250 0.0473
0.00 2,250.00 - 0 0.10
2,250.00 - 0 0.007
2,250.00 - 0
2,250.00 - 0
2,250.00 - 0
2,250.00 - 0
2,250.00 - 0
SUBTOTAL (M) 0.04 2,250.00 83.25 0
2,250.00 - 0
RENDIMIENTO COSTO 2,250.00 MANO DE OBRA
0.10 0.1755 2,250.00 394.88 1125 0.1755
0.10 0.1775 2,250.00 399.38 1125 0.1775
0.10 0.3930 2,250.00 884.25 2250 0.393
2,250.00 - 0
SUBTOTAL (N) 0.746 2,250.00 1,678.50 0
2,250.00 MATERIALES
P. UNITARIO COSTO 2,250.00
0.10 0.10 2,250.00 225.00 2250
1.00 0.01 varios 2,250.00 22.50 22.5
0.73 0.007 2,250.00 16.43 22.5
0.00 2,250.00 - 0
0.00 2,250.00 - 0
0.00 2,250.00 - 0
SUBTOTAL (O) 0.12 2,250.00 270.00 0
2,250.00 TRANSPORTE
TARIFA COSTO 2,250.00 #VALUE! 0
0 0 2,250.00 - 0
0 0 2,250.00 - 0
SUBTOTAL (P) 0 2,250.00 - 0
2,250.00 - 0
0.90 2,250.00 2,025.00 0
25% 0.23 2,250.00 517.50 0
2,250.00 - 0
2,250.00 - 0
2,250.00 - 0
1.13 2,250.00 2,542.50 0
1.13 0
a VARIOS
a MADERA ASERRADA
a CEMENTO
ANALISIS DE PRECIOS UNITARIOS
RUBRO:
EXCAVACION MANUAL
DETALLE: RENDIMIENTO H/U

EQUIPOS

DESCRIPCION CANTIDAD TARIFA/DIA


Herramientas manuales (5% M.O.) 1.00 5% DE MANO DE OBRA

MANO DE OBRA

DESCRIPCION CANTIDAD JORNAL/HORA


Peón 1.00 3.51

MATERIALES

DESCRIPCION UNIDAD

TRANSPORTE
DESCRIPCION UNIDAD
0 0
0 0

Estos precios no incluyen IVA


TOTAL COSTOS DIRECTOS (M+N+O+P)
INDIRECTOS Y UTILIDADES
OTROS INDIRECTOS

XXXXXXXXXXXX COSTO TOTAL DEL RUBRO


OFERENTE VALOR OFERTADO
OS UNITARIOS
HOJA 1 DE 2
CAS015
2.00 UNIDAD: m3

EQUIPOS

COSTO =
RENDIM*C.HORA*CANTID
COSTO/HORA RENDIMIENTO AD EQUIPOS
0.35 787.50 276.4125
787.50 0
787.50 0
787.50 0
787.50 0
787.50 0
787.50 0
787.50 0
SUBTOTAL (M) 0.35 787.50 276.4125
787.50 MANO DE OBRA
COSTO =
RENDIM*C.HORA*CANTID
COSTO-HORA RENDIMIENTO AD 787.50 #VALUE!
3.51 2.00 7.02 787.50 5528.25
0.00 787.50 0
0.00 787.50 0
787.50 0
SUBTOTAL (N) 7.02 787.50 5528.25
787.50 0
COSTO=CANT.*P.UNITARI
CANTIDAD P. UNITARIO O 787.50 MATERIALES
0 787.50 0
0 787.50 0
0 787.50 0
0 787.50 0
0 787.50 0
0 787.50 0
SUBTOTAL (O) 0 787.50 0
787.50 0
CANTIDAD TARIFA COSTO=CANT.*TARIFA 787.50 TRANSPORTE
0 0 0 787.50 0
0 0 0 787.50 0
SUBTOTAL (P) 0 787.50 0
787.50 0
S DIRECTOS (M+N+O+P) 7.37 787.50 5804.6625
UTILIDADES 25% 1.84 787.50 1451.16563
787.50 0
787.50 0
787.50 0
DEL RUBRO 9.21 787.50 7255.82813
9.21 787.50 7255.82813
0.351 a VARIOS
ANALISIS DE PRECIOS UNITARIOS
RUBRO:
HORMIGON SIMPLE 210 kg/cm2 EN ACERAS
DETALLE: RENDIMIENTO H/U 1.0
INCLUYE ENCOFRADO
EQUIPOS

DESCRIPCION CANTIDAD TARIFA/DIA COSTO/HORA


Herramientas manuales (5% M.O.) 5% DE MANO DE OBRA
CONCRETERA 1.00 3.13 3.13
VIBRADOR 1.00 3.13 3.13
ELEVADOR 1.00 3.13 3.13

MANO DE OBRA

DESCRIPCION CANTIDAD JORNAL/HORA COSTO-HORA


Peón 10.00 3.51 35.10
ALBAÑIL 1.00 3.55 3.55
MAESTRO DE OBRA 0.50 3.93 1.97

MATERIALES

DESCRIPCION UNIDAD CANTIDAD


ARENA M3 0.7
GRAVA M3 0.95
CEMENTO KG 365.00
AGUA LIT 220
ADITIVO PLASTIFICANTE KG 1.1
ENCOFRADO METALICO u. 1.00

TRANSPORTE

DESCRIPCION UNIDAD CANTIDAD


0 0 0
0 0 0

Estos precios no incluyen IVA


TOTAL COSTOS DIRECTOS (M+N+O+P)
INDIRECTOS Y UTILIDADES
OTROS INDIRECTOS

XXXXXXXXXXXX COSTO TOTAL DEL RUBRO


OFERENTE VALOR OFERTADO
ARIOS
HOJA 1 DE 2
CAS015
UNIDAD: m3

#REF! EQUIPOS

COSTO =
RENDIM*C.HORA*CA
RENDIMIENTO NTIDAD CANTIDAD DE EQUIPOS
2.03 180.00 365.54 0
1.00 3.13 180.00 563.40 180
1.00 3.13 180.00 563.40 180
1.00 3.13 180.00 563.40 180
180.00 - 0
180.00 - 0
180.00 - 0
180.00 - 0
SUBTOTAL (M) 11.42 180.00 2,055.74 0
180.00 - 0
COSTO =
RENDIM*C.HORA*CA
RENDIMIENTO NTIDAD 180.00 MANO DE OBRA
1.00 35.100 180.00 6,318.00 1800
1.00 3.550 180.00 639.00 180
1.00 1.965 180.00 353.70 90
180.00 - 0
SUBTOTAL (N) 40.615 180.00 7,310.70 0
180.00 - 0
COSTO=CANT.*P.UNIT
P. UNITARIO ARIO 180.00 MATERIALES
15.00 10.500 180.00 1,890.00 126
15.00 14.250 180.00 2,565.00 171
0.15 54.750 180.00 9,855.00 65700
0.00 0.308 180.00 55.44 39600
1.27 1.397 180.00 251.46 198
25.00 25.000 180.00 4,500.00 180
SUBTOTAL (O) 106.205 180.00 19,116.90 0
180.00 - 0

TARIFA COSTO=CANT.*TARIFA 180.00 TRANSPORTE


0 0 180.00 - 0
0 0 180.00 - 0
SUBTOTAL (P) 0 180.00 -
180.00 -
158.24 180.00 28,483.34
25% 39.56 180.00 7,120.83
180.00 -
180.00 -
180.00 -
197.80 180.00 35,604.17
197.80 180.00 35,604.17
2.33875 a VARIOS
24.750 a MATERIALES PETREOS
25 a MADERA ASERRADA
9.39 A MAQUINARIA Y EQUIPO
56.147 a CEMENTO
ENTIDAD CONTRATANTE
DEPARTAMENTO

OBRA XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

Ponderación del Valor Agregado Ecuatoriano

PRECIO
Nro.
DESCRIPCIÓN UNIDAD CANTIDAD UNITARIO
RUBRO
US$

3237 Caseta para Gaurdianía m2 1.00 446.86

1 Limpieza y desbroce manual ml 2,250.00 2.76

1505 Replanteo y nivelación m2 2,250.00 1.13

1505 EXCAVACION MANUAL m3 787.50 9.21

450 HORMIGON SIMPLE 210 kg/cm2 EN ACERAS m3 180.00 197.80

PORCENTAJE DE PARTICIPACION NACIONAL MINIMA PPNM (%): 95.25%

COLUMNA G
R= PESO RELATIVO DEL RUBRO
G= COSTO TOTAL DEL RUBRO
M= COSTO TOTAL DE LA OBRA
NTE

Ecuatoriano

AGREGADO AGREGADO
PESO RELATIVO ECUATORIANO
ECUATORIANO
DEL RUBRO PONDERADO
COSTO PONDERADO
TOTAL US$ DEL RUBRO
(%) (%) (%)
R=G/M VAE AEP = R * VAE
52,056.24
446.86 0.858% 98.32% 0.844%
6,210.00 11.929% 100.00% 11.929%
2,542.50 4.884% 87.00% 4.249%
7,252.88 13.933% 100.00% 13.933%
35,604.00 68.395% 94.00% 64.292%
52,056.24 100.00% 95.247%

OLUMNA G COLUMNA H VALOR DEL COLUMNA I


ELATIVO DEL RUBRO VAE CALCULADO DE CADA MULTIPLICAMOS
UNO DE LOS RUBROS DE
O TOTAL DEL RUBRO SUS COMPONENTES EN COLUMNA H *
O TOTAL DE LA OBRA APUS COLUMNA G
PRESUPUESTO GENERAL DE LA OBRA
PRECIO
Nro. COSTO
DESCRIPCIÓN UNIDAD CANTIDAD UNITARIO
RUBRO TOTAL US$
US$

3237 Caseta para Gaurdianía glb 1.00 446.86 446.86

1 Limpieza y desbroce manual m2 2,250.00 2.76 6,210.00

2 Replanteo y nivelación m2 2,250.00 1.13 2,542.50

2 EXCAVACION MANUAL m3 787.50 9.21 7,252.88

3 HORMIGON SIMPLE 210 kg/cm2 EN ACERAS m3 180.00 197.80 35,604.00

52,056.24
RENDIMIENTOS DE LOS CALCULO DE TIEMPOS EN CALCULO DE TIEMPOS
APUS HORAS DIAS

TIEMPO HORAS /8HORAS


HORAS/UNIDAD RENDIMIENTO*CANTIDAD
DIARIAS

7.00 7.00 1
0.20 450.00 56
0.10 225.00 28
2.00 1,575.00 197
1.00 180.00 23
TOTAL DIAS 305

PLAZO DE EJECUCION 3 MESES


CRONOGRAMA VALORADO DE TRA
PRECIO

RUBRO U CANTIDAD
UNITARIO

PRELIMINARES
glb 1.00 446.86
3,237 Caseta para Gaurdianía

m2 2,250.00 2.76
1 Limpieza y desbroce manual

m2 2,250.00 1.13
2 Replanteo y nivelación

m3 787.50 9.21
2 EXCAVACION MANUAL

m3 180.00 197.80
3 HORMIGON SIMPLE 210 kg/cm2 EN ACERAS

Valores Parciales
Valores Acumulados
Porcentajes Parciales
Porcentajes Acumulados
ADO DE TRABAJOS
PRECIO TIEMPO EN MESES Ingrese el porcentaje de traba

TOTAL M1 M2 M3 %1

446.86 1.00 0.00 0.00


100
$ 446.86 $ 0.00 $ 0.00
6,210.00 2,250.00 0.00 0.00
100
$ 6,210.00 $ 0.00 $ 0.00
2,542.50 2,250.00 0.00 0.00
100
$ 2,542.50 $ 0.00 $ 0.00
7,252.88 236.25 275.63 275.63
30
$ 2,175.86 $ 2,538.51 $ 2,538.51
35,604.00 36.00 72.00 72.00
20
$ 7,120.80 ### ###
52,056.24
Valores Parciales $ 18,496.02 $ 16,780.11 $ 16,780.10
Valores Acumulados 18496.02 35276.13 52056.23
Porcentajes Parciales 35.53% 32.23% 32.23%
Porcentajes Acumulados 35.53% 67.77% 100.00%
ngrese el porcentaje de trabajo a realizar en cada periodo

%2 %3 %4 %5 %6 %7 %8 %9

35 35

40 40
%10 %11 %12 %13 %14 %15 %16 %17
%18 %19 %20 %21 %22 %23 %24 %25
%26 %27 %28 %29 %30 %31 %32 %33
%34 %35 %36 %37 %38 %39 %40 %41
%42 %43 %44 %45 %46 %47 %48 %49
%50 %51 %52 %53 %54 %55 %56 %57
%58 %59 %60 %61 %62 %63 %64 %65
%66 %67 %68 %69 %70 %71 %72 %73
%74 %75 %76 %77 %78 %79 %80 %81
%82 %83 %84 %85
MATERIAL UNIDAD CANTIDAD P.UNIT TOTAL
Arena Gruesa m3. 126.00 15.00 1,890.00 P
Grava m3. 171.00 15.00 2,565.00 P
Agua Lt. 39,600.00 0.00 55.44 X
Cemento kg. 65,700.00 0.15 9,855.00 C
Cal P-24 (25 kg) saco. 22.50 0.73 16.43 C
Aditivo plastocrete 161 HE kg. 198.00 1.27 251.46 C
Tablas de encofrado u. 44.00 3.25 143.00 M
Encofrado Global. 180.00 25.00 4,500.00 M
Clavos KG. 6.00 1.50 9.00 M
Estacas-varios u. 2,250.00 0.10 225.00 M
CANDADO VIRO U. 1.00 10.00 10.00 X
CUARTÓN 2" U. 18.00 2.50 45.00 M
Planchas de zinc 3.60m e=0.25 U. 5.00 9.00 45.00 A
Picaporte U. 1.00 2.00 2.00 A
Piola rollo. 22.50 1.00 22.50 X
TOTAL 19,634.83
SUMATORIA DE P= 4455.00
SUMATORIA DE X= 87.94
SUMATORIA DE C= 10122.89
SUMATORIA DE M= 4922.00
SUMATORIA DE A= 47.00
ESTRUCTURA
OCUPACIONAL C1 MAESTRO MAYOR
ESTRUCTURA
OCUPACIONAL D2 ALBAÑIL CARPINTERO
ESTRUCTURA
OCUPACIONAL E2 PEON

ESTRUCTURA
MANO DE OBRA
OCUPACIONAL C1
Nº RUBRO UNID CANT COSTO UNIT COSTO TOT COSTO UNIT

ACER001 Caseta para Gaurdianía GLB 1.00 98.560 98.560


Limpieza y desbroce
ACER002 M2 2,250.00 2.106 4738.500
manual
ACER003 Replanteo y nivelación KM 2,250.00 0.746 1678.500 0.393
ACER004 EXCAVACION MANUAL M3 787.50 7.020 5528.250
HORMIGON SIMPLE 210
ACER005 M3 180.00 40.615 7310.700 1.965
kg/cm2 EN ACERAS
COSTO TOTAL
19,354.510

LA SUMATORIA DE LAS ESTRUCT


ESTRUCTURA ESTRUCTURA ESTRUCTURA OCUPACIONAL
OCUPACIONAL C1 OCUPACIONAL D2 E2
COSTO TOT COSTO UNIT COSTO TOT COSTO UNIT COSTO TOT

0.000 24.850 24.850 73.710 73.710


0.000 0.000 2.106 4738.500
884.250 0.178 399.375 0.176 394.875
0.000 0.000 7.020 5528.250

353.700 3.550 639.000 35.100 6318.000

1,237.950 1,063.225 17,053.335

LA SUMATORIA DE LAS ESTRUCTURAS OCUPACIONALES = TOTAL DE MANO DE OBRA


EQUIPO ASIGNADO A OBRA
1 Herramientas manuales (5% M.O.) 967.7255 COSTO /H CANTIDAD X
3 Concretera 563.4 3.13 180 E
4 Vibrador 563.4 3.13 180 E
10 Elevador 563.4 3.13 180 E
1690.2
COSTOS DIRECTOS

Nº RUBRO UNID CANT. C. UNIT


ECER001 Caseta para Gaurdianía GLB 1.00 357.488
ECER002 Limpieza y desbroce manual M2 2,250.00 2.2113
ECER003 Replanteo y nivelación KM 2,250.00 0.9006
ECER004 EXCAVACION MANUAL M3 787.50 7.371
ECER005 HORMIGON SIMPLE 210 kg/cm2 EN ACERAS M3 180.00 158.24075
0 COSTO TOTAL

SUMATORIA DE P= 4455.00
SUMATORIA DE X= 87.94
SUMATORIA DE C= 10122.89
SUMATORIA DE M= 4922.00
SUMATORIA DE A= 47.00
Acero en barras Cemento Portland Equipo y maquinaria
COSTOS DIRECTOS Mano de obra sacos de Construc. vial

C. TOT C. UNIT C. TOT C. UNIT C. TOT C. UNIT C. TOT C. UNIT


357.490 98.56 98.560 47.000 47.000 0.000
4,975.430 2.106 4,738.500 0.000 0.000
2,026.350 0.746 1,678.500 0.000 0.0073 16.430
5,804.660 7.02 5,528.250 0.000 0.000
28,483.340 40.615 7,310.700 0.000 56.147 10,106.460 9.39

41,647.270 19,354.510 47.000 10,122.890

46% 0.11% 24.31%


Madera aserrada,
Equipo y maquinaria VARIOS DE INDICE
cepillada y/o Materiales pétreos
de Construc. vial PRECIOS AL
escuadrada
CONSUMIDOR
(preparada)
C. TOT C. UNIT C. TOT C. UNIT C. TOT C. UNIT C. TOT
0.000 197 197.000 0.000 14.928 14.930
0.000 0.000 0.000 0.1053 236.930
0.000 0.1 225.000 0.000 0.0473 106.430
0.000 0.000 0.000 0.351 276.410
1,690.200 25 4,500.000 24.75 4,455.000 2.33875 420.980
0.000
1,690.200 4,922.000 4,455.000 1,055.680

ESTA SUMA DEBE DAR 100%


4.06% 11.82% 10.70% 2.53% 100%
STA SUMA DEBE DAR 100%
SIMBOLO DESCRIPCIÓN C. DIRECTO

B Mano de obra 19,354.51


Acero en barras
C 47.00
Cemento Portland sacos

D 10,122.89
Equipo y maquinaria de
Construc. vial
E 1,690.20
Madera aserrada,
cepillada y/o escuadrada
F (preparada) 4,922.00
Materiales pétreos
G 4,455.00
VARIOS DE INDICE
PRECIOS AL
H CONSUMIDOR 1,055.68

41,647.28

Pr=Po(0.465B1/Bo+0.001C1/Co+0.243D1/Do+0.041E1/Eo
+0.118F1/Fo+0.107G1/Go+0.025H1/Ho+I1/Io+J1/Jo+K1/K
o+X1/Xo)

CUADRILLA TIPO

C. DIRECTO SAL/HORA N. HORAS


A B C=A/B
ESTRUCTURA
EO C1 OCUPACIONAL C1 1,237.95 3.93 315.00
ESTRUCTURA
EO D2 OCUPACIONAL D2 1,063.23 3.55 299.50
ESTRUCTURA
EO E2 OCUPACIONAL E2 17,053.34 3.51 4,858.50

TOT 5,473.000
FACTOR

0.465 0.46472447

0.001 0.00112853

0.243 0.24306245

0.041 0.04058368

0.118 0.11818299

0.107 0.10696977

0.025 0.02534811

1
1.000

+0.041E1/Eo
+J1/Jo+K1/K

FACTOR
D=C/TOT

0.058 0.05755527 315

0.055

0.888

1.001

También podría gustarte