Abutment
1st footing 1 2 10.90 3.30 0.60 Cum 43.16
2nd footing 1 2 10.10 2.90 0.60 Cum 35.15
3 rd footing 1 2 9.30 2.50 0.60 Cum 27.90
WING WALL
1st footing 2 2 5.00 2.60 0.60 Cum 31.20
2nd footing 2 2 5.00 2.20 0.60 Cum 26.40
3 rd footing 2 2 5.00 1.80 0.60 Cum 21.60
Total 242.86
Abutment
1st footing 2 2 (10.9+3.3) 0.60 Sqm 34.08
2nd footing 2 2 (10.1+2.9) 0.60 Sqm 31.20
3 rd footing 2 2 (9.3+2.5) 0.60 Sqm 28.32
Wing wall
1st footing 2 4 5.00 0.60 Sqm 24.00
2nd footing 2 4 5.00 0.60 Sqm 24.00
3 rd footing 2 4 5.00 0.60 Sqm 24.00
Retaining Wall
1st footing 1 2 12.50 0.45 Sqm 11.25
2nd footing 1 2 12.50 0.45 Sqm 11.25
3 rd footing 1 2 12.50 0.45 Sqm 11.25
ASL 1 2 12.50 2.00 Sqm 50.00
Total 249.35
Centering: Providing form work for
centering, shuttering etc., for all RCC
6 works including strutting up to 3.29m
in all floors using mild steel sheets of
size 90 x 60 cm of B G 10 stiffened
with mild steel angles of size 25 x 25 x
3mm laid over silver oak
Above Sil Level
Abutment
2 2 (7.5+1.6) 1.50 Cum 54.60
Wing wall
2 4 (5+.7) 2.50 Cum 114.00
Deck Slab
Deck Slab 1 1 7.50 6.00 45.00
Sides 1 2 6.80 0.48 6.53
Kerb 2 2 7.40 0.20 5.92
vertical pillar 2 4 0.80 0.90 cum 5.76
Horizontal 2 3 7.40 0.60 26.64
Bedblock
Abutment 2 2 7.50 0.25 7.50
Dirt wall
abutment 2 2 7.50 0.48 14.40
280.35
Total MT 2.50
providing and fixing 20mm thick
compressible
8 fiber board in expansion joint
complete as
per drawing and MORD technical
specification
unforseen Charges
ABSTRACT ESTIMATE
Name of Work : Construction of 6m span of Single vent slab culvert @ Seelamuthaiyapuram
Vandiyur Road to Muthurajapuram Road at Thummagundu Panchayat
1 2 3 4 5 6
Photography Charges