EDT Nombre de tarea Duración Comienzo Costo Fin 19 ago '19

S D L M X J V S
PS_1 PROYECTO PISCINA 63 días 19/08/19 08:00 a.m. S/. 216,577.25 09/11/19 12:00 p.m.
INICIO 0 días 19/08/19 08:00 a.m. S/. 0.00 19/08/19 08:00 a.m.
PS_1.1 ESTRUCTURAS 44.5 días 19/08/19 08:00 a.m. S/. 118,021.50 16/10/19 12:00 p.m.
PS_1.1.1 TRABAJOS PRELIMINARES 1 día 19/08/19 08:00 a.m. S/. 184.00 19/08/19 05:00 p.m.
PS_1.1.1.1 TRAZO Y NIVELES DE PISCINA 1 día 19/08/19 08:00 a.m. S/. 184.00 19/08/19 05:00 p.m.
PS_1.1.2 MOVIMIENTO DE TIERRAS 9 días 20/08/19 08:00 a.m. S/. 28,140.00 31/08/19 12:00 p.m.
PS_1.1.2.1 EXCAVACIÓN CON MAQUINARIAS 8 días 20/08/19 08:00 a.m. S/. 14,640.00 29/08/19 12:00 p.m.
PS_1.1.2.2 ELIMINACIÓN DE MATERIAL EXCEDENTE 5 días 24/08/19 08:00 a.m. S/. 13,500.00 31/08/19 12:00 p.m.
PS_1.1.3 OBRAS DE CONCRETO SIMPLE 4 días 13/09/19 08:00 a.m. S/. 8,042.50 18/09/19 12:00 p.m.
PS_1.1.3.1 SOLADO E=4" CEMENTO-HORMIGÓN 4 días 13/09/19 08:00 a.m. S/. 8,042.50 18/09/19 12:00 p.m.
PS_1.1.4 OBRAS DE CONCRETO ARMADO 31 días 05/09/19 01:00 p.m. S/. 81,655.00 16/10/19 12:00 p.m.
PS_1.1.4.1 FONDO DE PISCINA 18 días 05/09/19 01:00 p.m. S/. 47,890.00 27/09/19 05:00 p.m.
PS_1.1.4.1.1 CONCRETO F´C=210KG/CM2 PARA FONDO 1 día 27/09/19 08:00 a.m. S/. 23,710.00 27/09/19 05:00 p.m.
PS_1.1.4.1.2 HABILITACIÓN DE ACERO PARA FONDO 4 días 05/09/19 01:00 p.m. S/. 21,240.00 11/09/19 08:00 a.m.
PS_1.1.4.1.3 COLOCACIÓN DE ACERO PARA FONDO 3 días 18/09/19 01:00 p.m. S/. 2,940.00 21/09/19 12:00 p.m.
PS_1.1.4.2 MUROS DE PISCINA 27 días 11/09/19 08:00 a.m. S/. 33,765.00 16/10/19 12:00 p.m.
PS_1.1.4.2.1 CONCRETO F´C=210KG/CM2 PARA MURO 1 día 14/10/19 01:00 p.m. S/. 7,010.00 15/10/19 12:00 p.m.
PS_1.1.4.2.2 ENCOFRADO PARA MUROS 2 sem. 28/09/19 08:00 a.m. S/. 14,870.00 14/10/19 12:00 p.m.
PS_1.1.4.2.3 HABILITACIÓN DE ACERO PARA MUROS 6 días 11/09/19 08:00 a.m. S/. 8,615.00 18/09/19 12:00 p.m.
PS_1.1.4.2.4 COLOCACIÓN DE ACERO PARA MUROS 4 días 23/09/19 08:00 a.m. S/. 3,000.00 26/09/19 05:00 p.m.
PS_1.1.4.2.5 DESENCOFRADO PARA MUROS 1 día 15/10/19 01:00 p.m. S/. 270.00 16/10/19 12:00 p.m.
PS_1.2 ARQUITECTURA 18.5 días 16/10/19 01:00 p.m. S/. 28,555.75 09/11/19 12:00 p.m.
PS_1.3 INSTALACIONES SANITARIAS 10.5 días 29/08/19 01:00 p.m. S/. 14,000.00 12/09/19 05:00 p.m.
PS_1.3.1 TUBERIAS DE CIRCULACIÓN 9 días 29/08/19 01:00 p.m. S/. 12,040.00 11/09/19 12:00 p.m.
PS_1.3.1.1 TUBERIA PVC SAP 2" 2 días 09/09/19 01:00 p.m. S/. 2,000.00 11/09/19 12:00 p.m.
PS_1.3.1.2 TUBERIA PVC SAP 4" 3 días 05/09/19 08:00 a.m. S/. 3,240.00 09/09/19 12:00 p.m.
PS_1.3.1.3 TUBERIA PVC SAP 6" 4 días 29/08/19 01:00 p.m. S/. 6,800.00 04/09/19 05:00 p.m.
PS_1.3.2 ACCESORIOS 9 días 29/08/19 01:00 p.m. S/. 1,100.00 11/09/19 12:00 p.m.
PS_1.3.2.1 ACCESORIO TUBERIAS DE CIRCULACIÓN 9 días 29/08/19 01:00 p.m. S/. 1,100.00 11/09/19 12:00 p.m.
PS_1.3.3 VARIOS 1.5 días 11/09/19 01:00 p.m. S/. 860.00 12/09/19 05:00 p.m.
PS_1.3.3.1 PRUEBA HIDRAULICA 1.5 días 11/09/19 01:00 p.m. S/. 860.00 12/09/19 05:00 p.m.
PS_1.4 SALA DE MAQUINAS 27.5 días 03/10/19 01:00 p.m. S/. 56,000.00 09/11/19 12:00 p.m.
PS_1.4.1 INSTALACION DE EQUIPOS DE BOMBEO 27.5 días 03/10/19 01:00 p.m. S/. 56,000.00 09/11/19 12:00 p.m.
PS_1.4.1.1 LIMPIEZA Y ACONDICIONAMIENTO DE CASETA EXISTEN5 días 03/10/19 01:00 p.m. S/. 1,250.00 10/10/19 05:00 p.m.
PS_1.4.1.2 COMPRA Y TRANSPORTE DE EQUIPOS BOMBEO IMPORTAD1 ms 03/10/19 01:00 p.m. S/. 50,000.00 02/11/19 12:00 p.m.
PS_1.4.1.3 INSTALACIÓN Y PRUEBA POR TECNICO ESPECIALISTA 1 sem 04/11/19 08:00 a.m. S/. 4,750.00 09/11/19 12:00 p.m.
FIN 0 días 16/10/19 12:00 p.m. S/. 0.00 16/10/19 12:00 p.m.
26 ago '19 02 sep '19 09 sep '19 16 sep '19 23 sep '19 30 sep '19
D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X
07 oct '19 14 oct '19 21 oct '19 28 oct '19 04 nov '19
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D