Está en la página 1de 24

ANALISIS DE MOVILIZACION Y DESMOVILIZACION DE EQUIPO

PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN
JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC"
PROPIET: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO

A) MOVILIZACION DE EQUIPO CON PLATAFORMA

TRASPORTADOS EN
N° DESCRIPCION DEL EQUIPO CANTIDAD PESO UNIT.(TN) OBSERVACIONES
PLATAFORMA (TN)

1 TRACTOR DE ORUGAS DE 270 A 295 HP 1.00 20.00 20.00


2 RETROEXCAVADOR S/ORUG 115-165HP .75-1.4Y 1.00 20.00 20.00
3 COMPACTADOR VIBR. TIPO CANGURO 7 HP 1.00 0.18 0.18
4 MEZCLADORA DE CONCRETO DE 9 -11P3 1.00 0.50 0.50
5 COMPRESORA NEUMATICA 150 HP. 380-590 PCM 1.00 1.50 1.50

TOTAL S/. 42.18

NUMERO DE VIAJES = PESO TOTAL MAQUINARIAS 42.18 2.11


PESO CARGA PLATAFORMA 20.00
NUMERO DE VIAJES = 3+ 3

TIEMPO
N° DESCRIPCION TIPO DE CARRETERA LONGITUD (Km) VELOCIDAD
(HORAS)
1 ANDAHUAYALS - SAN JERONIMO ASFALTADO 3.00 12.00 0.25
2
TIEMPO TOTAL DE MOVILIZACION POR VIAJE 0.25
COSTO DE OPERACIÓN HORARIA S/. 169.49
NUMERO DE VIAJES 3.00
COSTO TOTAL …………. S/ . 127.00

B) MOVILIZACION DE EQUIPO AUTOPROPULSADO

TIEMPO
N° DESCRIPCION TIPO DE CARRETERA LONGITUD (Km) VELOCIDAD
(HORAS)
1 VOLQUETE DE 15M3 (2 UND) ASFALTADO 3.00 30.00 0.10
2 CARGADOR FRONTAL 125-155 HP 3 YD3. ASFALTADO 3.00 15.00 0.20
3 RETROEXCAVADOR S/LLANTAS 58 HP 1 YD3 ASFALTADO 3.00 15.00 0.20

TIEMPO TOTAL DE MOVILIZACION POR VIAJE 0.50


COSTO DE OPERACIÓN HORARIA S/. 84.75
NUMERO DE UNIDADES (5 UND) 4.00
COSTO TOTAL …………. S/ . 169.00

COSTO TOTAL DE MOVILIZACION DE EQUIPO (A+B) S/. = 1,114.59 Precios no incluyen IGV
COSTO TOTAL DE DESMOVILIZACION DE EQUIPO S/. = 1,114.59 Precios no incluyen IGV
COSTO TOTAL S/. 2,229.18
CALCULO DEL FLETE

PROYECTO : "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN

JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC"

PROPIET: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO

1- DATOS GENERALES

A- POR PESO

MATERIALES UNIDAD AFECTO IGV PESO.UNIT. PESO.TOTAL


CEMENTO BL. 6,631.30 42.50 281,830.25
FIERRO, CLAV. ETC KG 21,897.13 1.00 21,897.13
MADERA P2 13,377.77 1.50 20,066.66
LADRILLO UN 0.00 4.50 0.00
CALAMINA UN 0.00 3.00 0.00
YESO DE 28GK BL 51.26 25.00 1,281.50
EXPLOSIVOS(dinamita)KG 0.00 1.00 0.00
ADOQUIN DE CONCRET UN 0.00 0.10 0.00
OTROS KG 33,000.00 1.00 33,000.00

PESO TOTAL 358,075.54

B- POR VOLUMEN

EN AGREGADOS Y MADERA
DESCRIPC. UNIDAD AFECTO IGV SIN IGV
ARENA M3 0.00 0.00
PIEDRA M3 0.00 0.00
HORMIGÓN M3 0.00 0.00 NOTA:
MADERA P2 0.00 0.00 LOS AGREGADOS SERAN PUESTO EN PIE DE OBRA
GRAVA M3 0.00 0.00
MAT. ZARANDEAD M3 0.00 0.00

VOLUMEN TOTAL
CAPACIDAD DEL CAMION (M3)
NUMERO DE VIAJES
REDONDEO

EN TUBERIA UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 2.00 M.


CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML No de tubos No VIAJES
Tub, 1" 3,360.00 U
Tub,1 1/2" 1,690.00 U
Tub 2:" 994.00 U
Tub, 3" 470.00 U
Tub 4": 259.00 U
Tub 6:" U-PVC 110.00 U
Tub 8" U-PVC 65.00 U
Tub 6'; CSN 160.00 U
Tub 8'; CSN 80.00 U
NUMERO TOTAL DE VIAJES
REDONDEO
TUBERIA EN VOLUMEN

2- FLETE TERRESTRE

UNIDAD DE TRANSPORTE
UNIDAD QUE DA COMPROBANTE UNIDAD QUE NO DA COMPROBANTE
CAPACIDAD DEL CAMION ( M3 ) 6.00 CAPACIDAD DEL CAMION ( M3 )
COSTO POR VIAJE S/. 135.00 COSTO POR VIAJE S/.
CAPACIDAD DEL CAMION (KG) 6,000.00 CAPACIDAD DEL CAMION (KG)
FLETE POR KG 0.02
AFECTO IGV SIN IGV FLETE POR PESO =Peso Total * Flete por peso
FLETE POR PESO 8,014.10 FLETE POR VOLUMEN=No viajes*costo por viaje
FLETE POR VOLUMEN
AGREGADOS
TUBERIA
COSTO FLETE TERRESTRE 8,014.10

3- FLETE FLUVIAL

UNIDAD DE TRANSPORTE QUE DA COMPROBANTE


UNIDAD DE TRANSPORTE QUE NO DA COMPROB.

CAPACIDAD DEL BOTE EN PESO (KG)


CAPACIDAD DEL BOTE EN VOLUMEN (M3)
COSTO POR VIAJE
COSTO POR PESO

AFECTO IGV SIN IGV FLETE POR PESO =Peso Total * Flete por peso
FLETE POR PESO FLETE POR VOLUMEN=No viajes*costo por viaje
FLETE POR VOLUMEN
AGREGADOS
TUBERIA
COSTO FLETE FLUVIAL

4- FLETE EN ACEMILA

La tubería será transportada por peones

Costos de transporte por viaje


Acemila S/.
Peon S/.

Cantidad Unidades de Capacidad de Número de Flete no


Carga Carga Viajes Afecto a IGV
Peso total tubería de agua
Peso total tubería desague CSN
Peso total tubería desague PVC
Numero bolsas de cemento
Peso resto de materiales
Agregados Total en Kilos

COSTO TOTAL DEL FLETE EN ACEMILA S/.

RESUMEN DE FLETE TOTAL

AFECTO IGV SIN IGV


FLETE TERRESTRE 8,014.10
FLETE FLUVIAL
FLETE EN ACEMILA
FLETES TOTALES S/. 8,014.10 FLETE TOTAL: 8,014.10
RESUMEN PRESUPUESTO ANALÍTICO - COSTO DIRECTO

PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN
JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC"

PROPIET: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO

TOTAL PRESUPUESTO DE OBRA S/ 1,390,152.86


TOTAL COSTO DIRECTO S/ 995,558.80

CÓDIGO ESPECIFICA DE GASTOS C.DIRECTO


65.11.10 RETRIBUCIONES COMPLEMENTARIAS 191,966.90
65.11.11 OBLIGACIONES DEL EMPLEADOR 28,684.71
65.11.13 GASTOS VARIABLES Y OCASIONALES 0.00
65.11.18 ESCOLARIDAD, AGUINALDOS Y GRATIFICACI 0.00
65.11.20 VIÁTICOS 0.00
65.11.22 VESTUARIO 0.00
65.11.23 COMBUSTIBLES Y LUBRICANTES 10,243.28
65.11.24 ALIMENTOS 0.00
65.11.26 MATERIAL EXPLOSIVO 0.00
65.11.29 MATERIALES DE CONSTRUCCION 627,397.02
65.11.30 MATERIAL DE CONSUMO 6,552.07
65.11.36 TARIFA DE SERVICIOS BASICOS 0.00
65.11.38 SEGUROS 0.00
65.11.39 OTROS SERVICIOS PERSONAS JURÍDICAS 130,714.83
65.11.49 MATERIALES DE ESCRITORIO 0.00
65.11.51 EQUIPO Y MATERIAL DURADERO 0.00
TOTAL COSTO DIRECTO 995,558.80
DESAGREGADO DEL PRESUPUESTO ANALÍTICO

COSTO DIRECTO
65.11.10 RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO S/. 191,966.90

01 JORNAL

DEL EMPLEADO EVENTUAL

CARGO UNID. P.U. CANTIDAD SUB TOTAL


TOPOGRAFO HH 42.93 14.00 601.08
OPERARIO HH 5,498.84 13.75 75,608.98
OFICIAL HH 3,069.69 12.00 36,836.29
PEON HH 7,552.21 10.45 78,920.55
TOTAL 191,966.90

65.11.11 OBLIGACIONES DEL EMPLEADOR S/. 28,684.71

01 DESCUENTO DE JORNAL

DESCUENTO SNP 13%

CARGO UNID. P.U. CANTIDAD SUB TOTAL


TOPOGRAFO HH 6.42 14.00 89.82
OPERARIO HH 821.67 13.75 11,297.89
OFICIAL HH 458.69 12.00 5,504.27
PEON HH 1,128.49 10.45 11,792.73
TOTAL 28,684.71

65.11.23 COMBUSTIBLES , CARBURANTES Y LUBRICANTES S/. 10,243.28

DESCRIPCION UND P.U. CANTIDAD TOTAL


FLETE ANDAHUAYLAS - SAN JERONIMO GLB 8,014.10 1.00 8,014.10
MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 2,229.18 1.00 2,229.18
TOTAL 10,243.28

65.11.29 MATERIALES DE CONSTRUCCION S/. 627,397.02

01 MATERIALES DE CONSTRUCCION

DESCRIPCION UNIDAD P.U. CANTIDAD TOTAL


EMBONE PARA TUBO DE Ø 20mm. TP pza 8.05 76.59 616.55
PERFILADO Y COMPACTADO MANUAL m2 11.45 159.67 1,828.22
ALAMBRE NEGRO RECOCIDO # 16 kg 3.81 350.43 1,335.14
ALAMBRE NEGRO RECOCIDO # 8 kg 3.81 382.47 1,457.21
LIMPIEZA FINAL DE OBRA GLB 2,966.10 1.00 2,966.10
INSTALACION Y COLOCACION DE ESTRUCTURA DE TECHO. INC. PINTURA Y OTROS A TODO GLB 59,224.11 1.00 59,224.11
INSTALACION Y COLOCACION DE ESTRUCTURA DE TOBOGAN. INC. PINTURA Y OTROS SEG GLB 29,661.02 1.00 29,661.02
CLAVOS PARA MADERA C/C 3" kg 3.81 350.95 1,337.12
CLAVOS PARA MADERA C/C 2 1/2 " kg 3.81 1.27 4.84
CLAVOS PARA MADERA C/C 4" kg 3.81 81.94 312.19
PERNOS DE ANCLAJE D 1/2"x8" und 2.12 220.96 468.44
VOLANDAS DE PRESION 3/4" pza 0.20 74.76 14.95
MECHA NARANJA m 1.27 10.00 12.70
FULMINANTE und 2.00 20.00 40.00
DINAMITA kg 64.00 3.00 192.00
BARRENO 5´ x 1/8" und 145.00 0.24 34.80
JABONERA C/ASA P/BAÑO 15 x 15 BLANCA und 25.12 4.00 100.48
TERMINAL DE COBRE PARA CONDUCTOR DE 50mm2. und 4.86 2.20 10.69
PLANCHA DE POLICARBONATO TRASLUCIDO STANDAD DE e=6 mm m2 38.14 1,542.77 58,841.25
TIRAFON DE 1/4" X 2½" und 1.10 1,425.00 1,567.50
ACERO DE REFUERZO FY=4200 GRADO 60 kg 2.97 20,184.88 59,949.09
MOLDE METALICO PARA BUZON und 45.76 1.00 45.76
ARENA FINA m3 76.27 61.75 4,709.67
ARPILLERA m 3.50 213.10 745.85
ADOQUIN DE CONCRETO DE 0.10X0.20X0.05m. DE COLORES und 0.93 54,668.65 50,841.84
ARENA m3 76.27 56.88 4,338.24
TIERRA COMUN CERNIDA m3 54.62 1.00 54.62
PIEDRA CHANCADA DE 1/2" m3 33.90 426.28 14,450.89
PIEDRA GRANDE DE 8" m3 29.66 75.33 2,234.29
PIEDRA MEDIANA DE 4" m3 26.66 107.59 2,868.35
PIEDRA MEDIANA DE 6" m3 26.66 306.24 8,164.36
ARENA GRUESA m3 33.90 288.26 9,772.01
AFIRMADO m3 25.42 564.15 14,340.69
MATERIAL GRANULAR SELECCIONADO m3 25.42 19.50 495.69
MATERIAL SELECCIONADO m3 25.42 5.00 127.10
CONECTOR ANDERSON pza 8.47 1.00 8.47
CONDUCTOR DE COBRE DESNUDO BLANDO DE 50mm2. m 4.50 22.00 99.00
CONDUCTOR SUBTERRANEO DE 2-1x50mm2. TIPO NYY m 4.50 29.14 131.13
CONDUCTOR DE COBRE de 2.5mm2 TIPO TW (ROJO, AZUL Y NEGRO) m 1.50 602.09 903.14
CONDUCTOR DE COBRE de 2.5mm2 TIPO TW (VERDE) m 1.50 216.18 324.27
TECNOPORT DE 1" x 4" x 8´ pln 29.50 8.77 258.72
CABLE TW # 12 AWG - 6 MM2 m 2.37 27.00 63.99
CABLE DE ENERGIA 4mm NHX-90 m 3.90 47.88 186.73
CABLE DE ENERGIA 6mm NHX-90 m 2.37 47.88 113.48
CABLE DE ENERGIA N2XH DE 16mm m 10.36 31.50 326.34
TECNOPORT DE 12 x 30 x 3M PARA TECHO und 3.56 1,297.37 4,618.64
INODORO TQUE. BAJO NORMAL BLANCO C/A. und 256.92 5.00 1,284.60
DUCHA GIRATORIA und 64.90 4.00 259.60
ESCALERA DE GATO METALICA CON F°G° 1"INC.INST. ESCALERA DE GATO MET.ANTICOR., A und 5,508.47 1.00 5,508.47
REDUCCION PVC SAP 3/4" A 1/2" pza 3.12 10.00 31.20
REDUCCION PVC SAP 4" x 2" pza 5.51 4.00 22.04
ADAPTADOR PVC-SAP DE 1/2" pza 0.85 40.00 34.00
ADAPTADOR PVC-SAP DE 1 1/2" pza 0.90 2.00 1.80
TARUGO DE PVC DE 1/4" und 1.18 30.00 35.40
TABLERO METALICO CON PUERTA Y CHAPA PARA EMPOTRAR CON 03 BAR und 72.27 1.00 72.27
TABLERO METALICO CON PUERTA Y CHAPA P/EMPOTRAR C/36 POLOS und 76.27 3.00 228.81
TRAMPA PVC SAL P 2" pza 10.50 4.00 42.00
TRAMPA PVC SAL P 4" pza 22.50 1.00 22.50
TRAMPA PVC SAL P 3" pza 15.50 2.00 31.00
INTERRUPTOR TERMOMAGNETICO DE 3x60Ax220V. FIJO und 38.98 1.00 38.98
INTERRUPTOR TERMOMAGNETICO DE 3x80Ax220V. FIJO und 93.22 2.00 186.44
INTERRUPTOR TERMOMAGNETICO DE 3x200Ax220V. FIJO und 40.34 1.00 40.34
INTERRUPTOR TERMOMAGNETICO DE 3x20Ax220V. und 40.34 3.00 121.02
INTERRUPTOR TERMOMAGNETICO DE 3x15Ax220V. und 40.34 5.00 201.70
INTERRUPTOR SIMPLE und 5.90 15.00 88.50
CAJA PVC OCTOGONAL TP. pza 1.27 27.50 34.93
CAJA PVC RECTANGULAR TP pza 1.27 33.85 42.99
LAMPARA DE VAPOR DE SODIO DE 70W. CON DEFLECTOR pza 207.63 13.00 2,699.19
ARTEFACTO FLUORESCENTE DE 3 X 36 W. A/F pza 83.05 21.00 1,744.05
REFLECTOR DE 250V, HALOGENURO METALICO C/EQUIPO pza 288.14 4.00 1,152.56
TOALLERA C/BARRA PLASTICA BLANCA und 21.18 4.00 84.72
TOMACORRIENTE DOBLE CON PUESTA A TIERRA 250V. PESADO pza 9.61 18.85 181.15
ASFALTO RC-250 gln 21.19 1.27 26.91
PAPELERA DE 13 x 15 BLANCA und 27.12 5.00 135.60
LADRILLO ARCILLA KK. 9 x 12 x 24cm. und 0.35 14,847.61 5,196.66
FRAGUA kg 3.81 36.43 138.80
LOSETA CERAMICA 40 x 40cm. m2 27.12 31.19 845.87
LOSETA CERAMICA 30 x 30cm. m2 27.12 50.82 1,378.24
LUMINARIA DE EMERGENCIA C/ 2 LAMP. ENCAND. 50 W und 55.08 10.00 550.80
CERAMICO 60 cm x 60 cm DE ALTO TRANSITO m2 38.14 33.15 1,264.34
CONTRAZOCALO DE CERAMICO DE H= 10CM m 3.81 26.88 102.41
CEMENTO PORTLAND TIPO I (42.5KG) BOL 18.64 4,699.99 87,607.81
BISAGRA CAPUCHINA 4" und 5.93 16.00 94.88
CERRADURA DE PERRILLA PARA INTERIOR und 27.12 8.00 216.96
BISAGRA CAPUCHINA PLOMA 3 1/2" X 3 1/2" PAR 5.93 4.00 23.72
MANIJA DE BRONCE PARA PUERTA 4" und 5.08 8.00 40.64
CERRADURA PARA PUERTAS DE TRES GOLPES und 55.08 1.00 55.08
CINTA SEÑALIZADORA AMARILLA PARA CABLE DE BAJA TENSION m 0.60 33.30 19.98
CINTA AISLANTE 20m. 3M. 1700 rll 4.23 7.28 30.79
CINTA TEFLON rll 1.18 12.25 14.46
OCRE kg 10.17 98.73 1,004.08
SOLDADURA CELLOCORD 1/8" kg 12.53 23.83 298.59
YESO DE 28 Kg BOL 8.47 70.33 595.70
VARILLA DE COBRE DE 3/4" x 2.40m und 211.86 1.00 211.86
LAVATORIO TIPO ESTANDAR BLANCO INC. ACCESORIOS pza 101.69 1.00 101.69
OVALIN LOZA BLANCA DE PRIMERA INC. ACCESORIOS und 137.66 6.00 825.96
SILICONA und 16.94 186.74 3,163.38
PEGAMENTO DE MAYOLICA kg 10.42 30.95 322.50
PEGAMENTO PARA PVC gln 72.88 2.81 204.79
CRUCETAS cto 0.25 5.52 1.38
RODOPLAST PARA BORDE DE MAYOLICAS m 4.34 13.20 57.29
IMPRIMANTE gln 17.70 8.90 157.53
IMPERMEABILIZANTE gln 33.90 30.99 1,050.56
LIJA und 1.27 42.24 53.64
WINCHA DE 50 M und 55.00 24.67 1,356.85
HORMIGON m3 33.90 327.81 11,112.76
LIJA PARA MADERA und 1.69 17.37 29.36
AGUA m3 0.25 823.47 205.87
ALMACEN DE OBRA, OFICINA TECNICA Y GUARDIANIA GLB 3,813.56 1.00 3,813.56
CARTEL DE OBRA INC.INSTALACION Y TRANSP GLB 2,372.88 1.00 2,372.88
PRUEBA HIDRAULICA MAS DESINFECCION DE SIST. DE AGUA GLB 296.61 2.00 593.22
MADERA CORRIENTE PARA ESTACAS p2 1.50 245.54 368.31
MADERA NACIONAL PARA ENCOFRADO p2 2.97 824.29 2,448.14
VENTANA DE VIDRIO TEMPLADO DE 8mm CON ACC. DE ACERO m2 169.49 105.34 17,854.08
REGLA DE MADERA p2 5.51 207.27 1,142.06
ANDAMIO DE MADERA p2 1.50 1,066.05 1,599.08
MADERA EUCALIPTO ROLLIZO p2 1.50 1,044.19 1,566.29
MADERA MACHIEMBRADA DE TORNILLO 3/4"X4"X3' p2 4.50 625.00 2,812.50
LISTONES MADERA 3"X4"X3M pza 12.72 118.47 1,506.94
TRIPLAY DE 19 MM.(TRATADO CON ADITIVO) pln 67.80 87.42 5,927.08
MADERA TORNILLO INC.CORTE P/ENCOFRADO p2 2.97 7,515.05 22,319.70
CAJA DE DESAGUE DE 12"X24" und 55.00 8.00 440.00
CAJA DE REGISTRO DE CONCRETO CON TAPA SEÑALIZADA und 80.51 1.00 80.51
CAJA METALICA CON TAPA DE 15 x 15 x 10 (1/16) pza 16.95 2.00 33.90
CAJA DE CONCRETO P/MEDIDOR AGUA und 38.14 16.00 610.24
TAPA C/MARCO FºFº DE DESAGUE 12" X 24" pza 45.00 3.00 135.00
TAPA CIEGA PARA CAJA OCTAGONAL pza 1.02 1.78 1.82
TAPA DE CONCRETO ARMADO 0.60 x 0.80m. und 127.20 1.00 127.20
TAPA METALICA CON MARCO Y SEGURO und 35.00 16.00 560.00
PUERTA DE MADERA CONTRAPLACADA CON TRYPLAY DE 6mm m2 110.00 3.96 435.60
ANGULO 1 1/2" x 1 1/2" x 1/4" m 11.30 281.40 3,179.82
PLATINA DE ACERO 1/2" x 1/2" m 8.41 469.00 3,944.29
ANGULO ALUMINIO 1" x 1" x 1/8" m 3.98 9.01 35.86
TEE DE ALUMINIO 1 1/2" x 1 1/2" x 1/8" x 1/8 m 6.36 3.31 21.05
THINER gln 18.49 16.35 302.31
PINTURA LATEX gln 21.19 7.98 169.10
PINTURA ANTICORROSIVO ZINCROMATICO gln 31.36 0.40 12.54
BARNIZ MARINO gln 50.85 0.40 20.34
BENTONITA SODICA (BOLSAx30KG) bls 42.37 2.00 84.74
FABRICACION Y COLOCACION CASILLEROS GUARDA ROPAS SEGUN DISEÑO und 1,864.41 2.00 3,728.82
FABRICACION Y COLOCACION DE BANCAS DE MADERA SEGUN DISEÑO und 423.73 2.00 847.46
FABRICACION Y COLOCACION DE MESA DE TENCION DE MADERA, SEGUN DISEÑO und 2,118.64 1.00 2,118.64
CONSTRUCCION DE JARDINERIA DE CONCRETO ARMADO SEGUN DISEÑO GLB 10,169.49 1.00 10,169.49
FABRICACION Y COLOCACION DE BANCAS DE MADERA SEGUN DISEÑO EN PARQUE pza 2,509.14 5.00 12,545.70
PEDESTAL DE CONCRETO SEGUN DISEÑO GLB 1,271.19 6.00 7,627.14
FABRICACION Y COLOCACION DE BANCA DE CONCRETO (L=1.00M) SEGUN DISEÑO GLB 508.47 1.00 508.47
SARDINEL SOBRE MURO DE PROTECCION EXISTENTE GLB 2,542.37 1.00 2,542.37
FABRICACION Y COLOCACION DE ESCALERA TIPO GATO EN PISCINA, SEGUN DISEÑO GLB 1,694.92 2.00 3,389.84
FABRICACION Y COLOCACION DE ESCALERA METALICA EN ADMINISTRACION, SEGUN DISE GLB 4,237.29 1.00 4,237.29
PINTURA ESMALTE gln 38.14 17.06 650.67
PINTURA EPOXICA PARA PISCINA gln 169.49 13.39 2,269.47
SELLADOR gln 25.42 11.30 287.25
SAL INDUSTRIAL kg 42.37 2.00 84.74
PUERTA DE DOS HOJAS und 240.00 2.22 532.80
UNION UNIVERSAL PVC SAP DE 3/4" und 8.84 34.00 300.56
UNION UNIVERSAL DE Fo. GALV. DE 1 1/2" und 8.80 2.00 17.60
NIPLE DE Fo Go DE 1 1/2" x 2 1/2" und 1.20 2.00 2.40
SUMIDERO DE BRONCE CROMADO 2" pza 3.81 4.00 15.24
SUMIDERO DE BRONCE CROMADO 4" pza 7.63 1.00 7.63
SUMIDERO DE FONDO PVC PARA PISCINA und 100.00 7.00 700.00
SUMIDERO DE BRONCE CROMADO 3" pza 5.62 2.00 11.24
ABRAZADERA DE F° F° DE 4" pza 8.42 15.00 126.30
TUB. PVC SAP PRESION P/AGUA C-10 R. 2" m 10.00 66.25 662.50
TEE PVC SAP DE 1/2" C/R PARA AGUA und 2.20 10.00 22.00
TEE PVC SAP DE 2" C/R PARA AGUA und 8.00 64.95 519.60
CURVA PARA TUBOS DE Ø 35mm. TP pza 2.50 9.75 24.38
CURVA PARA TUBOS DE Ø 15mm. TP pza 1.50 45.65 68.48
CURVA PARA TUBOS DE Ø 20mm. TP pza 1.80 188.34 339.01
CURVA PARA TUBOS DE Ø 25mm. TP pza 2.00 15.00 30.00
TUBERIA F° G° 2" m 11.30 88.70 1,002.31
TUBERIA PVC TP PARA INSTALACIONES ELECTRICAS DE Ø 35mmx3m. pza 8.50 13.65 116.03
TUBERIA PVC TP PARA INSTALACIONES ELECTRICAS DE Ø 15mmx3m. pza 7.00 63.91 447.37
TUBERIA PVC TP PARA INSTALACIONES ELECTRICAS DE Ø 20mmx3m. pza 7.50 236.00 1,770.00
TUBERIA PVC SAL DE 2" m 4.08 186.57 761.21
TUBERIA PVC TP PARA INSTALACIONES ELECTRICAS DE Ø 25mmx3m. pza 8.00 17.50 140.00
TUBERIA PVC SAP C-10 Ø 3/4" AGUA m 4.71 96.82 456.02
TUBERIA PVC UF Ø 6" DESAGUE m 36.66 29.36 1,076.34
TEE PVC SAL 4" x 4" pza 5.51 4.00 22.04
TEE PVC SAL 4" x 2" pza 5.51 4.00 22.04
YEE PVC SAL DE 4" x 2" pza 6.36 4.00 25.44
TUBERIA PVC SAL DE 3" m 10.00 26.81 268.10
TUBERIA PVC SAP C-10 Ø 1 1/2" AGUA m 17.97 1.05 18.87
TUBERIA PVC SAP C-10 Ø 1/2" AGUA m 2.20 11.33 24.93
CODO PVC SAL 2" x 90° pza 5.51 196.28 1,081.52
CODO PVC SAL 2" x 45° pza 5.51 4.00 22.04
CODO PVC SAL 4" - 2° pza 2.12 4.00 8.48
CODO PVC SAL 4" x 90° pza 2.12 4.00 8.48
CODO PVC SAP (AGUA) CON ROSCA 1/2" x 90. pza 2.12 40.00 84.80
YEE PVC SAL 2" x 2" pza 3.12 5.00 15.60
TUBO PVC SAL 4" m 6.36 310.08 1,972.11
TUBO DE F° G° DE 1 1/2" ML 10.30 300.00 3,090.00
PUERTA DE PLANCHA METALICA DE TUBO LAC e=2mm m2 104.24 12.80 1,334.27
DIVISIONES DE TUBO LAC e=2mm PARA SS.HH Y ADMINISTRACION m2 101.69 37.60 3,823.54
TUBO DE F° G° DE 3/4" ML 13.27 1.00 13.27
DESNATADOR P/PISCINA P/TUB. DE 1 1/2" und 250.00 9.00 2,250.00
BOQUILLA DE LLENADO DE PVC 4" und 20.00 4.00 80.00
PUERTA DE POLICARBONATO ALBEOLAR DE 6mm, CON MARCOS DE ALUMINIO. m2 104.24 27.22 2,837.41
CODOS PVC SAL 3" X 90° pza 5.51 26.03 143.43
YEE PVC SAL DE 4" X 4" pza 5.51 4.00 22.04
SOMBRERO DE VENTILACION PVC SAL 2" pza 3.54 4.00 14.16
TUBO Fª DE 4" INC. DETALLE pza 101.69 13.00 1,321.97
TUBO CUADRADO DE ALUM.1.1/2"X1.1/2" x 2MM m 9.83 3.98 39.12
UNION PVC SEL 1/2" pza 0.85 2.50 2.13
VALVULA ESFERICA DE 3/4" und 35.59 15.00 533.85
VALVULA COMPUERTA DE 1 1/2" und 38.14 1.00 38.14
VIDRIO TEMPLADO DE E=6mm. p2 16.50 27.52 454.08
ESPEJO BISELADO DE 0.60 x 1.20 m und 111.86 2.00 223.72
MARCO FºFº PARA BUZON DE D=0.60CMX125KG und 41.30 1.00 41.30

TOTAL 627,397.02

65.11.30 MATERIALES DE CONSUMO S/. 6,552.07

01 HERRAMIENTAS

DESCRIPCION UNI CANT P.U TOTAL


PALAS INCL MANGO PZA 20.00 30.00 600.00
PICO INCL MANGO PZA 20.00 30.00 600.00
MANGUERA DE 3/4" ROLL 2.00 90.00 180.00
BOOGUIES UND 10.00 190.00 1,900.00
LLANTA PARA BOOGUIE PZA 10.00 28.00 280.00
HOJA DE SIERRA METALICA HJA 5.00 8.00 40.00
WINCHA DE 7.5 M. PZA 1.00 35.00 35.00
WINCHA DE 5 M. PZA 1.00 30.00 30.00
COMBA DE 4 LBS PZA 1.00 25.00 25.00
COMBA DE 6 LBS PZA 1.00 45.00 45.00
COMBA DE 20 LB PZA 1.00 70.00 70.00
CINCEL PZA 1.00 12.00 12.00
BALDE DE 18 LT PZA 10.00 3.50 35.00
CILINDRO PZA 5.00 120.00 600.00
RASTRILLO PZA 2.00 15.00 30.00
CORDEL ROLL 3.00 10.00 30.00
OTROS HERRAMIENTAS GLB 1.00 2,040.07 2,040.07
TOTAL 6,552.07

65.11.39 OTROS SERVICIOS DE TERCEROS S/. 130,714.83

01 ALQUILER DE MAQUINARIA Y EQUIPO

DESCRIPCION UND P.U. CANT. SUB TOTAL


TRACTOR DE ORUGAS DE 270 A 295 HP hm 186.44 29.13 5,431.00
MOTOBOMBA 10 HP 4" hm 16.95 3.46 58.65
SOLDADURA ELECTRICA hm 11.25 149.56 1,682.55
VOLQUETE DE 15 M3 hm 93.22 173.57 16,180.20
COMPRESORA NEUMATICA 150 HP. 380-590 PCM hm 42.37 3.35 141.94
MARTILLO NEUMATICO DE 25KG. hm 20.50 0.91 18.66
SUMINIS E INST. DE EQUIPO DE BOMBEO DE PISCINA, ELECTROBOMBA DE 2HP, TIPO HF (ALTund 35,073.08 1.00 35,073.08
CARGADOR S/LLANTAS 100-115 HP 2-2 25 YD3 hm 152.54 56.49 8,616.98
RETROEXCAVADOR S/ORUG 115-165HP .75-1.4Y hm 169.49 275.17 46,638.56
VIBRADOR DE CONCRETO 4 HP 2.40" hm 5.93 170.85 1,013.14
MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 12.71 362.75 4,610.55
NIVEL TOPOGRAFICO hm 5.00 33.20 166.00
ESTACION TOTAL hm 16.95 44.35 751.73
COMPACTADOR VIBR. TIPO CANGURO hm 8.47 1,219.81 10,331.79
TOTAL 130,714.83

COSTO DIRECTO TOTAL S/. 995,558.80


DESAGREGADO DE GASTOS GENERALES

"MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN JERÓNIMO, PROVINCIA DE
OBRA:
ANDAHUAYLAS-APURIMAC"

CLIENTE:MUNICIPALIDAD DISTRITAL DE SAN JERONIMO


REGIÓN: APURÍMAC PROVINCIA: ANDAHUAYLAS DISTRITO: SAN JERONIMO

A. CARACTERÍSTICAS
Costo Directo 995,558.80
Gastos Generales (Fijos + Variables 7.7599132% 77,254.50
Utilidad (7.00%) 69,689.12
SUB TOTAL 1,142,502.42
IGV (18%) 205,650.44
PRESUPUESTO TOTAL 1,348,152.86
SUPERVISION 31,000.00
LIQUIDACION DE OBRA 11,000.00
PRESUPUESTO TOTAL DE OBRA 1,390,152.86

Plazo de ejecución 180 días calendarios

B. GASTOS GENERALES VARIABLES

1.00. ADMINISTRACIÓN Y GENERALES DE OBRA


1.01. Personal necesario de obra
a) Obra Tiempo Costo Participación Parcial Total
Residente de Obra ING. CIVIL 6.00 3,000.00 1.00 18,000.00 55,500.00
Asistente de Obra Especialista en Obras Civiles - Construccion ING. CIVIL 6.00 3,000.00 0.50 9,000.00
Especialista en Suelos (CIVIL y GEOLOGO) 6.00 3,000.00 0.25 4,500.00
Topografo (Tecnico en Construccion Civil) 6.00 2,000.00 0.25 3,000.00
Asistente Administrativo (Administrador) 6.00 1,500.00 1.00 9,000.00
Maestro de Obra 6.00 2,000.00 1.00 12,000.00

b) Leyes Sociales (planilla sin oficina) 55,500.00 0.00 0.00 0.00

SUB TOTAL 55,500.00

TOTAL 1.00. ADMINISTRACIÓN Y GENERALES DE OBRA 55,500.00

2.00. ADMINISTRACIÓN Y GENERALES DE OFICINA


2.01. Personal necesario de oficina
a) Oficina Central Tiempo Costo Participación Parcial Total
Gerente 6.00 1,000.00 0.25 1,500.00 4,425.00
Ing. Coordinador 2,500.00 0.25 0.00
Secretaria 6.00 1,500.00 0.13 1,125.00
Contabilidad 6.00 1,500.00 0.20 1,800.00

b) Leyes Sociales (planilla sin oficina) 4,425.00 0.00 0.00 0.00

c) Varios
Alquiler cede central 6.00 500.00 0.25 750.00 4,827.92
Viajes a Obra 6.00 100.00 0.25 150.00
Útiles de Oficina y Dibujo 6.00 500.00 0.25 750.00
Teléfono y telefax 6.00 100.00 0.25 150.00
Computadora e Impresora 6.00 500.00 0.25 750.00
Fotocopiadora de Planos y Otros 6.00 500.00 0.25 750.00
Seguros y Pólizas 6.00 250.00 1.00 1,500.00
Otros Gastos 1.00 27.92 1.00 27.92
SUB TOTAL 9,252.92

TOTAL 2.00. ADMINISTRACIÓN Y GENERALES DE OFICINA 9,252.92

3.00. GASTOS FINANCIEROS


3.01. Gastos de Carta Fianza Tiempo Costo Participación Parcial Total
a) Carta Fianza por Adelanto Directo 1.00 269,630.57 0.003 808.89 808.89
0.20
b) Carta Fianza por Adelanto Materiales 1.00 539,261.14 0.003 1,617.78 1,617.78
0.40
c) Carta Fianza por Fiel Cumplimiento 1.00 134,815.29 0.003 404.45 404.45
0.10
SUB TOTAL 3.01 2,831.12
3.02. Tributos
a) Varios 1,390,152.86 0.001 1390.15 1,390.15
SUB TOTAL 3.02 1,390.15

TOTAL 3.00. GASTOS FINANCIEROS 4,221.27

TOTAL GASTOS GENERALES VARIABLES


TOTAL 1.00. ADMINISTRACIÓN Y GENERALES DE OBRA S/. 55,500.00
TOTAL 2.00. ADMINISTRACIÓN Y GENERALES DE OFICINA S/. 9,252.92
TOTAL 3.00. GASTOS FINANCIEROS S/. 4,221.27
TOTAL S/. 68,974.19
C. GASTOS GENERALES FIJOS
DESCRIPCIÓN Unidad Cantidad Costo Parcial Total
a) Gastos de licitación y contratación
Gastos en documentos de presentación de licitación. Glb. 1.00 200.00 200.00 800.00
Gastos de visita a obra. Glb. 1.00 100.00 100.00
Gastos de elaboración de propuestas. Glb. 1.00 250.00 250.00
Gastos de estudios de programación. Glb. 1.00 250.00 250.00

SUB TOTAL a) 800.00


b) Gastos indirectos varios
Gastos de licitación no otorgadas. Glb. 1.00 300.00 300.00 4,700.00
Inscripción en el Registro Nacional de Contratistas. Glb. 1.00 1,000.00 1,000.00
Patentes y Regalías. Glb. 1.00 1,000.00 1,000.00
Consultores y asesores. Glb. 1.00 1,200.00 1,200.00
Obligaciones fiscales. Glb. 1.00 1,200.00 1,200.00
SUB TOTAL b) 4,700.00

c) Aportaciones obligatorias
Contribucion a Sencico (0.2%) Glb. 1.00 2,780.31 2,780.31 2,780.31

TOTAL GASTOS GENERALES FIJOS


a) Gastos de licitación y contratación S/. 800.00
b) Gastos indirectos varios S/. 4,700.00
c) Aportaciones obligatorias S/. 2,780.31
TOTAL S/. 8,280.31

D. RESÚMEN GENERAL

INCIDENCIA DE GASTOS GENERALES MONTO PORCENTAJE


VARIABLES 68,974.19 89.28 %
FIJOS 8,280.31 10.72 %
TOTAL 77,254.50 100.00 %
RESUMEN PRESUPUESTO ANALÍTICO - SUPERVISION

PROYECTO"MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN


JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC"

PROPIET: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO

COSTO TOTAL PROYECTO S/ 1,390,152.86


COSTO DIRECTO S/ 995,558.80
SUPERVISION S/ 31,000.00

CÓDIGO ESPECIFICA DE GASTOS G. GRALES


65.11.10 RETRIBUCIONES COMPLEMENTARIAS 24,000.00
65.11.11 OBLIGACIONES DEL EMPLEADOR 0.00
65.11.13 GASTOS VARIABLES Y OCASIONALES 0.00
65.11.20 VIÁTICOS 0.00
65.11.22 VESTUARIO 318.00
65.11.23 COMBUSTIBLES Y LUBRICANTES 1,200.00
65.11.24 ALIMENTOS 0.00
65.11.26 MATERIAL EXPLOSIVO 0.00
65.11.29 MATERIALES DE CONSTRUCCION 0.00
65.11.30 MATERIAL DE CONSUMO 434.05
65.11.32 PASAJES Y GASTO DE TRANSPORTE 0.00
65.11.38 SEGUROS 2,523.97
65.11.39 OTROS SERVICIOS DE TERCEROS 0.00
65.11.51 EQUIPO Y MATERIAL DURADERO 2,523.97
TOTAL GASTOS GENERALES 3.00 % COSTO DIRECTO 31,000.00
DESAGREGADO DEL PRESUPUESTO ANALÍTICO

GASTOS GENERALES
5.11.10 RETRIBUCIONES COMPLEMENTARIAS-CONTRATOS A PLAZO FIJO S/. 24,000.00

DEL EMPLEADO EVENTUAL

CARGO N° DE PERSONAS MESES COSTO SUB TOTAL


SUPERVISOR DE OBRA 1.00 6.00 4,000.00 24,000.00
TOTAL 24,000.00

5.11.22 VESTUARIO S/. 318.00

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


CASCOS PVC REFORZADOS UND 1.00 18.00 18.00
ZAPATOS DE CUERO MARCA CAT PAR 1.00 300.00 300.00
TOTAL 318.00

5.11.23 COMBUSTIBLES , CARBURANTES Y LUBRICANTES S/. 1,200.00

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


PETROLIO DIESEL (CAMIONETA DE OBRA) GLN 100.00 12.00 1,200.00
TOTAL 1,200.00

5.11.30 MATERIALES DE CONSUMO


`02 MATERIALES DE ESCRITORIO S/. 434.05

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


ARCHIVADOR DE LOMO ANCHO PARA FORMATO A-4 UND 2.00 6.00 12.00
ANILLOS DE 5/8" UND 2.00 1.00 2.00
BORRADOR BR40 UND 2.00 0.50 1.00
CD RW REGRABABLES UND 4.00 15.00 60.00
CLIP WINGO PEQUEÑO X 100 UNID CJA 2.00 1.00 2.00
CINTA MASKING X 1/2" UND 2.00 3.00 6.00
CORRECTOR UND 2.00 3.50 7.00
CUADERNO 50 HJAS UND 4.00 1.20 4.80
CUTER GRANDE UND 2.00 6.00 12.00
ENGRAMPADOR UND 1.00 22.00 22.00
ESPIRALES DE 7 MM UND 5.00 0.25 1.25
FASTENERX50 UND CJA 2.00 6.00 12.00
FILES UND 5.00 0.20 1.00
LAPICERO AZUL/NEGRO 033 FABER CASTELL UND 10.00 0.50 5.00
LIBRETA DE CAMPO UND 2.00 6.00 12.00
PAPEL CARBON X100 HJAS CJA 1.00 20.00 20.00
PAPEL FOTOCOPIA 80 GR A-4 MLL 2.00 25.00 50.00
PEGAMENTO EN BARRA UND 1.00 5.00 5.00
PERFORADOR S/C UND 1.00 15.00 15.00
PLUMONES DELGADOS FC 45 UND 2.00 2.50 5.00
PLUMONES GRUESOS PARA PAEL FC UND 2.00 2.50 5.00
PLUMON INDELEBLE GRUESO DIFER. COLORES UND 2.00 2.50 5.00
POST IT CUADRADO COLORES PZA 2.00 2.50 5.00
PORTAMINAS UND 2.00 15.00 30.00
REPUESTOS PARA PORTAMINAS UND 2.00 5.00 10.00
RESALTADOR UND 2.00 2.00 4.00
SELLO DE OBRA UND 2.00 35.00 70.00
THONER HP LASERJET 1020 O SIMILAR UND 1.00 50.00 50.00
1.00 434.05

5.11.51 EQUIPO Y MATERIAL DURADERO S/. 2,523.97

DESCRIPCIÓN UND. CANTIDAD P.U. SUB TOTAL


COMPUTADORA PENTIUN IV UND 1.00 2,200.00 2,200.00
ESCRITORIO UND 1.00 300.00 300.00
SILLAS UND 1.00 23.97 23.97
TOTAL 2,523.97

TOTAL GASTOS GENERALES S/. 31,000.00


CRONOGRAMA DE EJECUCIÓN FISICA Y FINANCIERA DE LA OBRA
PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC”
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO FECHA: JUNIO DEL 2016
COD DESCRIPCIÓN DE PRESUP. PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
PAR PARTIDA S/. 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S

01 ESTRUCTURAS 665,896.84
S/. 12,404.45 12,404.45
01.01 OBRAS PROVICIONALES A
% 100%

S/. 71,516.06 35,758.03 35,758.03


01.02 TRABAJOS PRELIMINARES A
% 50% 50%
S/. 66,806.76 16,701.69 16,701.69 16,701.69 16,701.69
01.03 MOVIMIENTO DE TIERRAS A
% 25% 25% 25% 25%
S/. 19,091.45 4,772.86 4,772.86 4,772.86 4,772.86
01.04 CONFORMACION DE BASE Y SUB BASE (PAVIMENTO) A -
% 25% 25% 25% 25%
S/. 105,624.68 26,406.17 26,406.17 26,406.17 26,406.17
01.05 CONCRETO SIMPLE A
% 25% 25% 25% 25%
S/. 223,621.56 18,635.13 18,635.13 18,635.13 18,635.13 18,635.13 18,635.13 18,635.13 18,635.13 18,635.13 18,635.13 18,635.13 18,635.13
01.06 CONCRETO ARMADO A
% - 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8% 8%
S/. 88,885.13 14,814.19 14,814.19 14,814.19 14,814.19 14,814.19 14,814.19
01.07 ESTRUCTURAS METALICAS A
% 17% 17% 17% 17% 17% 17%
S/. 77,946.75 19,486.69 19,486.69 19,486.69 19,486.69
01.08 COBERTURAS A -
% 25% 25% 25% 25%
02 ARQUITECTURA 217,024.62
S/. 17,975.65 4,493.91 4,493.91 4,493.91 4,493.91
02.01 MUROS Y TABIQUES A
% 25% 25% 25% 25%
21,701.35 5,425.34 5,425.34 5,425.34 5,425.34
02.02 REVOQUES ENLUCIDOS Y MOLDURAS A
% 25% 25% 25% 25%
S/. 1,309.92 654.96 654.96
02.03 CIELORASOS A
% 50% 50%
S/. 74,735.04 12,455.84 12,455.84 12,455.84 12,455.84 12,455.84 12,455.84
02.04 PISOS A
% 17% 17% 17% 17% 17% 17%
CRONOGRAMA DE EJECUCIÓN FISICA Y FINANCIERA DE LA OBRA
PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC”
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO FECHA: JUNIO DEL 2016
COD DESCRIPCIÓN DE PRESUP. PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
PAR PARTIDA S/. 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S

S/. 3,277.90 1,638.95 1,638.95


02.05 ZOCALOS Y CONTRAZOCALOS A
% 50% 50%
S/. 8,834.30 2,208.57 2,208.57 2,208.57 2,208.57
02.06 PINTURA A
% 25% 25% 25% 25%
S/. 23,684.83 11,842.41 11,842.41
02.07 CARPINTERIA METALICA A
% 50% 50%
S/. 816.98 816.98
02.08 CERRAJERIA A -
% 100%
CRONOGRAMA DE EJECUCIÓN FISICA Y FINANCIERA DE LA OBRA
PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC”
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO FECHA: JUNIO DEL 2016
COD DESCRIPCIÓN DE PRESUP. PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
PAR PARTIDA S/. 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S 1S 2S 3S 4S

S/. 19,066.32 4,766.58 4,766.58 4,766.58 4,766.58


02.09 VIDRIOS, CRISTALES Y SIMILARES A -
% 25% 25% 25% 25%
S/. 37,608.25 18,804.13 18,804.13
02.10 OBRAS VARIAS A -
% 50% 50%
S/. 8,014.10 1,335.68 1,335.68 1,335.68 1,335.68 1,335.68 1,335.68
02.11 FLETE TERRESTRE A -
% 17% 17% 17% 17% 17% 17%

03 INSTALACIONES ELECTRICAS Y SISTEMAS ESPE 23,335.20


S/. 23,335.20 3,889.20 3,889.20 3,889.20 3,889.20 3,889.20 3,889.20
03 INSTALACIONES ELECTRICAS Y SISTEMAS ESPECIALES A -
% 17% 17% 17% 17% 17% 17%
04 INSTALACIONES SANITARIAS 89,302.14
S/. 54,980.91 7,854.42 7,854.42 7,854.42 7,854.42 7,854.42 7,854.42 7,854.42
04 INSTALACIONES SANITARIAS A
% 14% 14% 14% 14% 14% 14% 14%
S/. 4,759.70 1,189.92 1,189.92 1,189.92 1,189.92
04.07 APARATOS Y ACCESORIOS SANITARIOS A -
% 25% 25% 25% 25%
S/. 29,561.53 7,390.38 7,390.38 7,390.38 7,390.38
04.08 SISTEMA DE DRENAJE PLUVIAL A -
% 25% 25% 25% 25%
49,498.16 52,459.72 16,701.69 16,701.69 63,078.67 45,041.30 45,041.30 57,389.63 32,319.14 30,983.46 30,983.46 38,945.38 44,170.27 42,834.58 49,794.36 56,858.64 46,949.58 31,519.11 51,889.46 46,464.12 46,257.69 44,922.00 27,786.18 26,969.20
COSTO DIRECTO 995,558.80 135,361.26 210,550.90 133,231.44 193,657.85 176,822.27 145,935.08
GASTOS GENERALES (7.7599132%) 77,254.50 10,503.92 16,338.57 10,338.64 15,027.68 13,721.25 11,324.44
UTILIDAD (7.00%) 69,689.12 9,475.29 14,738.56 9,326.20 13,556.05 12,377.56 10,215.46
SUB TOTAL 1,142,502.42 155,340.47 241,628.03 152,896.29 222,241.58 202,921.08 167,474.97
IMPUESTO IGV. (18%) 205,650.43 27,961.28 43,493.05 27,521.33 40,003.49 36,525.79 30,145.49
PRESUPUESTO TOTAL 1,348,152.85 183,301.75 285,121.07 180,417.62 262,245.07 239,446.88 197,620.46
SUPERVISION 31,000.01 5,166.67 5,166.67 5,166.67 5,166.67 5,166.67 5,166.67
LIQUIDACION DE OBRA 11,000.00 11,000.00
PRESUPUESTO TOTAL DE INVERSION 1,390,152.86 188,468.42 290,287.74 185,584.29 267,411.74 244,613.54 213,787.13
AVANCE FISICO EN % 100.0% 13.56% 20.88% 13.35% 19.24% 17.60% 15.38%
AVANCE ACUMULADO EN % 0.00% 13.56% 34.44% 47.79% 67.03% 84.62% 100.00%
CRONOGRAMA DE ADQUISICION DE MANO DE OBRA, MATERIALES E INSUMOS
PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC”

PROPIET: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO 13.56% 20.88% 13.35% 19.24% 17.60% 15.38%
PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
ITEM DESCR IP CIO N UND CANTID. PRECIO TOTAL
% CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO

MANO DE OBRA
0147000032 TOPOGRAFO hh 49.35 14.00 690.90 13.56% 6.69 93.67 20.88% 10.31 144.27 13.35% 6.59 92.23 19.24% 9.49 132.90 17.60% 8.68 121.57 15.38% 7.59 106.25
0147010002 OPERARIO hh 6,320.50 13.75 86,906.88 13.56% 856.89 11,782.30 20.88% 1,319.83 18,147.64 13.35% 843.78 11,602.00 19.24% 1,215.82 16,717.53 17.60% 1,112.17 15,292.27 15.38% 972.01 13,365.13
0147010003 OFICIAL hh 3,528.38 12.00 42,340.56 13.56% 478.36 5,740.27 20.88% 736.79 8,841.43 13.35% 471.04 5,652.43 19.24% 678.72 8,144.69 17.60% 620.86 7,450.31 15.38% 542.62 6,511.42
0147010004 PEON hh 8,680.70 10.45 90,713.27 13.56% 1,176.88 12,298.35 20.88% 1,812.68 18,942.49 13.35% 1,158.87 12,110.15 19.24% 1,669.83 17,449.73 17.60% 1,527.47 15,962.05 15.38% 1,334.98 13,950.50
MATERIALES
0201000027 EMBONE PARA TUBO DE Ø 20mm. TP pza 76.59 8.05 616.55 13.56% 10.38 83.59 20.88% 15.99 128.75 13.35% 10.22 82.31 19.24% 14.73 118.60 17.60% 13.48 108.49 15.38% 11.78 94.82
0201000031 PERFILADO Y COMPACTADO MANUAL m2 159.67 11.45 1,828.22 13.56% 21.65 247.86 20.88% 33.34 381.76 13.35% 21.32 244.07 19.24% 30.71 351.68 17.60% 28.10 321.70 15.38% 24.56 281.16
0202000007 ALAMBRE NEGRO RECOCIDO # 16 kg 350.43 3.81 1,335.14 13.56% 47.51 181.01 20.88% 73.18 278.80 13.35% 46.78 178.24 19.24% 67.41 256.83 17.60% 61.66 234.93 15.38% 53.89 205.33
0202000008 ALAMBRE NEGRO RECOCIDO # 8 kg 382.47 3.81 1,457.21 13.56% 51.85 197.56 20.88% 79.87 304.29 13.35% 51.06 194.54 19.24% 73.57 280.31 17.60% 67.30 256.41 15.38% 58.82 224.10
0202000010 LIMPIEZA FINAL DE OBRA GLB 1.00 2,966.10 2,966.10 13.56% 0.14 402.13 20.88% 0.21 619.37 13.35% 0.13 395.97 19.24% 0.19 570.56 17.60% 0.18 521.92 15.38% 0.15 456.15
0202000012 INSTALACION Y COLOCACION DE ESTRUCTURA DE TECHO. INC. PINT GLB 1.00 59,224.11 59,224.11 13.56% 0.14 8,029.24 20.88% 0.21 12,367.01 13.35% 0.13 7,906.37 19.24% 0.19 11,392.43 17.60% 0.18 10,421.17 15.38% 0.15 9,107.88
0202000013 INSTALACION Y COLOCACION DE ESTRUCTURA DE TOBOGAN. INC. P GLB 1.00 29,661.02 29,661.02 13.56% 0.14 4,021.26 20.88% 0.21 6,193.73 13.35% 0.13 3,959.72 19.24% 0.19 5,705.64 17.60% 0.18 5,219.20 15.38% 0.15 4,561.47
0202010005 CLAVOS PARA MADERA C/C 3" kg 350.95 3.81 1,337.12 13.56% 47.58 181.28 20.88% 73.28 279.21 13.35% 46.85 178.50 19.24% 67.51 257.21 17.60% 61.75 235.28 15.38% 53.97 205.63
0202010009 CLAVOS PARA MADERA C/C 2 1/2 " kg 1.27 3.81 4.84 13.56% 0.17 0.66 20.88% 0.27 1.01 13.35% 0.17 0.65 19.24% 0.24 0.93 17.60% 0.22 0.85 15.38% 0.20 0.74
0202010013 CLAVOS PARA MADERA C/C 4" kg 81.94 3.81 312.19 13.56% 11.11 42.33 20.88% 17.11 65.19 13.35% 10.94 41.68 19.24% 15.76 60.05 17.60% 14.42 54.93 15.38% 12.60 48.01
0202080014 PERNOS DE ANCLAJE D 1/2"x8" und 220.96 2.12 468.44 13.56% 29.96 63.51 20.88% 46.14 97.82 13.35% 29.50 62.54 19.24% 42.50 90.11 17.60% 38.88 82.43 15.38% 33.98 72.04
0202080015 VOLANDAS DE PRESION 3/4" pza 74.76 0.20 14.95 13.56% 10.14 2.03 20.88% 15.61 3.12 13.35% 9.98 2.00 19.24% 14.38 2.88 17.60% 13.15 2.63 15.38% 11.50 2.30
0202130022 MECHA NARANJA m 10.00 1.27 12.70 13.56% 1.36 1.72 20.88% 2.09 2.65 13.35% 1.33 1.70 19.24% 1.92 2.44 17.60% 1.76 2.23 15.38% 1.54 1.95
0202130023 FULMINANTE und 20.00 2.00 40.00 13.56% 2.71 5.42 20.88% 4.18 8.35 13.35% 2.67 5.34 19.24% 3.85 7.69 17.60% 3.52 7.04 15.38% 3.08 6.15
0202130024 DINAMITA kg 3.00 64.00 192.00 13.56% 0.41 26.03 20.88% 0.63 40.09 13.35% 0.40 25.63 19.24% 0.58 36.93 17.60% 0.53 33.78 15.38% 0.46 29.53
0202130025 BARRENO 5´ x 1/8" und 0.24 145.00 34.80 13.56% 0.03 4.72 20.88% 0.05 7.27 13.35% 0.03 4.65 19.24% 0.05 6.69 17.60% 0.04 6.12 15.38% 0.04 5.35
0202130031 JABONERA C/ASA P/BAÑO 15 x 15 BLANCA und 4.00 25.12 100.48 13.56% 0.54 13.62 20.88% 0.84 20.98 13.35% 0.53 13.41 19.24% 0.77 19.33 17.60% 0.70 17.68 15.38% 0.62 15.45
0202130033 TERMINAL DE COBRE PARA CONDUCTOR DE 50mm2. und 2.20 4.86 10.69 13.56% 0.30 1.45 20.88% 0.46 2.23 13.35% 0.29 1.43 19.24% 0.42 2.06 17.60% 0.39 1.88 15.38% 0.34 1.64
0202130039 PLANCHA DE POLICARBONATO TRASLUCIDO STANDAD DE e=6 mm m2 1,542.77 38.14 58,841.25 13.56% 209.16 7,977.34 20.88% 322.16 12,287.06 13.35% 205.96 7,855.26 19.24% 296.77 11,318.78 17.60% 271.47 10,353.80 15.38% 237.26 9,049.01
0202460096 TIRAFON DE 1/4" X 2½" und 1,425.00 1.10 1,567.50 13.56% 193.19 212.51 20.88% 297.56 327.32 13.35% 190.24 209.26 19.24% 274.11 301.53 17.60% 250.75 275.82 15.38% 219.15 241.06
0202970002 ACERO DE REFUERZO FY=4200 GRADO 60 kg 20,184.88 2.97 59,949.09 13.56% 2,736.54 8,127.53 20.88% 4,214.95 12,518.40 13.35% 2,694.67 8,003.16 19.24% 3,882.79 11,531.89 17.60% 3,551.76 10,548.74 15.38% 3,104.17 9,219.38
0203000042 MOLDE METALICO PARA BUZON und 1.00 45.76 45.76 13.56% 0.14 6.20 20.88% 0.21 9.56 13.35% 0.13 6.11 19.24% 0.19 8.80 17.60% 0.18 8.05 15.38% 0.15 7.04
0204000000 ARENA FINA m3 61.75 76.27 4,709.67 13.56% 8.37 638.51 20.88% 12.89 983.46 13.35% 8.24 628.74 19.24% 11.88 905.96 17.60% 10.87 828.72 15.38% 9.50 724.29
0204000001 ARPILLERA m 213.10 3.50 745.85 13.56% 28.89 101.12 20.88% 44.50 155.75 13.35% 28.45 99.57 19.24% 40.99 143.47 17.60% 37.50 131.24 15.38% 32.77 114.70
0204000002 ADOQUIN DE CONCRETO DE 0.10X0.20X0.05m. DE COLORES und 54,668.65 0.93 50,841.84 13.56% 7,411.64 6,892.83 20.88% 11,415.75 10,616.65 13.35% 7,298.22 6,787.35 19.24% 10,516.14 9,780.01 17.60% 9,619.58 8,946.21 15.38% 8,407.32 7,818.80
0204000003 ARENA m3 56.88 76.27 4,338.24 13.56% 7.71 588.15 20.88% 11.88 905.90 13.35% 7.59 579.15 19.24% 10.94 834.51 17.60% 10.01 763.36 15.38% 8.75 667.16
0204010012 TIERRA COMUN CERNIDA m3 1.00 54.62 54.62 13.56% 0.14 7.41 20.88% 0.21 11.41 13.35% 0.13 7.29 19.24% 0.19 10.51 17.60% 0.18 9.61 15.38% 0.15 8.40
0205000003 PIEDRA CHANCADA DE 1/2" m3 426.28 33.90 14,450.89 13.56% 57.79 1,959.16 20.88% 89.01 3,017.59 13.35% 56.91 1,929.18 19.24% 82.00 2,779.79 17.60% 75.01 2,542.80 15.38% 65.56 2,222.36
0205000009 PIEDRA GRANDE DE 8" m3 75.33 29.66 2,234.29 13.56% 10.21 302.91 20.88% 15.73 466.56 13.35% 10.06 298.28 19.24% 14.49 429.79 17.60% 13.26 393.15 15.38% 11.58 343.60
0205000010 PIEDRA MEDIANA DE 4" m3 107.59 26.66 2,868.35 13.56% 14.59 388.87 20.88% 22.47 598.96 13.35% 14.36 382.92 19.24% 20.70 551.76 17.60% 18.93 504.72 15.38% 16.55 441.11
0205000011 PIEDRA MEDIANA DE 6" m3 306.24 26.66 8,164.36 13.56% 41.52 1,106.87 20.88% 63.95 1,704.86 13.35% 40.88 1,089.94 19.24% 58.91 1,570.51 17.60% 53.89 1,436.61 15.38% 47.10 1,255.57
0205010004 ARENA GRUESA m3 288.26 33.90 9,772.01 13.56% 39.08 1,324.83 20.88% 60.19 2,040.56 13.35% 38.48 1,304.56 19.24% 55.45 1,879.76 17.60% 50.72 1,719.50 15.38% 44.33 1,502.81
0205010005 AFIRMADO m3 564.15 25.42 14,340.69 13.56% 76.48 1,944.22 20.88% 117.80 2,994.58 13.35% 75.31 1,914.47 19.24% 108.52 2,758.60 17.60% 99.27 2,523.41 15.38% 86.76 2,205.41
0205010007 MATERIAL GRANULAR SELECCIONADO m3 19.50 25.42 495.69 13.56% 2.64 67.20 20.88% 4.07 103.51 13.35% 2.60 66.17 19.24% 3.75 95.35 17.60% 3.43 87.22 15.38% 3.00 76.23
0205010008 MATERIAL SELECCIONADO m3 5.00 25.42 127.10 13.56% 0.68 17.23 20.88% 1.04 26.54 13.35% 0.67 16.97 19.24% 0.96 24.45 17.60% 0.88 22.36 15.38% 0.77 19.55
0206980002 CONECTOR ANDERSON pza 1.00 8.47 8.47 13.56% 0.14 1.15 20.88% 0.21 1.77 13.35% 0.13 1.13 19.24% 0.19 1.63 17.60% 0.18 1.49 15.38% 0.15 1.30
0206980003 CONDUCTOR DE COBRE DESNUDO BLANDO DE 50mm2. m 22.00 4.50 99.00 13.56% 2.98 13.42 20.88% 4.59 20.67 13.35% 2.94 13.22 19.24% 4.23 19.04 17.60% 3.87 17.42 15.38% 3.38 15.22
0206980004 CONDUCTOR SUBTERRANEO DE 2-1x50mm2. TIPO NYY m 29.14 4.50 131.13 13.56% 3.95 17.78 20.88% 6.08 27.38 13.35% 3.89 17.51 19.24% 5.61 25.22 17.60% 5.13 23.07 15.38% 4.48 20.17
0206980007 CONDUCTOR DE COBRE de 2.5mm2 TIPO TW (ROJO, AZUL Y NEGRO) m 602.09 1.50 903.14 13.56% 81.63 122.44 20.88% 125.73 188.59 13.35% 80.38 120.57 19.24% 115.82 173.73 17.60% 105.94 158.92 15.38% 92.59 138.89
0206980008 CONDUCTOR DE COBRE de 2.5mm2 TIPO TW (VERDE) m 216.18 1.50 324.27 13.56% 29.31 43.96 20.88% 45.14 67.71 13.35% 28.86 43.29 19.24% 41.58 62.38 17.60% 38.04 57.06 15.38% 33.25 49.87
0207010016 TECNOPORT DE 1" x 4" x 8´ pln 8.77 29.50 258.72 13.56% 1.19 35.07 20.88% 1.83 54.02 13.35% 1.17 34.54 19.24% 1.69 49.77 17.60% 1.54 45.52 15.38% 1.35 39.79
0207010017 CABLE TW # 12 AWG - 6 MM2 m 27.00 2.37 63.99 13.56% 3.66 8.68 20.88% 5.64 13.36 13.35% 3.60 8.54 19.24% 5.19 12.31 17.60% 4.75 11.26 15.38% 4.15 9.84
0207010018 CABLE DE ENERGIA 4mm NHX-90 m 47.88 3.90 186.73 13.56% 6.49 25.32 20.88% 10.00 38.99 13.35% 6.39 24.93 19.24% 9.21 35.92 17.60% 8.43 32.86 15.38% 7.36 28.72
0207010019 CABLE DE ENERGIA 6mm NHX-90 m 47.88 2.37 113.48 13.56% 6.49 15.38 20.88% 10.00 23.70 13.35% 6.39 15.15 19.24% 9.21 21.83 17.60% 8.43 19.97 15.38% 7.36 17.45
0207010020 CABLE DE ENERGIA N2XH DE 16mm m 31.50 10.36 326.34 13.56% 4.27 44.24 20.88% 6.58 68.15 13.35% 4.21 43.57 19.24% 6.06 62.78 17.60% 5.54 57.42 15.38% 4.84 50.19
0207010021 TECNOPORT DE 12 x 30 x 3M PARA TECHO und 1,297.37 3.56 4,618.64 13.56% 175.89 626.17 20.88% 270.91 964.45 13.35% 173.20 616.58 19.24% 249.56 888.45 17.60% 228.29 812.70 15.38% 199.52 710.29
0210020052 INODORO TQUE. BAJO NORMAL BLANCO C/A. und 5.00 256.92 1,284.60 13.56% 0.68 174.16 20.88% 1.04 268.25 13.35% 0.67 171.49 19.24% 0.96 247.11 17.60% 0.88 226.04 15.38% 0.77 197.55
0210060009 DUCHA GIRATORIA und 4.00 64.90 259.60 13.56% 0.54 35.19 20.88% 0.84 54.21 13.35% 0.53 34.66 19.24% 0.77 49.94 17.60% 0.70 45.68 15.38% 0.62 39.92
0210140040 ESCALERA DE GATO METALICA CON F°G° 1"INC.INST. ESCALERA DE Gund 1.00 5,508.47 5,508.47 13.56% 0.14 746.80 20.88% 0.21 1,150.26 13.35% 0.13 735.38 19.24% 0.19 1,059.62 17.60% 0.18 969.28 15.38% 0.15 847.13
0211430015 REDUCCION PVC SAP 3/4" A 1/2" pza 10.00 3.12 31.20 13.56% 1.36 4.23 20.88% 2.09 6.52 13.35% 1.33 4.17 19.24% 1.92 6.00 17.60% 1.76 5.49 15.38% 1.54 4.80
0211430016 REDUCCION PVC SAP 4" x 2" pza 4.00 5.51 22.04 13.56% 0.54 2.99 20.88% 0.84 4.60 13.35% 0.53 2.94 19.24% 0.77 4.24 17.60% 0.70 3.88 15.38% 0.62 3.39
0211430017 ADAPTADOR PVC-SAP DE 1/2" pza 40.00 0.85 34.00 13.56% 5.42 4.61 20.88% 8.35 7.10 13.35% 5.34 4.54 19.24% 7.69 6.54 17.60% 7.04 5.98 15.38% 6.15 5.23
0211430018 ADAPTADOR PVC-SAP DE 1 1/2" pza 2.00 0.90 1.80 13.56% 0.27 0.24 20.88% 0.42 0.38 13.35% 0.27 0.24 19.24% 0.38 0.35 17.60% 0.35 0.32 15.38% 0.31 0.28
0212000048 TARUGO DE PVC DE 1/4" und 30.00 1.18 35.40 13.56% 4.07 4.80 20.88% 6.26 7.39 13.35% 4.00 4.73 19.24% 5.77 6.81 17.60% 5.28 6.23 15.38% 4.61 5.44
0212000049 TABLERO METALICO CON PUERTA Y CHAPA PARA EMPOTRAR CON 03 und 1.00 72.27 72.27 13.56% 0.14 9.80 20.88% 0.21 15.09 13.35% 0.13 9.65 19.24% 0.19 13.90 17.60% 0.18 12.72 15.38% 0.15 11.11
0212000050 TABLERO METALICO CON PUERTA Y CHAPA P/EMPOTRAR C/36 POLOS und 3.00 76.27 228.81 13.56% 0.41 31.02 20.88% 0.63 47.78 13.35% 0.40 30.55 19.24% 0.58 44.01 17.60% 0.53 40.26 15.38% 0.46 35.19
0212000052 TRAMPA PVC SAL P 2" pza 4.00 10.50 42.00 13.56% 0.54 5.69 20.88% 0.84 8.77 13.35% 0.53 5.61 19.24% 0.77 8.08 17.60% 0.70 7.39 15.38% 0.62 6.46
0212000053 TRAMPA PVC SAL P 4" pza 1.00 22.50 22.50 13.56% 0.14 3.05 20.88% 0.21 4.70 13.35% 0.13 3.00 19.24% 0.19 4.33 17.60% 0.18 3.96 15.38% 0.15 3.46
0212000055 TRAMPA PVC SAL P 3" pza 2.00 15.50 31.00 13.56% 0.27 4.20 20.88% 0.42 6.47 13.35% 0.27 4.14 19.24% 0.38 5.96 17.60% 0.35 5.45 15.38% 0.31 4.77
0212020090 INTERRUPTOR TERMOMAGNETICO DE 3x60Ax220V. FIJO und 1.00 38.98 38.98 13.56% 0.14 5.28 20.88% 0.21 8.14 13.35% 0.13 5.20 19.24% 0.19 7.50 17.60% 0.18 6.86 15.38% 0.15 5.99
0212020091 INTERRUPTOR TERMOMAGNETICO DE 3x80Ax220V. FIJO und 2.00 93.22 186.44 13.56% 0.27 25.28 20.88% 0.42 38.93 13.35% 0.27 24.89 19.24% 0.38 35.86 17.60% 0.35 32.81 15.38% 0.31 28.67
0212020092 INTERRUPTOR TERMOMAGNETICO DE 3x200Ax220V. FIJO und 1.00 40.34 40.34 13.56% 0.14 5.47 20.88% 0.21 8.42 13.35% 0.13 5.39 19.24% 0.19 7.76 17.60% 0.18 7.10 15.38% 0.15 6.20
0212020096 INTERRUPTOR TERMOMAGNETICO DE 3x20Ax220V. und 3.00 40.34 121.02 13.56% 0.41 16.41 20.88% 0.63 25.27 13.35% 0.40 16.16 19.24% 0.58 23.28 17.60% 0.53 21.29 15.38% 0.46 18.61
0212020097 INTERRUPTOR TERMOMAGNETICO DE 3x15Ax220V. und 5.00 40.34 201.70 13.56% 0.68 27.35 20.88% 1.04 42.12 13.35% 0.67 26.93 19.24% 0.96 38.80 17.60% 0.88 35.49 15.38% 0.77 31.02
CRONOGRAMA DE ADQUISICION DE MANO DE OBRA, MATERIALES E INSUMOS
PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC”

PROPIET: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO 13.56% 20.88% 13.35% 19.24% 17.60% 15.38%
PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
ITEM DESCR IP CIO N UND CANTID. PRECIO TOTAL
% CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO
0212030030 INTERRUPTOR SIMPLE und 15.00 5.90 88.50 13.56% 2.03 12.00 20.88% 3.13 18.48 13.35% 2.00 11.81 19.24% 2.89 17.02 17.60% 2.64 15.57 15.38% 2.31 13.61
0212090050 CAJA PVC OCTOGONAL TP. pza 27.50 1.27 34.93 13.56% 3.73 4.73 20.88% 5.74 7.29 13.35% 3.67 4.66 19.24% 5.29 6.72 17.60% 4.84 6.15 15.38% 4.23 5.37
0212090051 CAJA PVC RECTANGULAR TP pza 33.85 1.27 42.99 13.56% 4.59 5.83 20.88% 7.07 8.98 13.35% 4.52 5.74 19.24% 6.51 8.27 17.60% 5.96 7.56 15.38% 5.21 6.61
CRONOGRAMA DE ADQUISICION DE MANO DE OBRA, MATERIALES E INSUMOS
PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC”

PROPIET: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO 13.56% 20.88% 13.35% 19.24% 17.60% 15.38%
PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
ITEM DESCR IP CIO N UND CANTID. PRECIO TOTAL
% CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO
0212140047 LAMPARA DE VAPOR DE SODIO DE 70W. CON DEFLECTOR pza 13.00 207.63 2,699.19 13.56% 1.76 365.94 20.88% 2.71 563.64 13.35% 1.74 360.34 19.24% 2.50 519.22 17.60% 2.29 474.95 15.38% 2.00 415.10
0212140050 ARTEFACTO FLUORESCENTE DE 3 X 36 W. A/F pza 21.00 83.05 1,744.05 13.56% 2.85 236.45 20.88% 4.39 364.19 13.35% 2.80 232.83 19.24% 4.04 335.49 17.60% 3.70 306.89 15.38% 3.23 268.21
0212140051 REFLECTOR DE 250V, HALOGENURO METALICO C/EQUIPO pza 4.00 288.14 1,152.56 13.56% 0.54 156.26 20.88% 0.84 240.67 13.35% 0.53 153.87 19.24% 0.77 221.71 17.60% 0.70 202.81 15.38% 0.62 177.25
0212310021 TOALLERA C/BARRA PLASTICA BLANCA und 4.00 21.18 84.72 13.56% 0.54 11.49 20.88% 0.84 17.69 13.35% 0.53 11.31 19.24% 0.77 16.30 17.60% 0.70 14.91 15.38% 0.62 13.03
0212310022 TOMACORRIENTE DOBLE CON PUESTA A TIERRA 250V. PESADO pza 18.85 9.61 181.15 13.56% 2.56 24.56 20.88% 3.94 37.83 13.35% 2.52 24.18 19.24% 3.63 34.85 17.60% 3.32 31.88 15.38% 2.90 27.86
0213000006 ASFALTO RC-250 gln 1.27 21.19 26.91 13.56% 0.17 3.65 20.88% 0.27 5.62 13.35% 0.17 3.59 19.24% 0.24 5.18 17.60% 0.22 4.74 15.38% 0.20 4.14
0213510003 PAPELERA DE 13 x 15 BLANCA und 5.00 27.12 135.60 13.56% 0.68 18.38 20.88% 1.04 28.32 13.35% 0.67 18.10 19.24% 0.96 26.08 17.60% 0.88 23.86 15.38% 0.77 20.85
0217000024 LADRILLO ARCILLA KK. 9 x 12 x 24cm. und 14,847.61 0.35 5,196.66 13.56% 2,012.95 704.53 20.88% 3,100.44 1,085.15 13.35% 1,982.14 693.75 19.24% 2,856.11 999.64 17.60% 2,612.61 914.41 15.38% 2,283.37 799.18
0217000026 FRAGUA kg 36.43 3.81 138.80 13.56% 4.94 18.82 20.88% 7.61 28.98 13.35% 4.86 18.53 19.24% 7.01 26.70 17.60% 6.41 24.42 15.38% 5.60 21.35
0217000027 LOSETA CERAMICA 40 x 40cm. m2 31.19 27.12 845.87 13.56% 4.23 114.68 20.88% 6.51 176.63 13.35% 4.16 112.92 19.24% 6.00 162.71 17.60% 5.49 148.84 15.38% 4.80 130.08
0217000028 LOSETA CERAMICA 30 x 30cm. m2 50.82 27.12 1,378.24 13.56% 6.89 186.85 20.88% 10.61 287.80 13.35% 6.78 183.99 19.24% 9.78 265.12 17.60% 8.94 242.52 15.38% 7.82 211.95
0217000033 LUMINARIA DE EMERGENCIA C/ 2 LAMP. ENCAND. 50 W und 10.00 55.08 550.80 13.56% 1.36 74.67 20.88% 2.09 115.02 13.35% 1.33 73.53 19.24% 1.92 105.95 17.60% 1.76 96.92 15.38% 1.54 84.71
0217000034 CERAMICO 60 cm x 60 cm DE ALTO TRANSITO m2 33.15 38.14 1,264.34 13.56% 4.49 171.41 20.88% 6.92 264.02 13.35% 4.43 168.79 19.24% 6.38 243.21 17.60% 5.83 222.48 15.38% 5.10 194.44
0217000035 CONTRAZOCALO DE CERAMICO DE H= 10CM m 26.88 3.81 102.41 13.56% 3.64 13.88 20.88% 5.61 21.39 13.35% 3.59 13.67 19.24% 5.17 19.70 17.60% 4.73 18.02 15.38% 4.13 15.75
0221000000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 4,699.99 18.64 87,607.81 13.56% 637.20 11,877.33 20.88% 981.44 18,294.01 13.35% 627.44 11,695.57 19.24% 904.10 16,852.36 17.60% 827.02 15,415.61 15.38% 722.80 13,472.92
0226020071 BISAGRA CAPUCHINA 4" und 16.00 5.93 94.88 13.56% 2.17 12.86 20.88% 3.34 19.81 13.35% 2.14 12.67 19.24% 3.08 18.25 17.60% 2.82 16.70 15.38% 2.46 14.59
0226070056 CERRADURA DE PERRILLA PARA INTERIOR und 8.00 27.12 216.96 13.56% 1.08 29.41 20.88% 1.67 45.30 13.35% 1.07 28.96 19.24% 1.54 41.73 17.60% 1.41 38.18 15.38% 1.23 33.37
0226080066 BISAGRA CAPUCHINA PLOMA 3 1/2" X 3 1/2" PAR 4.00 5.93 23.72 13.56% 0.54 3.22 20.88% 0.84 4.95 13.35% 0.53 3.17 19.24% 0.77 4.56 17.60% 0.70 4.17 15.38% 0.62 3.65
0226140021 MANIJA DE BRONCE PARA PUERTA 4" und 8.00 5.08 40.64 13.56% 1.08 5.51 20.88% 1.67 8.49 13.35% 1.07 5.43 19.24% 1.54 7.82 17.60% 1.41 7.15 15.38% 1.23 6.25
0226540071 CERRADURA PARA PUERTAS DE TRES GOLPES und 1.00 55.08 55.08 13.56% 0.14 7.47 20.88% 0.21 11.50 13.35% 0.13 7.35 19.24% 0.19 10.60 17.60% 0.18 9.69 15.38% 0.15 8.47
0229040003 CINTA SEÑALIZADORA AMARILLA PARA CABLE DE BAJA TENSION m 33.30 0.60 19.98 13.56% 4.51 2.71 20.88% 6.95 4.17 13.35% 4.45 2.67 19.24% 6.41 3.84 17.60% 5.86 3.52 15.38% 5.12 3.07
0229040004 CINTA AISLANTE 20m. 3M. 1700 rll 7.28 4.23 30.79 13.56% 0.99 4.17 20.88% 1.52 6.43 13.35% 0.97 4.11 19.24% 1.40 5.92 17.60% 1.28 5.42 15.38% 1.12 4.74
0229050001 CINTA TEFLON rll 12.25 1.18 14.46 13.56% 1.66 1.96 20.88% 2.56 3.02 13.35% 1.64 1.93 19.24% 2.36 2.78 17.60% 2.16 2.54 15.38% 1.88 2.22
0229150099 OCRE kg 98.73 10.17 1,004.08 13.56% 13.39 136.13 20.88% 20.62 209.67 13.35% 13.18 134.04 19.24% 18.99 193.15 17.60% 17.37 176.68 15.38% 15.18 154.41
0229500093 SOLDADURA CELLOCORD 1/8" kg 23.83 12.53 298.59 13.56% 3.23 40.48 20.88% 4.98 62.35 13.35% 3.18 39.86 19.24% 4.58 57.44 17.60% 4.19 52.54 15.38% 3.66 45.92
0230020001 YESO DE 28 Kg BOL 70.33 8.47 595.70 13.56% 9.53 80.76 20.88% 14.69 124.39 13.35% 9.39 79.52 19.24% 13.53 114.59 17.60% 12.38 104.82 15.38% 10.82 91.61
0230100002 VARILLA DE COBRE DE 3/4" x 2.40m und 1.00 211.86 211.86 13.56% 0.14 28.72 20.88% 0.21 44.24 13.35% 0.13 28.28 19.24% 0.19 40.75 17.60% 0.18 37.28 15.38% 0.15 32.58
0230450053 LAVATORIO TIPO ESTANDAR BLANCO INC. ACCESORIOS pza 1.00 101.69 101.69 13.56% 0.14 13.79 20.88% 0.21 21.23 13.35% 0.13 13.58 19.24% 0.19 19.56 17.60% 0.18 17.89 15.38% 0.15 15.64
0230450055 OVALIN LOZA BLANCA DE PRIMERA INC. ACCESORIOS und 6.00 137.66 825.96 13.56% 0.81 111.98 20.88% 1.25 172.47 13.35% 0.80 110.26 19.24% 1.15 158.88 17.60% 1.06 145.34 15.38% 0.92 127.02
0230460032 SILICONA und 186.74 16.94 3,163.38 13.56% 25.32 428.87 20.88% 38.99 660.57 13.35% 24.93 422.31 19.24% 35.92 608.51 17.60% 32.86 556.63 15.38% 28.72 486.49
0230460037 PEGAMENTO DE MAYOLICA kg 30.95 10.42 322.50 13.56% 4.20 43.72 20.88% 6.46 67.34 13.35% 4.13 43.05 19.24% 5.95 62.04 17.60% 5.45 56.75 15.38% 4.76 49.60
0230460038 PEGAMENTO PARA PVC gln 2.81 72.88 204.79 13.56% 0.38 27.76 20.88% 0.59 42.76 13.35% 0.38 27.34 19.24% 0.54 39.39 17.60% 0.49 36.04 15.38% 0.43 31.49
0230460046 CRUCETAS cto 5.52 0.25 1.38 13.56% 0.75 0.19 20.88% 1.15 0.29 13.35% 0.74 0.18 19.24% 1.06 0.27 17.60% 0.97 0.24 15.38% 0.85 0.21
0230460047 RODOPLAST PARA BORDE DE MAYOLICAS m 13.20 4.34 57.29 13.56% 1.79 7.77 20.88% 2.76 11.96 13.35% 1.76 7.65 19.24% 2.54 11.02 17.60% 2.32 10.08 15.38% 2.03 8.81
0230900002 IMPRIMANTE gln 8.90 17.70 157.53 13.56% 1.21 21.36 20.88% 1.86 32.89 13.35% 1.19 21.03 19.24% 1.71 30.30 17.60% 1.57 27.72 15.38% 1.37 24.23
0230900004 IMPERMEABILIZANTE gln 30.99 33.90 1,050.56 13.56% 4.20 142.43 20.88% 6.47 219.38 13.35% 4.14 140.25 19.24% 5.96 202.09 17.60% 5.45 184.86 15.38% 4.77 161.56
0230990019 LIJA und 42.24 1.27 53.64 13.56% 5.73 7.27 20.88% 8.82 11.20 13.35% 5.64 7.16 19.24% 8.13 10.32 17.60% 7.43 9.44 15.38% 6.50 8.25
0230990080 WINCHA DE 50 M und 24.67 55.00 1,356.85 13.56% 3.34 183.95 20.88% 5.15 283.33 13.35% 3.29 181.14 19.24% 4.75 261.01 17.60% 4.34 238.75 15.38% 3.79 208.67
0232000055 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 2,229.18 2,229.18 13.56% 0.14 302.22 20.88% 0.21 465.49 13.35% 0.13 297.59 19.24% 0.19 428.81 17.60% 0.18 392.25 15.38% 0.15 342.82
0232000057 FLETE ANDAHUAYLAS - SAN JERONIMO GLB 1.00 8,014.10 8,014.10 13.56% 0.14 1,086.50 20.88% 0.21 1,673.48 13.35% 0.13 1,069.88 19.24% 0.19 1,541.60 17.60% 0.18 1,410.17 15.38% 0.15 1,232.46
0238000000 HORMIGON m3 327.81 33.90 11,112.76 13.56% 44.44 1,506.60 20.88% 68.45 2,320.53 13.35% 43.76 1,483.54 19.24% 63.06 2,137.67 17.60% 57.68 1,955.42 15.38% 50.41 1,709.00
0239020075 LIJA PARA MADERA und 17.37 1.69 29.36 13.56% 2.35 3.98 20.88% 3.63 6.13 13.35% 2.32 3.92 19.24% 3.34 5.65 17.60% 3.06 5.17 15.38% 2.67 4.51
0239050000 AGUA m3 823.47 0.25 205.87 13.56% 111.64 27.91 20.88% 171.95 42.99 13.35% 109.93 27.48 19.24% 158.40 39.60 17.60% 144.90 36.22 15.38% 126.64 31.66
0239100100 ALMACEN DE OBRA, OFICINA TECNICA Y GUARDIANIA GLB 1.00 3,813.56 3,813.56 13.56% 0.14 517.02 20.88% 0.21 796.34 13.35% 0.13 509.11 19.24% 0.19 733.58 17.60% 0.18 671.04 15.38% 0.15 586.48
0239900095 CARTEL DE OBRA INC.INSTALACION Y TRANSP GLB 1.00 2,372.88 2,372.88 13.56% 0.14 321.70 20.88% 0.21 495.50 13.35% 0.13 316.78 19.24% 0.19 456.45 17.60% 0.18 417.54 15.38% 0.15 364.92
0239900097 PRUEBA HIDRAULICA MAS DESINFECCION DE SIST. DE AGUA GLB 2.00 296.61 593.22 13.56% 0.27 80.43 20.88% 0.42 123.87 13.35% 0.27 79.19 19.24% 0.38 114.11 17.60% 0.35 104.38 15.38% 0.31 91.23
0243000025 MADERA CORRIENTE PARA ESTACAS p2 245.54 1.50 368.31 13.56% 33.29 49.93 20.88% 51.27 76.91 13.35% 32.78 49.17 19.24% 47.23 70.85 17.60% 43.21 64.81 15.38% 37.76 56.64
0243110013 MADERA NACIONAL PARA ENCOFRADO p2 824.29 2.97 2,448.14 13.56% 111.75 331.90 20.88% 172.13 511.21 13.35% 110.04 326.82 19.24% 158.56 470.93 17.60% 145.04 430.78 15.38% 126.76 376.49
0243130073 VENTANA DE VIDRIO TEMPLADO DE 8mm CON ACC. DE ACERO m2 105.34 169.49 17,854.08 13.56% 14.28 2,420.55 20.88% 22.00 3,728.24 13.35% 14.06 2,383.50 19.24% 20.26 3,434.44 17.60% 18.54 3,141.63 15.38% 16.20 2,745.72
0243160052 REGLA DE MADERA p2 207.27 5.51 1,142.06 13.56% 28.10 154.83 20.88% 43.28 238.48 13.35% 27.67 152.46 19.24% 39.87 219.69 17.60% 36.47 200.96 15.38% 31.88 175.63
0243550001 ANDAMIO DE MADERA p2 1,066.05 1.50 1,599.08 13.56% 144.53 216.79 20.88% 222.61 333.91 13.35% 142.32 213.48 19.24% 205.07 307.60 17.60% 187.58 281.38 15.38% 163.94 245.92
0243570055 MADERA EUCALIPTO ROLLIZO p2 1,044.19 1.50 1,566.29 13.56% 141.56 212.35 20.88% 218.04 327.07 13.35% 139.40 209.10 19.24% 200.86 301.29 17.60% 183.74 275.61 15.38% 160.58 240.87
0243940005 MADERA MACHIEMBRADA DE TORNILLO 3/4"X4"X3' p2 625.00 4.50 2,812.50 13.56% 84.73 381.30 20.88% 130.51 587.30 13.35% 83.44 375.47 19.24% 120.23 541.02 17.60% 109.98 494.89 15.38% 96.12 432.53
0244010041 LISTONES MADERA 3"X4"X3M pza 118.47 12.72 1,506.94 13.56% 16.06 204.30 20.88% 24.74 314.67 13.35% 15.82 201.18 19.24% 22.79 289.88 17.60% 20.85 265.16 15.38% 18.22 231.75
0244030006 TRIPLAY DE 19 MM.(TRATADO CON ADITIVO) pln 87.42 67.80 5,927.08 13.56% 11.85 803.56 20.88% 18.25 1,237.68 13.35% 11.67 791.26 19.24% 16.82 1,140.14 17.60% 15.38 1,042.94 15.38% 13.44 911.51
0245010001 MADERA TORNILLO INC.CORTE P/ENCOFRADO p2 7,515.05 2.97 22,319.70 13.56% 1,018.84 3,025.97 20.88% 1,569.27 4,660.74 13.35% 1,003.25 2,979.66 19.24% 1,445.61 4,293.45 17.60% 1,322.36 3,927.41 15.38% 1,155.72 3,432.47
0250010000 CAJA DE DESAGUE DE 12"X24" und 8.00 55.00 440.00 13.56% 1.08 59.65 20.88% 1.67 91.88 13.35% 1.07 58.74 19.24% 1.54 84.64 17.60% 1.41 77.42 15.38% 1.23 67.67
0250010001 CAJA DE REGISTRO DE CONCRETO CON TAPA SEÑALIZADA und 1.00 80.51 80.51 13.56% 0.14 10.92 20.88% 0.21 16.81 13.35% 0.13 10.75 19.24% 0.19 15.49 17.60% 0.18 14.17 15.38% 0.15 12.38
0250010002 CAJA METALICA CON TAPA DE 15 x 15 x 10 (1/16) pza 2.00 16.95 33.90 13.56% 0.27 4.60 20.88% 0.42 7.08 13.35% 0.27 4.53 19.24% 0.38 6.52 17.60% 0.35 5.97 15.38% 0.31 5.21
0250010005 CAJA DE CONCRETO P/MEDIDOR AGUA und 16.00 38.14 610.24 13.56% 2.17 82.73 20.88% 3.34 127.43 13.35% 2.14 81.47 19.24% 3.08 117.39 17.60% 2.82 107.38 15.38% 2.46 93.85
0250060010 TAPA C/MARCO FºFº DE DESAGUE 12" X 24" pza 3.00 45.00 135.00 13.56% 0.41 18.30 20.88% 0.63 28.19 13.35% 0.40 18.02 19.24% 0.58 25.97 17.60% 0.53 23.75 15.38% 0.46 20.76
0250060012 TAPA CIEGA PARA CAJA OCTAGONAL pza 1.78 1.02 1.82 13.56% 0.24 0.25 20.88% 0.37 0.38 13.35% 0.24 0.24 19.24% 0.34 0.35 17.60% 0.31 0.32 15.38% 0.27 0.28
0250060013 TAPA DE CONCRETO ARMADO 0.60 x 0.80m. und 1.00 127.20 127.20 13.56% 0.14 17.24 20.88% 0.21 26.56 13.35% 0.13 16.98 19.24% 0.19 24.47 17.60% 0.18 22.38 15.38% 0.15 19.56
0250060014 TAPA METALICA CON MARCO Y SEGURO und 16.00 35.00 560.00 13.56% 2.17 75.92 20.88% 3.34 116.94 13.35% 2.14 74.76 19.24% 3.08 107.72 17.60% 2.82 98.54 15.38% 2.46 86.12
0251990005 PUERTA DE MADERA CONTRAPLACADA CON TRYPLAY DE 6mm m2 3.96 110.00 435.60 13.56% 0.54 59.06 20.88% 0.83 90.96 13.35% 0.53 58.15 19.24% 0.76 83.79 17.60% 0.70 76.65 15.38% 0.61 66.99
0252270033 ANGULO 1 1/2" x 1 1/2" x 1/4" m 281.40 11.30 3,179.82 13.56% 38.15 431.10 20.88% 58.76 664.00 13.35% 37.57 424.50 19.24% 54.13 611.67 17.60% 49.52 559.53 15.38% 43.28 489.01
0252270035 PLATINA DE ACERO 1/2" x 1/2" m 469.00 8.41 3,944.29 13.56% 63.58 534.74 20.88% 97.94 823.64 13.35% 62.61 526.56 19.24% 90.22 758.73 17.60% 82.53 694.04 15.38% 72.13 606.58
0252270042 ANGULO ALUMINIO 1" x 1" x 1/8" m 9.01 3.98 35.86 13.56% 1.22 4.86 20.88% 1.88 7.49 13.35% 1.20 4.79 19.24% 1.73 6.90 17.60% 1.59 6.31 15.38% 1.39 5.51
0252270043 TEE DE ALUMINIO 1 1/2" x 1 1/2" x 1/8" x 1/8 m 3.31 6.36 21.05 13.56% 0.45 2.85 20.88% 0.69 4.40 13.35% 0.44 2.81 19.24% 0.64 4.05 17.60% 0.58 3.70 15.38% 0.51 3.24
0253030027 THINER gln 16.35 18.49 302.31 13.56% 2.22 40.99 20.88% 3.41 63.13 13.35% 2.18 40.36 19.24% 3.15 58.15 17.60% 2.88 53.20 15.38% 2.51 46.49
0254010051 PINTURA LATEX gln 7.98 21.19 169.10 13.56% 1.08 22.93 20.88% 1.67 35.31 13.35% 1.07 22.57 19.24% 1.54 32.53 17.60% 1.40 29.75 15.38% 1.23 26.00
CRONOGRAMA DE ADQUISICION DE MANO DE OBRA, MATERIALES E INSUMOS
PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC”

PROPIET: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO 13.56% 20.88% 13.35% 19.24% 17.60% 15.38%
PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
ITEM DESCR IP CIO N UND CANTID. PRECIO TOTAL
% CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO
0254020082 PINTURA ANTICORROSIVO ZINCROMATICO gln 0.40 31.36 12.54 13.56% 0.05 1.70 20.88% 0.08 2.62 13.35% 0.05 1.67 19.24% 0.08 2.41 17.60% 0.07 2.21 15.38% 0.06 1.93
0254080000 BARNIZ MARINO gln 0.40 50.85 20.34 13.56% 0.05 2.76 20.88% 0.08 4.25 13.35% 0.05 2.72 19.24% 0.08 3.91 17.60% 0.07 3.58 15.38% 0.06 3.13
0254080003 BENTONITA SODICA (BOLSAx30KG) bls 2.00 42.37 84.74 13.56% 0.27 11.49 20.88% 0.42 17.70 13.35% 0.27 11.31 19.24% 0.38 16.30 17.60% 0.35 14.91 15.38% 0.31 13.03
0254080004 FABRICACION Y COLOCACION CASILLEROS GUARDA ROPAS SEGUN Dund 2.00 1,864.41 3,728.82 13.56% 0.27 505.53 20.88% 0.42 778.64 13.35% 0.27 497.79 19.24% 0.38 717.28 17.60% 0.35 656.13 15.38% 0.31 573.44
0254080005 FABRICACION Y COLOCACION DE BANCAS DE MADERA SEGUN DISEÑ und 2.00 423.73 847.46 13.56% 0.27 114.89 20.88% 0.42 176.96 13.35% 0.27 113.14 19.24% 0.38 163.02 17.60% 0.35 149.12 15.38% 0.31 130.33
0254080006 FABRICACION Y COLOCACION DE MESA DE TENCION DE MADERA, SE und 1.00 2,118.64 2,118.64 13.56% 0.14 287.23 20.88% 0.21 442.41 13.35% 0.13 282.84 19.24% 0.19 407.54 17.60% 0.18 372.80 15.38% 0.15 325.82
0254080008 CONSTRUCCION DE JARDINERIA DE CONCRETO ARMADO SEGUN DIS GLB 1.00 10,169.49 10,169.49 13.56% 0.14 1,378.72 20.88% 0.21 2,123.56 13.35% 0.13 1,357.62 19.24% 0.19 1,956.22 17.60% 0.18 1,789.44 15.38% 0.15 1,563.93
0254080009 FABRICACION Y COLOCACION DE BANCAS DE MADERA SEGUN DISEÑ pza 5.00 2,509.14 12,545.70 13.56% 0.68 1,700.87 20.88% 1.04 2,619.76 13.35% 0.67 1,674.84 19.24% 0.96 2,413.31 17.60% 0.88 2,207.56 15.38% 0.77 1,929.36
0254080011 PEDESTAL DE CONCRETO SEGUN DISEÑO GLB 6.00 1,271.19 7,627.14 13.56% 0.81 1,034.04 20.88% 1.25 1,592.68 13.35% 0.80 1,018.22 19.24% 1.15 1,467.17 17.60% 1.06 1,342.08 15.38% 0.92 1,172.95
0254080012 FABRICACION Y COLOCACION DE BANCA DE CONCRETO (L=1.00M) S GLB 1.00 508.47 508.47 13.56% 0.14 68.94 20.88% 0.21 106.18 13.35% 0.13 67.88 19.24% 0.19 97.81 17.60% 0.18 89.47 15.38% 0.15 78.20
0254080013 SARDINEL SOBRE MURO DE PROTECCION EXISTENTE GLB 1.00 2,542.37 2,542.37 13.56% 0.14 344.68 20.88% 0.21 530.89 13.35% 0.13 339.40 19.24% 0.19 489.05 17.60% 0.18 447.36 15.38% 0.15 390.98
0254080014 FABRICACION Y COLOCACION DE ESCALERA TIPO GATO EN PISCINA, GLB 2.00 1,694.92 3,389.84 13.56% 0.27 459.57 20.88% 0.42 707.86 13.35% 0.27 452.54 19.24% 0.38 652.07 17.60% 0.35 596.48 15.38% 0.31 521.31
0254080015 FABRICACION Y COLOCACION DE ESCALERA METALICA EN ADMINIST GLB 1.00 4,237.29 4,237.29 13.56% 0.14 574.47 20.88% 0.21 884.82 13.35% 0.13 565.67 19.24% 0.19 815.09 17.60% 0.18 745.60 15.38% 0.15 651.64
0254110090 PINTURA ESMALTE gln 17.06 38.14 650.67 13.56% 2.31 88.21 20.88% 3.56 135.87 13.35% 2.28 86.86 19.24% 3.28 125.16 17.60% 3.00 114.49 15.38% 2.62 100.06
0254110091 PINTURA EPOXICA PARA PISCINA gln 13.39 169.49 2,269.47 13.56% 1.82 307.68 20.88% 2.80 473.90 13.35% 1.79 302.97 19.24% 2.58 436.56 17.60% 2.36 399.34 15.38% 2.06 349.01
0254610001 SELLADOR gln 11.30 25.42 287.25 13.56% 1.53 38.94 20.88% 2.36 59.98 13.35% 1.51 38.35 19.24% 2.17 55.26 17.60% 1.99 50.54 15.38% 1.74 44.17
0254610002 SAL INDUSTRIAL kg 2.00 42.37 84.74 13.56% 0.27 11.49 20.88% 0.42 17.70 13.35% 0.27 11.31 19.24% 0.38 16.30 17.60% 0.35 14.91 15.38% 0.31 13.03
0256990001 PUERTA DE DOS HOJAS und 2.22 240.00 532.80 13.56% 0.30 72.23 20.88% 0.46 111.26 13.35% 0.30 71.13 19.24% 0.43 102.49 17.60% 0.39 93.75 15.38% 0.34 81.94
0265050012 UNION UNIVERSAL PVC SAP DE 3/4" und 34.00 8.84 300.56 13.56% 4.61 40.75 20.88% 7.10 62.76 13.35% 4.54 40.12 19.24% 6.54 57.82 17.60% 5.98 52.89 15.38% 5.23 46.22
0265050013 UNION UNIVERSAL DE Fo. GALV. DE 1 1/2" und 2.00 8.80 17.60 13.56% 0.27 2.39 20.88% 0.42 3.68 13.35% 0.27 2.35 19.24% 0.38 3.39 17.60% 0.35 3.10 15.38% 0.31 2.71
0265130065 NIPLE DE Fo Go DE 1 1/2" x 2 1/2" und 2.00 1.20 2.40 13.56% 0.27 0.33 20.88% 0.42 0.50 13.35% 0.27 0.32 19.24% 0.38 0.46 17.60% 0.35 0.42 15.38% 0.31 0.37
0268040003 SUMIDERO DE BRONCE CROMADO 2" pza 4.00 3.81 15.24 13.56% 0.54 2.07 20.88% 0.84 3.18 13.35% 0.53 2.03 19.24% 0.77 2.93 17.60% 0.70 2.68 15.38% 0.62 2.34
0268040004 SUMIDERO DE BRONCE CROMADO 4" pza 1.00 7.63 7.63 13.56% 0.14 1.03 20.88% 0.21 1.59 13.35% 0.13 1.02 19.24% 0.19 1.47 17.60% 0.18 1.34 15.38% 0.15 1.17
0268040005 SUMIDERO DE FONDO PVC PARA PISCINA und 7.00 100.00 700.00 13.56% 0.95 94.90 20.88% 1.46 146.17 13.35% 0.93 93.45 19.24% 1.35 134.65 17.60% 1.23 123.17 15.38% 1.08 107.65
0268040006 SUMIDERO DE BRONCE CROMADO 3" pza 2.00 5.62 11.24 13.56% 0.27 1.52 20.88% 0.42 2.35 13.35% 0.27 1.50 19.24% 0.38 2.16 17.60% 0.35 1.98 15.38% 0.31 1.73
0271270003 ABRAZADERA DE F° F° DE 4" pza 15.00 8.42 126.30 13.56% 2.03 17.12 20.88% 3.13 26.37 13.35% 2.00 16.86 19.24% 2.89 24.30 17.60% 2.64 22.22 15.38% 2.31 19.42
0272000084 TUB. PVC SAP PRESION P/AGUA C-10 R. 2" m 66.25 10.00 662.50 13.56% 8.98 89.82 20.88% 13.83 138.34 13.35% 8.84 88.44 19.24% 12.74 127.44 17.60% 11.66 116.57 15.38% 10.19 101.88
0272070000 TEE PVC SAP DE 1/2" C/R PARA AGUA und 10.00 2.20 22.00 13.56% 1.36 2.98 20.88% 2.09 4.59 13.35% 1.33 2.94 19.24% 1.92 4.23 17.60% 1.76 3.87 15.38% 1.54 3.38
0272070003 TEE PVC SAP DE 2" C/R PARA AGUA und 64.95 8.00 519.60 13.56% 8.81 70.44 20.88% 13.56 108.50 13.35% 8.67 69.37 19.24% 12.49 99.95 17.60% 11.43 91.43 15.38% 9.99 79.91
0272090003 CURVA PARA TUBOS DE Ø 35mm. TP pza 9.75 2.50 24.38 13.56% 1.32 3.30 20.88% 2.04 5.09 13.35% 1.30 3.25 19.24% 1.88 4.69 17.60% 1.72 4.29 15.38% 1.50 3.75
0272090004 CURVA PARA TUBOS DE Ø 15mm. TP pza 45.65 1.50 68.48 13.56% 6.19 9.28 20.88% 9.53 14.30 13.35% 6.09 9.14 19.24% 8.78 13.17 17.60% 8.03 12.05 15.38% 7.02 10.53
0272090005 CURVA PARA TUBOS DE Ø 20mm. TP pza 188.34 1.80 339.01 13.56% 25.53 45.96 20.88% 39.33 70.79 13.35% 25.14 45.26 19.24% 36.23 65.21 17.60% 33.14 59.65 15.38% 28.96 52.14
0272090006 CURVA PARA TUBOS DE Ø 25mm. TP pza 15.00 2.00 30.00 13.56% 2.03 4.07 20.88% 3.13 6.26 13.35% 2.00 4.00 19.24% 2.89 5.77 17.60% 2.64 5.28 15.38% 2.31 4.61
0272130068 TUBERIA F° G° 2" m 88.70 11.30 1,002.31 13.56% 12.03 135.89 20.88% 18.52 209.30 13.35% 11.84 133.81 19.24% 17.06 192.81 17.60% 15.61 176.37 15.38% 13.64 154.14
0272130071 TUBERIA PVC TP PARA INSTALACIONES ELECTRICAS DE Ø 35mmx3m. pza 13.65 8.50 116.03 13.56% 1.85 15.73 20.88% 2.85 24.23 13.35% 1.82 15.49 19.24% 2.63 22.32 17.60% 2.40 20.42 15.38% 2.10 17.84
0272130072 TUBERIA PVC TP PARA INSTALACIONES ELECTRICAS DE Ø 15mmx3m. pza 63.91 7.00 447.37 13.56% 8.66 60.65 20.88% 13.35 93.42 13.35% 8.53 59.72 19.24% 12.29 86.06 17.60% 11.25 78.72 15.38% 9.83 68.80
0272130073 TUBERIA PVC TP PARA INSTALACIONES ELECTRICAS DE Ø 20mmx3m. pza 236.00 7.50 1,770.00 13.56% 32.00 239.97 20.88% 49.28 369.61 13.35% 31.51 236.29 19.24% 45.40 340.48 17.60% 41.53 311.45 15.38% 36.29 272.20
0272130074 TUBERIA PVC SAL DE 2" m 186.57 4.08 761.21 13.56% 25.29 103.20 20.88% 38.96 158.95 13.35% 24.91 101.62 19.24% 35.89 146.43 17.60% 32.83 133.94 15.38% 28.69 117.06
0272130076 TUBERIA PVC TP PARA INSTALACIONES ELECTRICAS DE Ø 25mmx3m. pza 17.50 8.00 140.00 13.56% 2.37 18.98 20.88% 3.65 29.23 13.35% 2.34 18.69 19.24% 3.37 26.93 17.60% 3.08 24.63 15.38% 2.69 21.53
0272130077 TUBERIA PVC SAP C-10 Ø 3/4" AGUA m 96.82 4.71 456.02 13.56% 13.13 61.82 20.88% 20.22 95.23 13.35% 12.93 60.88 19.24% 18.62 87.72 17.60% 17.04 80.24 15.38% 14.89 70.13
0272130078 TUBERIA PVC UF Ø 6" DESAGUE m 29.36 36.66 1,076.34 13.56% 3.98 145.92 20.88% 6.13 224.76 13.35% 3.92 143.69 19.24% 5.65 207.05 17.60% 5.17 189.39 15.38% 4.52 165.53
0272130079 TEE PVC SAL 4" x 4" pza 4.00 5.51 22.04 13.56% 0.54 2.99 20.88% 0.84 4.60 13.35% 0.53 2.94 19.24% 0.77 4.24 17.60% 0.70 3.88 15.38% 0.62 3.39
0272130080 TEE PVC SAL 4" x 2" pza 4.00 5.51 22.04 13.56% 0.54 2.99 20.88% 0.84 4.60 13.35% 0.53 2.94 19.24% 0.77 4.24 17.60% 0.70 3.88 15.38% 0.62 3.39
0272130081 YEE PVC SAL DE 4" x 2" pza 4.00 6.36 25.44 13.56% 0.54 3.45 20.88% 0.84 5.31 13.35% 0.53 3.40 19.24% 0.77 4.89 17.60% 0.70 4.48 15.38% 0.62 3.91
0272130086 TUBERIA PVC SAL DE 3" m 26.81 10.00 268.10 13.56% 3.63 36.35 20.88% 5.60 55.98 13.35% 3.58 35.79 19.24% 5.16 51.57 17.60% 4.72 47.18 15.38% 4.12 41.23
0272130087 TUBERIA PVC SAP C-10 Ø 1 1/2" AGUA m 1.05 17.97 18.87 13.56% 0.14 2.56 20.88% 0.22 3.94 13.35% 0.14 2.52 19.24% 0.20 3.63 17.60% 0.18 3.32 15.38% 0.16 2.90
0272130088 TUBERIA PVC SAP C-10 Ø 1/2" AGUA m 11.33 2.20 24.93 13.56% 1.54 3.38 20.88% 2.37 5.20 13.35% 1.51 3.33 19.24% 2.18 4.79 17.60% 1.99 4.39 15.38% 1.74 3.83
0272140005 CODO PVC SAL 2" x 90° pza 196.28 5.51 1,081.52 13.56% 26.61 146.63 20.88% 40.99 225.84 13.35% 26.20 144.38 19.24% 37.76 208.04 17.60% 34.54 190.31 15.38% 30.19 166.32
0272140006 CODO PVC SAL 2" x 45° pza 4.00 5.51 22.04 13.56% 0.54 2.99 20.88% 0.84 4.60 13.35% 0.53 2.94 19.24% 0.77 4.24 17.60% 0.70 3.88 15.38% 0.62 3.39
0272140007 CODO PVC SAL 4" - 2° pza 4.00 2.12 8.48 13.56% 0.54 1.15 20.88% 0.84 1.77 13.35% 0.53 1.13 19.24% 0.77 1.63 17.60% 0.70 1.49 15.38% 0.62 1.30
0272140008 CODO PVC SAL 4" x 90° pza 4.00 2.12 8.48 13.56% 0.54 1.15 20.88% 0.84 1.77 13.35% 0.53 1.13 19.24% 0.77 1.63 17.60% 0.70 1.49 15.38% 0.62 1.30
0272140009 CODO PVC SAP (AGUA) CON ROSCA 1/2" x 90. pza 40.00 2.12 84.80 13.56% 5.42 11.50 20.88% 8.35 17.71 13.35% 5.34 11.32 19.24% 7.69 16.31 17.60% 7.04 14.92 15.38% 6.15 13.04
0272320004 YEE PVC SAL 2" x 2" pza 5.00 3.12 15.60 13.56% 0.68 2.11 20.88% 1.04 3.26 13.35% 0.67 2.08 19.24% 0.96 3.00 17.60% 0.88 2.75 15.38% 0.77 2.40
0273010011 TUBO PVC SAL 4" m 310.08 6.36 1,972.11 13.56% 42.04 267.37 20.88% 64.75 411.81 13.35% 41.40 263.27 19.24% 59.65 379.36 17.60% 54.56 347.02 15.38% 47.69 303.28
0273010014 TUBO DE F° G° DE 1 1/2" ML 300.00 10.30 3,090.00 13.56% 40.67 418.92 20.88% 62.65 645.24 13.35% 40.05 412.51 19.24% 57.71 594.40 17.60% 52.79 543.72 15.38% 46.14 475.20
0273010015 PUERTA DE PLANCHA METALICA DE TUBO LAC e=2mm m2 12.80 104.24 1,334.27 13.56% 1.74 180.89 20.88% 2.67 278.62 13.35% 1.71 178.12 19.24% 2.46 256.66 17.60% 2.25 234.78 15.38% 1.97 205.19
0273010016 DIVISIONES DE TUBO LAC e=2mm PARA SS.HH Y ADMINISTRACION m2 37.60 101.69 3,823.54 13.56% 5.10 518.37 20.88% 7.85 798.42 13.35% 5.02 510.44 19.24% 7.23 735.50 17.60% 6.62 672.80 15.38% 5.78 588.01
0273010017 TUBO DE F° G° DE 3/4" ML 1.00 13.27 13.27 13.56% 0.14 1.80 20.88% 0.21 2.77 13.35% 0.13 1.77 19.24% 0.19 2.55 17.60% 0.18 2.34 15.38% 0.15 2.04
0273010018 DESNATADOR P/PISCINA P/TUB. DE 1 1/2" und 9.00 250.00 2,250.00 13.56% 1.22 305.04 20.88% 1.88 469.84 13.35% 1.20 300.37 19.24% 1.73 432.81 17.60% 1.58 395.91 15.38% 1.38 346.02
0273010019 BOQUILLA DE LLENADO DE PVC 4" und 4.00 20.00 80.00 13.56% 0.54 10.85 20.88% 0.84 16.71 13.35% 0.53 10.68 19.24% 0.77 15.39 17.60% 0.70 14.08 15.38% 0.62 12.30
0273010020 PUERTA DE POLICARBONATO ALBEOLAR DE 6mm, CON MARCOS DE ALm2 27.22 104.24 2,837.41 13.56% 3.69 384.68 20.88% 5.68 592.50 13.35% 3.63 378.79 19.24% 5.24 545.81 17.60% 4.79 499.28 15.38% 4.19 436.36
0273110005 CODOS PVC SAL 3" X 90° pza 26.03 5.51 143.43 13.56% 3.53 19.44 20.88% 5.44 29.95 13.35% 3.47 19.15 19.24% 5.01 27.59 17.60% 4.58 25.24 15.38% 4.00 22.06
EQUIPOS
0303000034 TRACTOR DE ORUGAS DE 270 A 295 HP hm 29.13 186.44 5,431.00 13.56% 3.95 736.30 20.88% 6.08 1,134.09 13.35% 3.89 725.03 19.24% 5.60 1,044.71 17.60% 5.13 955.65 15.38% 4.48 835.22
0303000037 MOTOBOMBA 10 HP 4" hm 3.46 16.95 58.65 13.56% 0.47 7.95 20.88% 0.72 12.25 13.35% 0.46 7.83 19.24% 0.67 11.28 17.60% 0.61 10.32 15.38% 0.53 9.02
0329500094 SOLDADURA ELECTRICA hm 149.56 11.25 1,682.55 13.56% 20.28 228.11 20.88% 31.23 351.35 13.35% 19.97 224.62 19.24% 28.77 323.66 17.60% 26.32 296.06 15.38% 23.00 258.75
0348110004 VOLQUETE DE 15 M3 hm 173.57 93.22 16,180.20 13.56% 23.53 2,193.61 20.88% 36.24 3,378.70 13.35% 23.17 2,160.04 19.24% 33.39 3,112.44 17.60% 30.54 2,847.09 15.38% 26.69 2,488.30
0349030002 COMPRESORA NEUMATICA 150 HP. 380-590 PCM hm 3.35 42.37 141.94 13.56% 0.45 19.24 20.88% 0.70 29.64 13.35% 0.45 18.95 19.24% 0.64 27.30 17.60% 0.59 24.98 15.38% 0.52 21.83
0349030003 MARTILLO NEUMATICO DE 25KG. hm 0.91 20.50 18.66 13.56% 0.12 2.53 20.88% 0.19 3.90 13.35% 0.12 2.49 19.24% 0.18 3.59 17.60% 0.16 3.28 15.38% 0.14 2.87
0349030005 SUMINIS E INST. DE EQUIPO DE BOMBEO DE PISCINA, ELECTROBOMBA
und 1.00 35,073.08 35,073.08 13.56% 0.14 4,754.99 20.88% 0.21 7,323.86 13.35% 0.13 4,682.23 19.24% 0.19 6,746.71 17.60% 0.18 6,171.52 15.38% 0.15 5,393.78
0349040007 CARGADOR S/LLANTAS 100-115 HP 2-2 25 YD3 hm 56.49 152.54 8,616.98 13.56% 7.66 1,168.24 20.88% 11.80 1,799.37 13.35% 7.54 1,150.36 19.24% 10.87 1,657.58 17.60% 9.94 1,516.26 15.38% 8.69 1,325.18
CRONOGRAMA DE ADQUISICION DE MANO DE OBRA, MATERIALES E INSUMOS
PROYECTO: "MEJORAMIENTO DE LOS SERVICIOS DE LA PISCINA MUNICIPAL DE SAN JERÓNIMO, DISTRITO DE SAN JERÓNIMO, PROVINCIA DE ANDAHUAYLAS-APURIMAC”

PROPIET: MUNICIPALIDAD DISTRITAL DE SAN JERONIMO 13.56% 20.88% 13.35% 19.24% 17.60% 15.38%
PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
ITEM DESCR IP CIO N UND CANTID. PRECIO TOTAL
% CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO % CANTID. PRECIO
0349040023 RETROEXCAVADOR S/ORUG 115-165HP .75-1.4Y hm 275.17 169.49 46,638.56 13.56% 37.31 6,322.97 20.88% 57.46 9,738.93 13.35% 36.73 6,226.21 19.24% 52.93 8,971.46 17.60% 48.42 8,206.60 15.38% 42.32 7,172.39
0349070004 VIBRADOR DE CONCRETO 4 HP 2.40" hm 170.85 5.93 1,013.14 13.56% 23.16 137.36 20.88% 35.68 211.56 13.35% 22.81 135.25 19.24% 32.86 194.89 17.60% 30.06 178.27 15.38% 26.27 155.81
0349100007 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 362.75 12.71 4,610.55 13.56% 49.18 625.07 20.88% 75.75 962.76 13.35% 48.43 615.51 19.24% 69.78 886.89 17.60% 63.83 811.28 15.38% 55.79 709.04
0349190002 NIVEL TOPOGRAFICO hm 33.20 5.00 166.00 13.56% 4.50 22.51 20.88% 6.93 34.66 13.35% 4.43 22.16 19.24% 6.39 31.93 17.60% 5.84 29.21 15.38% 5.11 25.53
0349190003 ESTACION TOTAL hm 44.35 16.95 751.73 13.56% 6.01 101.92 20.88% 9.26 156.97 13.35% 5.92 100.36 19.24% 8.53 144.60 17.60% 7.80 132.28 15.38% 6.82 115.61

370101 HERRAMIENTAS MANUALES %MO 6,552.07 1.00 6,552.07 13.56% 888.29 888.29 20.88% 1,368.18 1,368.18 13.35% 874.70 874.70 19.24% 1,260.36 1,260.36 17.60% 1,152.91 1,152.91 15.38% 1,007.62 1,007.62
COSTO DIRECTO 982,536.50 13.56% 133,206.29 20.88% ### 13.35% 131,167.83 19.24% 189,002.09 17.60% 172,888.71 15.38% 151,101.12