RUBRO: CERRAMIENTO DE BLOQUE H=3,2 m UNIDAD: M2
DETALLE:
EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA RENDIMIENTO COSTO
A B C=AxB R D=CxR
HERRAMIENTA MENOR (5% M.O.) 3.44
CONCRETERA 1.00 3.75 3.75 0.8800 3.30
VIBRADOR 1.00 3.13 3.13 0.8800 2.75
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
SUBTOTAL 1 9.49
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL /HR COSTO HORA RENDIMIENTO COSTO
A B C=AxB R D=CxR
PEON (ESTR.OC E2) 4.00 3.51 14.04 2.2000 30.89
MAESTRO MAYOR DE EJECUCION DE OBRA
0.10 3.93 0.39 1.8000 0.70
(ESTR.OC C1)
ALBAÑIL (ESTR.OC D2) 2.00 3.55 7.10 2.2000 15.62
FIERRERO (ESTR.OC D2) 1.00 3.55 3.55 1.8000 6.39
CARPINTERO (ESTR.OC D2) 1.00 3.55 3.55 4.3000 15.27
0.00 0.00
0.00 0.00
0.00 0.00
SUBTOTAL 2 68.87
MATERIALES
DESCRIPCION UNIDAD CANTIDAD P. UNITARIO COSTO
A B C=AxB
BLOQUE ALIVIANADO 25X25X40 U 13.00 0.70 9.10
PIEDRA M3 0.21 12.50 2.63
TABLA DE ENCOFRADO 2,4 x 0,28 U 0.61 3.50 2.13
PINGOS EUCALIPTO 2,4 M U 0.35 3.00 1.04
LISTONES 0,05 X 0,04 X 2,4 M U 1.51 4.00 6.05
ALAMBRE GALVANIZADO # 16 KG 0.14 5.70 0.79
CLAVO GALVANIZADO 2 1/2 PULG. KG 0.59 2.13 1.25
VARILLA CORRUGADA D= 8- 10-12 MM KG 4.04 0.88 3.56
TRANSPORTE
DESCRIPCION DISTANCIA CANTIDAD TARIFA COSTO
UNIDAD A B C=AxB
0.00
0.00
0.00
SUBTOTAL 4 0.00
Sub total 4 0