Está en la página 1de 9

PLANILLA DE METRA

ITEM PARTIDA

OE 1 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD.


01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES
01.01.01 LIMPIEZA DE TERRENO

01.01.02 TRAZO, NIVELACION Y REPLANTEO PRELIMINAR

OE.2 ESTRUCTURAS

02.01 MOVIMIENTO DE TIERRAS


02.01.01 EXCAVACION PARA ZAPATAS EN TERRENO NORMAL

02.01.02 EXCAVACION DE ZANJAS PARA CIMENTACION

02.01.03 RELLENOS CON MATERIAL PROPIO Y APISONADO DE ZANJAS

02.01.04 NIVELACION, REFINE Y COMPACTACION PARA RECIBIR FALSOS PISOS


02.01.05 NIVELACION RELLENO Y COMPACTADO CON MATERIAL PRESTAMO

02.02 CONCRETO SIMPLE


02.02.01 CIMIENTO 1:10 CH + 30% DE P.G.

02.02.02 SOBRECIMIENTO, CONCRETO DE 1:8 + 30 % P.M.

02.02.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS

02.02.04 SOLADO PARA ZAPATAS e=4" MEZCLA 1:10 CEMENTO - HORMIGON CONFETILLADO
02.02.05 FALSO PISO DE 4" CONCRETO 1:10
PLANILLA DE METRADOS

N° DE
DESCRIPCION LARGO ANCHO ALTO PARCIAL TOTAL
VECES

237.25
aula 1.00 1.00 23.94 9.91 237.25
- 237.25
1.00 1.00 23.94 9.91 237.25

174.50
AULAS
Z- 1 2.00 1.70 1.60 2.00 10.88
Z- 2 2.00 2.20 2.10 2.00 18.48
Z- 3 4.00 2.70 2.60 2.00 56.16
Z- 4 1.00 2.00 1.90 2.00 7.60
Z- 5 1.00 2.10 2.00 2.00 8.40
Z- 6 1.00 2.70 2.50 2.00 13.50
Z- 7 2.00 2.30 1.90 2.00 17.48
Z- 8 corrida 2.00 7.00 1.50 2.00 42.00

12.15
AULAS
EJE 1 1.00 13.30 0.40 0.70 3.72
EJE 3 1.00 13.30 0.40 0.70 3.72
EJE A 1.00 3.00 0.60 0.90 1.62
EJE B 1.00 2.55 0.60 0.90 1.38
EJE G 1.00 2.10 0.90 0.90 1.70

75.85
AULAS
ZAPATAS
Z- 1 2.00 area 1.76 1.50 5.29
Z- 2 2.00 area 3.19 1.50 9.57
Z- 3 4.00 area 5.94 1.50 35.64
Z- 4 1.00 area 2.66 1.50 3.99
Z- 5 1.00 area 2.92 1.50 4.38
Z- 6 1.00 area 5.90 1.50 8.85
Z- 7 2.00 area 2.71 1.50 8.13

152.36
AULAS
SS.HH. V 1.00 3.72 6.70 24.92
SSS.HH. D 1.00 3.70 6.70 24.79
AULA 1 1.00 7.66 6.70 51.32
AULA 2 1.00 7.66 6.70 51.32

152.36
AULAS
SS.HH. V 1.00 3.72 6.70 24.92
SSS.HH. D 1.00 3.70 6.70 24.79
AULA 1 1.00 7.66 6.70 51.32
AULA 2 1.00 7.66 6.70 51.32

15.70
AULAS
EJE 1 1.00 21.15 0.40 0.50 4.23
EJE 3 1.00 21.15 0.40 0.50 4.23
EJE A y G 2.00 5.65 0.60 0.70 4.75
EJE B 1.00 5.94 0.60 0.70 2.49

4.26

AULAS
EJE 1 1.00 21.15 0.15 0.40 1.27
EJE 3 1.00 21.15 0.15 0.40 1.27
EJE A y G 2.00 5.65 0.25 0.40 1.13
EJE B 1.00 5.94 0.25 0.40 0.59

47.63

AULAS
EJE 1 1.00 2.00 21.15 0.40 16.92
EJE 3 1.00 2.00 21.15 0.40 16.92
EJE A y G 2.00 2.00 5.65 0.40 9.04
EJE B 1.00 2.00 5.94 0.40 4.75

FETILLADO 87.25
AULAS
Z- 1 2.00 1.70 1.60 5.44
Z- 2 2.00 2.20 2.10 9.24
Z- 3 4.00 2.70 2.60 28.08
Z- 4 1.00 2.00 1.90 3.80
Z- 5 1.00 2.10 2.00 4.20
Z- 6 1.00 2.70 2.50 6.75
Z- 7 2.00 2.30 1.90 8.74
Z- 8 corrido 2.00 7.00 1.50 21.00

152.36

AULAS
SS.HH. V 1.00 3.72 6.70 24.92
SSS.HH. D 1.00 3.70 6.70 24.79
AULA 1 1.00 7.66 6.70 51.32
AULA 2 1.00 7.66 6.70 51.32
UND

M2

M2

M3

M3

M3

M2
M2

M3

M3

M2

M2
M2