CRONOGRAMA VALORIZADO DE AVANCE DE OB

PRESUPUESTO CONTRATADO:
VALOR REFERENCIAL :
FACTOR DE RELACION :
TIEMPO DE EJECUCION DE OBRA
ITEM DESCRIPCION PARCIALES NOV DIC ENE
28 DIAS 31 DIAS 31 DIAS
1.00 Campamento pro104,534.70
2.00 Movilización 24,144.42 24,144.42
3.00 Cartel de iden 23,400.91 17,550.68 5,850.23
4.00 Trazo y replan 35,742.86 30,075.81 5,667.05
5.00 Replanteo fina 40,050.29 12,015.09 24,030.17 4,005.03
6.00 Servicio de a 12,925.44 3,877.63 9,047.81
7.00 Servicio de bañ 2,000.00 500.00 700.00
8.00 Señalizaciones 81,009.33 12,151.40 20,252.33
9.00 Cono fibra vid 15,100.13 3,775.03 3,775.03
10.00 Cerco de mall 1,210.36
11.00 Tranquera tipo 33,003.56
12.00 Puente de mad 11,280.74 3,384.22
13.00 Desvío de agua 17,156.09 6,862.44
14.00 Desmontaje y 15,654.65
15.00 Eliminación de 2,164.95 2,164.95
16.00 Proteccion de 7,119.83 3,559.92
17.00 Proteccion de 1,260.27
18.00 Ubicacion y p 1,231.87 1,231.87
19.00 Proteccion de 5,494.85
20.00 Proteccion de 11,278.52 5,639.26 5,639.26
21.00 Equipos de prot 85,000.59 51,000.35 17,000.12
22.00 Plan de seguri 431,281.30 172,512.52
23.00 Demolición de 10,362.11
24.00 Demolición de 10,762.29
25.00 Eliminación d 135,225.96 47,329.09 87,896.87
26.00 Buzón I t. nor 12,962.95 3,240.74
27.00 Buzón I t. nor 1,647.21 1,647.21

28.00 Buzón I t. nor 3,454.49 1,105.43 2,349.06


29.00 Buzón I t. nor 4,044.59 2,583.54 1,461.05
30.00 Sellado de buz 1,656.76 1,656.76
31.00 Sellado de buz 3,250.60 1,142.80
32.00 Prueba de cal 5,416.66 1,354.17 2,437.50
33.00 Prueba de com 4,320.75
34.00 Trazo y replan 61,220.88 61,220.88
35.00 Replanteo fina 1,897.23
COSTO DIRE 1,218,268.14 85,017.87 170,070.48 406,749.37
GASTOS GENE 182,740.22 12,752.68 25,510.57 61,012.41
UTILIDAD 10. 121,826.81 8,501.79 17,007.05 40,674.94
PARCIAL 1,522,835.17 106,272.34 212,588.10 508,436.72
FACTOR DE RE1,370,551.92 104,188.55 208,419.67 498,467.29
IGV 18.00% 246,699.35 18,753.94 37,515.54 89,724.11

TOTAL DEL P 1,617,251.27 122,942.49 245,935.21 588,191.40


PORCENTAJE PARCIAL 7.60% 15.21% 36.37%
PORCENTAJE ACUMULADO 7.60% 22.81% 59.18%
E AVANCE DE OBRA

1,522,835.17
1,553,292.14
0.98039199 0.9
EJECUCION DE OBRA
FEB MARZO
28 DIAS 17 DIAS

24,144.42

800.00
48,605.60
7,550.07
1,210.36
13,201.42 19,802.14
2,256.15 5,640.37
2,573.41 6,004.63
9,392.79 6,261.86

3,559.92
1,260.27

5,494.85

17,000.12
43,128.13 215,640.65
10,362.11
2,690.57 8,071.72

3,240.74 6,481.48

2,107.80
1,624.99
4,320.75
1,897.23
152,304.05 322,020.48
22,845.61 48,303.07
15,230.41 32,202.05
190,380.07 402,525.60
186,647.10 394,632.87
33,596.48 71,033.92

220,243.58 465,666.79
13.62% 28.79%
72.80% 101.59%